JP4514179B2 - Tunnel lining concrete compaction apparatus and compaction method using the same - Google Patents

Tunnel lining concrete compaction apparatus and compaction method using the same Download PDF

Info

Publication number
JP4514179B2
JP4514179B2 JP2001194558A JP2001194558A JP4514179B2 JP 4514179 B2 JP4514179 B2 JP 4514179B2 JP 2001194558 A JP2001194558 A JP 2001194558A JP 2001194558 A JP2001194558 A JP 2001194558A JP 4514179 B2 JP4514179 B2 JP 4514179B2
Authority
JP
Japan
Prior art keywords
concrete
tunnel
vibrator
guide
lining concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2001194558A
Other languages
Japanese (ja)
Other versions
JP2003003795A (en
Inventor
利行 村本
俊明 佐々木
彦三 今岡
康弘 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sato Kogyo Co Ltd
Original Assignee
Sato Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sato Kogyo Co Ltd filed Critical Sato Kogyo Co Ltd
Priority to JP2001194558A priority Critical patent/JP4514179B2/en
Publication of JP2003003795A publication Critical patent/JP2003003795A/en
Application granted granted Critical
Publication of JP4514179B2 publication Critical patent/JP4514179B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、トンネル内面に構築される覆工コンクリートの締固め装置およびこれを用いた締固め方法に係り、詳しくはトンネル内面に沿って打設される覆工コンクリートをバイブレータによって締め固めるに際し、空洞等の不良箇所を無くし高品質のコンクリートを打設するとともに、締固め作業の省力化を図った締固め装置および方法に関する。
【0002】
【従来の技術】
シールド工法に代表される都市トンネル工法や、発破工法および自由断面掘削機に代表される山岳トンネル工法によって地下に形成される各種トンネルの内壁面には、漏水等を防止するとともに、所定の内面形状に仕上げる等のために、トンネル内壁面に沿って所定厚の覆工コンクリートが打設される。
【0003】
この覆工コンクリートの構築は、トンネルの内壁面より覆工コンクリート厚だけ離間した位置に型枠を組み立て、トンネル内壁面と型枠との狭空間に覆工コンクリートを充填することにより施工されるが、覆工コンクリートの品質を良好なものにするには、型枠とトンネル内壁面との間に空洞が無いようにコンクリートを密実に充填するとともに、充填した際にコンクリートに振動を与え十分な締固めを行う必要がある。
【0004】
従来、覆工コンクリートの締固めには、図11に示されるように、棒状のバイブレータ50を検査窓51から覆工コンクリート打設空間内に挿入し、打設したコンクリートの上部側に振動を与えるように、バイブレータ50を手作業で引上げ操作しながらコンクリートを締固める方法や、自振モータを有する起振装置を型枠の外面に取付け、型枠を介してコンクリートに振動を伝達して締固める方法などが採用されている。
【0005】
【発明が解決しようとする課題】
しかしながら、前者の検査窓51からバイブレータ50を挿入して締固めを行う場合には、打設したコンクリートの上部位置(レベル位置)を視認することができず、勘に頼りながらバイブレータ50の引上げ操作しなければならず、コンクリートを十分に締固めできない場合があるとともに、トンネル壁面形状は円弧状に形成されており、検査窓51から挿入したバイブレータ50のケーブル部分52の剛性が高い場合にはトンネル壁面に接触する位置に偏倚し、剛性が小さい場合には型枠に接触する位置に偏倚したり、或いは鉄筋に当たったりするなど、覆工コンクリート打設空間内の略中央に位置保持することが実質的に困難であり、振動が地山または型枠・鉄筋に伝達され振動エネルギーが逸散するため、打設コンクリートに対し効率良く振動を与えることが出来ないなどの問題があった。
【0006】
一方、後者の型枠外面に起振装置を取付ける方法の場合には、振動を伝え難い型枠を間に介するため、起振装置による振動を効率よくコンクリートに伝達し得ない。特に、型枠の厚みが大きい場合や覆工コンクリートの厚みが大きい場合にはこの傾向が顕著となるなどの問題があった。
【0007】
また、トンネル覆工の型枠に設置してある点検窓を下端とする天端コンクリートの締固め作業では、棒状のバイブレータを使用することは、作業員が打設箇所に入れる場合等の条件が揃わないとできないため、型枠外面に起振装置を取り付けることが多いが、前述の理由により天端部コンクリートを十分に締固めることはできない。
【0008】
さらに、天端部コンクリートの打ち継ぎ部の最天端部は、打ち継ぎ目位置から0.5〜1.0m離れたコンクリート打設口からコンクリートを圧入するため、大きな空気溜まりが生じやすく、かつバイブレータの振動を与えづらいことと相まって空隙が生じる結果と成り易い。
【0009】
また、天端コンクリートの充填状態の把握は、妻型枠の一部を外して目視確認していることが多いが、コンクリートの電気抵抗を利用した検知センサを用いることも可能である。しかし、この場合はコンクリート内壁面が円弧状であり、充填されたことを検知するためには多数の位置にセンサを設置する必要があり、コストが掛かり過ぎるため、通常はセンサを埋め殺しする条件で試験施工を行い、その結果を後の覆工コンクリート打設に反映させる施工管理が一般的である。
【0010】
他方、従来よりトンネル覆工コンクリートの締固めに関しては、特開平7-189488号公報、特開平8-260896号公報、特開平11-210393号公報、特開平7-48994号公報などにおいて種々の提案が成されているが、バイブレータ方式に限定すれば、いずれもトンネル側壁部の締固めに関するものであり、トンネル天端に限定した締固め方法については効率的な締固め方法を提案するものは見当たらない。
【0011】
そこで本発明の課題は、トンネル覆工の天端部コンクリートの締固めをバイブレータを使用して行うに当たって、覆工コンクリート打設空間内の厚み方向略中央に位置保持するようにするとともに、作業員の勘に頼ることなく、かつ空洞等の不良箇所を無くし締固め不足部分が生じないように引抜き操作できるようにして高品質のコンクリートを打設可能とするとともに、締固め作業の省力化を図ることにある。
【0012】
【課題を解決するための手段】
記課題を解決するための請求項1に係る本発明は、トンネルの内壁面より覆工コンクリート厚だけ離間した位置に型枠を組み立てるとともに、端部に妻型枠が設けられ、トンネル内壁面と型枠との間のコンクリート打設空間内に覆工コンクリートを充填することにより施工される天端部覆工コンクリートの締固め装置であって、
前記コンクリート打設空間内にトンネル長手方向に沿って配設された引込みガイド用条部材と、この引込みガイド用条部材と係合するガイド保持材を一体的に備え、前記引込みガイド用条部材に懸垂状態で保持されるとともに、引込みガイド用条部材に沿って引込み操作されるバイブレータと、前記ガイド保持材の上端部位置、または別部材を介してトンネル天端側位置に配置され、前記バイブレータと共に移動する1または複数のコンクリート検知センサとを備えることを特徴とするものである。
【0013】
この場合において、前記バイブレータの後端面から連続し前記妻型枠を貫通して外に出されたケーブルを巻き取るケーブルリールと、前記コンクリート検知センサによる検出信号に基づいて前記ケーブルリールを駆動制御する制御器とを備えることが望ましい。また、前記バイブレータの後端面に連続し、前記妻型枠を貫通して外部まで延在するとともに、バイブレータの後端面から連続するケーブルを収容するパイプ状部材を備え、前記パイプ状部材を押し引き操作することにより前記バイブレータをトンネル長手方向に移動可能とすることもできる。
【0014】
上記発明においては、前記コンクリート検知センサは、バイブレータ移動方向に離間して複数配設するのが望ましく、かつ前記バイブレータからコンクリート検知センサへの振動伝達を低減するための振動絶縁材を配設してあるのが望ましい。さらには、前記コンクリート検知センサによる検出信号に基づいてバイブレータの駆動/停止を制御する制御器を設けてあるのが望ましい。
【0015】
他方、前記課題に対応する締固め方法は、トンネルの内壁面より覆工コンクリート厚だけ離間した位置に型枠を組み立てるとともに、端部に妻型枠が設けられ、トンネル内壁面と型枠との間のコンクリート打設空間内に覆工コンクリートを充填することにより施工される天端部覆工コンクリートの締固め方法であって、
前記コンクリート打設空間内にトンネル長手方向に沿って引込みガイド用条部材を設けておき、この引込みガイド用条部材と係合するガイド保持材を一体的に備え、前記引込みガイド用条部材に懸垂状態で保持されるとともに、引込みガイド用条部材に沿って引込み操作されるバイブレータを配設し、かつ前記ガイド保持材の上端部位置、または別部材を介してトンネル天端側位置に前記バイブレータと共に移動する1または複数のコンクリート検知センサを取り付けておき、
コンクリートを前記コンクリート打設空間に充填するに当たり、前記コンクリート検知センサによる検出信号に基づいて、前記バイブレータを引込みガイド用条部材に沿って所定量づつ引込みながらコンクリートの締固めを行うことを特徴とするものである。
【0016】
【発明の実施の形態】
以下、本発明の実施の形態について図面を参照しながら詳述する。図1はトンネル覆工コンクリートを打設するための型枠設置状態図である。
【0017】
図1に示されるように、トンネル内壁面に対して覆工コンクリートを打設するには、トンネル内壁面1から覆工コンクリートの厚みだけ離間した位置にトンネル周方向に沿って型枠2を設置し、トンネル内壁面1と型枠2との間のコンクリート打設空間4内に覆工コンクリートを打設する。なお、覆工コンクリートの打設は、トンネルの一方側から所定区間毎、順に行われ、端部には妻型枠(図示せず)が設けられる。
【0018】
なお、図示例のトンネルは、掘削後の地山壁面に支保のために吹付けコンクリート3(一次覆工)を所定厚で吹き付けており、この吹付けコンクリート3の内面側に二次覆工としてコンクリートが打設される。ここでいうトンネル内壁面とは、覆工コンクリートを打設する直前のトンネル内壁面を言い、本例のように吹付けコンクリート面であったり、地山が良好で一次覆工を行わない場合には地山面であったり、またシールド工法の場合にはセグメントであったりする。
【0019】
覆工コンクリートを打設するには、トンネル断面を周方向に天端部Aと両側の側壁部B、Bとに分け、先ず最初に側壁部B、Bの覆工コンクリート打設を行った後、天端部Aの覆工コンクリート打設を行う。したがって、以下側壁部B、Bの施工と、天端部Aの施工とに分けて、締固め装置および方法について詳述することにする。
【0020】
〔側壁部B、Bの覆工コンクリート打設〕
図2〜図5に基づいて側壁部B、Bの覆工コンクリート打設について詳述すると、図2および図3に示されるように、型枠2の側壁部Bと天端部Aとの境界部にはトンネル長手方向に適宜の間隔で、具体的には1.5〜3m程度の間隔で検査窓2a、2a…が設けられ、この検査窓2aからバイブレータを挿入し打設したコンクリートに振動が加えられる。
【0021】
先ず、本締固め方法では、型枠2の設置前の段階で、コンクリート打設空間4内であって、かつ検査窓2aの対応位置に水平方向に所定幅だけ離間させて2条の引上げガイド用条部材5,5がトンネル内壁面形状に沿うとともに、上下方向に沿って配設される。この場合、前記引上げガイド用条部材5としては、例えば鋼棒または鉄筋等の容易に変形しない高剛性部材を用いることができる。また、前記引上げガイド用条部材5、5は、覆工コンクリート厚み方向の略中央位置に配設される。
【0022】
前記引上げガイド用条部材5,5に保持され、引上げガイド用条部材5,5に沿って引上げ操作されるバイブレータ装置6Aは、詳細には図4および図5に示されるように、回転振動子を内設する振動部10と、前記回転振動子を回転させる加振用モータ等を内設するケーシング筒部11とが縦列的に連設された構造のもので、前記ケーシング筒部11には、長手方向に間隔をおいて2箇所に前記引上げガイド用条部材5,5が挿通されるガイド保持材12A,12Aが一体的に設けられている。
【0023】
前記ガイド保持材12Aは、図5に示されるように、両端部に取付けフランジ14a、14aを備える半割状のバンド部材14の外面に、前記引上げガイド用条部材5のための挿通孔15aを有するガイドアーム片15を備えた部材を左右対で用意し、前記ケーシング筒部11に外嵌し、対面合わせされる前記取付けフランジ14a、14a同士をボルト・ナット16で締結することにより前記ケーシング筒部11に一体的に取り付けられる。また、前記ガイド保持材12Aの一方側端部にはコンクリートの存在を検知するコンクリート検知センサ17が付設されている。このコンクリート検知センサ17は、外面に突出した2本の棒状電極17a、17b間に交流電圧を印加し、電極17a、17b間の抵抗値を測定するもので、コンクリートが前記電極17a、17b間に存在すると、電極17a、17b間の抵抗値が下がり、コンクリートが充填されたことを検知するようになっている。なお、前記コンクリート検知センサ17は、前記ガイド保持材12Aに取り付けられた別部材に対して間接的に設けるようにしてもよい。
【0024】
前記コンクリート検知センサ17は、前記振動部10の振動が前記ガイドアーム片15を介して前記コンクリート検知センサ17に伝達して破壊されないように、前記バンド部材14とケーシング筒部11との間に振動絶縁材としてのゴムシート13が介在されている。なお、振動絶縁材としては、他にガイドアーム片15の中間部にゴム材を介する構造とすることによって振動の絶縁を図るようにしてもよい。
【0025】
一方、前記ケーシング筒部11の後端部には、前記ケーシング筒部11内に内設されたモータに給電するための給電ケーブル18および前記コンクリート検知センサ17からのリード線19が延長され、前記検査窓2aから外に出され、ケーブルリール21に巻回されている。なお、前記給電ケーブル18およびリード線19は、ばらけないようにホース20内に収容されるとともに、断線しないように、好ましくはケプラー等の補強繊維によって引張強度の増大が図られた素材を被覆材として用いたものが望ましい。
【0026】
前記給電ケーブル18およびリード線19(以下、まとめてケーブルという。)は、ケーブルリール21を介して電気的に制御器22に接続され、前記コンクリート検知センサ17による検出信号に基づいて前記ケーブルリール21の巻取り用モータ24が駆動制御されるとともに、加振用モータの駆動/停止が制御されるようになっている。
【0027】
以下、側壁部覆工コンクリートの締固め方法について具体的かつ手順に従って説明すると、前記バイブレータ装置6Aを引上げガイド用条部材5,5に沿って引上げできるように、ガイド保持材12Aの挿通孔15aに前記引上げガイド用条部材5,5を挿通させた状態で設置した後、ケーブルリール21を繰出し、バイブレータ装置6Aを最下端位置まで降ろした状態とする。なお、前記バイブレータ装置6Aは基本的にはコンクリート打設区間内において、水平方向に適宜の間隔で複数設置される。
【0028】
この状態で、ある検査窓2aから挿入したコンクリート圧送ホースまたは別途設けたコンクリート打設口からコンクリートをコンクリート打設空間4内に流し込む。コンクリートのレベル面が徐々に上がり、下段側コンクリート検知センサ17がコンクリートを検知したならば、所定時間の間、バイブレータ装置6Aの加振用モータに給電を行い振動によりコンクリートを締固める。なお、バイブレータによる振動を掛け過ぎると、逆に材料分離を促進する結果となるため、適度な振動時間が設定される。
【0029】
以後、コンクリート打設を継続し、上段側コンクリート検知センサ17がコンクリートを検知したならば、ケーブルリール21を巻き方向に駆動しバイブレータ装置6Aを所定量だけ上方に引き上げる。この引上げ量は、振動部10が空気中に露出しない長さで適宜設定されるが、たとえば振動部10の上部に位置する下段側コンクリート検知センサ17が空気中に露出した検出信号を制御信号として前記ケーブルリール21の巻上げを停止するようにしてもよい。
【0030】
バイブレータ装置6Aを所定量だけ引き上げたならば、再び所定時間の間、バイブレータ装置6Aの加振用モータに給電を行い振動によりコンクリートを締固める。その後は、コンクリートの打設に伴って、コンクリート検知センサ17、17による検出信号に基づいて、バイブレータ装置6Aの引上げと所定時間の振動とを繰り返し、打設されるコンクリートのすべてに均等に振動を加えるようにする。
【0031】
ところで、上記例では引上げガイド用条部材5を2条配設し、バイブレータ装置6Aの引上げガイド用条部材5周りの回転を防止するようにしたが、場合によっては、前記引上げガイド用条部材5は1条であってもよい。この場合には、前記ガイド保持材12Aのガイドアーム片15の長さを極力小さくし、バイブレータ装置6Aが振れても、バイブレータ装置6Aの位置が極端にコンクリート壁面寄り側位置および型枠寄り側位置に偏倚しないようにすることが望ましい。
【0032】
〔天端部Aの覆工コンクリート打設〕
次いで、図6〜図9に基づいて天端部Aの覆工コンクリート打設について詳述する。
【0033】
天端部Aでは、図1に示されるように、型枠2の設置前の段階において、トンネル周方向に適宜の間隔で、かつトンネル長手方向に沿って引込みガイド用条部材25,25…が配置される。この場合、前記引込みガイド用条部材25としては、たとえば鋼棒/鉄筋等の容易に変形しない高剛性部材またはPC鋼線等の索状部材等を用いることができる。但し、可撓性が大きい索状部材等を用いる場合には、弛みがないように緊張した状態としておく必要がある。また、前記引込みガイド用条部材25の配設位置は、引込みガイド用条部材25に懸垂されるバイブレータ装置6Bが覆工コンクリートの厚み方向略中央に位置するように配設するのが望ましい。
【0034】
前記引込みガイド用条部材25に懸垂され、引込みガイド用条部材25に沿って引込み操作されるバイブレータ装置6Bは、詳細には図8および図9に示されるように、回転振動子を内設する振動部10と、前記回転振動子を回転させる加振用モータ等を内設するケーシング筒部11とが縦列的に連設された構造のもので、前記ケーシング筒部11には、長手方向に間隔をおいて2箇所に前記引込みガイド用条部材25,25が挿通されるガイド保持材12B,12Bが一体的に設けられている。
【0035】
前記ガイド保持材12Bは、図9に示されるように、両端部に取付けフランジ14a、14aを備える半割状のバンド部材14の外面に、前記引込みガイド用条部材25のための挿通孔15aを有するガイドアーム片15を備えた一方側部材と、両端部に取付けフランジ14a、14aを備える半割状のバンド部材14を他方側部材とし、前記ケーシング筒部11に外嵌し、対面合わせされる前記取付けフランジ14a、14a同士をボルト・ナット16で締結することにより前記ケーシング筒部11に一体的に取り付けられる。
【0036】
前記ガイド保持材12Bの上端部に直接、若しくは前記ガイド保持材12Bに取り付けられた別部材を介してさらに上部側位置に(図示せず)コンクリートの存在を検知するコンクリート検知センサ17、17が設けられている。このコンクリート検知センサ17は、外面に突出した2本の棒状電極17a、17b間に交流電圧を印加し、電極17a、17b間の抵抗値を測定するもので、コンクリートが前記電極17a、17b間に存在すると、電極17a、17b間の抵抗値が下がり、コンクリートが充填されたことを検知するようになっている。
【0037】
前記コンクリート検知センサ17は、前記振動部10の振動が前記ガイドアーム片15を介して前記コンクリート検知センサ17に伝達して破壊されないように、前記バンド部材14とケーシング筒部11との間に振動絶縁材としてのゴムシート13が介在されている。なお、振動絶縁材としては、他にガイドアーム片15の中間部にゴム材を介する構造とすることによって振動の絶縁を図るようにしてもよい。
【0038】
一方、前記ケーシング筒部11の後端部には、前記ケーシング筒部11内に内設されたモータに給電するための給電ケーブル18および前記コンクリート検知センサ17からのリード線19が延長され、妻型枠2Bに形成された挿通孔から外に出され、ケーブルリール21に巻回されている。なお、前記給電ケーブル18およびリード線19は、ばらけないようにホース20内に収容されるとともに、断線しないように、好ましくはケプラー等の補強繊維によって引張強度の増大が図られた素材を被覆材として用いたものが望ましい。
【0039】
前記給電ケーブル18およびリード線19は、ケーブルリール21を介して電気的に制御器22に接続され、前記コンクリート検知センサ17による検出信号に基づいて前記ケーブルリール21の巻取り用モータ24が駆動制御されるとともに、加振用モータの駆動/停止が制御されるようになっている。
【0040】
以下、天端部覆工コンクリートの締固め方法について具体的かつ手順に従って説明すると、前記バイブレータ装置6Bを引込みガイド用条部材25に沿って引込みできるように、ガイド保持材12Bの挿通孔15aに前記引込みガイド用条部材25を挿通させた状態で設置した後、ケーブルリール21を繰出し、バイブレータ装置6Bを打設済みコンクリート7の近傍位置に位置決めする。なお、前記引込みガイド用条部材25は、既設済みコンクリート7に埋め殺してある引込みガイド用条部材25の突出端に対して連結具26により連結するか、溶接等によって連結することができる。
【0041】
この状態で型枠2の天端面であって、かつ打設済みコンクリート7の近接する位置に形成したコンクリート打設口8からコンクリートをコンクリート打設空間4内に流し込む。コンクリートが徐々にコンクリート打設空間4内に充填され、相対的にコンクリート打設口8側に位置するコンクリート検知センサ17がコンクリートを検知したならば、所定時間の間、バイブレータ装置6Bの加振用モータに給電を行い振動によりコンクリートを締固める。なお、バイブレータによる振動を掛け過ぎると、逆に材料分離を促進する結果となるため、適度な振動時間が設定される。
【0042】
以後、コンクリート打設を継続し、妻型枠2B側のコンクリート検知センサ17がコンクリートを検知したならば、ケーブルリール21を巻き方向に駆動しバイブレータ装置6Bを所定量だけ引き込む。この引込み量は、振動部10が空気中に露出しない長さで適宜設定されるが、たとえばコンクリート打設口8側に位置するコンクリート検知センサ17が空気中に露出した検出信号を制御信号として前記ケーブルリール21の巻上げを停止するようにしてもよい。
【0043】
バイブレータ装置6Bを所定量だけ引き込んだならば、再び所定時間の間、バイブレータ装置6Bの加振用モータに給電を行い振動によりコンクリートを締固める。その後は、コンクリートの打設に伴って、コンクリート検知センサ17、17による検出信号に基づいて、バイブレータ装置6Bの引込みと所定時間の振動とを繰り返し、打設されるコンクリートのすべてに均等に振動を加えるようにする。
【0044】
天端部Aのコンクリート打設に際しては、最上部位置に大きな空気溜まりが生じやすく、かつバイブレータの振動を与えづらいことと相まって空隙が生じる結果と成り易い。しかし、本締固め装置では、コンクリート検知センサ17、17をバイブレータ装置6Bを懸垂しているガイド保持材12Bの上端部または前記ガイド保持材12Bに取り付けられた別部材を介して、たとえばさらに上部側位置に取り付けられているため、打設されたコンクリートが天端部Aの最上部まで確実に充填されているかを確認しながら締固めが行われる。
【0045】
ところで、トンネル天端面はアーチ形状を成しているため、コンクリート打設空間4内に圧入されたコンクリートが下方側に流下するため、トンネル周方向に適宜の間隔で設置されたバイブレータ装置6B、6B…のコンクリート打設中におけるトンネル長手方向位置は均一とはならず、図7に示されるように、両側に配置されるバイブレータ装置6Bほど引き込みが早く行われる。この場合、天井部に位置するバイブレータ装置6Bに振動を掛けた際、振動によって流動性が促進され、コンクリートが下方側に流下することにより、自然にバイブレータ装置6Bが空気中に露出してしまうことがある。ケーブル18を送り出してバイブレータ装置6Bを押出し出来ればよいが、ケーブル18が可撓性であるために押し出すことは実質的に困難である。
【0046】
そこで、図10に示されるように、前記バイブレータ装置6Bの後端面に連続し前記妻型枠2Bを貫通して外部まで延在するとともに、バイブレータ装置6Bの後端面から連続するケーブル18,19を収容するパイプ状部材27を設け、前記パイプ状部材27を手動または駆動ローラ28,28により押し引き操作可能としておけば、バイブレータ装置6Bが空気中に露出した際に、前記バイブレータ装置6Bを送り出し再びコンクリート中に埋没できるようになる。
【0047】
【発明の効果】
以上詳説のとおり本発明によれば、トンネル覆工の天端部コンクリートの締固めをバイブレータを使用して行うに当たって、覆工コンクリート打設空間内の厚み方向略中央に位置保持できるようになるとともに、作業員の勘に頼ることなく、かつ空洞等の不良箇所を無くし締固め不足部分が生じないように引抜き操作できるようになるため高品質のコンクリートを打設可能となるとともに、締固め作業の省力化を図ることが可能になる。
【図面の簡単な説明】
【図1】 トンネル覆工コンクリートを打設するための型枠設置状態図である。
【図2】 側壁部覆工コンクリートの締固め状態を示す断面図である。
【図3】 その正面図である。
【図4】 バイブレータ装置6Aを示す、(A)は正面図、(B)は側面図である。
【図5】 図4のV−V線矢視図である。
【図6】 天端部覆工コンクリートの締固め状態を示す縦断面図である。
【図7】 その平面図である。
【図8】 バイブレータ装置6Bを示す、(A)は側面図、(B)は平面図である。
【図9】 図8のIX−IX線矢視図である。
【図10】 バイブレータ装置6Bをトンネル長手方向に移動可能とした縦断面図である。
【図11】 バイブレータを用いた従来の締固め方法を示す横断面図である。
【符号の説明】
1…トンネル内壁面、2…型枠、3…吹付けコンクリート、4…コンクリート打設空間、5…引上げガイド用条部材、6A・6B…バイブレータ装置、7…打設済みコンクリート、8…コンクリート打設口、10…振動部、11…ケーシング筒部、12A・12B…ガイド保持材、13…ゴムシート(振動絶縁材)、17…コンクリート検知センサ、18…給電ケーブル、19…リード線、20…ホース、21…ケーブルリール、22…制御器、24…巻取り用モータ、25…引込みガイド用条部材、26…連結具、27…パイプ状部材、28…駆動ローラ
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a compacting device for lining concrete constructed on the inner surface of a tunnel and a compaction method using the same, and more specifically, when compacting lining concrete placed along the inner surface of a tunnel with a vibrator, The present invention relates to a compacting device and method that eliminates defective parts such as high-quality concrete and saves the compaction work.
[0002]
[Prior art]
The inner wall surface of various tunnels formed underground by the urban tunnel method represented by the shield method and the mountain tunnel method represented by the blasting method and the free-section excavator prevents leakage and the prescribed inner surface shape. For example, lining concrete having a predetermined thickness is placed along the inner wall surface of the tunnel.
[0003]
This lining concrete is constructed by assembling the formwork at a position separated from the inner wall surface of the tunnel by the thickness of the lining concrete, and filling the narrow space between the inner wall surface of the tunnel and the formwork with the lining concrete. In order to improve the quality of the lining concrete, the concrete should be filled tightly so that there are no cavities between the formwork and the inner wall of the tunnel, and when filled, the concrete will be vibrated and tightened sufficiently. It is necessary to harden.
[0004]
Conventionally, for compacting lining concrete, as shown in FIG. 11, a rod-like vibrator 50 is inserted into the lining concrete placement space from the inspection window 51, and vibration is applied to the upper side of the placed concrete. As described above, the concrete is compacted while the vibrator 50 is manually pulled up, or a vibration generator having a self-vibrating motor is attached to the outer surface of the mold, and the vibration is transmitted to the concrete through the mold and compacted. Method is adopted.
[0005]
[Problems to be solved by the invention]
However, when the vibrator 50 is inserted and compacted from the former inspection window 51, the upper position (level position) of the placed concrete cannot be visually confirmed, and the vibrator 50 is pulled up while relying on intuition. In some cases, the concrete may not be sufficiently compacted, and the tunnel wall surface is formed in an arc shape, and the cable portion 52 of the vibrator 50 inserted from the inspection window 51 has a high rigidity. It is biased to a position that contacts the wall surface, and if the rigidity is low, it can be biased to a position that contacts the formwork or hits a reinforcing bar, etc. It is practically difficult, and vibration energy is dissipated by transferring vibration to the ground or formwork / rebar. Well there is a problem such as not being able to give the vibration.
[0006]
On the other hand, in the case of the latter method of mounting the vibration generator on the outer surface of the mold, the vibration by the vibration generator cannot be efficiently transmitted to the concrete because the mold is difficult to transmit. In particular, when the thickness of the formwork is large or the thickness of the lining concrete is large, there is a problem that this tendency becomes remarkable.
[0007]
In addition, in the compaction work of the top concrete with the inspection window installed in the tunnel lining formwork as the lower end, the use of a rod-shaped vibrator is a condition when an operator puts it in the placement site. Since it cannot be done unless it is aligned, a vibration generator is often attached to the outer surface of the mold, but the top end concrete cannot be sufficiently compacted for the reasons described above.
[0008]
Furthermore, since the topmost end of the joint portion of the top end concrete is pressed into the concrete from the concrete placement port at a distance of 0.5 to 1.0 m from the joint position, a large air pool is likely to occur, and the vibrator This is likely to result in voids coupled with the difficulty of giving vibrations.
[0009]
In addition, in many cases, the state of filling the top concrete is visually checked by removing a part of the end formwork, but it is also possible to use a detection sensor using the electrical resistance of the concrete. However, in this case, the concrete inner wall has an arc shape, and it is necessary to install sensors at a number of positions to detect that it has been filled. In general, construction management is performed in which test construction is performed and the results are reflected in the subsequent lining concrete placement.
[0010]
On the other hand, regarding the compaction of tunnel lining concrete, various proposals are disclosed in Japanese Patent Laid-Open Nos. 7-189488, 8-260896, 11-210393, 7-48994, etc. However, if it is limited to the vibrator system, all are related to the compaction of the tunnel side wall, and there is no suggestion of an efficient compaction method for the compaction method limited to the top of the tunnel. Absent.
[0011]
Therefore, the present invention Section The title is to hold the top end concrete of the tunnel lining by using a vibrator, and keep it at the center of the lining concrete placement space in the thickness direction and rely on the intuition of the workers. In addition, it is possible to place a high-quality concrete so that a high-quality concrete can be placed so that a defective portion such as a cavity is eliminated and an insufficiently compacted portion is generated, and the labor of compaction work is reduced.
[0012]
[Means for Solving the Problems]
in front Lesson In order to solve the problem, the present invention according to claim 1 assembles the formwork at a position separated from the inner wall surface of the tunnel by the thickness of the lining concrete. In addition, a wife formwork is provided at the end. A compacting device for top-end lining concrete that is constructed by filling the concrete placement space between the tunnel inner wall surface and the formwork with lining concrete,
A pull-in guide strip member disposed along the longitudinal direction of the tunnel in the concrete placement space and a guide holding member that engages with the pull-in guide strip member are integrally provided, and the pull-in guide strip member A vibrator which is held in a suspended state and is operated to be retracted along the guide member for the retracting guide, and is arranged at the top end position of the guide retaining material or the tunnel top end side position via another member, together with the vibrator It is characterized by comprising one or more concrete detection sensors that move.
[0013]
In this case, drive control of the cable reel is performed based on the detection signal from the cable reel that winds up the cable that is continuous from the rear end surface of the vibrator and passes through the end form and is taken out. It is desirable to provide a controller. And a pipe-like member that is continuous with the rear end surface of the vibrator, extends through the end form to the outside, and accommodates a cable continuous from the rear end surface of the vibrator, and pushes and pulls the pipe-like member. By operating it, the vibrator can be moved in the tunnel longitudinal direction.
[0014]
In the above invention, it is desirable that a plurality of the concrete detection sensors be disposed apart from each other in the vibrator moving direction, and a vibration insulating material for reducing vibration transmission from the vibrator to the concrete detection sensor is disposed. It is desirable. Furthermore, it is desirable to provide a controller for controlling the driving / stopping of the vibrator based on the detection signal from the concrete detection sensor.
[0015]
On the other hand Lesson The compaction method corresponding to the problem is to assemble the formwork at a position separated from the inner wall of the tunnel by the thickness of the lining concrete. In addition, a wife formwork is provided at the end. A method for compacting the top end lining concrete to be constructed by filling the concrete placement space between the tunnel inner wall surface and the formwork with lining concrete,
A pull-in guide strip member is provided along the longitudinal direction of the tunnel in the concrete placing space, and a guide holding member that engages with the pull-in guide strip member is integrally provided, and is suspended from the pull-in guide strip member. A vibrator that is held in a state and is operated to be retracted along the guide member for the retracting guide is disposed, and at the top end position of the guide retaining member or the tunnel top end side position via the separate member together with the vibrator Attach one or more moving concrete detection sensors,
When filling the concrete placement space with concrete, the concrete is compacted while pulling the vibrator along the guide guide member by a predetermined amount based on a detection signal from the concrete detection sensor. Is.
[0016]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a view showing a state of installing a formwork for placing tunnel lining concrete.
[0017]
As shown in FIG. 1, in order to place lining concrete on the inner wall surface of the tunnel, the formwork 2 is installed along the circumferential direction of the tunnel at a position separated from the inner wall surface 1 by the thickness of the lining concrete. Then, lining concrete is placed in the concrete placement space 4 between the tunnel inner wall surface 1 and the formwork 2. The lining concrete is placed in order from the one side of the tunnel every predetermined section, and a end form (not shown) is provided at the end.
[0018]
In the illustrated tunnel, spray concrete 3 (primary lining) is sprayed to the wall surface of the ground after excavation at a predetermined thickness, and secondary lining is applied to the inner surface of the shot concrete 3. Concrete is cast. The inner wall surface of the tunnel here refers to the inner wall surface of the tunnel just before placing the lining concrete, and it is a sprayed concrete surface as in this example, or when the ground is good and primary lining is not performed. May be a natural surface, or a segment in the case of shield construction.
[0019]
In order to place lining concrete, the tunnel cross section is divided into the top end A and the side wall parts B and B on both sides in the circumferential direction. Then, lining concrete is cast at the top end A. Therefore, it is divided into the construction of the side wall parts B and B below and the construction of the top end part A. , Tighten The consolidation device and method will be described in detail.
[0020]
[Concrete placement of side walls B, B]
The lining concrete placement of the side walls B and B will be described in detail with reference to FIGS. 2 to 5. As shown in FIGS. 2 and 3, the boundary between the side wall B and the top end A of the mold 2. Are provided with inspection windows 2a, 2a... At an appropriate interval in the longitudinal direction of the tunnel, specifically at an interval of about 1.5 to 3 m, and a vibrator is inserted through the inspection window 2a to vibrate in the placed concrete. Is added.
[0021]
First, in this compaction method, two stages of pulling guides are provided in the concrete placement space 4 and spaced apart by a predetermined width in the horizontal direction from the corresponding position of the inspection window 2a before the mold 2 is installed. The strip members 5 and 5 are disposed along the inner wall surface of the tunnel and along the vertical direction. In this case, as the pulling guide strip member 5, for example, a highly rigid member that is not easily deformed, such as a steel rod or a reinforcing bar, can be used. The pull-up guide strip members 5 and 5 are disposed at a substantially central position in the lining concrete thickness direction.
[0022]
The vibrator device 6A held by the pulling guide strip members 5 and 5 and pulled up along the pulling guide strip members 5 and 5 has a rotary vibrator as shown in detail in FIGS. And a casing cylinder portion 11 in which a vibration motor for rotating the rotating vibrator and the like are connected in series. The casing cylinder portion 11 includes The guide holding members 12A and 12A through which the pull-up guide strip members 5 and 5 are inserted are provided integrally at two places with an interval in the longitudinal direction.
[0023]
As shown in FIG. 5, the guide holding member 12A has insertion holes 15a for the pull-up guide strip member 5 on the outer surface of the half-shaped band member 14 having mounting flanges 14a, 14a at both ends. A member provided with a guide arm piece 15 is prepared in a pair of left and right, and is externally fitted to the casing cylinder portion 11, and the mounting flanges 14 a and 14 a that are face-to-face are fastened with bolts and nuts 16 to thereby form the casing cylinder. It is attached to the part 11 integrally. A concrete detection sensor 17 for detecting the presence of concrete is attached to one end of the guide holding member 12A. The concrete detection sensor 17 applies an AC voltage between the two rod-shaped electrodes 17a and 17b protruding from the outer surface, and measures a resistance value between the electrodes 17a and 17b. Concrete is detected between the electrodes 17a and 17b. When present, the resistance value between the electrodes 17a and 17b decreases, and it is detected that the concrete is filled. In addition, you may make it provide the said concrete detection sensor 17 indirectly with respect to another member attached to the said guide holding material 12A.
[0024]
The concrete detection sensor 17 vibrates between the band member 14 and the casing tube part 11 so that the vibration of the vibration part 10 is transmitted to the concrete detection sensor 17 via the guide arm piece 15 and is not destroyed. A rubber sheet 13 as an insulating material is interposed. In addition, as a vibration insulating material, you may make it aim at the insulation of a vibration by making it the structure which interposed a rubber material in the intermediate part of the guide arm piece 15. FIG.
[0025]
On the other hand, at the rear end portion of the casing tube portion 11, a power supply cable 18 for supplying power to a motor installed in the casing tube portion 11 and a lead wire 19 from the concrete detection sensor 17 are extended, It goes out from the inspection window 2 a and is wound around the cable reel 21. The feeding cable 18 and the lead wire 19 are housed in the hose 20 so as not to be separated, and preferably are reinforced fibers such as Kepler so as not to be disconnected. Therefore It is desirable to use a material with an increased tensile strength as a covering material.
[0026]
The feeding cable 18 and the lead wire 19 (hereinafter collectively referred to as a cable) are electrically connected to a controller 22 via a cable reel 21, and the cable reel 21 is based on a detection signal from the concrete detection sensor 17. The winding motor 24 is driven and controlled, and the driving / stopping of the vibration motor is controlled.
[0027]
Hereinafter, the concrete method of compacting the side wall lining concrete will be described according to the procedure. The vibrator device 6A can be inserted into the insertion hole 15a of the guide holding member 12A so that the vibrator device 6A can be pulled up along the pulling guide strip members 5 and 5. After the pulling guide strip members 5 and 5 are installed, the cable reel 21 is fed out and the vibrator device 6A is lowered to the lowermost position. Note that a plurality of vibrator devices 6A are basically installed at appropriate intervals in the horizontal direction in the concrete placing section.
[0028]
In this state, concrete is poured into the concrete placement space 4 from a concrete pressure hose inserted from a certain inspection window 2a or a concrete placement port provided separately. The level surface of the concrete gradually rises, and the lower concrete detection sensor 17 D If concrete is detected, power is supplied to the vibration motor of the vibrator device 6A for a predetermined time, and the concrete is compacted by vibration. Note that, if excessive vibration is applied by the vibrator, the material separation is promoted conversely, so an appropriate vibration time is set.
[0029]
Thereafter, the concrete placement is continued, and the upper concrete detection sensor 17 U If concrete is detected, the cable reel 21 is driven in the winding direction and the vibrator device 6A is pulled upward by a predetermined amount. The pulling amount is appropriately set to such a length that the vibrating part 10 is not exposed to the air. For example, the lower concrete detecting sensor 17 located at the upper part of the vibrating part 10. D However, the winding of the cable reel 21 may be stopped using a detection signal exposed to the air as a control signal.
[0030]
When the vibrator device 6A is pulled up by a predetermined amount, the vibration motor of the vibrator device 6A is supplied with power again for a predetermined time and the concrete is compacted by vibration. After that, the concrete detection sensor 17 is accompanied with the concrete placement. U , 17 D On the basis of the detection signal, the vibration of the vibrator device 6A and the vibration for a predetermined time are repeated to uniformly apply vibration to all of the placed concrete.
[0031]
In the above example, two pulling guide strip members 5 are arranged to prevent rotation around the pulling guide strip member 5 of the vibrator device 6A. However, in some cases, the pulling guide strip member 5 is used. May be one. In this case, even if the length of the guide arm piece 15 of the guide holding member 12A is made as small as possible and the vibrator device 6A swings, the position of the vibrator device 6A is extremely close to the concrete wall side position and the mold side side position. It is desirable not to be biased.
[0032]
[Concrete casting of top edge A]
Next, the lining concrete placement of the top end A will be described in detail with reference to FIGS.
[0033]
At the top end A, as shown in FIG. 1, at the stage before installation of the mold 2, there are retract guide strip members 25, 25... At appropriate intervals in the tunnel circumferential direction and along the tunnel longitudinal direction. Be placed. In this case, as the lead-in guide strip member 25, for example, a highly rigid member that does not easily deform such as a steel bar / rebar or a cord-like member such as a PC steel wire can be used. However, when a highly flexible cord-like member or the like is used, it is necessary to be in a tensioned state so that there is no slack. Further, it is desirable that the retracting guide strip member 25 is disposed such that the vibrator device 6B suspended from the retracting guide strip member 25 is positioned at the approximate center in the thickness direction of the lining concrete.
[0034]
The vibrator device 6B suspended from the pull-in guide strip member 25 and pulled in along the pull-in guide strip member 25 includes a rotary vibrator as shown in detail in FIGS. The vibration part 10 and a casing cylinder part 11 in which a vibration motor for rotating the rotary vibrator and the like are provided are connected in series, and the casing cylinder part 11 has a longitudinal direction. Guide holding members 12B and 12B, through which the pull-in guide strip members 25 and 25 are inserted, are integrally provided at two positions at intervals.
[0035]
As shown in FIG. 9, the guide holding member 12B has insertion holes 15a for the pull-in guide strip member 25 on the outer surface of the half-shaped band member 14 having mounting flanges 14a, 14a at both ends. The one side member provided with the guide arm piece 15 and the half-shaped band member 14 provided with the attachment flanges 14a, 14a at the both ends are used as the other side member, and are externally fitted to the casing cylinder portion 11 and face to face. The mounting flanges 14 a and 14 a are fastened to each other by fastening the bolts and nuts 16 to the casing cylinder portion 11.
[0036]
Concrete detection sensors 17 and 17 for detecting the presence of concrete are provided directly on the upper end portion of the guide holding member 12B or at an upper side position (not shown) via another member attached to the guide holding member 12B. It has been. The concrete detection sensor 17 applies an AC voltage between the two rod-shaped electrodes 17a and 17b protruding from the outer surface, and measures a resistance value between the electrodes 17a and 17b. Concrete is detected between the electrodes 17a and 17b. When present, the resistance value between the electrodes 17a and 17b decreases, and it is detected that the concrete is filled.
[0037]
The concrete detection sensor 17 vibrates between the band member 14 and the casing tube part 11 so that the vibration of the vibration part 10 is transmitted to the concrete detection sensor 17 via the guide arm piece 15 and is not destroyed. A rubber sheet 13 as an insulating material is interposed. In addition, as a vibration insulating material, you may make it aim at the insulation of a vibration by setting it as the structure which interposed a rubber material in the intermediate part of the guide arm piece 15. FIG.
[0038]
On the other hand, at the rear end portion of the casing tube portion 11, a power supply cable 18 for supplying power to a motor installed in the casing tube portion 11 and a lead wire 19 from the concrete detection sensor 17 are extended. It is taken out from the insertion hole formed in the mold 2 </ b> B and is wound around the cable reel 21. The feeding cable 18 and the lead wire 19 are housed in the hose 20 so as not to be separated, and preferably are reinforced fibers such as Kepler so as not to be disconnected. Therefore It is desirable to use a material with an increased tensile strength as a covering material.
[0039]
The feeding cable 18 and the lead wire 19 are electrically connected to a controller 22 via a cable reel 21, and the winding motor 24 of the cable reel 21 is driven and controlled based on a detection signal from the concrete detection sensor 17. At the same time, the drive / stop of the vibration motor is controlled.
[0040]
Hereinafter, the concrete method for compacting the top end lining concrete will be described in accordance with the procedure. The vibrator device 6B can be drawn into the insertion hole 15a of the guide holding member 12B so that the vibrator device 6B can be drawn along the drawing guide strip member 25. After installing the retracting guide strip member 25 in the inserted state, the cable reel 21 is fed out and the vibrator device 6B is positioned in the vicinity of the placed concrete 7. The pull-in guide strip member 25 can be connected to the projecting end of the pull-in guide strip member 25 buried in the existing concrete 7 by a connector 26 or by welding or the like.
[0041]
In this state, the concrete is poured into the concrete placement space 4 from the concrete placement opening 8 formed on the top end surface of the mold 2 and at a position close to the placed concrete 7. Concrete is gradually filled into the concrete placement space 4, and a concrete detection sensor 17 located relatively on the concrete placement port 8 side. R If concrete is detected, power is supplied to the vibration motor of the vibrator device 6B for a predetermined time, and the concrete is compacted by vibration. Note that, if excessive vibration is applied by the vibrator, the material separation is promoted conversely, so an appropriate vibration time is set.
[0042]
Thereafter, the concrete placement is continued, and the concrete detection sensor 17 on the end form 2B side L If concrete is detected, the cable reel 21 is driven in the winding direction and the vibrator device 6B is pulled in by a predetermined amount. The pull-in amount is appropriately set to a length that does not expose the vibration unit 10 to the air. For example, the concrete detection sensor 17 located on the concrete placing port 8 side. R However, the winding of the cable reel 21 may be stopped using a detection signal exposed to the air as a control signal.
[0043]
When the vibrator device 6B is pulled in by a predetermined amount, the vibration motor of the vibrator device 6B is again fed for a predetermined time and the concrete is compacted by vibration. After that, the concrete detection sensor 17 is accompanied with the concrete placement. R , 17 L On the basis of the detection signal, the retraction of the vibrator device 6B and the vibration for a predetermined time are repeated so that the vibration is evenly applied to all of the placed concrete.
[0044]
When placing the concrete at the top end A, a large air pocket is likely to be generated at the uppermost position, and a gap is likely to be generated in combination with the vibration of the vibrator being difficult to apply. However, in the compacting device, the concrete detection sensors 17 and 17 are connected to the upper side of the guide holding member 12B that suspends the vibrator device 6B or another member attached to the guide holding member 12B, for example, on the upper side. Since it is attached to the position, compaction is performed while confirming whether the cast concrete is filled up to the top of the top end portion A.
[0045]
By the way, since the tunnel top end face has an arch shape, the concrete press-fitted into the concrete placement space 4 flows downward, so that the vibrator devices 6B and 6B installed at appropriate intervals in the circumferential direction of the tunnel. The position in the longitudinal direction of the tunnel during the placement of the concrete is not uniform, and as shown in FIG. 7, the vibrator device 6B disposed on both sides is pulled in earlier. In this case, when vibration is applied to the vibrator device 6B located on the ceiling, the fluidity is promoted by the vibration, and the concrete flows down downward, so that the vibrator device 6B is naturally exposed to the air. There is. Although it is sufficient that the cable 18 can be sent out and the vibrator device 6B can be pushed out, it is substantially difficult to push out because the cable 18 is flexible.
[0046]
Therefore, as shown in FIG. 10, cables 18 and 19 are connected to the rear end surface of the vibrator device 6B, extend through the end form 2B to the outside, and continue from the rear end surface of the vibrator device 6B. If a pipe-like member 27 is provided and the pipe-like member 27 can be pushed or pulled manually or by driving rollers 28, 28, when the vibrator device 6B is exposed to the air, the vibrator device 6B is sent out again. Can be buried in concrete.
[0047]
【The invention's effect】
As described in detail above, according to the present invention, The When compacting the top end concrete of the tunnel lining using a vibrator, it can be held at the center of the thickness direction in the lining concrete placement space, and without relying on the intuition of the worker, In addition, since it becomes possible to perform the drawing operation so as to eliminate defective portions such as cavities and to prevent an insufficiently compacted portion, it is possible to place high-quality concrete and to save labor in the compacting operation.
[Brief description of the drawings]
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is a diagram showing a state of installing a form for placing tunnel lining concrete.
FIG. 2 is a cross-sectional view showing a compacted state of side wall covering concrete.
FIG. 3 is a front view thereof.
4A and 4B show a vibrator device 6A, where FIG. 4A is a front view, and FIG. 4B is a side view.
FIG. 5 is a view taken along the line VV in FIG. 4;
FIG. 6 is a longitudinal sectional view showing a compacted state of the top end lining concrete.
FIG. 7 is a plan view thereof.
8A and 8B show a vibrator device 6B, where FIG. 8A is a side view and FIG. 8B is a plan view.
9 is a view taken along the line IX-IX in FIG.
FIG. 10 is a longitudinal sectional view in which the vibrator device 6B is movable in the tunnel longitudinal direction.
FIG. 11 is a cross-sectional view showing a conventional compacting method using a vibrator.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Tunnel inner wall surface 2 ... Formwork, 3 ... Shotcrete, 4 ... Concrete placement space, 5 ... Pull guide member, 6A, 6B ... Vibrator device, 7 ... Concrete cast, 8 ... Concrete placement Installation port, 10 ... vibrating part, 11 ... casing cylinder part, 12A and 12B ... guide holding material, 13 ... rubber sheet (vibration insulating material), 17 ... concrete detection sensor, 18 ... feed cable, 19 ... lead wire, 20 ... Hose, 21 ... cable reel, 22 ... controller, 24 ... winding motor, 25 ... retraction guide strip member, 26 ... connector, 27 ... pipe member, 28 ... drive roller

Claims (7)

トンネルの内壁面より覆工コンクリート厚だけ離間した位置に型枠を組み立てるとともに、端部に妻型枠が設けられ、トンネル内壁面と型枠との間のコンクリート打設空間内に覆工コンクリートを充填することにより施工される天端部覆工コンクリートの締固め装置であって、
前記コンクリート打設空間内にトンネル長手方向に沿って配設された引込みガイド用条部材と、この引込みガイド用条部材と係合するガイド保持材を一体的に備え、前記引込みガイド用条部材に懸垂状態で保持されるとともに、引込みガイド用条部材に沿って引込み操作されるバイブレータと、前記ガイド保持材の上端部位置、または別部材を介してトンネル天端側位置に配置され、前記バイブレータと共に移動する1または複数のコンクリート検知センサとを備えることを特徴とするトンネル覆工コンクリートの締固め装置。
Rutotomoni assembled mold to a position spaced apart by lining concrete thickness from the inner wall surface of the tunnel, Wife formwork is provided at the end, lining concrete in between concrete設空between the tunnel inner wall and the mold A compaction device for the top end lining concrete constructed by filling
A pull-in guide strip member disposed along the longitudinal direction of the tunnel in the concrete placement space and a guide holding member that engages with the pull-in guide strip member are integrally provided, and the pull-in guide strip member A vibrator which is held in a suspended state and is operated to be retracted along the guide member for the retracting guide, and is arranged at the top end position of the guide retaining material or the tunnel top end side position via another member, together with the vibrator A tunnel lining concrete compaction device comprising one or more concrete detection sensors that move.
前記バイブレータの後端面から連続し前記妻型枠を貫通して外に出されたケーブルを巻き取るケーブルリールと、前記コンクリート検知センサによる検出信号に基づいて前記ケーブルリールを駆動制御する制御器とを備える請求項記載のトンネル覆工コンクリートの締固め装置。A cable reel that winds up a cable that is continuous from a rear end surface of the vibrator and that passes through the end form and is pulled out; and a controller that drives and controls the cable reel based on a detection signal from the concrete detection sensor. The tunnel lining concrete compaction device according to claim 1 . 前記バイブレータの後端面に連続し、前記妻型枠を貫通して外部まで延在するとともに、バイブレータの後端面から連続するケーブルを収容するパイプ状部材を備え、前記パイプ状部材を押し引き操作することにより前記バイブレータをトンネル長手方向に移動可能としてある請求項記載のトンネル覆工コンクリートの締固め装置。A pipe-like member that is continuous with the rear end surface of the vibrator, extends through the end form to the outside, and accommodates a cable continuous from the rear end surface of the vibrator, and pushes and pulls the pipe-like member. compaction apparatus tunnel lining concrete according to claim 1, wherein you have to be movable in the tunnel longitudinal direction the vibrator by. 前記コンクリート検知センサは、バイブレータ移動方向に離間して複数配設してある請求項1〜いずれかに記載のトンネル覆工コンクリートの締固め装置。The said concrete detection sensor is spaced apart in the vibrator moving direction, and the plurality is arrange | positioned, The compacting apparatus of the tunnel lining concrete in any one of Claims 1-3 . 前記バイブレータからコンクリート検知センサへの振動伝達を低減するための振動絶縁材を配設してある請求項1〜いずれかに記載のトンネル覆工コンクリートの締固め装置。The tunnel lining concrete compaction device according to any one of claims 1 to 4, further comprising a vibration insulating material for reducing vibration transmission from the vibrator to the concrete detection sensor. 前記コンクリート検知センサによる検出信号に基づいてバイブレータの駆動/停止を制御する制御器を設けてある請求項1〜いずれかに記載のトンネル覆工コンクリートの締固め装置。The tunnel lining concrete compaction device according to any one of claims 1 to 5 , further comprising a controller that controls driving / stopping of a vibrator based on a detection signal from the concrete detection sensor. トンネルの内壁面より覆工コンクリート厚だけ離間した位置に型枠を組み立てるとともに、端部に妻型枠が設けられ、トンネル内壁面と型枠との間のコンクリート打設空間内に覆工コンクリートを充填することにより施工される天端部覆工コンクリートの締固め方法であって、
前記コンクリート打設空間内にトンネル長手方向に沿って引込みガイド用条部材を設けておき、この引込みガイド用条部材と係合するガイド保持材を一体的に備え、前記引込みガイド用条部材に懸垂状態で保持されるとともに、引込みガイド用条部材に沿って引込み操作されるバイブレータを配設し、かつ前記ガイド保持材の上端部位置、または別部材を介してトンネル天端側位置に前記バイブレータと共に移動する1または複数のコンクリート検知センサを取り付けておき、
コンクリートを前記コンクリート打設空間に充填するに当たり、前記コンクリート検知センサによる検出信号に基づいて、前記バイブレータを引込みガイド用条部材に沿って所定量づつ引込みながらコンクリートの締固めを行うことを特徴とするトンネル覆工コンクリートの締固め方法。
Rutotomoni assembled mold to a position spaced apart by lining concrete thickness from the inner wall surface of the tunnel, Wife formwork is provided at the end, lining concrete in between concrete設空between the tunnel inner wall and the mold A method of compacting the top edge lining concrete to be constructed by filling
A pull-in guide strip member is provided along the longitudinal direction of the tunnel in the concrete placing space, and a guide holding member that engages with the pull-in guide strip member is integrally provided, and is suspended from the pull-in guide strip member. A vibrator that is held in a state and is operated to be retracted along the guide member for the retracting guide is disposed, and at the top end position of the guide retaining member or the tunnel top end side position via the separate member together with the vibrator Attach one or more moving concrete detection sensors,
When filling the concrete placement space with concrete, the concrete is compacted while pulling the vibrator along the guide guide member by a predetermined amount based on a detection signal from the concrete detection sensor. Compaction method for tunnel lining concrete.
JP2001194558A 2001-06-27 2001-06-27 Tunnel lining concrete compaction apparatus and compaction method using the same Expired - Lifetime JP4514179B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001194558A JP4514179B2 (en) 2001-06-27 2001-06-27 Tunnel lining concrete compaction apparatus and compaction method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001194558A JP4514179B2 (en) 2001-06-27 2001-06-27 Tunnel lining concrete compaction apparatus and compaction method using the same

Publications (2)

Publication Number Publication Date
JP2003003795A JP2003003795A (en) 2003-01-08
JP4514179B2 true JP4514179B2 (en) 2010-07-28

Family

ID=19032671

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001194558A Expired - Lifetime JP4514179B2 (en) 2001-06-27 2001-06-27 Tunnel lining concrete compaction apparatus and compaction method using the same

Country Status (1)

Country Link
JP (1) JP4514179B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108825265A (en) * 2018-06-07 2018-11-16 中铁隧道股份有限公司 A kind of vault casting concrete automatic vibrating device of working jumbo for tunnel lining

Families Citing this family (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1317471C (en) * 2004-11-05 2007-05-23 耿福明 Electric-cylinder concrete lining apparatus
JP2006192841A (en) * 2005-01-17 2006-07-27 Toyo Constr Co Ltd Vibration compaction apparatus for concrete in closed space and vibration compaction method
JP4566891B2 (en) * 2005-11-18 2010-10-20 株式会社奥村組 Tunnel lining concrete placement method
JP4624243B2 (en) * 2005-11-18 2011-02-02 株式会社奥村組 Tunnel lining concrete placing method and wife formwork device
JP4557942B2 (en) * 2006-08-31 2010-10-06 株式会社奥村組 Tunnel lining concrete placement method and placement structure
JP4557941B2 (en) * 2006-08-31 2010-10-06 株式会社奥村組 Tunnel lining concrete placement method and placement structure
JP4557946B2 (en) * 2006-09-28 2010-10-06 株式会社奥村組 Tunnel lining concrete placement method and placement structure
JP2008088696A (en) * 2006-10-02 2008-04-17 Maeda Corp Tunnel lining construction method
JP4979420B2 (en) * 2007-03-19 2012-07-18 株式会社奥村組 Tunnel lining concrete casting structure
JP4841476B2 (en) * 2007-03-19 2011-12-21 株式会社奥村組 Tunnel lining concrete casting structure
CN103697932B (en) * 2013-12-25 2016-11-16 中国建筑第五工程局有限公司 Tunnel detector
JP6235908B2 (en) * 2014-01-09 2017-11-22 株式会社奥村組 Vibration compaction method for tunnel lining concrete.
JP6371556B2 (en) * 2014-03-31 2018-08-08 前田建設工業株式会社 Placing trace pattern elimination apparatus and casting trace pattern elimination method in tunnel lining
JP6588319B2 (en) * 2015-11-27 2019-10-09 鹿島建設株式会社 Concrete placement method and concrete placement structure
JP6478245B2 (en) * 2016-09-02 2019-03-06 飛島建設株式会社 Centle formwork device for tunnel lining and lining placement system
JP7015122B2 (en) * 2017-07-24 2022-02-02 東急建設株式会社 How to drive concrete
JP6942025B2 (en) * 2017-10-12 2021-09-29 前田建設工業株式会社 How to compact construction seams in tunnel lining
JP6983054B2 (en) * 2017-12-21 2021-12-17 株式会社フジタ Lining concrete placing equipment
JP7176882B2 (en) * 2018-01-15 2022-11-22 佐藤工業株式会社 Concrete Compaction Vibrator and Concrete Placement Management System
JP7329927B2 (en) * 2019-01-23 2023-08-21 清水建設株式会社 Concrete compaction system and concrete compaction method
JP7132878B2 (en) * 2019-03-26 2022-09-07 五洋建設株式会社 Fitting joint construction method, vibrator and protection pipe that can be used for this method
JP7289240B2 (en) * 2019-07-30 2023-06-09 前田建設工業株式会社 Automatic operation device for pull-out vibrator used for construction of tunnel lining
JP7437902B2 (en) * 2019-09-30 2024-02-26 前田建設工業株式会社 Concrete placement method at the top of the tunnel
JP6919937B1 (en) * 2020-05-14 2021-08-18 エクセン株式会社 Concrete vibrator
CN113958340B (en) * 2020-07-21 2024-01-23 中铁一局集团有限公司 Rotary lining trolley pouring mechanism and method

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61187855U (en) * 1985-05-14 1986-11-22
JPS6213657A (en) * 1985-07-10 1987-01-22 清水建設株式会社 Method and apparatus for casting concrete into steel shell
JPS62178624A (en) * 1986-01-30 1987-08-05 Kajima Corp Driver for concrete under water
JPH04125339U (en) * 1991-05-08 1992-11-16 株式会社大林組 concrete vibrator
JPH07189488A (en) * 1993-12-27 1995-07-28 Maeda Corp Compactor for concrete
JPH08254098A (en) * 1995-03-17 1996-10-01 Ohbayashi Corp Stamping device of lining concrete for tunneling method
JPH08260896A (en) * 1995-03-24 1996-10-08 Ohbayashi Corp Compaction method of tunnel lining concrete
JPH1037689A (en) * 1996-07-19 1998-02-10 Fukudagumi:Kk Forming method of tunnel and centre for forming tunnel
JP2000356099A (en) * 1999-04-14 2000-12-26 Maeda Corp Method for compacting concrete of tunnel lining
JP2001012196A (en) * 2000-05-02 2001-01-16 Saga Kogyo Kk Compacting method for arch concrete and arch center for placing concrete
JP2001082087A (en) * 1999-07-13 2001-03-27 Maeda Corp Concrete compacting method and its device

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61187855U (en) * 1985-05-14 1986-11-22
JPS6213657A (en) * 1985-07-10 1987-01-22 清水建設株式会社 Method and apparatus for casting concrete into steel shell
JPS62178624A (en) * 1986-01-30 1987-08-05 Kajima Corp Driver for concrete under water
JPH04125339U (en) * 1991-05-08 1992-11-16 株式会社大林組 concrete vibrator
JPH07189488A (en) * 1993-12-27 1995-07-28 Maeda Corp Compactor for concrete
JPH08254098A (en) * 1995-03-17 1996-10-01 Ohbayashi Corp Stamping device of lining concrete for tunneling method
JPH08260896A (en) * 1995-03-24 1996-10-08 Ohbayashi Corp Compaction method of tunnel lining concrete
JPH1037689A (en) * 1996-07-19 1998-02-10 Fukudagumi:Kk Forming method of tunnel and centre for forming tunnel
JP2000356099A (en) * 1999-04-14 2000-12-26 Maeda Corp Method for compacting concrete of tunnel lining
JP2001082087A (en) * 1999-07-13 2001-03-27 Maeda Corp Concrete compacting method and its device
JP2001012196A (en) * 2000-05-02 2001-01-16 Saga Kogyo Kk Compacting method for arch concrete and arch center for placing concrete

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108825265A (en) * 2018-06-07 2018-11-16 中铁隧道股份有限公司 A kind of vault casting concrete automatic vibrating device of working jumbo for tunnel lining

Also Published As

Publication number Publication date
JP2003003795A (en) 2003-01-08

Similar Documents

Publication Publication Date Title
JP4514179B2 (en) Tunnel lining concrete compaction apparatus and compaction method using the same
JP2009127230A (en) Placing management method for tunnel lining concrete
JP4557941B2 (en) Tunnel lining concrete placement method and placement structure
JP2019127692A (en) Joint structure of concrete members
CN110552370A (en) Reverse construction method based annular lining wall integral single-side formwork construction method
JP2015090030A (en) Tunnel lining construction method and management method for tunnel lining concrete placing
JP4566890B2 (en) Tunnel lining concrete placing method and wife formwork device
JP4799453B2 (en) Tunnel lining concrete placement method
JP2005273255A (en) Concrete tamping device of arch crown part of tunnel lining
JP3692002B2 (en) Vibrator device for concrete compaction
JP4624243B2 (en) Tunnel lining concrete placing method and wife formwork device
JP4557946B2 (en) Tunnel lining concrete placement method and placement structure
JP6942025B2 (en) How to compact construction seams in tunnel lining
JP2000356096A (en) Method for constructing tunnel lining
JP2008231739A (en) Method for placing tunnel-lining concrete
JP4610540B2 (en) Tunnel lining concrete placement method and placement structure
JP4948142B2 (en) How to build an underpass
JP2000356099A (en) Method for compacting concrete of tunnel lining
JP2973861B2 (en) Compaction method for tunnel lining concrete
JP2003227297A6 (en) Concrete compaction method and apparatus
CN211571665U (en) Fixing structure of concrete surface soil pressure cell
JP4979420B2 (en) Tunnel lining concrete casting structure
JP4557942B2 (en) Tunnel lining concrete placement method and placement structure
JP2978957B2 (en) Concrete placing machine at the bottom of gutter
KR20190081405A (en) Vibrator for lining concrete of tunnel and mold apparatus using the same

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080408

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20091020

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100128

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100202

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100218

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100507

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100510

R150 Certificate of patent or registration of utility model

Ref document number: 4514179

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130521

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130521

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140521

Year of fee payment: 4

EXPY Cancellation because of completion of term