JP3946342B2 - Bridge erection device - Google Patents
Bridge erection device Download PDFInfo
- Publication number
- JP3946342B2 JP3946342B2 JP07486998A JP7486998A JP3946342B2 JP 3946342 B2 JP3946342 B2 JP 3946342B2 JP 07486998 A JP07486998 A JP 07486998A JP 7486998 A JP7486998 A JP 7486998A JP 3946342 B2 JP3946342 B2 JP 3946342B2
- Authority
- JP
- Japan
- Prior art keywords
- bridge
- rebar
- formwork
- reinforcing bar
- cage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【産業上の利用分野】
本願発明は、張出し架設施工法により橋桁を延長形成するように構成された橋梁架設装置に関するものである。
【0002】
【従来の技術】
従来より、大径間のプレストレストコンクリート橋梁の架設工法として張出し架設施工法が知られている。
【0003】
この張出し架設施工法は、足場型枠(作業足場および型枠)を吊下支持する片持ち架設作業車を用い、施工中の橋桁の先端に新たなコンクリートを打設して該橋桁を延長形成する施工法であり、具体的には次のような手順で施工が行われるようになっている。
【0004】
すなわち、まず、前段のコンクリート打設位置での施工完了後、ワーゲンを橋軸方向前方へ移動させてこれを橋桁の先端部に据え付けた後、コンクリート打設位置に外型枠をセットして、下スラブ鉄筋組、ウェブ鉄筋組およびシース接続を行うとともに、内型枠をセットして、上スラブ鉄筋組、横締鋼材の配置およびシース接続を行い、その後、コンクリートの打設および養生を行った後、PC鋼材の緊張および脱型を行うようになっている。
【0005】
【発明が解決しようとする課題】
しかしながら、上記従来の張出し架設施工法においては、ワーゲンに足場型枠が吊下固定されており、またコンクリート打設位置において鉄筋組作業が行われるようになっているので、鉄筋を部分的にプレハブ化することは可能であるが、これを完全にもしくは一部の継手施工を残してプレハブ化することはできない。このため、施工にかなりの長時間を要し、施工コストも高いものとなっている。
【0006】
本願発明は、このような事情に鑑みてなされたものであって、張出し架設施工により橋桁を延長形成するように構成された橋梁架設装置において、施工の工期短縮および経済性向上を図ることができる橋梁架設装置を提供することを目的とするものである。
【0007】
【課題を解決するための手段】
本願発明は、足場型枠を可動構造にするとともに、完全にもしくは一部の継手施工を残してプレハブ化された鉄筋カゴをコンクリート打設位置へ搬送し得る構成とすることにより、上記目的達成を図るようにしたものである。
【0008】
すなわち、本願第1の発明に係る橋梁架設装置は、
足場型枠を吊下支持する片持ち架設作業車を用い、施工中の橋桁の先端に新たなコンクリートを打設して該橋桁を延長形成する橋梁架設装置において、
上記足場型枠を、コンクリート打設位置と該コンクリート打設位置から外れた退避位置との間において移動させる足場型枠移動手段と、
所定の鉄筋カゴ供給位置で鉄筋カゴを吊り下げて、該鉄筋カゴを上記コンクリート打設位置へ搬送する鉄筋カゴ搬送手段と、を備えてなり、
上記鉄筋カゴ搬送手段が、上記鉄筋カゴを橋軸方向前方へ搬送する橋軸方向搬送手段を備えており、
上記退避位置が、上記コンクリート打設位置の下方位置に設定されており、
上記鉄筋カゴ搬送手段が、搬送途中で上記鉄筋カゴを上記橋軸方向搬送手段から上記足場型枠移動手段へ吊り換えるように構成されている、ことを特徴とするものであり、
また、本願第2の発明に係る橋梁架設装置は、
足場型枠を吊下支持する片持ち架設作業車を用い、施工中の橋桁の先端に新たなコンクリートを打設して該橋桁を延長形成する橋梁架設装置において、
上記足場型枠を、コンクリート打設位置と該コンクリート打設位置から外れた退避位置との間において移動させる足場型枠移動手段と、
所定の鉄筋カゴ供給位置で鉄筋カゴを吊り下げて、該鉄筋カゴを上記コンクリート打設位置へ搬送する鉄筋カゴ搬送手段と、を備えてなり、
上記退避位置が、上記コンクリート打設位置の橋軸方向前方位置に設定されている、ことを特徴とするものである。
【0010】
上記「鉄筋カゴ」とは、予め全部あるいは一部の鉄筋を組み立てたものを意味するものである。
【0011】
本願第2の発明において、上記「鉄筋カゴ搬送手段」は、単一の手段で上記鉄筋カゴを上記コンクリート打設位置へ搬送する構成としてもよいし、第1の手段で上記鉄筋カゴを途中まで搬送した後、第2の手段に吊り換えて(あるいはさらに第3の手段等に吊り換えて)上記コンクリート打設位置へ搬送する構成としてもよい。後者の場合、上記第2の手段(あるいは第3の手段等)として上記足場型枠移動手段を利用するようにしてもよい。
【0012】
上記「所定の鉄筋カゴ供給位置」は、上記鉄筋カゴを吊り下げてこれを上記コンクリート打設位置へ搬送することが可能な位置であれば、特定の位置に限定されるものではなく、例えば、橋脚近傍に設置された鉄筋カゴ組立ヤードあるいは上記コンクリート打設位置の下方に敷設されたレール上の位置等が採用可能である。
【0013】
【発明の作用効果】
上記構成に示すように、本願発明に係る橋梁架設装置は、上記片持ち架設作業車に吊下支持された足場型枠が、上記足場型枠移動手段により上記コンクリート打設位置および上記退避位置間で移動可能とされており、また、上記鉄筋カゴが、上記鉄筋カゴ搬送手段により上記鉄筋カゴ供給位置から上記コンクリート打設位置へ搬送されるようになっているが、
その際、本願第1の発明においては、上記鉄筋カゴ搬送手段が、上記鉄筋カゴを橋軸方向前方へ搬送する橋軸方向搬送手段を備えており、上記退避位置が、上記コンクリート打設位置の下方位置に設定されており、上記鉄筋カゴ搬送手段が、搬送途中で上記鉄筋カゴを上記橋軸方向搬送手段から上記足場型枠移動手段へ吊り換えるように構成されており、
また、本願第2の発明においては、上記退避位置が、上記コンクリート打設位置の橋軸方向前方位置に設定されているので、次のような作用効果を得ることができる。
【0014】
すなわち、上記足場型枠を上記退避位置へ移動させた状態で、上記鉄筋カゴを上記鉄筋カゴ供給位置から上記コンクリート打設位置へ搬送し、その後、上記足場型枠を上記コンクリート打設位置へ戻すようにすれば、従来上記コンクリート打設位置で行われていた鉄筋組作業を廃止してこれを完全にもしくは一部の継手施工を残してプレハブ化することができる。このため、施工を短時間でかつ低コストで行うことができる。
【0015】
したがって、本願発明によれば、張出し架設施工により橋桁を延長形成するように構成された橋梁架設装置において、施工の工期短縮および経済性向上を図ることができる。
【0016】
その際、本願第1の発明においては、上記鉄筋カゴ搬送手段が、上記鉄筋カゴを橋軸方向前方へ搬送する橋軸方向移動手段を備えた構成となっているので、上記鉄筋カゴを、橋脚近傍に設置された鉄筋カゴ組立ヤード等から上記コンクリート打設位置へ容易に搬送することが可能となる。
【0017】
また、本願第1の発明においては、上記「退避位置」が上記コンクリート打設位置の下方位置に設定されているので、上記足場型枠移動手段を簡易な構成とすることができる。一方、本願第2の発明においては、上記「退避位置」が上記コンクリート打設位置の橋軸方向前方位置に設定されているので、上記コンクリート打設位置の下方に十分なスペースがない場合においても、上記足場型枠を容易に退避させることが可能となる。
【0018】
さらに、本願第1の発明においては、上記鉄筋カゴ搬送手段の構成として、搬送途中で上記鉄筋カゴを上記橋軸方向移動手段から上記足場型枠移動手段へ吊り換える構成となっているので、上記足場型枠移動手段を上記鉄筋カゴ搬送手段の一部として活用することができ、橋梁架設装置の構成簡素化を図ることができる。
【0019】
本願第1の発明において、上記鉄筋カゴの吊換えを、該鉄筋カゴを上記橋軸方向搬送手段により上記橋桁の先端部まで搬送した後、該鉄筋カゴを上記退避位置にある上記足場型枠上に載置するとともに該鉄筋カゴの上記橋軸方向搬送手段に対する吊下状態を解除することにより行う構成とすれば、上記鉄筋カゴの吊換作業効率を高めることができ、かつ、上記足場型枠を上記コンクリート打設位置へ移動させる動作により上記鉄筋カゴについても同時に上記コンクリート打設位置へ移動させることができ、この点でも作業効率を高めることができる。
【0020】
なお、上記いずれの構成を採用した場合においても、それが上記片持ち架設作業車の能力を決定するほどの要因となるものではない。
【0021】
【発明の実施の形態】
以下、本願発明の実施形態について説明する。
【0022】
まず、本願発明に係る橋梁架設装置の第1実施形態について説明する。
【0023】
図1は、本実施形態に係る橋梁架設装置10を示す側面図であり、図2は、その左半分が図1のIIa-IIa 線矢視図、その右半分が図1のIIb-IIb 線矢視図である。
【0024】
これらの図に示すように、上記橋梁架設装置10は、足場型枠12を吊下支持するワーゲン14(片持ち架設作業車)を用い、施工中の橋桁2の先端に新たなコンクリートを打設して該橋桁2を延長形成するように構成されている。
【0025】
上記ワーゲン14は、上記橋桁2の先端部において橋軸方向前方へ突き出すように据え付けられる左右1対の菱形のメインフレーム16と、これら1対のメインフレーム16の上端部において上記橋軸方向と直交する水平方向に延び、上記両メインフレーム16を連結する前後1対の横梁18A、18Bとを備えてなっている。
【0026】
上記各メインフレーム16は、上記橋桁2の上面2aに敷設されたレール20上に載置されており、モータ22の駆動により該レール20上を橋軸方向に移動し得るように構成されている。また、上記各メインフレーム16は、その下部前端部においてメインジャッキ24により上記橋桁2に支持されるとともに、その下部後端部においてアンカー部材26により跳ね上がらないように抑止された状態でアンカージャッキ28により上記橋桁2に支持されている。
【0027】
上記各横梁18A、18Bの左右両端部には、電動チェーンブロック30を介してチェーン32が吊下支持されており、さらに、これらチェーン32の外側に隣接するようにして所定長のチャンネル材34Aが吊下支持されている。
【0028】
上記足場型枠12は、作業足場36と、この作業足場36に支持された型枠受け材38、40と、これら型枠受け材38、40に支持された外型枠42とを備えてなっている。
【0029】
上記作業足場36は、上記各横梁18A、18Bと略同一形状でこれら各横梁18A、18Bの真下に配置された前後1対の横梁44A、44Bと、これら1対の横梁44A、44Bの下方近傍において水平に配置された格子状足場部材46、48とからなり、上記各横梁44A、44Bの左右両端部において上記チェーン32の下端部に連結され、これにより上記各横梁18A、18Bに吊下支持されるようになっている。また、上記各横梁44A、44Bの左右両端部には、上記各チャンネル材34Aの真下に位置するようにして短尺チャンネル材34Bが上方へ突出するように固定されている。これら各短尺チャンネル材34Bは、上記電動チェーンブロック30の駆動により上記チェーン32が巻き上げられて上記足場型枠12がコンクリート打設位置Aまで上昇したとき、上記各チャンネル材34Aの下端部とピン結合により連結固定され、これにより上記足場型枠12が上記コンクリート打設位置Aに位置決めされるようになっている。
【0030】
さらに、上記ワーゲン14の前方側の横梁18Aには、左右1対の高さ調整機構50が取り付けられている。これら各高さ調整機構50は、上記横梁18Aに吊下固定されたフレーム52と、このフレーム52に取り付けられた高さ調整ジャッキ54と、上記フレーム52に吊下支持された1対のチャンネル材(またはPC鋼棒)56Aとを備えてなっている。上記1対のチャンネル材56Aは、上記足場型枠12が上記コンクリート打設位置Aまで上昇したとき、該足場型枠12の前方側の横梁44Aに固定された1対の短尺チャンネル材56Bとピン結合により連結固定されるようになっている。そして、この連結固定が行われた状態で、上記高さ調整ジャッキ54を駆動することにより、上記フレーム52に対する上記1対のチャンネル材56Aの吊下支持高さ位置の調整、すなわち上記足場型枠12の高さ位置の調整を行うようになっている。
【0031】
上記前方側の横梁18Aにおける上記各高さ調整機構50の外側には、上記足場型枠12が上記コンクリート打設位置Aまで上昇したとき、上記型枠受け材38の前端部に連結されて該型枠受け材38を吊下支持する1対の吊材(異形PC鋼棒)60が吊下固定されている。また、上記横梁18Aにおける上記各高さ調整機構50の内側にも1対の吊材(異形PC鋼棒)62が吊下固定されている。これら吊材62は、上記足場型枠12が上記コンクリート打設位置Aまで上昇したとき、内型枠64を支持する型枠受け材66の前端部に連結されて該型枠受け材66を吊下支持するようになっている。なお、上記型枠受け材66は、上記足場型枠12が上記コンクリート打設位置Aまで上昇したとき、上記橋桁2の上床面下面から橋軸方向前方へ所定量繰り出されるようになっている。
【0032】
上記橋梁架設装置10は、上記ワーゲン14のほかに左右1対の鉄筋カゴ搬送車68を備えている。
【0033】
これら各鉄筋カゴ搬送車68は、上記橋桁2の上面2aにおいて上記レール20の外側に位置するように敷設されたレール70上に載置されており、該鉄筋カゴ搬送車68に搭載されたモータ72の駆動により上記レール70上を橋軸方向に走行し得るように構成されている。そして、これら各鉄筋カゴ搬送車68は、その上部材が前後2個所において上記橋桁2の側縁部よりも側方まで張り出しており、該各上部材の側方先端部には、電動チェーンブロック74を介してチェーン76が各々吊下支持されている。これら前後1対のチェーン76の下端部は、橋軸方向と直交する水平方向に延びる前後1対の鉄筋カゴ支持梁78の両端部に各々連結されている。
【0034】
上記各鉄筋カゴ支持梁78には、所定間隔で複数の吊材80が吊下支持されており、これら各吊材80の下端部において鉄筋カゴ4を吊下支持するようになっている。なお、上記鉄筋カゴ4は、上記橋桁2の基端部の橋脚近傍に設置された鉄筋カゴ組立ヤードにおいて予め組立てが行われるようになっており、上記1対の鉄筋カゴ搬送車68により、吊下支持された状態で上記橋桁2の下面近傍に沿って上記橋軸方向前方へ搬送されるようになっている。
【0035】
上記鉄筋カゴ4は、後述するように、上記各鉄筋カゴ搬送車68が上記橋桁2の先端部まで移動した後、上記足場型枠12の外型枠42上に載置されて該外型枠42と共に上記コンクリート打設位置Aに移動せしめられるようになっているが、上記ワーゲン14には、上記鉄筋カゴ4を上記コンクリート打設位置Aにおいて位置決め支持するための鉄筋カゴ支持構造が設けられている。
【0036】
すなわち、上記ワーゲン14の両横梁18A、18Bの左右両端部近傍下面には、橋軸方向に延びる1対の梁82が設けられている。これら各梁82は、上記ワーゲン14の各メインフレーム16の上部材16aよりも後方まで張り出すように形成されている。そして、これら各梁82には、1対の吊下フック84が橋軸方向に移動可能に取り付けられており、これら吊下フック84により、上記コンクリート打設位置Aに移動せしめられた上記鉄筋カゴ4を、吊材(これについては後述する)を介して吊下支持するようになっている。
【0037】
次に、上記橋梁架設装置10による張出し架設施工の工程について、図3〜8を用いて説明する。
【0038】
まず、図3に示すように、前段のコンクリート打設位置Aoにおいてコンクリートの打設が行われると、該コンクリートの養生の後、PC鋼材の緊張および脱型が行われる。そして、上記各チャンネル材34Aと上記各短尺チャンネル材34Bとの連結が解除される。
【0039】
次に、図4に示すように、上記電動チェーンブロック30の駆動により上記チェーン32が繰り出されて上記足場型枠12が所定量降下せしめられる。一方、上記橋桁2にレール70がその先端まで延長敷設された後、上記鉄筋カゴ4を吊下支持した上記1対の鉄筋カゴ搬送車68が橋軸方向前方へ移動する。
【0040】
これにより、図5に示すように、上記両鉄筋カゴ搬送車68が上記橋桁2の先端部の上記外型枠42の真上位置まで移動すると、上記電動チェーンブロック74(図2参照)の駆動により上記チェーン76が繰り出されて上記鉄筋カゴ4が降下せしめられる。
【0041】
そして、図6に示すように、上記鉄筋カゴ4が上記外型枠42上に載置される位置まで降下せしめられると、上記鉄筋カゴ4から上記各吊材80が取り外されて上記チェーン76が巻き上げられ、上記両鉄筋カゴ搬送車68は橋脚近傍の鉄筋カゴ供給位置へ向けて橋軸方向後方へ移動する。
【0042】
次に、図7に示すように、上記ワーゲン14が橋軸方向前方へ移動して上記橋桁2の先端部に据え付けられ、その後、上記電動チェーンブロック30の駆動により上記チェーン32が巻き上げられて上記足場型枠12が上昇せしめられる。このとき上記足場型枠12に載置された上記鉄筋カゴ4も上記足場型枠12と共に上昇せしめられる。
【0043】
これにより、図8に示すように、上記足場型枠12および上記鉄筋カゴ4が次のコンクリート打設位置A1まで上昇せしめられると、上記各チャンネル材34Aと上記各短尺チャンネル材34Bとが連結されて、上記足場型枠12が上記コンクリート打設位置A1に位置決めされる。次に、上記鉄筋カゴ4が、上記各吊下フック84に吊材86を介して吊り下げられ、上記コンクリート打設位置A1の所定位置にセットされる。また、上記外型枠42も上記コンクリート打設位置A1の所定位置にセットされ、継手部の鉄筋組、横締位置調整およびシース接続が行われる。さらに、上記内型枠64(図2参照)も上記コンクリート打設位置A1の所定位置にセットされる。この状態で、上記コンクリート打設位置A1においてコンクリートの打設が行われる。すなわち、図3と同様の状態に戻る。
【0044】
以上詳述したように、本実施形態に係る橋梁架設装置10は、上記足場型枠12を上記ワーゲン14に吊下支持する上記チェーン32を、上記電動チェーンブロック30の駆動により繰り出して、上記足場型枠12を上記コンクリート打設位置Aの下方の退避位置へ移動させた後、橋軸方向に移動可能な上記左右1対の鉄筋カゴ搬送車68により、上記鉄筋カゴ4を吊り下げた状態でこれを上記橋脚近傍の鉄筋カゴ組立ヤードから上記橋桁2の先端部まで搬送し、該鉄筋カゴ4を上記退避位置にある上記足場型枠12上に載置し、その後、上記ワーゲン14を上記橋桁2の先端部まで移動させた後、上記足場型枠12を上記コンクリート打設位置Aまで上昇させることにより、上記鉄筋カゴ4も同時に上記コンクリート打設位置Aへ移動させるようになっているので、従来上記コンクリート打設位置Aで行われていた鉄筋組作業を廃止してこれを完全にもしくは一部の継手施工を残してプレハブ化することができる。このため、施工を短時間でかつ低コストで行うことができる。
【0045】
したがって、本実施形態によれば、張出し架設施工により橋桁を延長形成するように構成された橋梁架設装置において、施工の工期短縮および経済性向上を図ることができる。
【0046】
しかも、本実施形態においては、上記退避位置が上記コンクリート打設位置Aの下方位置に設定されているので、上記ワーゲン14に上記電動チェーンブロック30を新たに設けただけの簡単な構成で、上記足場型枠4の移動を行わせることができる。
【0047】
また、本実施形態においては、上記電動チェーンブロック74が取り付けられた上記1対の鉄筋カゴ搬送車68の採用により、上記鉄筋カゴ4を上記鉄筋カゴ組立ヤードから上記橋桁2の先端部まで容易に搬送することができる。
【0048】
さらに、本実施形態においては、上記鉄筋カゴ4を上記退避位置にある上記足場型枠12上に載置するとともに該鉄筋カゴ4の上記両鉄筋カゴ搬送車68に対する吊下状態を解除することにより、上記鉄筋カゴ4を上記両鉄筋カゴ搬送車68から上記ワーゲン14へ吊り換えるようになっているので、足場型枠移動用の上記電動チェーンブロック30を鉄筋搬送手段の一部として活用することができ、これにより上記橋梁架設装置10の構成簡素化を図ることができる。また、上記足場型枠12を上記コンクリート打設位置Aへ移動させる動作により上記鉄筋カゴ4についても同時に上記コンクリート打設位置Aへ移動させることができるので、作業効率を非常に高いものとすることができる。
【0049】
次に、本願発明に係る橋梁架設装置の第2実施形態について説明する。
【0050】
図9は、本実施形態に係る橋梁架設装置110を示す側面図である。
【0051】
図示のように、この橋梁架設装置110も、上記橋梁架設装置10と同様、足場型枠112を吊下支持するワーゲン114を用い、施工中の橋桁2の先端に新たなコンクリートを打設して該橋桁2を延長形成するようになっている。
【0052】
上記ワーゲン114の基本的構成は、上記ワーゲン14と同様であるが、その左右1対の菱形のメインフレーム116の上部材の上面に橋軸方向前方へ張り出す張出梁188が各々設けられており、これら各張出梁188の上面にはレール190が敷設されている。そして、前後1対の横梁118A、118Bは、橋軸方向に延びる連結材192により連結された状態で上記レール190上に載置され、図示しない駆動手段により橋軸方向にスライドし得るようになっている。
【0053】
上記足場型枠112は、上記足場型枠12と略同様の構成であるが、上記両横梁118A、118Bの両端部に吊下支持された前後1対のチャンネル材194により、常に上記コンクリート打設位置Aと同じ高さ位置に保持されるようになっている。
【0054】
そして、上記ワーゲン114においては、上記横梁118A、118を橋軸方向にスライドさせることにより、上記足場型枠112を上記コンクリート打設位置Aとその橋軸方向前方の退避位置との間において移動させることができるようになっている。
【0055】
本実施形態に係る橋梁架設装置110も、上記橋梁架設装置10と同様、上記鉄筋カゴ4を橋脚近傍の鉄筋カゴ組立ヤードから上記コンクリート打設位置Aへ搬送する左右1対の鉄筋カゴ搬送車168を備えているが、これら各鉄筋カゴ搬送車168の構成は上記各鉄筋カゴ搬送車68と全く同様である。
【0056】
次に、上記橋梁架設装置110による張出し架設施工の工程について、図10〜16を用いて説明する。
【0057】
まず、図10に示すように、前段のコンクリート打設位置Aoにおいてコンクリートの打設が行われると、コンクリートの養生が行われた後、PC鋼材の緊張および脱型が行われる。
【0058】
次に、図11に示すように、上記両横梁118A、118Bが橋軸方向前方へスライドして、上記足場型枠112が上記退避位置へ移動せしめられる。一方、上記橋桁2にレール170が該橋桁2の先端まで延長敷設された後、上記鉄筋カゴ4を吊下支持した上記1対の鉄筋カゴ搬送車168が橋軸方向前方へ移動する。
【0059】
これにより、図12に示すように、上記両鉄筋カゴ搬送車168が上記橋桁2の先端部まで移動すると、上記鉄筋カゴ4を吊り下げていた各チェーン176が上記両鉄筋カゴ搬送車168から取り外される。
【0060】
そして、図13に示すように、上記鉄筋カゴ4は、上記ワーゲン114の各梁182の前後2つの吊下フック184に吊下げられたチェーン186に取り付けられる。このようにして上記鉄筋カゴ4の吊換えが行われると、上記両鉄筋カゴ搬送車168は橋脚近傍の鉄筋カゴ供給位置へ向けて橋軸方向後方へ移動する。
【0061】
次に、図14に示すように、上記ワーゲン114が橋軸方向前方へ移動して上記橋桁2の先端部に据え付けられ、その後、電動チェーンブロック(図示せず)の駆動により上記チェーン186が巻き上げられ、上記鉄筋カゴ4が上昇せしめられる。
【0062】
これにより、図15に示すように、上記鉄筋カゴ4が次のコンクリート打設位置A1の所定位置まで上昇せしめられると、上記両横梁118A、118Bが橋軸方向後方へスライドする。
【0063】
そして、このスライドにより、図16に示すように、上記足場型枠112が上記コンクリート打設位置A1に位置決めされると、外型枠142が上記コンクリート打設位置A1の所定位置にセットされ、継手部の鉄筋組、横締位置調整およびシース接続が行われる。また、内型枠(図2の内型枠64参照)も上記コンクリート打設位置A1の所定位置にセットされる。この状態で、上記コンクリート打設位置A1においてコンクリートの打設が行われる。すなわち、図10と同様の状態に戻る。
【0064】
以上詳述したように、本実施形態に係る橋梁架設装置10は、上記両横梁118A、118Bのスライドにより、上記足場型枠112を上記コンクリート打設位置Aの橋軸方向前方の退避位置へ移動させた後、橋軸方向に移動可能な上記左右1対の鉄筋カゴ搬送車168により、上記鉄筋カゴ4を吊り下げた状態でこれを上記橋脚近傍の鉄筋カゴ組立ヤードから上記橋桁2の先端部まで搬送し、該鉄筋カゴ4を上記ワーゲン114に吊り換えた後、該ワーゲン14を上記橋桁2の先端部まで移動させ、その後、上記鉄筋カゴ4を上記コンクリート打設位置Aまで上昇させた後、上記足場型枠112を上記コンクリート打設位置Aへ戻すようになっているので、従来上記コンクリート打設位置Aで行われていた鉄筋組作業を廃止してこれを完全にもしくは一部の継手施工を残してプレハブ化することができる。このため、施工を短時間でかつ低コストで行うことができる。
【0065】
したがって、本実施形態によれば、張出し架設施工により橋桁を延長形成するように構成された橋梁架設装置において、施工の工期短縮および経済性向上を図ることができる。
【0066】
しかも、本実施形態においては、上記退避位置が上記コンクリート打設位置Aの橋軸方向前方位置に設定されているので、上記コンクリート打設位置Aの下方に十分なスペースがない場合においても、上記足場型枠112を、上記鉄筋カゴ4の搬送の邪魔にならない位置まで容易に退避させることができる。
【0067】
本実施形態においても、上記第1実施形態と同様、上記電動チェーンブロック174が取り付けられた上記1対の鉄筋カゴ搬送車168の採用により、上記鉄筋カゴ4を上記鉄筋カゴ組立ヤードから上記橋桁2の先端部まで容易に搬送することができる。
【0068】
ところで、上記第2実施形態においては、上記鉄筋カゴ4を吊り下げた状態でこれを上記橋脚近傍の鉄筋カゴ組立ヤードから上記コンクリート打設位置Aまで搬送するように構成された張出し架設施工例について説明したが、上記第2実施形態に係る橋梁架設装置110を用いることにより、図17に示すような張出し架設施工を行うことも可能である。
【0069】
すなわち、同図に示すように、上記両横梁118A、118Bのスライドにより、上記足場型枠112を上記コンクリート打設位置Aの橋軸方向前方の退避位置へ移動させた後、上記ワーゲン114の各梁182の前後2つの吊下フック184に吊下げられた上記チェーン186を長く繰り出して、上記コンクリート打設位置Aの真下の鉄筋カゴ供給位置において上記鉄筋カゴ4を吊り下げ、上記チェーン186を巻き上げることにより、上記鉄筋カゴ4を上記コンクリート打設位置Aまで上昇させ、その後、上記足場型枠112を上記コンクリート打設位置Aへ戻すように構成することも可能である。
【0070】
このような施工方法を採用することによっても、上記第2実施形態の施工方法と同様、従来上記コンクリート打設位置Aで行われていた鉄筋組作業を廃止してこれを完全にもしくは一部の継手施工を残してプレハブ化することができる。しかも、このような施工方法を採用することにより、施工工程が極めて単純化されるので、施工を短時間でかつ低コストで行うことができる。
【0071】
なお、上記コンクリート打設位置Aの真下の鉄筋カゴ供給位置は、上記橋桁2の施工が進行するに従って徐々に橋軸方向前方へ変化するが、レールを敷設してその上に鉄筋カゴ供給台車を載置すること等により、上記鉄筋カゴ供給位置の変化に対応することが可能である。
【図面の簡単な説明】
【図1】本願発明の第1実施形態に係る橋梁架設装置を示す側面図
【図2】左半分が図1のIIa-IIa 線矢視図、右半分が図1のIIb-IIb 線矢視図
【図3】上記橋梁架設装置による張出し架設施工の手順を示す工程図(その1)
【図4】上記張出し架設施工の手順を示す工程図(その2)
【図5】上記張出し架設施工の手順を示す工程図(その3)
【図6】上記張出し架設施工の手順を示す工程図(その4)
【図7】上記張出し架設施工の手順を示す工程図(その5)
【図8】上記張出し架設施工の手順を示す工程図(その6)
【図9】本願発明の第2実施形態に係る橋梁架設装置を示す側面図
【図10】上記橋梁架設装置による張出し架設施工の手順を示す工程図(その1)
【図11】上記張出し架設施工の手順を示す工程図(その2)
【図12】上記張出し架設施工の手順を示す工程図(その3)
【図13】上記張出し架設施工の手順を示す工程図(その4)
【図14】上記張出し架設施工の手順を示す工程図(その5)
【図15】上記張出し架設施工の手順を示す工程図(その6)
【図16】上記張出し架設施工の手順を示す工程図(その7)
【図17】上記第2実施形態に係る橋梁架設装置による他の張出し架設施工例を示す側面図
【符号の説明】
2 橋桁
2a 上面
4 鉄筋カゴ
10 橋梁架設装置
12 足場型枠
14 ワーゲン(片持ち架設作業車)(鉄筋カゴ搬送手段)
16 メインフレーム
18A、18B 横梁
20 レール
22 モータ
30 電動チェーンブロック(足場型枠移動手段)(鉄筋カゴ搬送手段)
32 チェーン
34A チャンネル材
34B 短尺チャンネル材
36 作業足場
38、40 型枠受け材
42、 外型枠
44A、44B 梁
46、48 格子状足場部材
50 高さ調整機構
52 フレーム
54 高さ調整ジャッキ
56A チャンネル材
56B 短尺チャンネル材
60、62 吊材(異形PC鋼棒)
64 内型枠
66 型枠受け材
68 鉄筋カゴ搬送車(橋軸方向搬送手段)(鉄筋カゴ搬送手段)
70 レール
72 モータ
74 電動チェーンブロック
76 チェーン
78 鉄筋カゴ支持梁
80 吊材
82 梁
84 吊下フック
86 吊材
110 橋梁架設装置
112 足場型枠
114 ワーゲン(片持ち架設作業車)(鉄筋カゴ搬送手段)
116 メインフレーム
118A、118B 横梁(足場型枠移動手段)
142 外型枠
164 内型枠
168 鉄筋カゴ搬送車(橋軸方向搬送手段)(鉄筋カゴ搬送手段)
170 レール
184 吊下フック
186 チェーン
188 張出梁
190 レール
192 連結材
194 チャンネル材
A コンクリート打設位置
Ao 前段のコンクリート打設位置
A1 コンクリート打設位置[0001]
[Industrial application fields]
The present invention relates to a bridge erection device configured to extend a bridge girder by an overhanging construction method.
[0002]
[Prior art]
Conventionally, an overhanging construction method is known as a construction method of a prestressed concrete bridge between large spans.
[0003]
This overhang construction method uses a cantilever construction work vehicle that suspends and supports a scaffold formwork (work scaffold and formwork), and casts new concrete at the tip of the bridge girder under construction to extend the bridge girder. Specifically, the construction is performed according to the following procedure.
[0004]
That is, first, after completing the construction at the concrete placement position in the previous stage, after moving the wagen forward in the direction of the bridge axis and installing it at the tip of the bridge girder, set the outer formwork at the concrete placement position, The lower slab reinforcing bar group, web reinforcing bar group and sheath connection were performed, the inner mold was set, the upper slab reinforcing bar group, laterally clamped steel material was placed and the sheath was connected, and then concrete was placed and cured. After that, tension and demolding of the PC steel material are performed.
[0005]
[Problems to be solved by the invention]
However, in the above-described conventional overhang construction method, the scaffolding formwork is suspended and fixed on the wage, and the rebar assembly work is performed at the concrete placement position, so the rebar is partially prefabricated. However, it cannot be prefabricated completely or with some joint constructions left behind. For this reason, a considerable time is required for the construction, and the construction cost is high.
[0006]
The present invention has been made in view of such circumstances, and in a bridge erection device configured to extend a bridge girder by overhanging construction, it is possible to shorten the construction period and improve the economic efficiency. The object is to provide a bridge erection device.
[0007]
[Means for Solving the Problems]
The invention of the present application achieves the above object by making the scaffold formwork a movable structure, and making it possible to transport the prefabricated rebar cage to the concrete placement position while leaving the joint construction completely or partially. It is intended to be illustrated.
[0008]
That is, this applicationFirstThe bridge erection device according to the invention is,
In a bridge erection device that uses a cantilever erection vehicle that supports the scaffold formwork in a suspended manner, and casts new concrete at the tip of the bridge girder under construction to extend the bridge girder,
A scaffold formwork moving means for moving the scaffold formwork between a concrete placement position and a retreat position deviated from the concrete placement position;
Rebar basket transport means for suspending the rebar basket at a predetermined rebar basket supply position and transporting the rebar basket to the concrete placing position.The
The rebar basket transport means includes a bridge axis direction transport means for transporting the rebar basket forward in the bridge axis direction,
The retracted position is set to a position below the concrete placing position,
The rebar basket transport means is configured to suspend the rebar basket from the bridge axis direction transport means to the scaffold formwork moving means in the middle of transport,
The bridge erection device according to the second invention of the present application is
In a bridge erection device that uses a cantilever erection vehicle that supports the scaffold formwork in a suspended manner, and casts new concrete at the tip of the bridge girder under construction to extend the bridge girder,
A scaffold formwork moving means for moving the scaffold formwork between a concrete placement position and a retreat position deviated from the concrete placement position;
Rebar basket transport means for suspending the rebar basket at a predetermined rebar basket supply position and transporting the rebar basket to the concrete placement position,
The retreat position is set to the bridge axial direction front position of the concrete placing position,It is characterized by this.
[0010]
The “reinforcing bar cage” means an assembly of all or part of reinforcing bars in advance.
[0011]
In the second invention of the present application,The “reinforcing bar transport means” may be configured to transport the reinforcing bar cage to the concrete placement position by a single means, or after the reinforcing bar is transported halfway by the first means, It is good also as a structure which conveys to the said concrete placement position by suspending to a means (or further suspending to 3rd means etc.). In the latter case, the scaffold formwork moving means may be used as the second means (or third means or the like).
[0012]
The “predetermined reinforcing bar supply position” is not limited to a specific position as long as it is a position where the reinforcing bar can be suspended and transported to the concrete placing position. It is possible to adopt a reinforcing bar basket assembly yard installed in the vicinity of a pier or a position on a rail laid below the concrete placing position.
[0013]
[Effects of the invention]
As shown in the above configuration, in the bridge erection device according to the present invention, the scaffold formwork suspended and supported by the cantilever construction work vehicle is moved between the concrete placement position and the retreat position by the scaffold formwork moving means. The rebar basket is transported from the rebar basket supply position to the concrete placement position by the rebar basket transport means.But,
In this case, in the first invention of the present application, the reinforcing bar transporting means includes bridge axis direction transporting means for transporting the reinforcing bar cage forward in the bridge axis direction, and the retracted position is the concrete placement position. It is set at a lower position, and the rebar basket transport means is configured to suspend the rebar basket from the bridge axis direction transport means to the scaffold formwork moving means during the transport,
In the second invention of the present application, the retreat position is set to a position in the bridge axis direction front position of the concrete placing position.Therefore, the following effects can be obtained.
[0014]
That is, with the scaffold formwork moved to the retracted position, the rebar cage is transported from the rebar basket supply position to the concrete placement position, and then the scaffold formwork is returned to the concrete placement position. By doing so, it is possible to abolish the rebar assembling work conventionally performed at the concrete placement position and to prefabricate it completely or with some joint constructions left. For this reason, construction can be performed in a short time and at low cost.
[0015]
Therefore, according to the present invention, in the bridge erection device configured to extend the bridge girder by overhanging construction, the construction period can be shortened and the economic efficiency can be improved.
[0016]
At that time, in the first invention of the present application,, Reinforcing bar cage transport meansBut,A structure provided with a bridge axis direction moving means for conveying the reinforcing bar cage forward in the bridge axis direction;Because it isThe rebar cage can be easily transported from the rebar cage assembly yard or the like installed near the pier to the concrete placement position.
[0017]
In the first invention of the present application,, `` Retraction position '' aboveButSet below the concrete placement positionBecauseThe scaffold formwork moving means can have a simple configuration.The On the other hand, in the second invention of the present application, the above"Evacuation position"ButSet to the front position in the bridge axis direction of the concrete placement positionBecauseEven when there is not enough space below the concrete placement position, the scaffold formwork can be easily retracted.
[0018]
Furthermore, in the first invention of the present application,The rebar cage transport means is configured to suspend the rebar basket from the bridge axis direction moving means to the scaffold formwork moving means during the transportation.Because it isIn addition, the scaffold formwork moving means can be used as a part of the rebar basket conveying means, and the configuration of the bridge laying device can be simplified.
[0019]
First invention of the present applicationIn the above,,After the rebar basket is transported to the tip of the bridge girder by the bridge axis direction transport means, the rebar cage is placed on the scaffolding formwork at the retracted position and the rebar cage direction transport means of the rebar cage If the structure is performed by releasing the suspended state with respect to the reinforcing bar, the rebar cage can be reworked efficiently and the rebar cage is moved by moving the scaffold formwork to the concrete placement position. At the same time, it can be moved to the concrete placement position, and the working efficiency can be improved in this respect as well.
[0020]
In addition, in any case of adopting any of the above-described configurations, it does not become a factor that determines the ability of the cantilever erection work vehicle.
[0021]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described.
[0022]
First, a first embodiment of a bridge erection device according to the present invention will be described.
[0023]
FIG. 1 is a side view showing a
[0024]
As shown in these figures, the
[0025]
The
[0026]
Each
[0027]
A
[0028]
The
[0029]
The working
[0030]
Further, a pair of left and right
[0031]
On the outer side of each of the
[0032]
The
[0033]
Each of the reinforcing
[0034]
A plurality of
[0035]
As will be described later, the
[0036]
That is, a pair of
[0037]
Next, the overhanging construction process by the
[0038]
First, as shown in FIG. 3, when concrete is placed at the preceding concrete placement position Ao, the PC steel is tensioned and demolded after the concrete is cured. Then, the connection between each
[0039]
Next, as shown in FIG. 4, the
[0040]
As a result, as shown in FIG. 5, when the both-rebar
[0041]
Then, as shown in FIG. 6, when the
[0042]
Next, as shown in FIG. 7, the
[0043]
Thus, as shown in FIG. 8, when the
[0044]
As described above in detail, the
[0045]
Therefore, according to this embodiment, in the bridge erection device configured to extend the bridge girder by overhanging construction, it is possible to shorten the construction period and improve the economic efficiency.
[0046]
Moreover, in the present embodiment, since the retracted position is set at a position below the concrete placing position A, the
[0047]
Moreover, in this embodiment, by adopting the pair of reinforcing
[0048]
Further, in the present embodiment, the reinforcing
[0049]
Next, a second embodiment of the bridge erection device according to the present invention will be described.
[0050]
FIG. 9 is a side view showing the
[0051]
As shown in the figure, the
[0052]
The basic configuration of the
[0053]
The
[0054]
Then, in the
[0055]
The
[0056]
Next, the overhanging construction process by the
[0057]
First, as shown in FIG. 10, when concrete is placed at the preceding concrete placement position Ao, the concrete is cured, and then the PC steel is tensioned and demolded.
[0058]
Next, as shown in FIG. 11, the both
[0059]
Accordingly, as shown in FIG. 12, when both the rebar
[0060]
As shown in FIG. 13, the
[0061]
Next, as shown in FIG. 14, the
[0062]
As a result, as shown in FIG. 15, when the
[0063]
Then, by this slide, as shown in FIG. 16, when the
[0064]
As described above in detail, the
[0065]
Therefore, according to this embodiment, in the bridge erection device configured to extend the bridge girder by overhanging construction, it is possible to shorten the construction period and improve the economic efficiency.
[0066]
Moreover, in the present embodiment, since the retracted position is set at the bridge axial direction front position of the concrete placing position A, even when there is not enough space below the concrete placing position A, The
[0067]
Also in the present embodiment, similarly to the first embodiment, the
[0068]
By the way, in the said 2nd Embodiment, about the overhang construction example comprised so that it might convey to the said concrete placement position A from the rebar basket assembly yard near the said pier in the state which suspended the said
[0069]
That is, as shown in the figure, the
[0070]
By adopting such a construction method as well as the construction method of the second embodiment, the rebar assembling work conventionally performed at the concrete placing position A is abolished and this is completely or partially performed. It can be prefabricated, leaving the joint construction. In addition, by adopting such a construction method, the construction process is extremely simplified, so that construction can be performed in a short time and at low cost.
[0071]
In addition, the reinforcing bar supply position directly below the concrete placement position A gradually changes forward in the direction of the bridge axis as the construction of the
[Brief description of the drawings]
FIG. 1 is a side view showing a bridge erection device according to a first embodiment of the present invention.
2] Left half view taken along line IIa-IIa in FIG. 1, right half taken along line IIb-IIb in FIG.
FIG. 3 is a process diagram (No. 1) showing the procedure of overhang construction by the bridge erection device.
FIG. 4 is a process diagram showing the procedure for overhang construction (part 2).
FIG. 5 is a process diagram showing the procedure for overhang construction (Part 3).
FIG. 6 is a process diagram showing the procedure for overhang construction (Part 4).
FIG. 7 is a process diagram showing the procedure for overhang construction (No. 5).
FIG. 8 is a process diagram showing the procedure for overhang construction (No. 6)
FIG. 9 is a side view showing a bridge erection device according to a second embodiment of the present invention.
FIG. 10 is a process diagram showing the procedure of overhang construction by the bridge erection device (part 1).
FIG. 11 is a process diagram showing the procedure for overhang construction (Part 2).
FIG. 12 is a process diagram showing the procedure for overhang construction (Part 3).
FIG. 13 is a process diagram showing the procedure for overhang construction (Part 4).
FIG. 14 is a process diagram showing the procedure for overhang construction (No. 5).
FIG. 15 is a process diagram (No. 6) showing the procedure of the overhang construction work.
FIG. 16 is a process diagram (No. 7) showing the procedure of the overhang construction work.
FIG. 17 is a side view showing another overhanging construction example by the bridge erection device according to the second embodiment.
[Explanation of symbols]
2 Bridge girder
2a Top view
4 Rebar basket
10 Bridge erection device
12 scaffolding formwork
14 Wagen (cantilever erection work vehicle) (reinforcing bar cage transportation means)
16 Mainframe
18A, 18B Horizontal beam
20 rails
22 Motor
30 Electric chain block (scaffolding form moving means) (rebar cage transport means)
32 chain
34A channel material
34B short channel material
36 Working scaffold
38, 40 Formwork receiving material
42, outer formwork
44A, 44B Beam
46, 48 Lattice-like scaffold member
50 Height adjustment mechanism
52 frames
54 Height adjustment jack
56A channel material
56B short channel material
60, 62 Suspension material (deformed PC steel bar)
64 Inside formwork
66 Formwork receiving material
68 Reinforcing bar cage transport vehicle (bridge axial direction conveying means) (reinforcing bar cage conveying means)
70 rails
72 motor
74 Electric chain block
76 chain
78 Reinforcing bar cage support beam
80 Hanging material
82 Beam
84 Hanging hook
86 Hanging material
110 Bridge erection device
112 scaffold formwork
114 Wagen (cantilever erection vehicle) (reinforcing bar transport means)
116 mainframe
118A, 118B Cross beam (scaffolding formwork moving means)
142 External formwork
164 Inside formwork
168 Reinforcing Bar Carriage Car (Bridge Axis Direction Carrying Means) (Reinforcing Bar Basket Carrying Means)
170 rails
184 Hanging hook
186 chain
188
190 rails
192 connecting materials
194 Channel material
A Concrete placement position
Ao Previous concrete placement position
A1 concrete placement position
Claims (4)
上記足場型枠を、コンクリート打設位置と該コンクリート打設位置から外れた退避位置との間において移動させる足場型枠移動手段と、
所定の鉄筋カゴ供給位置で鉄筋カゴを吊り下げて、該鉄筋カゴを上記コンクリート打設位置へ搬送する鉄筋カゴ搬送手段と、を備えてなり、
上記鉄筋カゴ搬送手段が、上記鉄筋カゴを橋軸方向前方へ搬送する橋軸方向搬送手段を備えており、
上記退避位置が、上記コンクリート打設位置の下方位置に設定されており、
上記鉄筋カゴ搬送手段が、搬送途中で上記鉄筋カゴを上記橋軸方向搬送手段から上記足場型枠移動手段へ吊り換えるように構成されている、ことを特徴とする橋梁架設装置。In a bridge erection device that uses a cantilever erection vehicle that supports the scaffold formwork in a suspended manner, and casts new concrete at the tip of the bridge girder under construction to extend the bridge girder,
A scaffold formwork moving means for moving the scaffold formwork between a concrete placement position and a retreat position deviated from the concrete placement position;
Suspending the rebar cage at a predetermined rebar cage supply position, Ri and iron muscle car name and and a reinforcing steel cage transporting means for transporting into the concreting position,
The rebar basket transport means includes a bridge axis direction transport means for transporting the rebar basket forward in the bridge axis direction,
The retracted position is set to a position below the concrete placing position,
The bridge erection device , wherein the reinforcing bar transport means is configured to suspend the reinforcing bar cage from the bridge axial direction transport means to the scaffold formwork moving means during the transport .
上記足場型枠を、コンクリート打設位置と該コンクリート打設位置から外れた退避位置との間において移動させる足場型枠移動手段と、
所定の鉄筋カゴ供給位置で鉄筋カゴを吊り下げて、該鉄筋カゴを上記コンクリート打設位置へ搬送する鉄筋カゴ搬送手段と、を備えてなり、
上記退避位置が、上記コンクリート打設位置の橋軸方向前方位置に設定されている、ことを特徴とする橋梁架設装置。 In a bridge erection device that uses a cantilever erection vehicle that supports the scaffold formwork in a suspended manner, and casts new concrete at the tip of the bridge girder under construction to extend the bridge girder,
A scaffold formwork moving means for moving the scaffold formwork between a concrete placement position and a retreat position deviated from the concrete placement position;
Rebar basket transport means for suspending the rebar basket at a predetermined rebar basket supply position and transporting the rebar basket to the concrete placement position,
The retracted position is set to the bridge axis forward position of the concreting position, bridges bridging device you wherein a.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP07486998A JP3946342B2 (en) | 1998-03-09 | 1998-03-09 | Bridge erection device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP07486998A JP3946342B2 (en) | 1998-03-09 | 1998-03-09 | Bridge erection device |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11256521A JPH11256521A (en) | 1999-09-21 |
JP3946342B2 true JP3946342B2 (en) | 2007-07-18 |
Family
ID=13559779
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP07486998A Expired - Fee Related JP3946342B2 (en) | 1998-03-09 | 1998-03-09 | Bridge erection device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3946342B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101845795A (en) * | 2010-05-17 | 2010-09-29 | 广东省长大公路工程有限公司 | Cable-stayed cradle of adjustment-free cable tension long platform in construction of cable-stayed bridge |
CN108677754A (en) * | 2018-05-08 | 2018-10-19 | 中铁十五局集团有限公司 | A kind of cantilever cradle for the construction of concrete continuous beam variable cross section |
CN108867406A (en) * | 2018-06-14 | 2018-11-23 | 中铁三局集团有限公司 | A kind of construction method for being applicable in base-supporting Hanging Basket closure segment and quickly positioning |
Families Citing this family (49)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4361775B2 (en) * | 2003-11-10 | 2009-11-11 | 株式会社富士ピー・エス | Bridge erection method and bridge erection device |
JP5279347B2 (en) * | 2008-06-03 | 2013-09-04 | 鹿島建設株式会社 | Hydraulic control system for mobile work vehicles for cantilever installation |
CN101942809A (en) * | 2010-09-30 | 2011-01-12 | 中铁四局集团第一工程有限公司 | Hanging-basket main-truss prepressing system |
CN102102342A (en) * | 2010-12-30 | 2011-06-22 | 广东省航盛建设集团有限公司 | Integral-structure type rear upper separator of diamond cradle |
CN102220740B (en) * | 2011-04-13 | 2012-09-26 | 湖南中铁五新钢模有限责任公司 | Cantilever-concreting construction hanging basket for four-lane and wide-width continuous beam of high-speed rail |
CN102134834A (en) * | 2011-04-29 | 2011-07-27 | 湖南中铁五新钢模有限责任公司 | Small pier construction diamond cradle |
CN102330414B (en) * | 2011-08-09 | 2013-04-03 | 中铁十二局集团第二工程有限公司 | Hanging basket cantilever method construction method of large-span continuous rigid beam sidespan cast-in-place beam section |
JP5711179B2 (en) * | 2012-04-17 | 2015-04-30 | 川田建設株式会社 | Construction method of superstructure in elevated structure |
CN103628423A (en) * | 2012-08-25 | 2014-03-12 | 江苏雄宇重工科技股份有限公司 | Bevel hanging basket for triangular truss bridge |
CN104294768B (en) * | 2012-12-12 | 2016-01-27 | 中铁上海工程局有限公司 | Hanging Basket crosses the construction method of mast foundation for overhead contact wire system |
CN103046477B (en) * | 2012-12-31 | 2014-10-29 | 中铁十局集团第二工程有限公司 | Traveling-rail-free type triangular hanging basket traveling construction method |
CN103669217B (en) * | 2013-11-21 | 2017-12-05 | 中建三局建设工程股份有限公司 | A kind of rear-support hanging basket and its entirety change width method for traversing |
KR101657994B1 (en) * | 2014-05-22 | 2016-09-20 | 김남열 | Form traveler, and bridge construction method for using the same |
CN104264589B (en) * | 2014-09-26 | 2016-02-17 | 上海城建市政工程(集团)有限公司 | A kind of Hanging Basket status real time monitor method |
CN104480859B (en) * | 2014-10-21 | 2016-06-08 | 中铁建大桥工程局集团第五工程有限公司 | A kind of Hanging Basket entirety traveling test method |
CN104631341A (en) * | 2015-01-29 | 2015-05-20 | 中铁港航局集团有限公司 | Novel hanging basket prepressing system and detecting method thereof |
CN104612061B (en) * | 2015-02-05 | 2016-08-24 | 中铁上海工程局集团第五工程有限公司 | A kind of suspension open type hanging basket device and construction method thereof |
CN104652289B (en) * | 2015-03-20 | 2016-06-08 | 中建三局第三建设工程有限责任公司 | Dragging suspension basket slide installation method |
CN105002833B (en) * | 2015-07-25 | 2016-10-12 | 西安科技大学 | Suspension Hanging Basket preloading method |
CN105714691B (en) * | 2016-02-19 | 2017-06-09 | 四川公路桥梁建设集团有限公司 | A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method |
CN105735146B (en) * | 2016-03-11 | 2017-11-03 | 广东省长大公路工程有限公司 | The different rope construction method of dragging suspension basket of concrete deck cable stayed bridge |
CN105625195B (en) * | 2016-03-16 | 2017-10-20 | 河南大建桥梁钢构股份有限公司 | Wave forms steel web SCC engineering methods movable hanging basket and its construction method |
CN105908626A (en) * | 2016-04-15 | 2016-08-31 | 中铁五局集团有限公司 | Self-balancing reverse locking wheel structure of suspension basket |
CN105926463B (en) * | 2016-05-11 | 2017-08-25 | 山东博远重工有限公司 | A kind of Hanging Basket safety monitoring system |
CN105926464A (en) * | 2016-06-17 | 2016-09-07 | 贵州路桥集团有限公司 | Inverted hanging type trapezoid inclined climbing form traveler |
JP6752160B2 (en) * | 2017-01-13 | 2020-09-09 | 鹿島建設株式会社 | Mobile work vehicle |
CN106836011A (en) * | 2017-02-15 | 2017-06-13 | 中铁十九局集团第七工程有限公司 | Hanging Basket running gear and its construction method |
CN106812069B (en) * | 2017-03-01 | 2019-04-12 | 杭州市交通工程集团有限公司 | The bottom basket downward putting device and method of the high buttress Hanging Basket in mountain area |
CN107130526A (en) * | 2017-05-17 | 2017-09-05 | 贵州路桥集团有限公司 | A kind of Hanging Basket uses the traveling method of this device with towed running gear and Hanging Basket |
CN107761570B (en) * | 2017-09-30 | 2019-02-15 | 中铁大桥局集团有限公司 | A kind of accurate positioning hanger for longspan steel truss girder |
CN107761575A (en) * | 2017-10-19 | 2018-03-06 | 中交路桥华南工程有限公司 | Ultra-wide box beam Hanging Basket and its bottom basket system |
CN109868755B (en) * | 2019-04-09 | 2024-02-20 | 上海市机械施工集团有限公司 | Hanging basket construction method for diamond truss hanging basket and cantilever beam |
CN110004839A (en) * | 2019-04-18 | 2019-07-12 | 联建建设工程有限公司 | Large span front fulcrum dragging suspension basket installation method |
JP7290554B2 (en) * | 2019-04-18 | 2023-06-13 | 鹿島建設株式会社 | A formwork system comprising a formwork and a lifting device for lifting the formwork and the formwork |
CN110080117B (en) * | 2019-06-03 | 2021-04-20 | 倡创(上海)咨询管理事务所 | Movable simple concrete guardrail template vehicle and manufacturing method thereof |
CN111042004A (en) * | 2019-12-06 | 2020-04-21 | 中铁广州工程局集团有限公司 | Hanging basket track beam traveling method |
CN110965477B (en) * | 2019-12-19 | 2021-05-25 | 德州市公路工程总公司 | Construction method for shaped easy-to-detach hanging bracket of mid-span closure section of suspension casting box beam |
CN111501558A (en) * | 2020-03-31 | 2020-08-07 | 上海城建市政工程(集团)有限公司 | Construction method of three-span variable-height steel-concrete mixed continuous beam |
CN112279164A (en) * | 2020-10-29 | 2021-01-29 | 中铁一局集团有限公司 | Light track beam construction trolley |
CN112900287B (en) * | 2021-03-11 | 2023-01-24 | 中铁十六局集团第五工程有限公司 | Cantilever perfusion bridge fabrication machine |
CN113152302B (en) * | 2021-05-13 | 2022-12-06 | 中建八局第二建设有限公司 | Automatic moving device for continuous beam bridge hanging basket |
CN113417219B (en) * | 2021-05-31 | 2022-11-01 | 中铁十二局集团有限公司 | Hydraulic internal mold asynchronous traveling system and method for bridge suspension casting basket box chamber |
CN113430953B (en) * | 2021-07-28 | 2022-10-28 | 江苏瑞沃建设集团有限公司 | Pre-compaction device of hanging basket for cantilever construction bridge support |
CN114351602B (en) * | 2022-01-21 | 2023-10-17 | 江苏中车城市发展有限公司 | Hanging basket sliding system for viaduct |
CN114673097B (en) * | 2022-03-03 | 2023-08-29 | 福建建工基础设施建设集团有限公司 | Locking device and method for anchor point after basket hanging |
CN114673093B (en) * | 2022-03-29 | 2024-03-15 | 山东交工建设集团有限公司 | Temporary fixing device and method for hoisting construction rear end of reinforced concrete combined section |
CN115162204B (en) * | 2022-08-24 | 2024-06-14 | 中建八局第一建设有限公司 | Bridge concrete box Liang Zihang type self-adaptive vibrating device |
CN115402929A (en) * | 2022-08-30 | 2022-11-29 | 湖南中铁五新模板工程服务有限公司 | Crane for integral hoisting of continuous beam reinforcement cage and hoisting method thereof |
CN115897417B (en) * | 2022-10-28 | 2024-05-07 | 中铁上海工程局集团有限公司 | Template construction method and device in cantilever casting continuous beam process |
-
1998
- 1998-03-09 JP JP07486998A patent/JP3946342B2/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101845795A (en) * | 2010-05-17 | 2010-09-29 | 广东省长大公路工程有限公司 | Cable-stayed cradle of adjustment-free cable tension long platform in construction of cable-stayed bridge |
CN101845795B (en) * | 2010-05-17 | 2012-07-18 | 广东省长大公路工程有限公司 | Cable-stayed cradle of adjustment-free cable tension long platform in construction of cable-stayed bridge |
CN108677754A (en) * | 2018-05-08 | 2018-10-19 | 中铁十五局集团有限公司 | A kind of cantilever cradle for the construction of concrete continuous beam variable cross section |
CN108867406A (en) * | 2018-06-14 | 2018-11-23 | 中铁三局集团有限公司 | A kind of construction method for being applicable in base-supporting Hanging Basket closure segment and quickly positioning |
Also Published As
Publication number | Publication date |
---|---|
JPH11256521A (en) | 1999-09-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3946342B2 (en) | Bridge erection device | |
JP3721166B2 (en) | Floor slab erection device | |
JP4403051B2 (en) | Corrugated steel web bridge construction method | |
JP4748420B2 (en) | Construction method of corrugated steel web bridge using girder for erection work | |
JP5409178B2 (en) | Construction method of concrete bridge and moving work apparatus used in the construction method | |
JP2000265417A (en) | Moving timbering construction method for bridge floor slab overhang section | |
CN109267490B (en) | Long guide beam type movable formwork and construction method thereof | |
JP6713420B2 (en) | Rebar cage relocation device | |
JP7042706B2 (en) | Deck erection method | |
CN111996916A (en) | Cast-in-place box girder integrated construction equipment and construction method thereof | |
JP5184248B2 (en) | Construction method of level crossing | |
JP2768283B2 (en) | Bridge construction method | |
JP2894226B2 (en) | Bridge construction method | |
JP4329535B2 (en) | Mobile work vehicle for overhanging slabs | |
JP2768280B2 (en) | Bridge construction method | |
JP6468605B2 (en) | Method for attaching traveling device in concrete formwork support device | |
JP2004225275A (en) | Erection apparatus for corrugated steel plate web box girder bridge, and construction method for corrugated steel plate web box girder bridge | |
JPS6041165B2 (en) | Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections. | |
JP2020122359A (en) | Floor slab erection system, additional floor slab installation method, and floor slab removing method | |
JP6713419B2 (en) | Suspension method and suspension structure | |
JP3141775B2 (en) | Main girder rebar construction method and device for PC bridge | |
JP2768279B2 (en) | Construction girder for precast block method | |
JP2001020227A (en) | Carrying method of corrugated steel plate web member in bridge execution | |
JPH0689527B2 (en) | Construction work vehicle for PC cable-stayed bridge | |
JP3326724B2 (en) | Construction method of concrete cable-stayed bridge and form support trolley used for it |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040823 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060915 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060926 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20061114 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070410 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070411 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130420 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130420 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20160420 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |