KR20190081405A - Vibrator for lining concrete of tunnel and mold apparatus using the same - Google Patents

Vibrator for lining concrete of tunnel and mold apparatus using the same Download PDF

Info

Publication number
KR20190081405A
KR20190081405A KR1020170183918A KR20170183918A KR20190081405A KR 20190081405 A KR20190081405 A KR 20190081405A KR 1020170183918 A KR1020170183918 A KR 1020170183918A KR 20170183918 A KR20170183918 A KR 20170183918A KR 20190081405 A KR20190081405 A KR 20190081405A
Authority
KR
South Korea
Prior art keywords
vibration
tunnel
lining concrete
hole
main body
Prior art date
Application number
KR1020170183918A
Other languages
Korean (ko)
Other versions
KR102105956B1 (en
Inventor
박상진
Original Assignee
주식회사 상일테크
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 상일테크 filed Critical 주식회사 상일테크
Priority to KR1020170183918A priority Critical patent/KR102105956B1/en
Publication of KR20190081405A publication Critical patent/KR20190081405A/en
Application granted granted Critical
Publication of KR102105956B1 publication Critical patent/KR102105956B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B06GENERATING OR TRANSMITTING MECHANICAL VIBRATIONS IN GENERAL
    • B06BMETHODS OR APPARATUS FOR GENERATING OR TRANSMITTING MECHANICAL VIBRATIONS OF INFRASONIC, SONIC, OR ULTRASONIC FREQUENCY, e.g. FOR PERFORMING MECHANICAL WORK IN GENERAL
    • B06B1/00Methods or apparatus for generating mechanical vibrations of infrasonic, sonic, or ultrasonic frequency
    • B06B1/18Methods or apparatus for generating mechanical vibrations of infrasonic, sonic, or ultrasonic frequency wherein the vibrator is actuated by pressure fluid
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/06Solidifying concrete, e.g. by application of vacuum before hardening
    • E04G21/08Internal vibrators, e.g. needle vibrators
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries

Abstract

The present invention relates to an apparatus to vibro-float a ceiling part during the placement of lining concrete in a tunnel with a mold apparatus (200). The vibro-floatation apparatus includes: a body (110) having a pipe structure; a vibration application part (120) installed in the body (110) to be able to be operated in a vertical direction; a vibration rod (130) installed in the upper part of the vibration application part (120); an extending part (140) in which the vibration rod (130) is installed to be able to be operated in a vertical direction; and an operating part (150) installed in the body (110). Therefore, the apparatus is capable of preventing the occurrence of a crack after curing.

Description

터널 천정부 라이닝 콘크리트의 진동다짐장치 및 이를 이용한 터널 라이닝 콘크리트용 거푸집 장치{VIBRATOR FOR LINING CONCRETE OF TUNNEL AND MOLD APPARATUS USING THE SAME}TECHNICAL FIELD [0001] The present invention relates to a vibrating compaction apparatus for a tunnel lining lining concrete, and a tunnel lining concrete formwork apparatus using the same. [0002]

본 발명은 건설 기술분야에 관한 것으로서, 상세하게는 터널 천정부 라이닝 콘크리트의 진동다짐장치 및 이를 이용한 터널 라이닝 콘크리트용 거푸집 장치에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a field of construction technology, and more particularly, to a vibrating compaction apparatus for a tunnel lining lining concrete and a tunnel lining concrete formwork using the same.

터널의 굴착(일반적으로 발파) 후 숏크리트를 타설하고, 그 내부를 라이닝 콘크리트의 타설에 의해 마감하는 것이 일반적이다.After excavation (usually blasting) of tunnels, shotcrete is generally laid, and the interior of the tunnel is generally closed by pouring lining concrete.

라이닝 콘크리트는 거의 동일한 형상이 대규모로 반복되는 것이므로, 바퀴나 레일에 의해 터널의 길이방향을 따라 이동가능하도록 형성된 몸통부(21)와, 라이닝 콘크리트의 타설을 위하여, 터널의 내면에 인접하여 위치할 수 있도록, 몸통부(21)의 외측에 설치되는 몰드부(22)를 구비한 거푸집 장치(20)에 의해 라이닝 콘크리트의 타설작업을 실시한다(도 1).Since the lining concrete is substantially repeated in the same shape on a large scale, the lining concrete has a body 21 formed to be movable along the longitudinal direction of the tunnel by wheels or rails, and a body portion 21 located adjacent to the inner surface of the tunnel The lining concrete is poured by the molding machine 20 having the mold part 22 provided on the outer side of the body 21 (Fig. 1).

타설된 콘크리트가 재료의 분리 없이 밀실하게 양생되도록 하기 위해서는, 굳지 않은 상태에서 진동다짐을 실시하여야 한다.In order to ensure that the poured concrete can be cured tightly without separating the material, the vibration should be compacted in an uncured state.

터널의 라이닝 콘크리트의 경우, 몰드부(22)의 측벽에 구멍을 내고, 여기에 진동다짐장치의 진동봉을 삽입하여 진동다짐을 실시한다.In the case of the lining concrete of the tunnel, a hole is made in a side wall of the mold part 22, and a vibration bar of the vibration compaction device is inserted therein to perform vibration compaction.

그런데 터널의 라이닝 콘크리트의 천정부의 경우에는, 몰드부(22)의 천정부에 구멍을 낼 수 없으므로(굳지 않은 상태의 콘크리트가 쏟아지게 되므로), 진동다짐을 실시할 수 없고, 이로 인하여 재료의 분리 등이 발생함에 따라 양생 후 균열이 발생하는 주된 원인으로 지적되어 왔다.However, in the case of the ceiling portion of the lining concrete of the tunnel, it is not possible to make a hole in the ceiling portion of the mold portion 22 (since the unhardened concrete is poured), vibration compaction can not be performed, Has been pointed out as a main cause of cracking after curing.

본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 터널의 라이닝 콘크리트의 천정부에 대한 진동다짐을 실시할 수 있도록 하여, 양생 후 균열의 발생을 방지할 수 있는 터널 천정부 라이닝 콘크리트의 진동다짐장치 및 이를 이용한 터널 라이닝 콘크리트용 거푸집 장치를 제시하는 것을 그 목적으로 한다.The present invention has been made to solve the above problems and it is an object of the present invention to provide a vibration damping device for a tunnel lining concrete which can prevent vibrations of a lining concrete of a tunnel, And a molding apparatus for a tunnel lining concrete using the same.

상기 과제의 해결을 위하여, 본 발명은 거푸집 장치(200)에 의한 터널의 라이닝 콘크리트 타설작업 중 천정부를 진동다짐하기 위한 장치로서, 관 구조의 본체(110); 상기 본체(110)의 내부에 상하방향을 따라 구동가능하도록 설치된 진동인가부(120); 상기 진동인가부(120)에 의해 진동함과 아울러, 상부가 굳지 않은 상태의 상기 라이닝 콘크리트에 매설될 수 있도록 상기 진동인가부(120)의 상부에 설치된 진동봉(130); 상단이 상기 거푸집 장치(200)의 몰드부(220)의 천정부에 형성된 진동봉 관통공(221)에 결합하고, 하단이 상기 본체(110)의 상단에 결합하며, 내부에 상기 진동봉(130)이 상하구동가능하도록 설치된 연장부(140); 상기 진동인가부(120)의 상하구동을 가능하게 하도록 상기 본체(110)에 설치된 구동부(150);를 포함하고, 터널 천정부 라이닝 콘크리트 타설작업 중에는, 상기 구동부(150)에 의해 상기 진동인가부(120)가 상향구동하여 상기 진동봉(130)의 상부가 굳지 않은 상태의 상기 라이닝 콘크리트에 매설되어 진동다짐을 하고, 터널 천정부 라이닝 콘크리트 타설작업 후에는, 상기 구동부(150)에 의해 상기 진동인가부(120)가 하향구동하여 상기 진동봉(130)의 상부가 상기 라이닝 콘크리트로부터 이탈하는 것을 특징으로 하는 터널 천정부 라이닝 콘크리트의 진동다짐장치(100)를 제시한다.In order to solve the above problems, the present invention is an apparatus for vibrating a ceiling portion during a lining concrete pouring operation of a tunnel by a molding machine (200), comprising: a main body (110) of a pipe structure; A vibration applying unit 120 installed in the main body 110 so as to be able to move along a vertical direction; A vibration bar (130) installed on the vibration applying part (120) so that the vibration applying part (120) vibrates and the upper part is buried in the unhardened lining concrete; And a lower end of the upper end is coupled to an upper end of the main body 110. The upper end of the vibration rod 130 is coupled to the upper end of the main body 110, An extension part 140 installed to be movable up and down; And a drive unit 150 installed in the main body 110 to enable the vibration applying unit 120 to be driven up and down. During the tunneling lining concrete pouring operation, the driving unit 150 applies the vibration applying unit 120 are upwardly driven so that the upper portion of the vibration bar 130 is buried in the unlapped lining concrete to vibrate the vibration and after the tunnel ceiling lining concrete pouring operation, (120) is driven downward and the upper part of the vibration bar (130) is separated from the lining concrete.

상기 구동부(150)는, 상기 진동인가부(120)의 하부에 설치된 연장봉(151); 상기 연장봉(151)의 하부가 상기 본체(110)의 하측으로 노출되도록, 상기 본체(110)의 하단에 형성된 설치공(152);을 포함하는 것이 바람직하다.The driving unit 150 includes an extension rod 151 installed at a lower portion of the vibration applying unit 120; And an installation hole 152 formed at the lower end of the main body 110 so that the lower portion of the extension rod 151 is exposed to the lower side of the main body 110.

상기 설치공(152)에는 암나사부가 형성되고, 상기 연장봉(151)에는 숫나사부가 형성되며, 상기 연장봉(151)의 나사회전구동에 의해 상기 진동인가부(120)가 상하구동하는 것이 바람직하다.It is preferable that the installation hole 152 is formed with a female screw part and a male screw part is formed on the extension rod 151 and the vibration applying part 120 is driven up and down by the screw rotation of the extension rod 151 .

상기 본체(110)는, 내부에 상기 진동인가부(120)가 상하구동가능하도록 설치된 가이드관(111); 상기 가이드관(111)의 하단에 일체로 형성됨과 아울러, 심부에 상기 연장봉(151)의 관통공이 형성된 본체 하부 플랜지(112); 상기 하부 플랜지의 하부에 볼트결합함과 아울러, 심부에 상기 설치공(152)이 형성된 폐쇄판(113);을 포함하는 것이 바람직하다.The main body 110 includes a guide tube 111 installed inside the vibration applying part 120 so as to be vertically movable; A body lower flange 112 integrally formed at a lower end of the guide tube 111 and having a through hole of the extension rod 151 at a deep portion thereof; And a closing plate 113 having a mounting hole 152 formed at a bottom portion of the lower flange and a bolt-connection case formed at a lower portion of the lower flange.

상기 본체(110)는, 내부에 상기 진동인가부(120)가 상하구동가능하도록 설치된 가이드관(111); 상기 가이드관(111)의 상단에 일체로 형성됨과 아울러, 심부에 상기 진동봉(130)의 관통공이 형성된 본체 상부 플랜지(114);를 포함하고, 상기 연장부(140)는, 상단이 상기 거푸집 장치(200)의 몰드부(220)의 천정부에 형성된 진동봉 관통공(221)에 결합하고, 내부에 상기 진동봉(130)이 상하구동가능하도록 설치된 연장관(141); 상기 연장관(141)의 하단에 일체로 형성됨과 아울러, 상기 본체 상부 플랜지(114)의 상부에 볼트결합하고, 심부에 상기 진동봉(130)의 관통공이 형성된 연장부 하부 플랜지(142);를 포함하는 것이 바람직하다.The main body 110 includes a guide tube 111 installed inside the vibration applying part 120 so as to be vertically movable; And a body upper flange 114 integrally formed on the upper end of the guide pipe 111 and having a through hole of the vibration bar 130 formed in a deep portion thereof, An extension pipe 141 coupled to the vibration hole 221 formed in the ceiling portion of the mold unit 220 of the apparatus 200 and having the vibration bar 130 installed so as to be vertically movable; An extension lower flange 142 integrally formed at the lower end of the extension pipe 141 and bolted to an upper portion of the upper body flange 114 and having a through hole of the vibration bar 130 formed at the center thereof .

상기 진동인가부(120)는, 압력을 공급하기 위한 공급구(121); 압력을 배출하기 위한 배출구(122);를 구비하고, 상기 본체(110)의 측벽에는, 상하구동하는 상기 진동인가부(120)의 공급구(121) 및 배출구(122)가 외부로 노출되도록 상하방향 장공 구조의 노출공(115)이 형성된 것이 바람직하다.The vibration applying unit 120 includes a supply port 121 for supplying pressure; And a discharge port 122 for discharging the pressure so that the supply port 121 and the discharge port 122 of the vibration applying unit 120 to be vertically driven are exposed to the outside, It is preferable that an exposure hole 115 having a directional elongated hole structure is formed.

본 발명은 상기 진동다짐장치(100)를 이용한 터널 라이닝 콘크리트용 거푸집 장치(200)로서, 터널의 길이방향을 따라 이동가능하도록 형성된 몸통부(210); 라이닝 콘크리트의 타설을 위하여, 터널의 내면에 인접하여 위치할 수 있도록, 상기 몸통부(210)의 외측에 설치됨과 아울러, 천정부에 진동봉 관통공(221)이 형성된 몰드부(220); 상기 몰드부(220)의 천정부의 상부에 타설된 프레쉬 콘크리트를 진동다짐하도록, 상기 몰드부(220)의 진동봉 관통공(221)에 결합한 상기 진동다짐장치(100);를 포함하는 것을 특징으로 하는 터널 라이닝 콘크리트용 거푸집 장치(200)를 제시한다.The present invention relates to a molding apparatus (200) for tunnel lining concrete using the vibration compaction apparatus (100), comprising: a body portion (210) formed to be movable along a longitudinal direction of a tunnel; A mold part 220 installed on the outer side of the body part 210 so as to be positioned adjacent to the inner surface of the tunnel for pouring the lining concrete and having a vibration hole 221 in the ceiling part; And the vibrating compaction apparatus 100 coupled to the vibration hole 221 of the mold unit 220 so as to vibrate the fresh concrete laid on the top of the ceiling of the mold unit 220. [ A concrete lining 200 for a tunnel lining concrete is proposed.

상기 진동봉 관통공(221)의 하측 주위부와, 상기 진동다짐장치(100)의 연장부(140)의 상단 주위부는 용접결합한 것이 바람직하다.It is preferable that the lower peripheral portion of the vibration hole 221 is welded to the upper peripheral portion of the extension portion 140 of the vibration-

상기 진동봉 관통공(221)의 하측 주위부와, 상기 진동다짐장치(100)의 연장부(140)의 상단 주위부에는 보강리브(230)가 설치된 것이 바람직하다.It is preferable that a reinforcing rib 230 is installed on a lower peripheral portion of the vibration hole 221 and an upper peripheral portion of the extension portion 140 of the vibration-

본 발명은 상기 거푸집 장치(200)를 이용한 터널 라이닝 콘크리트의 시공방법으로서, 터널의 일지점에 상기 거푸집 장치(200)를 위치시키는 단계; 상기 거푸집 장치(200)에 의해 라이닝 콘크리트를 타설하는 타설단계; 상기 진동다짐장치(100)의 구동부(150)에 의해 상기 진동인가부(120)를 상향구동하여 상기 진동봉(130)의 상부가 프레쉬 콘크리트 상태의 상기 라이닝 콘크리트에 매설되도록 하여 진동다짐을 하는 진동다짐단계; 진동다짐 후, 상기 진동다짐장치(100)의 상기 구동부(150)에 의해 상기 진동인가부(120)를 하향구동하여 상기 진동봉(130)의 상부가 상기 라이닝 콘크리트로부터 이탈하도록 하는 진동봉 이탈단계; 상기 터널의 일지점에 대한 상기 라이닝 콘크리트의 양생 후, 상기 거푸집 장치(200)를 이동하여 터널의 타지점에 상기 거푸집 장치(200)를 위치시키는 단계; 상기 터널의 타지점에 대하여 상기 타설단계, 진동다짐단계, 진동봉 이탈단계를 반복실시하는 단계;를 포함하는 것을 특징으로 하는 터널 라이닝 콘크리트의 시공방법을 제시한다.A method of constructing a tunnel lining concrete using the molding machine (200), the method comprising: positioning the molding machine (200) at one point of a tunnel; A casting step of casting the lining concrete by the molding machine 200; The vibration applying unit 120 is driven upward by the driving unit 150 of the vibration compaction apparatus 100 so that the upper portion of the vibration rod 130 is buried in the lining concrete in the fresh concrete state, Compaction step; The vibration applying unit 120 is driven downward by the driving unit 150 of the vibration compaction apparatus 100 so that the upper portion of the vibration bar 130 is separated from the lining concrete ; Moving the molding machine (200) after the curing of the lining concrete to one point of the tunnel to position the molding machine (200) at another point of the tunnel; And repeating the pouring step, the vibrating compaction step, and the step of releasing the pivoting of the tunnel at another point of the tunnel.

본 발명은 터널의 라이닝 콘크리트의 천정부에 대한 진동다짐을 실시할 수 있도록 하여, 양생 후 균열의 발생을 방지할 수 있는 터널 천정부 라이닝 콘크리트의 진동다짐장치 및 이를 이용한 터널 라이닝 콘크리트용 거푸집 장치를 제시한다.The present invention proposes a vibrating compaction apparatus for a tunnel lining lining concrete and a tunnel lining concrete formwork apparatus using the same for preventing vibrations of the lining concrete of the tunnel from being generated after curing .

도 1은 종래의 터널의 거푸집 장치의 종단면도.
도 2 이하는 본 발명의 실시예를 도시한 것으로서,
도 2는 터널의 거푸집 장치의 종단면도.
도 3은 터널의 거푸집 장치의 횡단면도.
도 4는 진동다짐장치의 제1 사용상태의 단면도.
도 5는 진동다짐장치의 제2 사용상태의 단면도.
도 6은 진동다짐장치의 사시도.
1 is a longitudinal cross-sectional view of a conventional tunnel forming apparatus.
2 shows an embodiment of the present invention,
2 is a longitudinal sectional view of a molding apparatus of a tunnel.
3 is a cross-sectional view of a molding device of a tunnel.
4 is a cross-sectional view of the first use state of the vibration damping apparatus;
5 is a cross-sectional view of a second use state of the vibration dampening device;
6 is a perspective view of the vibration compaction apparatus;

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 2 이하에 도시된 바와 같이, 본 발명은 기본적으로 거푸집 장치(200)에 의한 터널의 라이닝 콘크리트 타설작업 중 천정부를 진동다짐하기 위한 장치(100)에 관한 것이다.As shown in FIG. 2 and subsequent drawings, the present invention basically relates to an apparatus 100 for vibrating a ceiling portion of a lining concrete installation work of a tunnel by a formwork device 200.

이는 관 구조의 본체(110); 본체(110)의 내부에 상하방향을 따라 구동가능하도록 설치된 진동인가부(120)(예컨대 에어 바이브레이터); 진동인가부(120)에 의해 진동함과 아울러, 상부가 굳지 않은 상태의 라이닝 콘크리트에 매설될 수 있도록 진동인가부(120)의 상부에 설치된 진동봉(130); 상단이 거푸집 장치(200)의 몰드부(220)의 천정부에 형성된 진동봉 관통공(221)에 결합하고, 하단이 본체(110)의 상단에 결합하며, 내부에 진동봉(130)이 상하구동가능하도록 설치된 연장부(140); 진동인가부(120)의 상하구동을 가능하게 하도록 상기 본체(110)에 설치된 구동부(150);를 포함하여 구성된다(도 4 내지 6).Which comprises a body 110 of tubular structure; A vibration applying unit 120 (for example, an air vibrator) installed so as to be able to drive along the vertical direction inside the main body 110; A vibration bar 130 installed on the upper portion of the vibration applying unit 120 so that the vibration applying unit 120 vibrates and the upper part of the lining concrete can be embedded in the unhardened lining concrete; The upper end is coupled to the vibration hole 221 formed in the ceiling portion of the mold unit 220 of the molding machine 200 and the lower end thereof is coupled to the upper end of the body 110, An extension part 140 installed to be able to be installed; And a driving unit 150 installed on the main body 110 to enable the vibration applying unit 120 to be driven up and down (FIGS. 4 to 6).

터널 천정부 라이닝 콘크리트 타설작업 중에는, 구동부(150)에 의해 진동인가부(120)가 상향구동하여 진동봉(130)의 상부가 굳지 않은 상태의 라이닝 콘크리트에 매설되어 진동다짐을 한다.Tunnel ceiling lining During the concrete pouring operation, the vibration applying unit 120 is driven upward by the driving unit 150, and the upper part of the vibration rod 130 is buried in the unlit lining concrete to vibrate.

터널 천정부 라이닝 콘크리트 타설작업 후에는, 구동부(150)에 의해 진동인가부(120)가 하향구동하여 진동봉(130)의 상부가 라이닝 콘크리트로부터 이탈한다.After the tunnel ceiling lining concrete pouring operation, the vibration applying part 120 is driven downward by the driving part 150, and the upper part of the vibration rod 130 is separated from the lining concrete.

본 발명에 의한 진동다짐장치(100)를 이용한 터널 라이닝 콘크리트용 거푸집 장치(200)는, 터널의 길이방향을 따라 바퀴나 레일에 의해 이동가능하도록 형성된 몸통부(210); 라이닝 콘크리트의 타설을 위하여, 터널의 내면에 인접하여 위치할 수 있도록, 몸통부(210)의 외측에 설치됨과 아울러, 천정부에 진동봉 관통공(221)이 형성된 몰드부(220); 몰드부(220)의 천정부의 상부에 타설된 프레쉬 콘크리트를 진동다짐하도록, 몰드부(220)의 진동봉 관통공(221)에 결합한 진동다짐장치(100);를 포함하여 구성된다.A tunnel-lining concrete formwork apparatus 200 using a vibration compaction apparatus 100 according to the present invention includes a body 210 formed to be movable by a wheel or a rail along a longitudinal direction of a tunnel; A mold part 220 installed on the outside of the body part 210 so as to be positioned adjacent to the inner surface of the tunnel for pouring the lining concrete and having vibration hole 221 in the ceiling part; And a vibrating compaction apparatus 100 coupled to the vibration hole 221 of the mold unit 220 so as to vibrate the fresh concrete laid on the top of the ceiling of the mold unit 220.

즉, 거푸집 장치(200)의 몰드부(220)의 천정부에 필요한 수만큼의 진동다짐장치(100)가 설치된다(도 2,3).That is, as many vibrating compaction apparatuses 100 as required are installed on the ceiling portion of the mold unit 220 of the molding apparatus 200 (FIGS.

이러한 거푸집 장치(200)를 이용한 터널 라이닝 콘크리트의 시공방법은 다음 공정에 의해 이루어진다.The method of constructing the tunnel lining concrete using the molding machine 200 is performed by the following process.

터널의 일지점에 거푸집 장치(200)를 위치시키고, 거푸집 장치(200)에 의해 라이닝 콘크리트를 타설한다(도 2).The molding machine 200 is positioned at one point of the tunnel and the lining concrete is poured by the molding machine 200 (FIG. 2).

진동다짐장치(100)의 구동부(150)에 의해 진동인가부(120)를 상향구동하여 진동봉(130)의 상부가 프레쉬 콘크리트 상태의 라이닝 콘크리트에 매설되도록 하여 진동다짐을 실시한다(도 4).The vibration applying unit 120 is driven upward by the driving unit 150 of the vibration damping apparatus 100 so that the upper portion of the vibration rod 130 is buried in the lining concrete in the fresh concrete state to perform vibration damping (FIG. 4) .

진동다짐 후, 진동다짐장치(100)의 구동부(150)에 의해 진동인가부(120)를 하향구동하여 진동봉(130)의 상부가 상기 라이닝 콘크리트로부터 이탈하도록 한다(도 5).The vibration applying unit 120 is driven downward by the driving unit 150 of the vibration compaction apparatus 100 so that the upper portion of the vibration rod 130 is separated from the lining concrete.

터널의 일지점에 대한 라이닝 콘크리트의 양생 후, 거푸집 장치(200)를 이동하여 터널의 타지점에 거푸집 장치(200)를 위치시킨 후, 터널의 타지점에 대하여 상기 타설단계, 진동다짐단계, 진동봉 이탈단계를 반복실시한다(도 3).After the curing of the lining concrete with respect to one point of the tunnel, the molding apparatus 200 is moved to the other point of the tunnel to position the molding apparatus 200 at another point of the tunnel, and then the pouring step, The enclosing release step is repeated (FIG. 3).

즉, 본 발명은 진동다짐장치(100)를 거푸집 장치(200)의 몰드부(220)의 천정부의 관통공(221)에 고정해 두고, 진동다짐이 필요한 경우에는 진동인가부(120)를 상향구동하여 진동봉(130)의 상부가 프레쉬 콘크리트 상태의 라이닝 콘크리트에 매설되도록 하여 진동다짐을 실시하는 한편, 진동다짐을 마치면 진동다짐장치(100)의 구동부(150)에 의해 진동인가부(120)를 하향구동하여 진동봉(130)의 상부가 라이닝 콘크리트로부터 이탈하도록 하고 거푸집 장치(200)를 이동하여 다음 구간의 작업을 하도록 한 것이다.That is, according to the present invention, the vibration damping apparatus 100 is fixed to the through hole 221 of the ceiling portion of the mold unit 220 of the molding apparatus 200, and when the vibration damping is required, The vibrating unit 120 is driven by the driving unit 150 of the vibration damping apparatus 100 after the vibrating compaction is completed, while the upper part of the vibrating rod 130 is driven to be embedded in the lining concrete in the fresh concrete state, So that the upper portion of the vibrating shaft 130 is separated from the lining concrete, and the worker 200 is moved to perform work of the next section.

몰드부(220)의 천정부의 관통공(221)에 진동다짐장치(100)가 고정된 상태로 설치되므로, 타설된 콘크리트가 관통공(221)을 통해 쏟아질 우려가 없고, 진동인가부(120) 및 진동봉(130)이 상하구동하므로, 진동다짐이 필요한 경우에는 상향구동하여 진동다짐을 실시하고, 진동다짐을 마친 후에는 하향구동하여 거푸집 장치의 이동을 가능하게 한다.Since the vibrating compaction apparatus 100 is installed in the through hole 221 of the ceiling portion of the mold unit 220 so that the poured concrete is not likely to be poured through the through hole 221, And the vibrating rod 130 are driven up and down. Therefore, when vibration compaction is required, the vibrating compaction is carried out in an upward direction, and after the vibration compaction is completed, the molding apparatus can be moved downward by driving downward.

따라서 종래와 달리 터널의 라이닝 콘크리트의 천정부에 대한 진동다짐을 가능하게 하므로, 그 부위의 재료의 분리를 방지할 수 있어 양생 후 균열의 발생을 방지할 수 있다는 효과가 있다.Therefore, unlike the prior art, since the lining concrete of the tunnel enables vibration compaction of the ceiling portion, it is possible to prevent the material of the lining concrete from being separated, thereby preventing the occurrence of cracks after curing.

이하, 본 발명의 구체적 구성에 관하여 설명한다.Hereinafter, a specific configuration of the present invention will be described.

구동부(150)는 고정된 본체(110)에 대하여 진동인가부(120) 및 진동봉(130)을 상하구동할 수 있는 구조이면 어느 것이나 관계없다.The driving unit 150 is not limited to a structure that can vertically drive the vibration applying unit 120 and the vibration bar 130 with respect to the fixed body 110.

진동인가부(120)의 하부에 설치된 연장봉(151); 연장봉(151)의 하부가 본체(110)의 하측으로 노출되도록, 본체(110)의 하단에 형성된 설치공(152);을 포함하는 구성을 취하는 경우, 본체(110)의 하측으로 노출된 연장봉(151)을 상하구동함으로써 진동인가부(120)의 상하구동을 쉽게 할 수 있다(도 4,5).An extension rod 151 provided below the vibration applying unit 120; And an installation hole 152 formed at the lower end of the main body 110 so that the lower portion of the extension rod 151 is exposed to the lower side of the main body 110. In this case, By vertically driving the rod 151, the vibration applying unit 120 can be easily moved up and down (Figs. 4 and 5).

설치공(152)에는 암나사부가 형성되고, 연장봉(151)에는 숫나사부가 형성되며, 연장봉(151)의 나사회전구동에 의해 진동인가부(120)가 상하구동하는 구성을 취하는 경우, 손잡이(153) 등에 의해 진동인가부(120)의 상하구동을 안정적으로 쉽게 수행할 수 있다는 점, 원하는 높이에서 진동인가부(120)가 안정적으로 위치하도록 할 수 있다는 점 등의 장점이 있다(도 4,5).In the case where the mounting hole 152 is formed with a female screw portion and a male screw portion is formed on the extending rod 151 and the vibration applying portion 120 is vertically driven by screw rotation driving of the extending rod 151, The vibration applying unit 120 can be stably and easily moved up and down by the vibration applying unit 120 and the vibration applying unit 120 can be stably positioned at a desired height, 5).

본체(110)는, 내부에 상기 진동인가부(120)가 상하구동가능하도록 설치된 가이드관(111); 가이드관(111)의 하단에 일체로 형성됨과 아울러, 심부에 연장봉(151)의 관통공이 형성된 본체 하부 플랜지(112); 하부 플랜지의 하부에 볼트결합함과 아울러, 심부에 설치공(152)이 형성된 폐쇄판(113);을 포함하는 구성을 취할 수 있다.The main body 110 includes a guide tube 111 installed inside the vibration applying part 120 so as to be vertically movable; A body lower flange 112 integrally formed at the lower end of the guide tube 111 and having a through hole of an extension rod 151 at a deep portion thereof; And a closure plate 113 having a bolt coupling at the lower part of the lower flange and an installation hole 152 at the core part.

이는 본체 하부 플랜지(112)와 폐쇄판(113)의 분리 또는 결합에 의해, 에어 바이브레이터와 같은 진동인가부(120)의 설치, 교체, 유지관리 등을 쉽게 할 수 있다는 장점이 있다.This is advantageous in that installation, replacement, maintenance, and the like of the vibration applying unit 120 such as an air vibrator can be easily performed by separating or coupling the main body lower flange 112 and the closing plate 113.

몰드부(220)의 진동봉 관통공(221)을 통한 라이닝 콘크리트의 이탈을 방지하기 위해서는, 진동봉 관통공(221)의 하측 주위부와, 진동다짐장치(100)의 연장부(140)의 상단 주위부가 견고한 용접결합구조를 취하는 것이 바람직하다.The lower peripheral portion of the vibration transmitting through hole 221 and the lower peripheral portion of the extension portion 140 of the vibration damping apparatus 100 may be formed in the same manner as the above- It is preferable that the upper peripheral portion has a solid welded structure.

진동봉 관통공(221)의 하측 주위부와, 진동다짐장치(100)의 연장부(140)의 연장관(141)의 상단 주위부에는 보강리브(230)가 설치되는 경우, 몰드부(220)와 연장관(141)의 결합구조의 파손에 의해 진동봉 관통공(221)을 통한 라이닝 콘크리트의 이탈이 발생하는 것을 방지할 수 있다는 장점이 있다.When the reinforcing rib 230 is provided on the lower peripheral portion of the vibration hole 221 and the upper peripheral portion of the extension pipe 141 of the extension portion 140 of the vibration damping device 100, It is possible to prevent the loss of the lining concrete through the vibration hole 221 by the breakage of the coupling structure of the extension pipe 141 and the extension pipe 141.

본체(110)는, 내부에 진동인가부(120)가 상하구동가능하도록 설치된 가이드관(111); 가이드관(111)의 상단에 일체로 형성됨과 아울러, 심부에 진동봉(130)의 관통공이 형성된 본체 상부 플랜지(114);를 포함하는 구성을 취할 수 있다.The main body 110 includes a guide tube 111 installed inside the vibration applying part 120 so as to be vertically movable; And a body upper flange 114 integrally formed on the upper end of the guide pipe 111 and having a penetration hole of the swinging rod 130 formed in a deep portion thereof.

이와 아울러, 연장부(140)는, 상단이 거푸집 장치(200)의 몰드부(220)의 천정부에 형성된 진동봉 관통공(221)에 결합하고, 내부에 진동봉(130)이 상하구동가능하도록 설치된 연장관(141); 연장관(141)의 하단에 일체로 형성됨과 아울러, 본체 상부 플랜지(114)의 상부에 볼트결합하고, 심부에 진동봉(130)의 관통공이 형성된 연장부 하부 플랜지(142);를 포함하는 구성을 취할 수 있다.The extension part 140 is coupled to the vibration hole 221 formed in the ceiling part of the mold part 220 of the molding device 200 so that the vibration rod 130 can be vertically driven An installed extension pipe 141; And an extension lower flange 142 integrally formed at the lower end of the extension pipe 141 and bolt-connected to the upper portion of the upper flange 114 of the main body and having a through hole of the vibration bar 130 formed at the center thereof I can take it.

연장부(140)의 연장관(141)의 상단은 몰드부(220)에 용접결합 등에 의해 고정되는데, 위와 같은 구성을 취하는 경우, 연장부(140)와 본체(110)의 분리 또는 결합을 쉽게 할 수 있으므로, 장치의 설치, 부품의 교체, 청소와 같은 유지관리 등을 쉽게 할 수 있다는 장점이 있다.The upper end of the extension pipe 141 of the extension part 140 is fixed to the molded part 220 by welding or the like. When the above configuration is adopted, the extension part 140 and the main body 110 can be easily separated Therefore, there is an advantage that maintenance such as installation of the apparatus, replacement of parts, and cleaning can be easily performed.

진동인가부(120)(에어 바이브레이터)는, 압력(공기압)을 공급하기 위한 공급구(121); 압력(공기압)을 배출하기 위한 배출구(122);를 구비하는데, 본체(110)의 측벽에 상하구동하는 진동인가부(120)의 공급구(121) 및 배출구(122)가 외부로 노출되도록(공급관과 연결되어야 하므로) 상하방향 장공 구조의 노출공(115)이 형성되는 것이 바람직하다.The vibration applying section 120 (air vibrator) includes a supply port 121 for supplying pressure (air pressure); The supply port 121 and the discharge port 122 of the vibration applying unit 120 which are vertically driven on the side wall of the main body 110 are exposed to the outside It is preferable to form an exposure hole 115 having a longitudinally elongated hole structure.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.

100 : 진동다짐장치 110 : 본체
111 : 가이드관 112 : 본체 하부 플랜지
113 : 폐쇄판 114 : 본체 상부 플랜지
115 : 노출공 120 : 진동인가부
121 : 공급구 122 : 배출구
130 : 진동봉 140 : 연장부
141 : 연장관 142 : 연장부 하부 플랜지
150 : 구동부 151 : 연장봉
152 : 설치공 200 : 거푸집 장치
210 : 몸통부 220 : 몰드부
221 : 진동봉 관통공 230 : 보강리브
100: Vibrating compaction device 110:
111: Guide tube 112: Lower flange of the main body
113: closing plate 114: upper body flange
115: Exposure hole 120: Vibration applying part
121: supply port 122:
130: vibrating shaft 140: extension part
141: extension pipe 142: extension part lower flange
150: driving part 151: extension rod
152: installation hole 200: formwork device
210: body part 220:
221: a vibration penetrating hole 230: a reinforcing rib

Claims (10)

거푸집 장치(200)에 의한 터널의 라이닝 콘크리트 타설작업 중 천정부를 진동다짐하기 위한 장치로서,
관 구조의 본체(110);
상기 본체(110)의 내부에 상하방향을 따라 구동가능하도록 설치된 진동인가부(120);
상기 진동인가부(120)에 의해 진동함과 아울러, 상부가 굳지 않은 상태의 상기 라이닝 콘크리트에 매설될 수 있도록 상기 진동인가부(120)의 상부에 설치된 진동봉(130);
상단이 상기 거푸집 장치(200)의 몰드부(220)의 천정부에 형성된 진동봉 관통공(221)에 결합하고, 하단이 상기 본체(110)의 상단에 결합하며, 내부에 상기 진동봉(130)이 상하구동가능하도록 설치된 연장부(140);
상기 진동인가부(120)의 상하구동을 가능하게 하도록 상기 본체(110)에 설치된 구동부(150);를 포함하고,
터널 천정부 라이닝 콘크리트 타설작업 중에는, 상기 구동부(150)에 의해 상기 진동인가부(120)가 상향구동하여 상기 진동봉(130)의 상부가 굳지 않은 상태의 상기 라이닝 콘크리트에 매설되어 진동다짐을 하고,
터널 천정부 라이닝 콘크리트 타설작업 후에는, 상기 구동부(150)에 의해 상기 진동인가부(120)가 하향구동하여 상기 진동봉(130)의 상부가 상기 라이닝 콘크리트로부터 이탈하는 것을 특징으로 하는 터널 천정부 라이닝 콘크리트의 진동다짐장치(100).
A lining of a tunnel by a formwork device (200) An apparatus for vibrating a ceiling portion during concrete pouring work,
A tubular structure body 110;
A vibration applying unit 120 installed in the main body 110 so as to be able to move along a vertical direction;
A vibration bar (130) installed on the vibration applying part (120) so that the vibration applying part (120) vibrates and the upper part is buried in the unhardened lining concrete;
And a lower end of the upper end is coupled to an upper end of the main body 110. The upper end of the vibration rod 130 is coupled to the upper end of the main body 110, An extension part 140 installed to be movable up and down;
And a driving unit 150 installed in the main body 110 to enable the vibration applying unit 120 to be driven up and down,
During the operation of installing the tunnel ceiling lining concrete, the vibration applying unit 120 is driven upward by the driving unit 150 so that the upper part of the vibration rod 130 is buried in the lining concrete in an uncured state,
Tunnel ceiling lining After the concrete pouring operation, the vibration applying part 120 is driven downward by the driving part 150 so that the upper part of the vibration rod 130 is separated from the lining concrete. (100).
제1항에 있어서,
상기 구동부(150)는,
상기 진동인가부(120)의 하부에 설치된 연장봉(151);
상기 연장봉(151)의 하부가 상기 본체(110)의 하측으로 노출되도록, 상기 본체(110)의 하단에 형성된 설치공(152);을
포함하는 것을 특징으로 하는 터널 천정부 라이닝 콘크리트의 진동다짐장치(100).
The method according to claim 1,
The driving unit 150 includes:
An extension rod 151 installed at a lower portion of the vibration applying unit 120;
An installation hole 152 formed at a lower end of the main body 110 so that a lower portion of the extension rod 151 is exposed to the lower side of the main body 110;
(100) of the tunnel lining lining concrete.
제2항에 있어서,
상기 설치공(152)에는 암나사부가 형성되고,
상기 연장봉(151)에는 숫나사부가 형성되며,
상기 연장봉(151)의 나사회전구동에 의해 상기 진동인가부(120)가 상하구동하는 것을 특징으로 하는 터널 천정부 라이닝 콘크리트의 진동다짐장치(100).
3. The method of claim 2,
The installation hole 152 is formed with a female screw,
A male screw portion is formed on the extension rod 151,
Wherein the vibration applying unit (120) is driven up and down by the screw rotation driving of the extension rod (151).
제3항에 있어서,
상기 본체(110)는,
내부에 상기 진동인가부(120)가 상하구동가능하도록 설치된 가이드관(111);
상기 가이드관(111)의 하단에 일체로 형성됨과 아울러, 심부에 상기 연장봉(151)의 관통공이 형성된 본체 하부 플랜지(112);
상기 하부 플랜지의 하부에 볼트결합함과 아울러, 심부에 상기 설치공(152)이 형성된 폐쇄판(113);을
포함하는 것을 특징으로 하는 터널 천정부 라이닝 콘크리트의 진동다짐장치(100).
The method of claim 3,
The main body (110)
A guide pipe 111 installed inside the vibration applying unit 120 so as to be vertically movable;
A body lower flange 112 integrally formed at a lower end of the guide tube 111 and having a through hole of the extension rod 151 at a deep portion thereof;
A closure plate 113 having a bolt coupling at a lower portion of the lower flange and a mounting hole 152 formed at a center portion thereof;
(100) of the tunnel lining lining concrete.
제1항에 있어서,
상기 본체(110)는,
내부에 상기 진동인가부(120)가 상하구동가능하도록 설치된 가이드관(111);
상기 가이드관(111)의 상단에 일체로 형성됨과 아울러, 심부에 상기 진동봉(130)의 관통공이 형성된 본체 상부 플랜지(114);를 포함하고,
상기 연장부(140)는,
상단이 상기 거푸집 장치(200)의 몰드부(220)의 천정부에 형성된 진동봉 관통공(221)에 결합하고, 내부에 상기 진동봉(130)이 상하구동가능하도록 설치된 연장관(141);
상기 연장관(141)의 하단에 일체로 형성됨과 아울러, 상기 본체 상부 플랜지(114)의 상부에 볼트결합하고, 심부에 상기 진동봉(130)의 관통공이 형성된 연장부 하부 플랜지(142);를
포함하는 것을 특징으로 하는 터널 천정부 라이닝 콘크리트의 진동다짐장치(100).
The method according to claim 1,
The main body (110)
A guide pipe 111 installed inside the vibration applying unit 120 so as to be vertically movable;
And a body upper flange 114 integrally formed on the upper end of the guide tube 111 and having a through hole of the vibration bar 130 formed at a deep portion thereof,
The extension (140)
An upper end coupled to the vibration hole 221 formed in the ceiling portion of the mold unit 220 of the molding apparatus 200 and having an extension pipe 141 installed therein so that the vibration rod 130 can be driven up and down;
An extension lower flange 142 integrally formed at the lower end of the extension pipe 141 and bolted to the upper portion of the main body upper flange 114 and having a through hole of the vibration bar 130 formed at the center thereof;
(100) of the tunnel lining lining concrete.
제1항에 있어서,
상기 진동인가부(120)는,
압력을 공급하기 위한 공급구(121);
압력을 배출하기 위한 배출구(122);를 구비하고,
상기 본체(110)의 측벽에는, 상하구동하는 상기 진동인가부(120)의 공급구(121) 및 배출구(122)가 외부로 노출되도록 상하방향 장공 구조의 노출공(115)이 형성된 것을 특징으로 하는 터널 천정부 라이닝 콘크리트의 진동다짐장치(100).
The method according to claim 1,
The vibration applying unit 120 includes:
A supply port 121 for supplying pressure;
And an outlet (122) for discharging the pressure,
The side wall of the main body 110 is formed with an exposure hole 115 having a vertical elongated hole structure so that the supply port 121 and the discharge port 122 of the vibration applying unit 120 to be vertically driven are exposed to the outside. A vibrating compaction apparatus for a tunnel ceiling lining concrete (100).
제1항 내지 제6항 중 어느 한 항의 진동다짐장치(100)를 이용한 터널 라이닝 콘크리트용 거푸집 장치(200)로서,
터널의 길이방향을 따라 이동가능하도록 형성된 몸통부(210);
라이닝 콘크리트의 타설을 위하여, 터널의 내면에 인접하여 위치할 수 있도록, 상기 몸통부(210)의 외측에 설치됨과 아울러, 천정부에 진동봉 관통공(221)이 형성된 몰드부(220);
상기 몰드부(220)의 천정부의 상부에 타설된 프레쉬 콘크리트를 진동다짐하도록, 상기 몰드부(220)의 진동봉 관통공(221)에 결합한 상기 진동다짐장치(100);를
포함하는 것을 특징으로 하는 터널 라이닝 콘크리트용 거푸집 장치(200).
A tunnel-lining concrete formwork apparatus (200) using the vibration-tightening apparatus (100) according to any one of claims 1 to 6,
A body 210 formed to be movable along the longitudinal direction of the tunnel;
A mold part 220 installed on the outer side of the body part 210 so as to be positioned adjacent to the inner surface of the tunnel for pouring the lining concrete and having a vibration hole 221 in the ceiling part;
The vibrating compaction apparatus 100 coupled to the vibration hole 221 of the mold unit 220 so as to vibrate the fresh concrete laid on the top of the ceiling of the mold unit 220;
(200) for a tunnel lining concrete.
제7항에 있어서,
상기 진동봉 관통공(221)의 하측 주위부와, 상기 진동다짐장치(100)의 연장부(140)의 상단 주위부는 용접결합한 것을 특징으로 하는 터널 라이닝 콘크리트용 거푸집 장치(200).
8. The method of claim 7,
The lower peripheral portion of the vibration hole 221 is welded to the upper peripheral portion of the extension portion 140 of the vibration damping device 100.
제7항에 있어서,
상기 진동봉 관통공(221)의 하측 주위부와, 상기 진동다짐장치(100)의 연장부(140)의 상단 주위부에는 보강리브(230)가 설치된 것을 특징으로 하는 터널 라이닝 콘크리트용 거푸집 장치(200).
8. The method of claim 7,
Wherein a reinforcing rib (230) is installed on a lower peripheral portion of the vibration hole (221) and an upper peripheral portion of an extension portion (140) of the vibration damping apparatus (100) 200).
제7항의 거푸집 장치(200)를 이용한 터널 라이닝 콘크리트의 시공방법으로서,
터널의 일지점에 상기 거푸집 장치(200)를 위치시키는 단계;
상기 거푸집 장치(200)에 의해 라이닝 콘크리트를 타설하는 타설단계;
상기 진동다짐장치(100)의 구동부(150)에 의해 상기 진동인가부(120)를 상향구동하여 상기 진동봉(130)의 상부가 프레쉬 콘크리트 상태의 상기 라이닝 콘크리트에 매설되도록 하여 진동다짐을 하는 진동다짐단계;
진동다짐 후, 상기 진동다짐장치(100)의 상기 구동부(150)에 의해 상기 진동인가부(120)를 하향구동하여 상기 진동봉(130)의 상부가 상기 라이닝 콘크리트로부터 이탈하도록 하는 진동봉 이탈단계;
상기 터널의 일지점에 대한 상기 라이닝 콘크리트의 양생 후, 상기 거푸집 장치(200)를 이동하여 터널의 타지점에 상기 거푸집 장치(200)를 위치시키는 단계;
상기 터널의 타지점에 대하여 상기 타설단계, 진동다짐단계, 진동봉 이탈단계를 반복실시하는 단계;를
포함하는 것을 특징으로 하는 터널 라이닝 콘크리트의 시공방법.
A method of constructing a tunnel lining concrete using the dies (200) of claim 7,
Positioning the molding machine (200) at one point in the tunnel;
A casting step of casting the lining concrete by the molding machine 200;
The vibration applying unit 120 is driven upward by the driving unit 150 of the vibration compaction apparatus 100 so that the upper portion of the vibration rod 130 is buried in the lining concrete in the fresh concrete state, Compaction step;
The vibration applying unit 120 is driven downward by the driving unit 150 of the vibration compaction apparatus 100 so that the upper portion of the vibration bar 130 is separated from the lining concrete ;
Moving the molding machine (200) after the curing of the lining concrete to one point of the tunnel to position the molding machine (200) at another point of the tunnel;
Repeating the pouring step, vibration compaction step, and departure / departure step with respect to another point of the tunnel;
Wherein the method comprises the steps of:
KR1020170183918A 2017-12-29 2017-12-29 Vibrator for lining concrete of tunnel and mold apparatus using the same KR102105956B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170183918A KR102105956B1 (en) 2017-12-29 2017-12-29 Vibrator for lining concrete of tunnel and mold apparatus using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170183918A KR102105956B1 (en) 2017-12-29 2017-12-29 Vibrator for lining concrete of tunnel and mold apparatus using the same

Publications (2)

Publication Number Publication Date
KR20190081405A true KR20190081405A (en) 2019-07-09
KR102105956B1 KR102105956B1 (en) 2020-04-29

Family

ID=67261666

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170183918A KR102105956B1 (en) 2017-12-29 2017-12-29 Vibrator for lining concrete of tunnel and mold apparatus using the same

Country Status (1)

Country Link
KR (1) KR102105956B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112895153A (en) * 2021-01-15 2021-06-04 中建八局天津建设工程有限公司 Pouring and vibrating all-in-one machine and construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002235496A (en) * 2001-02-09 2002-08-23 Hazama Gumi Ltd Concrete compacting method by vibrator
JP2007138593A (en) * 2005-11-18 2007-06-07 Okumura Corp Placing method and compaction structure for tunnel lining concrete
KR101056249B1 (en) * 2011-03-07 2011-08-11 양현기 A structure for transporting the tunnel steel lining foam

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002235496A (en) * 2001-02-09 2002-08-23 Hazama Gumi Ltd Concrete compacting method by vibrator
JP2007138593A (en) * 2005-11-18 2007-06-07 Okumura Corp Placing method and compaction structure for tunnel lining concrete
KR101056249B1 (en) * 2011-03-07 2011-08-11 양현기 A structure for transporting the tunnel steel lining foam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112895153A (en) * 2021-01-15 2021-06-04 中建八局天津建设工程有限公司 Pouring and vibrating all-in-one machine and construction method thereof

Also Published As

Publication number Publication date
KR102105956B1 (en) 2020-04-29

Similar Documents

Publication Publication Date Title
CN110374630B (en) Construction method for concrete vibration of tunnel vault
JP5232040B2 (en) Tunnel construction method and formwork vibrator
JP2020023797A (en) Method for placing concrete used for lining on upper end portion of tunnel
KR100977560B1 (en) Side mold for tunnel lining form
KR102300325B1 (en) Wet-type hoolw pc member production apparatus using coorrugated tube and production method using the same
KR20190081405A (en) Vibrator for lining concrete of tunnel and mold apparatus using the same
CN110952995A (en) Construction method for external tunnel door post-cast ring beam
KR101730725B1 (en) System And Method For Concrete Composition Using Mobile Vibrator
JP7076363B2 (en) How to place tunnel lining concrete
JP3962472B2 (en) Method and apparatus for placing concrete for tunnel
JP7125056B2 (en) Tunnel repair method
JP4624243B2 (en) Tunnel lining concrete placing method and wife formwork device
CN114012887B (en) Casting method and device for precast concrete pipe culvert
KR200202341Y1 (en) A tunnel steel materials mold concrete operation equipment
KR100936997B1 (en) Side mold for tunnel lining form
KR20090020416A (en) Tunnel lining forms provided with apparatus for exhausting air and working method of tunnel lining
KR100380286B1 (en) A tunnel steel materials mold concrete operation equipment
JP2004124641A (en) Outer form for tunnel entrance, and construction method of tunnel entrance using the same
JP4815262B2 (en) Tunnel lining method and formwork apparatus
CN108442698B (en) Deformation joint split bolt pvc sleeve plugging method and plugging fixing sleeve
JPH0925724A (en) Concrete placing hopper
JP7329404B2 (en) Compaction method and apparatus for concrete in formwork
JP3773734B2 (en) Staircase construction method and apparatus
JP7437860B2 (en) Formwork equipment and column member manufacturing method
JP2011084909A (en) Lining concrete, lining concrete forming method, and tunnel lining device

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant