JP4557942B2 - Tunnel lining concrete placement method and placement structure - Google Patents

Tunnel lining concrete placement method and placement structure Download PDF

Info

Publication number
JP4557942B2
JP4557942B2 JP2006235199A JP2006235199A JP4557942B2 JP 4557942 B2 JP4557942 B2 JP 4557942B2 JP 2006235199 A JP2006235199 A JP 2006235199A JP 2006235199 A JP2006235199 A JP 2006235199A JP 4557942 B2 JP4557942 B2 JP 4557942B2
Authority
JP
Japan
Prior art keywords
hollow pipe
tunnel
lining
concrete
vibrator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2006235199A
Other languages
Japanese (ja)
Other versions
JP2008057211A (en
Inventor
章 岡田
芳男 竹知
憲三 水原
直美 鷲見
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP2006235199A priority Critical patent/JP4557942B2/en
Publication of JP2008057211A publication Critical patent/JP2008057211A/en
Application granted granted Critical
Publication of JP4557942B2 publication Critical patent/JP4557942B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

本発明は、トンネル覆工用型枠を用いて覆工コンクリートを形成するトンネル覆工コンクリート打設方法、及び該覆工コンクリート打設方法に用いるトンネル覆工コンクリート打設構造に関する。   The present invention relates to a tunnel lining concrete placing method for forming lining concrete using a tunnel lining formwork, and a tunnel lining concrete placing structure used for the lining concrete placing method.

例えば山岳トンネル工法等のトンネル工法において、掘削したトンネルの内周面の地山を覆って構築されるトンネル覆工コンクリートを形成するための方法として、トンネル覆工用型枠(コンクリート覆工用型枠)を用いる工法が一般的に採用されている。トンネル覆工用型枠50は、図9(a),(b)に示すように、例えば馬蹄形等のアーチ形状部分52を含む形状のトンネル53の内周面54に沿って、トンネル53の側壁部55から上部に亘って設置されるものであり、設置されたトンネル覆工用型枠50と、トンネル53の内周面54の吹き付けコンクリート56によって覆われる地山との間の空間部61に、好ましくは無筋コンクリートを打設して硬化させることにより、トンネル底部のインバート部51のコンクリートと連続させるようにして、覆工コンクリートが形成されることになる。   For example, in tunnel construction methods such as the mountain tunnel construction method, a tunnel lining formwork (concrete lining mold is used as a method for forming tunnel lining concrete that is constructed to cover the natural ground on the inner peripheral surface of the excavated tunnel. A method using a frame is generally employed. As shown in FIGS. 9 (a) and 9 (b), the tunnel lining formwork 50 is formed on the side wall of the tunnel 53 along the inner peripheral surface 54 of the tunnel 53 having a shape including an arch-shaped portion 52 such as a horseshoe shape. In the space 61 between the installed tunnel lining form 50 and the natural ground covered with the sprayed concrete 56 on the inner peripheral surface 54 of the tunnel 53 The lining concrete is formed so as to be continuous with the concrete of the inverted portion 51 at the bottom of the tunnel, preferably by placing and hardening unreinforced concrete.

また、トンネル覆工用型枠50としては、例えばパラセントルと呼ばれる組立式のトンネル覆工用型枠の他、スライドセントルと呼ばれる移動式のトンネル覆工用型枠が知られており、トンネル53の掘削作業の進行に伴なって、例えば10m程度の所定のスパン毎にトンネル覆工用型枠50を据え付け直しながら、トンネル53の掘進方向の後方から前方に向かって、トンネル覆工用型枠50を用いてトンネル53の側部及び上部の覆工コンクリートを順次打設形成して行くことになる。   Moreover, as the tunnel lining formwork 50, for example, in addition to the assembly type tunnel lining formwork called paracentle, a mobile tunnel lining formwork called slide centle is known. With the progress of the excavation work, the tunnel lining formwork 50 is moved from the rear to the front in the digging direction of the tunnel 53 while the tunnel lining formwork 50 is reinstalled every predetermined span of about 10 m, for example. Then, the side and upper lining concrete of the tunnel 53 is sequentially cast and formed.

そして、トンネル覆工用型枠50を用いてトンネルの側部及び上部の覆工コンクリートを打設するには、例えば図10(a)〜(d)に示すように、設置したトンネル覆工用型枠50に設けられた検査窓56からコンクリートを打設可能な高さ領域として、例えばトンネル53の側壁部55からアーチ形状部分52の肩部までの領域に対しては、検査窓56を介してコンクリート57を供給すると共に、バイブレータ58を検査窓56から挿入し、供給されたコンクリート57を締固めながらコンクリート57を打設する。しかる後に、検査窓56からコンクリート57を供給しながらバイブレータ58によって締固めることが困難な高さ領域として、トンネル53の冠部(クラウン部)59(図9参照)の領域に対しては、トンネル覆工用型枠50の天端部に設けた吹き上げ口としてのコンクリート打設孔60から、コンクリートを吹き上げ方式で打ち込み、締固めを行うことなく冠部59のコンクリート57を形成するパターンが採用されている。   And in order to cast the lining concrete of the side part and the upper part of the tunnel using the tunnel lining formwork 50, for example, as shown in FIGS. For example, an area from the side wall portion 55 of the tunnel 53 to the shoulder portion of the arch-shaped portion 52 is provided through the inspection window 56 as a height region where concrete can be placed from the inspection window 56 provided in the mold 50. The concrete 57 is supplied and the vibrator 58 is inserted from the inspection window 56, and the concrete 57 is placed while the supplied concrete 57 is compacted. After that, as a height region that is difficult to be compacted by the vibrator 58 while supplying the concrete 57 from the inspection window 56, the tunnel 53 (see FIG. 9) region of the tunnel 53 is referred to as a tunnel region. A pattern is used in which concrete is driven in by a blow-up method from a concrete casting hole 60 as a blow-up opening provided at the top end of the lining mold 50 and the concrete 57 of the crown 59 is formed without compaction. ing.

より具体的には、所定位置にトンネル覆工用型枠50を設置した後に、例えば側壁部55の下部より、下段の検査窓56を介してコンクリート57を流し込みながらバイブレータ58を用いて締固める工程(図10(a)参照)と、さらに側壁部55の上部のアーチ形状部分52に向かって、中段の検査窓56を介してコンクリート57を流し込みながらバイブレータ58を用いて締固める工程(図10(b)参照)と、さらにアーチ形状部分52の冠部59の手前まで、上段の検査窓56及び必要に応じてコンクリート打設孔60を介してコンクリート57を流し込みながら、バイブレータ58を用いて締固める工程(図10(c)参照)と、冠部59の既設覆工コンクリート62側の部分からコンクリート打設孔60を介して順次コンクリート57を流し込み、締固めを行うことなく妻型枠63までコンクリートを充填する工程(図10(d)参照)とにより、覆工コンクリートが打設されることになる。   More specifically, after the tunnel lining formwork 50 is installed at a predetermined position, for example, the concrete 57 is poured from the lower portion of the side wall portion 55 through the lower inspection window 56 and compacted using the vibrator 58. (See FIG. 10 (a)), and further, a step of compacting using the vibrator 58 while pouring the concrete 57 through the middle inspection window 56 toward the arch-shaped portion 52 at the upper part of the side wall 55 (FIG. 10 ( b)), and further to the front of the crown 59 of the arch-shaped portion 52, the concrete 57 is poured through the upper inspection window 56 and, if necessary, the concrete placement hole 60, and then compacted using the vibrator 58. The process (see FIG. 10C) and the concrete from the portion on the existing lining concrete 62 side of the crown portion 59 through the concrete placement hole 60 in order. It poured over preparative 57, by a step of filling concrete to wife formwork 63 without compaction (see FIG. 10 (d)), so that the lining concrete is pouring.

上述のような従来のトンネル覆工用型枠50を用いた覆工コンクリートの打設方法では、トンネル冠部(クラウン部)59に打設されたコンクリート57の締固めを行うことができないことから、当該冠部59における覆工コンクリートの品質上の信頼性が低くなり、特に既設覆工コンクリート62の付近では、エア溜まりや空洞が発生しやすくなる。また、吹き上げ口としてのコンクリート打設孔60から集中してトンネル覆工用型枠50と地山との間の空間61にコンクリート57が打設されるので、コンクリート57がコンクリート打設孔60から周囲に流れる際の軌跡が縞模様として覆工コンクリートの表面に残りやすくなり、仕上りが悪くなる。   With the conventional method for placing lining concrete using the tunnel lining formwork 50 as described above, the concrete 57 placed on the tunnel crown (crown) 59 cannot be compacted. The reliability of the lining concrete at the crown portion 59 is lowered, and in the vicinity of the existing lining concrete 62, air accumulation and cavities are likely to occur. Further, since the concrete 57 is placed in the space 61 between the tunnel lining formwork 50 and the natural ground in a concentrated manner from the concrete placing hole 60 as a blow-up opening, the concrete 57 is removed from the concrete placing hole 60. The trajectory when flowing to the surroundings tends to remain on the surface of the lining concrete as a striped pattern, resulting in poor finish.

これに対して、トンネル冠部に打設されたコンクリートの締固めを行うことができるようにする技術が開示されている(例えば、特許文献1参照)。特許文献1の覆工コンクリート打設方法では、山岳トンネル工法とは異なるシールド工法によってトンネルを築造する際に、セグメントとセントルとの間の空隙のクラウン部に、トンネル軸方向の略全長に亘って延伸する、断面L型のアングルを凹向きに吊り下げ固定してなるガイドレールと、ガイドレールに沿って動く棒状バイブレータとを設置しておき、既設側からクラウン部の空隙にコンクリートを棒状バイブレータで締固めつつ打設し、コンクリートの充填に伴って、棒状バイブレータをガイドレールに沿って既設側から妻板側に向けて移動させるようにしたものである。また、特許文献1の覆工コンクリート打設方法では、ガイドレールは例えば二次覆工コンクリートの段取筋を兼ねて設けられるようになっている。
特開2002−30893号公報
On the other hand, a technique is disclosed that enables the concrete placed in the tunnel crown to be compacted (see, for example, Patent Document 1). In the lining concrete placement method of Patent Document 1, when a tunnel is constructed by a shield method different from the mountain tunnel method, the crown portion of the gap between the segment and the centle extends over substantially the entire length in the tunnel axis direction. An extending guide rail with an L-shaped angle suspended in a concave direction and a rod-shaped vibrator that moves along the guide rail are installed, and concrete is placed in the gap in the crown portion from the existing side with a rod-shaped vibrator. It was cast while compacted, and the rod-shaped vibrator was moved along the guide rail from the existing side toward the end plate side as the concrete was filled. Moreover, in the lining concrete placement method of patent document 1, a guide rail is provided also as a setup line of secondary lining concrete, for example.
JP 2002-30893 A

しかしながら、特許文献1に記載のトンネルのクラウン部にコンクリートを打設する方法では、棒状バイブレータをトンネル軸方向に案内するL型のアングルからなるガイドレールを、コンクリート中に残置される埋殺し部材として、コンクリートの打設箇所におけるトンネルの軸方向の略全長に亘って予め設けておく必要があるため、段取筋等を設置することなく好ましくは無筋コンクリートを用いて覆工コンクリートが形成されるトンネル覆工用型枠による山岳トンネル等においては、その材料や施工に多くの無駄を生じることになる。   However, in the method of placing concrete on the crown portion of the tunnel described in Patent Document 1, a guide rail having an L-shaped angle that guides the rod-like vibrator in the tunnel axial direction is used as the burying member left in the concrete. Since it is necessary to provide the entire length of the tunnel in the axial direction of the tunnel in advance, the lining concrete is preferably formed by using unreinforced concrete without installing a setup bar or the like. In a mountain tunnel or the like using a tunnel lining formwork, a lot of waste is caused in its materials and construction.

また、特許文献1に記載の打設方法では、例えばクラウン部の空隙にコンクリートを供給するコンクリート打設孔の位置を取り替えつつ、棒状バイブレータを移動させながら新たに打設されたコンクリートをその都度締固めて行く場合には、コンクリート中に埋入されるバイブレータケーブルの長さがそれ程長くなく、バイブレータケーブルを牽引しつつ棒状バイブレータを移動させることが容易である。しかしながら、例えばコンクリートの打設箇所におけるクラウン部の空隙の全体にコンクリートを先行して充填打設した後に、既設覆工コンクリートの近傍部分に配置した棒状バイブレータを、当該打設箇所の略全長に亘ってコンクリート中に埋入されたバイブレータケーブルを介して、妻板側に牽引しながら移動させてコンクリートを締固めて行く場合には、バイブレータケーブルとコンクリートとの間に大きな摩擦力(付着力)を生じて、牽引時の引抜抵抗が過大となり、棒状バイブレータを移動できなくなったり、バイブレータケーブルに破断や損傷を生じるおそれがある。   Further, in the placing method described in Patent Document 1, for example, the concrete placed newly is tightened each time the rod-like vibrator is moved while changing the position of the concrete placing hole for supplying the concrete to the gap in the crown portion. When solidifying, the length of the vibrator cable embedded in the concrete is not so long, and it is easy to move the rod-like vibrator while pulling the vibrator cable. However, for example, after filling concrete in the entire gap of the crown portion at the concrete placement site, and then placing the rod-shaped vibrator disposed in the vicinity of the existing lining concrete, the rod-like vibrator is provided over substantially the entire length of the placement site. When the concrete is compacted by moving it while pulling it to the side of the end plate via the vibrator cable embedded in the concrete, a large frictional force (adhesive force) is generated between the vibrator cable and the concrete. As a result, the pulling resistance at the time of towing becomes excessive, and the rod-like vibrator cannot be moved, or the vibrator cable may be broken or damaged.

本発明は、このような従来の課題に着目してなされたものであり、材料や施工に多くの無駄を生じることなく、簡易な構成で、トンネル覆工用型枠を用いて形成される特にトンネル冠部の覆工コンクリートを効率良く効果的に締固めることができると共に、覆工空間の全長に亘ってコンクリートを充填打設した後に棒状バイブレータによってコンクリートを締固める場合でも、バイブレータケーブルを妻型枠側に牽引する際の引抜抵抗を効果的に抑制して、棒状バイブレータをスムーズに移動させることのできるトンネル覆工コンクリート打設方法及びトンネル覆工コンクリート打設構造を提供することを目的とする。   The present invention has been made paying attention to such a conventional problem, and is formed using a tunnel lining formwork with a simple configuration without causing much waste in materials and construction. It is possible to efficiently and effectively compact the lining concrete at the crown of the tunnel, and even when the concrete is compacted with a rod-shaped vibrator after filling the concrete over the entire length of the lining space, the vibrator cable can be An object of the present invention is to provide a tunnel lining concrete placing method and a tunnel lining concrete placing structure capable of effectively suppressing a pulling resistance when pulling to the frame side and moving a rod-shaped vibrator smoothly. .

本発明は、トンネル覆工用型枠を用いて覆工コンクリートを形成するトンネル覆工コンクリート打設方法において、既に形成された既設覆工コンクリートの端面と妻型枠とによって挟まれる、前記トンネル覆工用型枠の外周面とトンネル内周の覆工面との間の覆工空間に、外径の異なる複数の中空パイプからなり、外径の小さな方の中空パイプを外径の大きな方の中空パイプに順次スライド可能に挿入して全体の長さを伸縮可能とした多段中空パイプを、外径の小さな方の中空パイプを前記既設覆工コンクリート側に配設してトンネルの軸方向に伸ばした状態で取り付けると共に、棒状バイブレータを多段中空パイプの前記既設覆工コンクリート側の端部から飛び出させて配設し、且つ該棒状バイブレータの後端部分に後続するバイブレータケーブルを、前記多段中空パイプに内挿して前記妻型枠側に延設させ、当該妻型枠を貫通させて配設することにより前記妻型枠の外側から牽引可能とし、前記覆工空間にコンクリートを充填打設すると共に、前記棒状バイブレータを振動させながら前記バイブレータケーブルを牽引して、当該バイブレータケーブルが最も外径の小さな第1中空パイプに前記棒状バイブレータを飛び出させたまま係止された状態から、前記第1中空パイプを、次に外径の大きな第2中空パイプに、当該第1中空パイプが前記第2中空パイプに係止されるまで挿入し、さらに前記バイブレータケーブルを牽引して、前記第1中空パイプが挿入された前記第2中空パイプを、次に外径の大きな第3中空パイプに、当該第2中空パイプが前記第3中空パイプに係止されるまで挿入する工程を含み、前記覆工空間に充填打設されたコンクリートを、外径の小さな方の中空パイプを外径の大きな方の中空パイプに順次挿入して多段中空パイプを収縮させながら、前記既設覆工コンクリート側の部分から前記妻型枠側に向けて締固めてゆくトンネル覆工コンクリート打設方法を提供することにより、上記目的を達成したものである。   The present invention provides a tunnel lining concrete placement method for forming lining concrete using a tunnel lining formwork, wherein the tunnel covering is sandwiched between the end face of the already formed lining concrete and the end formwork. The lining space between the outer peripheral surface of the work form and the inner lining surface of the tunnel consists of a plurality of hollow pipes with different outer diameters. The hollow pipe with the smaller outer diameter is replaced with the hollow pipe with the larger outer diameter. A multi-stage hollow pipe that was slidably inserted into the pipe to expand and contract the entire length, and the hollow pipe with the smaller outer diameter was placed on the existing lining concrete side and extended in the axial direction of the tunnel A vibrator that is attached in a state and is disposed so as to protrude from the end of the existing lining concrete side of the multistage hollow pipe, and that follows the rear end portion of the vibrator. A cable is inserted into the multi-stage hollow pipe so as to extend toward the end form frame, and is arranged to penetrate the end form frame so that it can be pulled from the outside of the end form frame. Concrete is placed and filled, and the vibrator cable is pulled while vibrating the rod-like vibrator, and the vibrator cable is locked with the rod-like vibrator protruding to the first hollow pipe having the smallest outer diameter. Then, the first hollow pipe is inserted into the second hollow pipe having the next largest outer diameter until the first hollow pipe is locked to the second hollow pipe, and the vibrator cable is further pulled. The second hollow pipe into which the first hollow pipe is inserted is locked to a third hollow pipe having the next largest outer diameter, and the second hollow pipe is locked to the third hollow pipe. The concrete filled and laid in the lining space is inserted into the hollow pipe having the smaller outer diameter into the hollow pipe having the larger outer diameter while the multistage hollow pipe is contracted. The above object is achieved by providing a tunnel lining concrete placing method that compacts the existing lining concrete side portion toward the end formwork side.

また、本発明のトンネル覆工コンクリート打設方法によれば、前記バイブレータケーブルは、前記棒状バイブレータを前記多段中空パイプの前記既設覆工コンクリート側の端部から直線状に飛び出させた状態で、前記第1中空パイプの前記第2中空パイプ側の基端部において前記第1中空パイプに係止されることが好ましい。   Further, according to the tunnel lining concrete placing method of the present invention, the vibrator cable is a state in which the rod-like vibrator is protruded linearly from an end portion on the existing lining concrete side of the multistage hollow pipe, It is preferable that the base end portion of the first hollow pipe on the second hollow pipe side is locked to the first hollow pipe.

さらに、本発明のトンネル覆工コンクリート打設方法によれば、前記覆工空間は、トンネル冠部の覆工空間であることが好ましい。   Furthermore, according to the tunnel lining concrete placing method of the present invention, it is preferable that the lining space is a lining space of a tunnel crown.

そして、本発明は、上記トンネル覆工コンクリート打設方法に用いるトンネル覆工コンクリート打設構造であって、既に形成された既設覆工コンクリートの端面と妻型枠とによって挟まれる、前記トンネル覆工用型枠の外周面とトンネル内周の覆工面との間の覆工空間に、外径の異なる複数の中空パイプからなり、外径の小さな方の中空パイプを外径の大きな方の中空パイプに順次スライド可能に挿入して全体の長さを伸縮可能とした多段中空パイプを、外径の小さな方の中空パイプを前記既設覆工コンクリート側に配設してトンネルの軸方向に伸ばした状態で取り付けると共に、棒状バイブレータを多段中空パイプの前記既設覆工コンクリート側の端部から飛び出させて配設し、且つ該棒状バイブレータの後端部分に後続するバイブレータケーブルを、前記多段中空パイプに内挿して前記妻型枠側に延設させ、当該妻型枠を貫通させて配設することにより前記妻型枠の外側から牽引可能としたトンネル覆工コンクリート打設構造を提供することにより、上記目的を達成したものである。   And this invention is the tunnel lining concrete placement structure used for the said tunnel lining concrete placement method, Comprising: The said tunnel lining which is pinched | interposed by the end surface of the existing lining concrete and the end formwork The lining space between the outer periphery of the formwork and the inner lining of the tunnel is composed of a plurality of hollow pipes with different outer diameters, and the hollow pipe with the smaller outer diameter is replaced with the hollow pipe with the larger outer diameter. A multi-stage hollow pipe that can be sequentially slidably inserted into the tube to expand and contract the entire length, and the hollow pipe with the smaller outer diameter is placed on the existing lining concrete side and extended in the axial direction of the tunnel And a vibrator that protrudes from the end of the existing lining concrete side of the multistage hollow pipe and follows the rear end portion of the vibrator A cable is inserted into the multi-stage hollow pipe so as to extend toward the end formwork side, and is disposed through the end formwork so as to be pulled from the outside of the end formwork. The above object is achieved by providing a structure.

本発明のトンネル覆工コンクリート打設方法又はトンネル覆工コンクリート打設構造によれば、 材料や施工に多くの無駄を生じることなく、簡易な構成で、トンネル覆工用型枠を用いて形成される特にトンネル冠部の覆工コンクリートを効率良く効果的に締固めることができると共に、覆工空間の全長に亘ってコンクリートを充填打設した後に棒状バイブレータによってコンクリートを締固める場合でも、バイブレータケーブルを妻型枠側に牽引する際の引抜抵抗を効果的に抑制して、棒状バイブレータをスムーズに移動させることができる。   According to the tunnel lining concrete placing method or the tunnel lining concrete placing structure of the present invention, it is formed using a tunnel lining formwork with a simple configuration without causing much waste in materials and construction. In particular, the lining concrete of the tunnel crown can be compacted efficiently and effectively, and the vibrator cable can be used even when the concrete is compacted with a rod-shaped vibrator after filling and placing the concrete over the entire length of the lining space. The rod-like vibrator can be moved smoothly by effectively suppressing the pull-out resistance when pulling toward the end form frame.

本発明の好ましい一実施形態に係るトンネル覆工コンクリート打設方法は、図1(a)〜(c)に示すように、例えば山岳トンネル工法において、コンクリート覆工用型枠としてのトンネル覆工用型枠10を用いてトンネル12の側部及び上部の覆工コンクリート11を打設形成してゆく際に、特にトンネル12の冠部(クラウン部)13の覆工コンクリート11aを、これより下方の例えばトンネル12の側壁部及びアーチ形状部分の覆工コンクリート11を打設した後に、充分に締固めながら打設してゆくための方法として採用されたものである。   As shown in FIGS. 1A to 1C, a tunnel lining concrete placing method according to a preferred embodiment of the present invention is for tunnel lining as a concrete lining formwork, for example, in a mountain tunnel construction method. When forming the lining concrete 11 on the side and the upper part of the tunnel 12 using the mold 10, in particular, the lining concrete 11a of the crown (crown) 13 of the tunnel 12 is placed below this. For example, it is employed as a method for placing the lining concrete 11 on the side wall portion and the arch-shaped portion of the tunnel 12 and then placing it while sufficiently compacting.

ここで、本実施形態では、トンネル覆工用型枠10は、従来技術として公知の例えばスライド移動式のセントルであり、トンネル12の掘削作業の進行に伴なって、例えば10m程度の所定のスパン毎にトンネル12の掘進方向Xの後方から前方に向かって据え付け直しながら、トンネル12の側部及び上部の覆工コンクリート11を順次打設形成してゆくことを可能にするものである。また、本実施形態では、側壁部及びアーチ形状部分の覆工コンクリート11は、例えば従来の工法と同様の方法により、設置したトンネル覆工用型枠10に設けられた検査窓14を介してコンクリートが供給されると共に、振動締固め装置としての棒状バイブレータ14aを検査窓14から挿入して供給されたコンクリートを締固めることによって、当該側壁部及びアーチ形状部分の覆工コンクリート11が、トンネル冠部13の覆工コンクリート11aに先行して打設されることになる。   Here, in this embodiment, the tunnel lining form 10 is, for example, a slide-movable centle known as the prior art, and a predetermined span of, for example, about 10 m as the tunnel 12 excavates. It is possible to sequentially cast and form the lining concrete 11 on the side portion and the upper portion of the tunnel 12 while re-installing the tunnel 12 from the rear to the front in the digging direction X. Moreover, in this embodiment, the lining concrete 11 of a side wall part and an arch-shaped part is concrete through the inspection window 14 provided in the installed tunnel lining formwork 10 by the method similar to the conventional construction method, for example. Is supplied, and a rod-like vibrator 14a as a vibration compaction device is inserted from the inspection window 14 to compact the supplied concrete, whereby the side wall portion and the arched portion of the lining concrete 11 are tunnel crown portions. It will be placed prior to the 13 lining concrete 11a.

本実施形態のトンネル覆工コンクリート打設方法は、トンネル覆工用型枠10を用いてトンネル12の冠部13の覆工コンクリート11aを形成するためのコンクリート打設方法であって、図1及び図2に示すように、コンクリートの打設作業に先立って、まず、既に形成された既設覆工コンクリート15の端面15aと妻型枠16とによって挟まれる、トンネル覆工用型枠10の外周面とトンネル内周の覆工面22との間の覆工空間23に、外径の異なる複数(本実施形態では3本)の中空パイプ17a,17b,17cからなり、外径の小さな方の中空パイプ17a,17bを外径の大きな方の中空パイプ17b,17cに順次スライド可能に挿入して全体の長さを伸縮可能とした多段中空パイプ18(図2参照)を、外径の小さな方の中空パイプ17a,17bを既設覆工コンクリート15側に配設してトンネル12の軸方向Xに伸ばした状態で取り付けると共に、棒状バイブレータ20を多段中空パイプ18の既設覆工コンクリート15側の端部から飛び出させて配設し、且つ棒状バイブレータ20の後端部分に後続するバイブレータケーブル19を、多段中空パイプ18に内挿して妻型枠16側に延設させ、当該妻型枠16を貫通させて配設することにより妻型枠16の外側から牽引可能として、トンネル覆工コンクリート打設するための打設構造を、例えばトンネル覆工用型枠10の組み立て作業時に設置しておく。   The tunnel lining concrete placement method of this embodiment is a concrete placement method for forming the lining concrete 11a of the crown portion 13 of the tunnel 12 by using the tunnel lining form 10, which is shown in FIG. As shown in FIG. 2, prior to the concrete placing work, first, the outer peripheral surface of the tunnel lining formwork 10 sandwiched between the end face 15 a of the existing lining concrete 15 and the end formwork 16. And a lining space 23 between the inner periphery of the tunnel and a lining surface 22 of the tunnel, which is composed of a plurality of (three in this embodiment) hollow pipes 17a, 17b, 17c having different outer diameters, and the hollow pipe having the smaller outer diameter. The multi-stage hollow pipe 18 (see FIG. 2) whose outer length can be expanded and contracted by sequentially inserting the 17a and 17b into the hollow pipes 17b and 17c having the larger outer diameter so as to be slidable, The empty pipes 17a and 17b are disposed on the existing lining concrete 15 side and attached in a state extending in the axial direction X of the tunnel 12, and the rod-like vibrator 20 is attached from the end of the multistage hollow pipe 18 on the existing lining concrete 15 side. A vibrator cable 19 which is disposed so as to protrude and which follows the rear end portion of the rod-shaped vibrator 20 is inserted into the multistage hollow pipe 18 so as to extend toward the end form 16 and penetrate the end form 16. A placement structure for placing tunnel lining concrete is installed at the time of assembling the tunnel lining form 10 so that it can be pulled from the outside of the end form 16 by being disposed.

そして、本実施形態では、上述のトンネル覆工コンクリート打設構造がトンネル12の冠部13に設置された状態で、覆工空間23にコンクリートを充填打設すると共に(図1(c)参照)、図3〜図6に示すように、棒状バイブレータ20を振動させながらバイブレータケーブル19を牽引して、当該バイブレータケーブル19が最も外径の小さな第1中空パイプ17aに棒状バイブレータ20を飛び出させたまま係止された状態から(図3参照)、第1中空パイプ17aを、次に外径の大きな第2中空パイプ17bに、当該第1中空パイプ17aが第2中空パイプ17bに係止されるまで挿入する(図5参照)。しかる後に、さらにバイブレータケーブル19を牽引して、第1中空パイプ17aが挿入された第2中空パイプ17bを、次に外径の大きな第3中空パイプ17cに、当該第2中空パイプ17bが第3中空パイプ17cに係止されるまで挿入する(図6参照)。このようにして、覆工空間23に充填打設されたコンクリート11aを、外径の小さな方の中空パイプ17a,17bを外径の大きな方の中空パイプ17b,17cに順次挿入して多段中空パイプ18を収縮させながら、既設覆工コンクリート15側の部分から妻型枠16側に向けて締固めてゆくことにより、トンネル12の冠部13の覆工コンクリート11aが形成されることになる。   And in this embodiment, while the above-mentioned tunnel lining concrete placement structure is installed in the crown part 13 of the tunnel 12, while filling concrete in the lining space 23 (refer FIG.1 (c)). 3 to 6, the vibrator cable 19 is pulled while vibrating the rod-shaped vibrator 20, and the vibrator cable 19 is left protruding in the first hollow pipe 17 a having the smallest outer diameter. From the locked state (see FIG. 3), until the first hollow pipe 17a is locked to the second hollow pipe 17b having the next largest outer diameter, and the first hollow pipe 17a is locked to the second hollow pipe 17b. Insert (see FIG. 5). Thereafter, the vibrator cable 19 is further pulled so that the second hollow pipe 17b into which the first hollow pipe 17a is inserted is then transferred to the third hollow pipe 17c having the next larger outer diameter, and the second hollow pipe 17b is connected to the third hollow pipe 17b. Insert until it is locked to the hollow pipe 17c (see FIG. 6). In this way, the concrete 11a filled in the lining space 23 is inserted into the hollow pipes 17b and 17c having the smaller outer diameter sequentially into the hollow pipes 17b and 17c having the larger outer diameter, so that the multistage hollow pipe is inserted. While shrinking 18, the lining concrete 11 a of the crown portion 13 of the tunnel 12 is formed by compacting from the portion on the existing lining concrete 15 side toward the end frame 16 side.

多段中空パイプ18は、いわゆるテレスコピック構造を備えることにより、長さを伸縮可能なロッド状部材であり、本実施形態では、例えば鋼製パイプからなる第1中空パイプ17aと、第2中空パイプ17bと、第3中空パイプ17cとによって構成される。第1中空パイプ17aは、最も外径の小さな中空パイプであり、例えば5.6cmの外径を備えると共に、3.0mの長さを有している。また、第1中空パイプ17aは、バイブレータケーブル19を挿通可能な内径を備えると共に、その第2中空パイプ17b側の基端部分に、内径を縮径させてバイブレータケーブル19に設けた係止突起26を当接係止させる係止スリーブ21aが装着固定されている(図4参照)。   The multi-stage hollow pipe 18 is a rod-shaped member that can extend and contract by providing a so-called telescopic structure. In the present embodiment, for example, a first hollow pipe 17a made of a steel pipe, a second hollow pipe 17b, And the third hollow pipe 17c. The first hollow pipe 17a is a hollow pipe having the smallest outer diameter. For example, the first hollow pipe 17a has an outer diameter of 5.6 cm and a length of 3.0 m. The first hollow pipe 17a has an inner diameter through which the vibrator cable 19 can be inserted, and a locking projection 26 provided on the vibrator cable 19 with a reduced inner diameter at the proximal end portion on the second hollow pipe 17b side. A locking sleeve 21a for abutting and locking is attached and fixed (see FIG. 4).

第2中空パイプ17bは、第1中空パイプ17aの次に外径の大きな中空パイプであり、例えば6.6cmの外径を備えると共に、3.0mの長さを有している。また、第2中空パイプ17bは、第1中空パイプ17aを挿通可能な内径を備えると共に、その第3中空パイプ17c側の基端部分に、内径を縮径させて第1中空パイプ17aの端部を当接係止させる係止スリーブ21bが装着固定されている(図2参照)。   The second hollow pipe 17b is a hollow pipe having the next largest outer diameter after the first hollow pipe 17a. For example, the second hollow pipe 17b has an outer diameter of 6.6 cm and a length of 3.0 m. The second hollow pipe 17b has an inner diameter through which the first hollow pipe 17a can be inserted, and an end of the first hollow pipe 17a with a reduced inner diameter at the base end portion on the third hollow pipe 17c side. A locking sleeve 21b for abutting and locking is attached and fixed (see FIG. 2).

第3中空パイプ17bは、最も外径の大きな中空パイプであり、例えば7.6cmの外径を備えると共に、3.0mの長さを有している。また、第3中空パイプ17bは、第2中空パイプ17aを挿通可能な内径を備えると共に、その妻型枠16側の基端部分に、内径を縮径させて第2中空パイプ17bの端部を当接係止させる係止スリーブ21cが装着固定されている(図2参照)。   The third hollow pipe 17b is a hollow pipe having the largest outer diameter. For example, the third hollow pipe 17b has an outer diameter of 7.6 cm and a length of 3.0 m. Further, the third hollow pipe 17b has an inner diameter through which the second hollow pipe 17a can be inserted, and the proximal end portion on the side of the end frame 16 is reduced in inner diameter so that the end of the second hollow pipe 17b is provided. A locking sleeve 21c for contact and locking is mounted and fixed (see FIG. 2).

なお、これらの中空パイプ17a,17b,17cには、その先端部内周面に沿って、これらに挿通される第1中空パイプ17a、第2中空パイプ17b、又はバイブレータケーブル19の外周面との間の隙間をシールする、例えばシールリング(図示せず。)が適宜の位置に設けられている。また、これらの中空パイプ17a,17b,17cの基端部外周面や、先端部内周面には、多段中空パイプ18を伸張させた際に、外径の小さな方の中空パイプ17a,17bが外径の大きな方の中空パイプ17b,17cから脱落するのを防止する、例えばストッパー突起(図示せず。)が適宜の位置に設けられている。   The hollow pipes 17a, 17b, and 17c are provided between the first hollow pipe 17a, the second hollow pipe 17b, and the outer peripheral surface of the vibrator cable 19 that are inserted through the inner peripheral surface of the tip portion. For example, a seal ring (not shown) is provided at an appropriate position. Further, when the multi-stage hollow pipe 18 is extended, the hollow pipes 17a, 17b having a smaller outer diameter are externally attached to the outer peripheral surface of the base end portion and the inner peripheral surface of the distal end portion of these hollow pipes 17a, 17b, 17c. For example, stopper protrusions (not shown) for preventing the hollow pipes 17b and 17c having larger diameters from falling off are provided at appropriate positions.

多段中空パイプ18の既設覆工コンクリート15側の端部から飛び出して配設される棒状バイブレータ20は、例えば電磁式振動体やモータの回転力によって振動する振動体等を内部に備える、コンクリート用の締固め装置として汎用されている公知の装置であり、当該棒状バイブレータ20の後端部分に接続される、導体等が収容されたフレキシブルな動力供給ホースからなるバイブレータケーブル19と一体として構成される。   The rod-like vibrator 20 that is disposed to protrude from the end of the existing lining concrete 15 of the multistage hollow pipe 18 includes, for example, an electromagnetic vibrator, a vibrator that vibrates by the rotational force of a motor, and the like. This is a known device that is widely used as a compacting device, and is configured integrally with a vibrator cable 19 that is connected to the rear end portion of the rod-like vibrator 20 and is composed of a flexible power supply hose containing a conductor or the like.

バイブレータケーブル19は、図7に示すように、例えば8mmの太さのワイヤー19aを、内径9.2mm、外径12mmのポリアミドチューブ19bで覆うと共に、ポリアミドチューブ19bの外周面に、導体19cと介在紐19dとを6本づつ周方向に交互に配置し、さらにこれらを外径が21.8mmのシース(外皮)19eで覆った後に、油圧ホース19fで被覆して形成される、外径が例えば37.2mmの公知のケーブル部材であり、覆工空間23に充填打設されたコンクート11a中に埋入される当該バイブレータケーブル19や中空パイプ17a,17b,17cを、コンクート11との摩擦力(付着力)に抗して、棒状バイブレータ20と共に妻型枠16側に牽引するのに十分な引張り強度を備えている。   As shown in FIG. 7, the vibrator cable 19 covers, for example, a wire 19 a having a thickness of 8 mm with a polyamide tube 19 b having an inner diameter of 9.2 mm and an outer diameter of 12 mm, and a conductor 19 c interposed on the outer peripheral surface of the polyamide tube 19 b. The cords 19d are alternately arranged in the circumferential direction by six pieces, and further covered with a sheath (outer skin) 19e having an outer diameter of 21.8 mm, and then covered with a hydraulic hose 19f. This is a known cable member of 37.2 mm, and the vibrator cable 19 and the hollow pipes 17a, 17b, and 17c embedded in the concrete 11a filled and laid in the lining space 23 are subjected to frictional force with the concrete 11 ( It has a sufficient tensile strength to pull it toward the end form frame 16 together with the rod-shaped vibrator 20 against the adhesive force.

また、バイブレータケーブル19には、棒状バイブレータ20との接続部分から第1中空パイプ17aの長さに相当する例えば3.0m程度離れた位置に、外周面から外側に突出して、係止突起26が、例えばバイブレータケーブル19をかしめることによって設けられている(図2、図4参照)。バイブレータケーブル19を牽引して、この係止突起26を、第1中空パイプ17aの基端部分に設けた係止スリーブ21aに当接係止させることにより、図3に示すように、棒状バイブレータ20が、多段中空パイプ18の既設覆工コンクリート15側の端部から直線状に飛び出した状態で、位置決めされることになる。   Further, the vibrator cable 19 protrudes outward from the outer peripheral surface at a position, for example, about 3.0 m corresponding to the length of the first hollow pipe 17a from the connecting portion with the rod-shaped vibrator 20, and a locking projection 26 is formed. For example, it is provided by caulking the vibrator cable 19 (see FIGS. 2 and 4). As shown in FIG. 3, the vibrator cable 19 is pulled so that the locking projection 26 is brought into contact with and locked with a locking sleeve 21a provided at the proximal end portion of the first hollow pipe 17a. However, it will be positioned in the state which protruded linearly from the edge part by the side of the existing lining concrete 15 of the multistage hollow pipe 18. As shown in FIG.

なお、バイブレータケーブル19は、第1中空パイプ17aの先端部分で多段中空パイプ18に係止して、棒状バイブレータ20を多段中空パイプ18と直線状に位置決めすることも可能であるが、上述のように、バイブレータケーブル19を第1中空パイプ17aの基端部分で当該第1中空パイプ17aに係止することにより、バイブレータケーブル19の牽引によって第1中空パイプ17aを妻型枠16側に移動させる際に、第1中空パイプ17aには先端側からの圧縮力は負荷されなくなるので、より合理的に、安定した状態で第1中空パイプ17aを移動させることが可能になる。   The vibrator cable 19 can be locked to the multi-stage hollow pipe 18 at the tip of the first hollow pipe 17a to position the rod-shaped vibrator 20 linearly with the multi-stage hollow pipe 18, but as described above. In addition, when the vibrator cable 19 is locked to the first hollow pipe 17a at the base end portion of the first hollow pipe 17a, the first hollow pipe 17a is moved to the end frame 16 side by pulling the vibrator cable 19. In addition, since the compressive force from the front end side is not applied to the first hollow pipe 17a, the first hollow pipe 17a can be moved in a more rational and stable state.

本実施形態では、図1(b)に示す、トンネル12の側壁部及びアーチ形状部分の覆工コンクリート11を打設形成した後の、多段中空パイプ18によるトンネル覆工コンクリート打設構造が設置されたトンネル12の冠部(クラウン部)13の覆工空間23に対して、例えば図1(c)示すように、コンクリートポンプをコンクリート打設孔24に接続して、当該コンクリート打設孔24からコンクリートを充填打設する。   In this embodiment, the tunnel lining concrete placement structure by the multistage hollow pipe 18 after the lining concrete 11 of the side wall portion and the arch-shaped portion of the tunnel 12 shown in FIG. For example, as shown in FIG. 1C, a concrete pump is connected to the concrete placement hole 24 with respect to the lining space 23 of the crown portion (crown portion) 13 of the tunnel 12. Fill and cast concrete.

なお、本実施形態では、図1(a)に示す、トンネル12の側壁部及びアーチ形状部分の覆工コンクリート11を打設する工程においては、多段中空パイプ18の既設覆工コンクリート側15の端部から飛び出して配設された棒状バイブレータ20を、トンネル覆工用型枠10に取り付けた滑車27(図2参照)を介して下方に誘導すると共に、バイブレータケーブル19を送り出して、側壁部やアーチ形状部分に吊り下げて配設し、側壁部やアーチ形状部分に打設されたコンクリートの上昇に伴って、バイブレータケーブル19を牽引しつつ棒状バイブレータ20を上方に移動して行くことにより、トンネル12の側壁部及びアーチ形状部分の覆工コンクリート11の締固め作業に用いることもできる。また、トンネル12の側壁部及びアーチ形状部分の覆工コンクリート11を打設し終わったら、例えばトンネル覆工用型枠10の天端部分に設けた検査窓からの作業によって滑車27を取り外すと共に、バイブレータケーブル19を牽引して、図3に示すように、棒状バイブレータ20を多段中空パイプ18の先端に直線状に連設するように配置する。   In the present embodiment, in the step of placing the lining concrete 11 on the side wall portion and the arch-shaped portion of the tunnel 12 shown in FIG. 1A, the end of the existing lining concrete side 15 of the multistage hollow pipe 18 is provided. The rod-like vibrator 20 that protrudes from the section is guided downward through a pulley 27 (see FIG. 2) attached to the tunnel lining mold 10, and the vibrator cable 19 is fed out to form a side wall or an arch. By suspending and arranging the rod-like vibrator 20 while pulling the vibrator cable 19 with the rise of the concrete placed on the side wall portion or the arch-shaped portion, the tunnel 12 is suspended. It can also be used for compacting the lining concrete 11 of the side wall and the arch-shaped portion. Further, when the lining concrete 11 on the side wall portion and the arch-shaped portion of the tunnel 12 is finished, for example, the pulley 27 is removed by work from the inspection window provided at the top end portion of the tunnel lining form 10, As shown in FIG. 3, the vibrator cable 19 is pulled, and the rod-like vibrator 20 is arranged so as to be linearly connected to the tip of the multistage hollow pipe 18.

トンネル12の冠部13の覆工空間23にコンクリートを充填打設したら、図1(c)に示すように、コンクリート打設孔24やその他の打設口から必要に応じてコンクリートを追加打設しつつ、棒状バイブレータ20を震動させながら、例えばコード巻取り装置25の牽引力によってバイブレータケーブル21を牽引することにより、棒状バイブレータ20を妻型枠16側に移動させる。   After filling and placing concrete in the lining space 23 of the crown portion 13 of the tunnel 12, as shown in FIG. 1 (c), additional concrete is placed from the concrete placement hole 24 and other placement openings as required. However, while vibrating the rod-shaped vibrator 20, the rod-shaped vibrator 20 is moved to the end form frame 16 side by pulling the vibrator cable 21 by the pulling force of the cord winding device 25, for example.

ここで、多段中空パイプ18を構成する中空パイプ17a,17b,17cは、略同じ長さでコンクリート中に埋入されており、既設覆工コンクリート15側の先端部分に配設された第1中空パイプ17aは、他の中空パイプ17b,17cよりも外径が小さく、コンクリートとの付着力も小さくなっていることから、バイブレータケーブル19の牽引により、図5に示すように、外径の大きな2本の中空パイプ17b,17cに先行して、当該第1中空パイプ17aのみが、これの端部が第2中空パイプ17bの基端部分の係止スリーブ21bに当接するまで第2中空パイプ17bに挿入されてゆく。   Here, the hollow pipes 17a, 17b, and 17c constituting the multi-stage hollow pipe 18 are embedded in the concrete with substantially the same length, and the first hollow disposed at the tip portion on the existing lining concrete 15 side. The pipe 17a has an outer diameter smaller than that of the other hollow pipes 17b and 17c, and also has a smaller adhesion force to concrete. Therefore, as shown in FIG. Prior to the hollow pipes 17b and 17c, only the first hollow pipe 17a is connected to the second hollow pipe 17b until the end thereof abuts against the locking sleeve 21b of the proximal end portion of the second hollow pipe 17b. It will be inserted.

第1中空パイプ17aが第2中空パイプ17bに挿入されたら、さらにバイブレータケーブル19を牽引して、第3中空パイプ17cよりも外径が小さく、コンクリートとの付着力も小さい第2中空パイプ17bのみを、図6に示すように、これの端部が第3中空パイプ17cの基端部分の係止スリーブ21cに当接するまで第3中空パイプ17cに挿入してゆく。   When the first hollow pipe 17a is inserted into the second hollow pipe 17b, the vibrator cable 19 is further pulled, and only the second hollow pipe 17b having an outer diameter smaller than that of the third hollow pipe 17c and a small adhesion to concrete. As shown in FIG. 6, this is inserted into the third hollow pipe 17c until its end abuts against the locking sleeve 21c at the base end portion of the third hollow pipe 17c.

しかる後に、第2中空パイプ17b及び第1中空パイプ17aが内側に重ねて挿入された第3中空パイプ17cを、例えば妻型枠16への固定状態を解除し、妻型枠16に設けられた引抜き孔16aを介して、バイブレータケーブル19の牽引により棒状バイブレータ20と共に覆工空間23から撤去することにより、トンネル覆工用型枠10が設置された当該スパンにおける覆工コンクリート11の打設作業が終了する。   After that, the third hollow pipe 17c in which the second hollow pipe 17b and the first hollow pipe 17a are overlapped and inserted inside is released from the fixed state to, for example, the wife mold 16 and is provided in the wife mold 16 By pulling the vibrator cable 19 through the extraction hole 16a and removing it from the lining space 23 together with the rod-like vibrator 20, the placement work of the lining concrete 11 in the span where the tunnel lining formwork 10 is installed can be performed. finish.

そして、本実施形態によれば、材料や施工に多くの無駄を生じることなく、簡易な構成で、トンネル覆工用型枠10を用いて形成される特にトンネル12の冠部13の覆工コンクリート11aを効率良く効果的に締固めることができると共に、覆工空間23の全長に亘ってコンクリートを充填打設した後に棒状バイブレータ20によってコンクリートを締固める場合でも、バイブレータケーブル19を妻型枠16側に牽引する際の引抜抵抗を効果的に抑制して、棒状バイブレータ20をスムーズに移動させることが可能になる。   And according to this embodiment, the covering concrete of the crown portion 13 of the tunnel 12 is formed by using the tunnel covering formwork 10 with a simple configuration without causing much waste in materials and construction. 11a can be efficiently and effectively compacted, and even when the concrete is compacted by the rod-shaped vibrator 20 after filling the concrete over the entire length of the lining space 23, the vibrator cable 19 is connected to the side of the end frame 16 side. It is possible to effectively suppress the pulling resistance at the time of towing, and to smoothly move the rod-shaped vibrator 20.

すなわち、本実施形態では、外径の異なる第1中空パイプ17a、第2中空パイプ17b、及び第3中空パイプ17cからなる、先端に棒状バイブレータ20を飛び出させて配置した多段中空パイプ18を覆工空間23に配置し、覆工空間23にコンクリートを充填打設した後に、バイブレータケーブル21の牽引によって、既設覆工コンクリート15側の外径の小さな第1中空パイプ17aや第2中空パイプ17bを、順次第2中空パイプ17bや第3中空パイプ17cに挿入しながら棒状バイブレータ20を妻型枠16側に移動してコンクリートの締固めを行うので、特に多段中空パイプ18が覆工空間23から撤去した後に再利用可能なことから、棒状バイブレータを案内するL型のアングル等のガイドレールを、トンネル覆工用型枠によるスパンの略全長に亘って予め設置しておく方法と比較して、簡易な方法によって材料や施工に多くの無駄を生じることなく、効率良く覆工コンクリート11aを締固めてゆくことが可能になる。これによって、十分な締固めがなされた、品質が良く表面の仕上りが良好な覆工コンクリート11aを容易に得ることが可能になる。   That is, in the present embodiment, the multi-stage hollow pipe 18 composed of the first hollow pipe 17a, the second hollow pipe 17b, and the third hollow pipe 17c having different outer diameters, with the rod-shaped vibrator 20 protruding from the tip, is covered. After placing in the space 23 and filling and placing the concrete in the lining space 23, the first hollow pipe 17 a and the second hollow pipe 17 b having a small outer diameter on the existing lining concrete 15 side are pulled by pulling the vibrator cable 21. The rod-shaped vibrator 20 is moved toward the end form 16 while being inserted into the second hollow pipe 17b and the third hollow pipe 17c sequentially, and the concrete is compacted, so that the multi-stage hollow pipe 18 is removed from the lining space 23 in particular. Since it can be reused later, a guide rail such as an L-shaped angle that guides the rod-shaped vibrator can be used as a tunnel lining formwork. Compared with the method of pre-installing over the entire length of the span, it is possible to efficiently compact the lining concrete 11a by a simple method without causing much waste in materials and construction. Become. As a result, it is possible to easily obtain the lining concrete 11a which is sufficiently compacted and has a good quality and a good surface finish.

また、本実施形態によれば、多段中空パイプ18を3分割する第1中空パイプ17a、第2中空パイプ17b、及び第3中空パイプ17cを、バイブレータケーブル21の牽引によって各々妻型枠16側に移動させながら先端の棒状バイブレータ20によってコンクリートの締固めを行うので、各中空パイプ17a,17b,17cを移動させる際の、バイブレータケーブル21の牽引による引抜抵抗が、分割することなく既設覆工コンクリート15に近接する部分まで連続してコンクリート中に埋入した中空パイプやバイブレータケーブルを1度に引抜く場合と比較して、例えば1/3程度の引抜抵抗となるので、覆工空間23の全長に亘ってコンクリートを充填打設した後に棒状バイブレータ20を移動させつつコンクリートを締固める際の引抜抵抗を効果的に軽減して、棒状バイブレータ20をスムーズに移動させることが可能になる。   Further, according to the present embodiment, the first hollow pipe 17a, the second hollow pipe 17b, and the third hollow pipe 17c that divide the multi-stage hollow pipe 18 into three parts are respectively brought to the end form 16 side by pulling the vibrator cable 21. Since the concrete is compacted by the rod-shaped vibrator 20 at the distal end while being moved, the pulling resistance due to the pulling of the vibrator cable 21 when the hollow pipes 17a, 17b, 17c are moved is not divided and the existing lining concrete 15 is divided. Compared to the case where a hollow pipe or a vibrator cable continuously embedded in the concrete is pulled out at a time, the pulling resistance is, for example, about 1/3. After filling and placing concrete, the concrete is compacted while moving the rod-like vibrator 20 To effectively reduce the pull-out resistance of, it is possible to move the rod-like vibrator 20 smoothly.

ここで、コンクリートと中空パイプとの付着力をfkgf/cm2とした場合、引抜抵抗力を(各パイプの外周面積)×(付着力)とすると、外径5.6cm、長さ3.0mの第1中空パイプ17aの最大引抜抵抗力は52.8fkgf/cm2、外径6.6cm、長さ3.0mの第2中空パイプ17bの最大引抜抵抗力は62.2fkgf/cm2、外径7.6cm、長さ3.0mの第3中空パイプ17cの最大引抜抵抗力は71.6fkgf/cm2となる。これに対して、一般の外径5.6cm、長さ9.0mの中空パイプ17aの全体を妻型枠からコンクリート中に埋入した際の最大引抜抵抗力は158.46fkgf/cm2となる。このことから、第1中空パイプ17a、第2中空パイプ17b、及び第3中空パイプ17cに3分割して多段中空パイプ18を構成することにより、バイブレータケーブル21の牽引による引抜抵抗が大幅に軽減されることになり、本実施形態によって、棒状バイブレータ20をコンクリート中でスムーズに移動できるようになることが確認される。 Here, when the adhesion force between the concrete and the hollow pipe is fkgf / cm 2 , the outer diameter is 5.6 cm and the length is 3.0 m when the pulling resistance force is (peripheral area of each pipe) × (adhesion force). The first hollow pipe 17a has a maximum pulling resistance of 52.8 fkgf / cm 2 , an outer diameter of 6.6 cm, and a second hollow pipe 17b having a length of 3.0 m has a maximum pulling resistance of 62.2 fkgf / cm 2 . The maximum pulling resistance of the third hollow pipe 17c having a diameter of 7.6 cm and a length of 3.0 m is 71.6 fkgf / cm 2 . On the other hand, the maximum pulling-out resistance when the entire hollow pipe 17a having a general outer diameter of 5.6 cm and a length of 9.0 m is embedded in the concrete from the end form is 158.46 fkgf / cm 2. . Therefore, the pulling resistance due to the pulling of the vibrator cable 21 is greatly reduced by forming the multi-stage hollow pipe 18 by dividing it into the first hollow pipe 17a, the second hollow pipe 17b, and the third hollow pipe 17c. Accordingly, it is confirmed that the rod-shaped vibrator 20 can be smoothly moved in the concrete according to the present embodiment.

なお、本発明は上記実施形態に限定されることなく種々の変更が可能である。例えば、本発明は、山岳トンネル以外のその他のトンネルにおける覆工コンクリートを形成するべく採用することもできる。また、トンネル覆工用型枠の外周面との間に覆工空間を形成するトンネルの内周面は、吹き付けコンクリートによって覆われる地山の他、1次覆工を行った後のトンネル内周面による、2次覆工を行うための覆工面であっても良い。さらに、本発明によって締固められる覆工コンクリートは、トンネル冠部の覆工コンクリートである必要は必ずしもなく、例えばトンネルの側壁部や肩部、アーチ形状部分等に多段中空パイプを配置して、本発明を適用することもできる。さらにまた、多段中空パイプは、3本の中空パイプからなる多段中空パイプである必要は必ずしもなく、4本以上の中空パイプからなる多段中空パイプであっても良い。   The present invention is not limited to the above-described embodiment, and various modifications can be made. For example, the present invention can be employed to form lining concrete in other tunnels other than mountain tunnels. In addition, the inner peripheral surface of the tunnel that forms a lining space between the outer surface of the tunnel lining formwork is the inner periphery of the tunnel after the primary lining is performed in addition to the ground covered with sprayed concrete. It may be a lining surface for performing secondary lining by a surface. Furthermore, the lining concrete to be compacted according to the present invention is not necessarily the lining concrete of the tunnel crown, for example, a multi-stage hollow pipe is disposed on the side wall, shoulder, arch-shaped part, etc. of the tunnel, The invention can also be applied. Furthermore, the multi-stage hollow pipe is not necessarily a multi-stage hollow pipe composed of three hollow pipes, and may be a multi-stage hollow pipe composed of four or more hollow pipes.

(a)〜(c)は、本発明の好ましい一実施形態に係るトンネル覆工コンクリート打設方法を含む覆工コンクリートの打設作業の作業手順を説明する、一部を断面図として示す略示側面図である。(A)-(c) is the abbreviation which shows the work procedure of the laying concrete placement work including the tunnel lining concrete placement method concerning one desirable embodiment of the present invention, and shows a part as a sectional view It is a side view. 本発明の好ましい一実施形態に係るトンネル覆工コンクリート打設方法の一作業工程を説明する略示断面図である。It is a schematic sectional drawing explaining one work process of the tunnel lining concrete placement method which concerns on preferable one Embodiment of this invention. 本発明の好ましい一実施形態に係るトンネル覆工コンクリート打設方法の一作業工程を説明する略示断面図である。It is a schematic sectional drawing explaining one work process of the tunnel lining concrete placement method which concerns on preferable one Embodiment of this invention. 図3のA部拡大断面図である。FIG. 4 is an enlarged cross-sectional view of a part A in FIG. 3. 本発明の好ましい一実施形態に係るトンネル覆工コンクリート打設方法の一作業工程を説明する略示断面図である。It is a schematic sectional drawing explaining one work process of the tunnel lining concrete placement method which concerns on preferable one Embodiment of this invention. 本発明の好ましい一実施形態に係るトンネル覆工コンクリート打設方法の一作業工程を説明する略示断面図である。It is a schematic sectional drawing explaining one work process of the tunnel lining concrete placement method which concerns on preferable one Embodiment of this invention. バイブレータケーブルの拡大断面図である。It is an expanded sectional view of a vibrator cable. 本発明の好ましい一実施形態に係るトンネル覆工コンクリート打設方法において用いる多段中空パイプと一般の中空パイプの最大引抜抵抗力を比較して示すチャートである。It is a chart which compares and shows the maximum drawing-out resistance of the multistage hollow pipe used in the tunnel lining concrete placement method concerning one desirable embodiment of the present invention, and a general hollow pipe. (a)はコンクリート覆工用型枠をトンネルの内周面に沿って設置した状態を説明するトンネル軸方向から見た断面図、(b)は同側面図である。(A) is sectional drawing seen from the tunnel axial direction explaining the state which installed the formwork for concrete lining along the inner peripheral surface of a tunnel, (b) is the same side view. (a)〜(d)は、従来のトンネル覆工コンクリート打設方法の作業手順を説明する、一部を断面図として示す側面図である。(A)-(d) is a side view which shows the work procedure of the conventional tunnel lining concrete placement method, and shows one part as sectional drawing.

符号の説明Explanation of symbols

10 トンネル覆工用型枠
11 覆工コンクリート
11a 冠部の覆工コンクリート
12 トンネル
13 トンネルの冠部
15 既設覆工コンクリート
15a 既設覆工コンクリートの端面
16 妻型枠
17a 第1中空パイプ
17b 第2中空パイプ
17c 第3中空パイプ
18 多段中空パイプ
19 バイブレータケーブル
20 棒状バイブレータ
21a,21b,21c 係止スリーブ
22 覆工面
23 覆工空間
24 コンクリート打設孔
25 コード巻取り装置
26 係止突起
X トンネルの軸方向(掘進方向)
DESCRIPTION OF SYMBOLS 10 Formwork 11 for tunnel lining Concrete lining concrete 11a Crown lining concrete 12 Tunnel 13 Tunnel crown 15 Existing lining concrete 15a End face 16 of existing lining concrete End form 17a First hollow pipe 17b Second hollow Pipe 17c Third hollow pipe 18 Multi-stage hollow pipe 19 Vibrator cable 20 Bar-shaped vibrators 21a, 21b, 21c Locking sleeve 22 Covering surface 23 Covering space 24 Concrete placement hole 25 Cord winding device 26 Locking protrusion X Tunnel axial direction (Drilling direction)

Claims (4)

トンネル覆工用型枠を用いて覆工コンクリートを形成するトンネル覆工コンクリート打設方法において、
既に形成された既設覆工コンクリートの端面と妻型枠とによって挟まれる、前記トンネル覆工用型枠の外周面とトンネル内周の覆工面との間の覆工空間に、外径の異なる複数の中空パイプからなり、外径の小さな方の中空パイプを外径の大きな方の中空パイプに順次スライド可能に挿入して全体の長さを伸縮可能とした多段中空パイプを、外径の小さな方の中空パイプを前記既設覆工コンクリート側に配設してトンネルの軸方向に伸ばした状態で取り付けると共に、棒状バイブレータを多段中空パイプの前記既設覆工コンクリート側の端部から飛び出させて配設し、且つ該棒状バイブレータの後端部分に後続するバイブレータケーブルを、前記多段中空パイプに内挿して前記妻型枠側に延設させ、当該妻型枠を貫通させて配設することにより前記妻型枠の外側から牽引可能とし、
前記覆工空間にコンクリートを充填打設すると共に、前記棒状バイブレータを振動させながら前記バイブレータケーブルを牽引して、当該バイブレータケーブルが最も外径の小さな第1中空パイプに前記棒状バイブレータを飛び出させたまま係止された状態から、前記第1中空パイプを、次に外径の大きな第2中空パイプに、当該第1中空パイプが前記第2中空パイプに係止されるまで挿入し、
さらに前記バイブレータケーブルを牽引して、前記第1中空パイプが挿入された前記第2中空パイプを、次に外径の大きな第3中空パイプに、当該第2中空パイプが前記第3中空パイプに係止されるまで挿入する工程を含み、
前記覆工空間に充填打設されたコンクリートを、外径の小さな方の中空パイプを外径の大きな方の中空パイプに順次挿入して多段中空パイプを収縮させながら、前記既設覆工コンクリート側の部分から前記妻型枠側に向けて締固めてゆくトンネル覆工コンクリート打設方法。
In the tunnel lining concrete placement method of forming lining concrete using a tunnel lining formwork,
A plurality of different outer diameters are provided in the lining space between the outer peripheral surface of the tunnel lining formwork and the lining surface of the inner periphery of the tunnel, which is sandwiched between the end surface of the existing lining concrete and the end formwork. A multi-stage hollow pipe with a smaller outer diameter, which is slidably inserted into a hollow pipe with a smaller outer diameter in order to allow the entire length to expand and contract. The hollow pipe is disposed on the existing lining concrete side and attached in a state of being extended in the axial direction of the tunnel, and a rod-like vibrator is disposed by protruding from the end of the existing lining concrete side of the multistage hollow pipe. The vibrator cable following the rear end portion of the rod-like vibrator is inserted into the multi-stage hollow pipe and extended toward the end form frame, and is disposed through the end form frame. And it can be towed from the outside of the Kitsuma formwork,
While filling and placing concrete in the lining space, pulling the vibrator cable while vibrating the rod-like vibrator, the vibrator cable is left protruding out into the first hollow pipe having the smallest outer diameter. From the locked state, insert the first hollow pipe into the second hollow pipe having the next largest outer diameter until the first hollow pipe is locked to the second hollow pipe,
Further, by pulling the vibrator cable, the second hollow pipe into which the first hollow pipe is inserted is engaged with the third hollow pipe having the next outer diameter, and the second hollow pipe is engaged with the third hollow pipe. Including the step of inserting until it is stopped,
The concrete filled in the lining space is inserted into the hollow pipe with the smaller outer diameter sequentially into the hollow pipe with the larger outer diameter to shrink the multi-stage hollow pipe, and the concrete on the existing lining concrete side A tunnel lining concrete pouring method that compacts from the portion toward the end formwork side.
前記バイブレータケーブルは、前記棒状バイブレータを前記多段中空パイプの前記既設覆工コンクリート側の端部から直線状に飛び出させた状態で、前記第1中空パイプの前記第2中空パイプ側の基端部において前記第1中空パイプに係止される請求項1に記載のトンネル覆工コンクリート打設方法。   The vibrator cable is in a state where the rod-like vibrator is linearly protruded from an end portion of the existing lining concrete of the multi-stage hollow pipe, at a base end portion of the first hollow pipe on the second hollow pipe side. The tunnel lining concrete placement method according to claim 1, wherein the tunnel lining concrete is locked to the first hollow pipe. 前記覆工空間は、トンネル冠部の覆工空間である請求項1又は2に記載のトンネル覆工コンクリート打設方法。   The tunnel lining concrete placement method according to claim 1 or 2, wherein the lining space is a lining space of a tunnel crown. 請求項1〜3のいずれかに記載のトンネル覆工コンクリート打設方法に用いるトンネル覆工コンクリート打設構造であって、
既に形成された既設覆工コンクリートの端面と妻型枠とによって挟まれる、前記トンネル覆工用型枠の外周面とトンネル内周の覆工面との間の覆工空間に、外径の異なる複数の中空パイプからなり、外径の小さな方の中空パイプを外径の大きな方の中空パイプに順次スライド可能に挿入して全体の長さを伸縮可能とした多段中空パイプを、外径の小さな方の中空パイプを前記既設覆工コンクリート側に配設してトンネルの軸方向に伸ばした状態で取り付けると共に、棒状バイブレータを多段中空パイプの前記既設覆工コンクリート側の端部から飛び出させて配設し、且つ該棒状バイブレータの後端部分に後続するバイブレータケーブルを、前記多段中空パイプに内挿して前記妻型枠側に延設させ、当該妻型枠を貫通させて配設することにより前記妻型枠の外側から牽引可能としたトンネル覆工コンクリート打設構造。
A tunnel lining concrete placement structure used in the tunnel lining concrete placement method according to any one of claims 1 to 3,
A plurality of different outer diameters are provided in the lining space between the outer peripheral surface of the tunnel lining formwork and the lining surface of the inner periphery of the tunnel, which is sandwiched between the end surface of the existing lining concrete and the end formwork. A multi-stage hollow pipe with a smaller outer diameter, which is slidably inserted into a hollow pipe with a smaller outer diameter in order to allow the entire length to expand and contract. The hollow pipe is disposed on the existing lining concrete side and attached in a state of being extended in the axial direction of the tunnel, and a rod-like vibrator is disposed by protruding from the end of the existing lining concrete side of the multistage hollow pipe. The vibrator cable following the rear end portion of the rod-like vibrator is inserted into the multi-stage hollow pipe and extended toward the end form frame, and is disposed through the end form frame. Available traction from the outside of Kitsuma mold and the tunnel lining concreting structure.
JP2006235199A 2006-08-31 2006-08-31 Tunnel lining concrete placement method and placement structure Expired - Fee Related JP4557942B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006235199A JP4557942B2 (en) 2006-08-31 2006-08-31 Tunnel lining concrete placement method and placement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006235199A JP4557942B2 (en) 2006-08-31 2006-08-31 Tunnel lining concrete placement method and placement structure

Publications (2)

Publication Number Publication Date
JP2008057211A JP2008057211A (en) 2008-03-13
JP4557942B2 true JP4557942B2 (en) 2010-10-06

Family

ID=39240292

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006235199A Expired - Fee Related JP4557942B2 (en) 2006-08-31 2006-08-31 Tunnel lining concrete placement method and placement structure

Country Status (1)

Country Link
JP (1) JP4557942B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101889810B1 (en) * 2018-03-30 2018-08-20 한국지질자원연구원 Top protection portion integral type power panel wire tube supporting device with the distance adjustment means and construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002030893A (en) * 2000-07-19 2002-01-31 Nishimatsu Constr Co Ltd Method of placing secondary lining concrete
JP2003003795A (en) * 2001-06-27 2003-01-08 Sato Kogyo Co Ltd Tunnel lining concrete compacting apparatus, and compacting method using the same
JP2003227297A (en) * 2001-11-28 2003-08-15 Maeda Corp Concrete tamping method and device for it

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2761152B2 (en) * 1992-06-17 1998-06-04 前田建設工業株式会社 Vibration imparting device for cast concrete
JPH07233641A (en) * 1994-02-22 1995-09-05 Penta Ocean Constr Co Ltd Vibrator operating device for compacting concrete

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002030893A (en) * 2000-07-19 2002-01-31 Nishimatsu Constr Co Ltd Method of placing secondary lining concrete
JP2003003795A (en) * 2001-06-27 2003-01-08 Sato Kogyo Co Ltd Tunnel lining concrete compacting apparatus, and compacting method using the same
JP2003227297A (en) * 2001-11-28 2003-08-15 Maeda Corp Concrete tamping method and device for it

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101889810B1 (en) * 2018-03-30 2018-08-20 한국지질자원연구원 Top protection portion integral type power panel wire tube supporting device with the distance adjustment means and construction method thereof

Also Published As

Publication number Publication date
JP2008057211A (en) 2008-03-13

Similar Documents

Publication Publication Date Title
JP4931777B2 (en) Tunnel lining concrete placement management method
JP4514179B2 (en) Tunnel lining concrete compaction apparatus and compaction method using the same
JP4557941B2 (en) Tunnel lining concrete placement method and placement structure
JP7095997B2 (en) How to join concrete members
KR101510297B1 (en) A removable prestressing steel pipe soil nailing structure
JP6395524B2 (en) Steel pipe for ground reinforcement and method for manufacturing the same
JP4799453B2 (en) Tunnel lining concrete placement method
JP2008095400A (en) Diagonal cable removal method
JP4557942B2 (en) Tunnel lining concrete placement method and placement structure
JP4566890B2 (en) Tunnel lining concrete placing method and wife formwork device
JP4557946B2 (en) Tunnel lining concrete placement method and placement structure
JP4812666B2 (en) Tunnel lining concrete placement method
JP5106802B2 (en) Widening part construction method of tunnel
JP4624243B2 (en) Tunnel lining concrete placing method and wife formwork device
JP4610540B2 (en) Tunnel lining concrete placement method and placement structure
JP4979420B2 (en) Tunnel lining concrete casting structure
JP4566891B2 (en) Tunnel lining concrete placement method
JP2973861B2 (en) Compaction method for tunnel lining concrete
JP2007247327A (en) Replacement member for construction of underground structure, underground structure, and its construction method
KR20140101483A (en) Apparatus for holding a wire strand of anchor
JP6353775B2 (en) Construction method of leading element of underground continuous wall, construction method of underground continuous wall, and construction device of leading element of underground continuous wall
JP2009127229A (en) Tunnel lining concrete placing method
JP2010144361A (en) Method for constructing underpass
JP4841476B2 (en) Tunnel lining concrete casting structure
KR20150103563A (en) Jacket pack anchor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20081107

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100707

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100713

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100720

R150 Certificate of patent or registration of utility model

Ref document number: 4557942

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130730

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees