CN105714691B - A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method - Google Patents

A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method Download PDF

Info

Publication number
CN105714691B
CN105714691B CN201610091967.4A CN201610091967A CN105714691B CN 105714691 B CN105714691 B CN 105714691B CN 201610091967 A CN201610091967 A CN 201610091967A CN 105714691 B CN105714691 B CN 105714691B
Authority
CN
China
Prior art keywords
hanging basket
anchor
traversing
long rails
stayed bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610091967.4A
Other languages
Chinese (zh)
Other versions
CN105714691A (en
Inventor
詹伟
徐国挺
徐威
陈雷
柏国胜
万中兵
李元华
姜笠
周晓玺
汪捍东
宋永安
刘欢
毛杰
张洪斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Road and Bridge Group Co Ltd
Original Assignee
Sichuan Road and Bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Road and Bridge Group Co Ltd filed Critical Sichuan Road and Bridge Group Co Ltd
Priority to CN201610091967.4A priority Critical patent/CN105714691B/en
Publication of CN105714691A publication Critical patent/CN105714691A/en
Application granted granted Critical
Publication of CN105714691B publication Critical patent/CN105714691B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges

Abstract

The invention discloses a kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method, it is short and small for solving curve low-pylon cable-stayed bridge 0# beam sections, Hanging Basket cannot normal mounting problem, using Hanging Basket both sides respectively stagger half interlock overlap joint install, after the completion of the construction of 1# beam sections, first by hanging basket advancing, by rear anchor point particular design, will grow up the traversing playback of Hanging Basket.The present invention has saved cost, has shortened the duration by the ingenious design to Hanging Basket traversing construction, rationally design, easy construction relative to conventional method.

Description

A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method
Technical field
The present invention relates to a kind of hanging basket cantilever method construction, in particular to a kind of curve low-pylon cable-stayed bridge Hanging Basket is short Special arrangement and traversing construction method in small 0# beam sections.
Background technology
At present, Hanging Basket cantilever pouring construction has been a kind of ripe cast-in-place construction technique, and the design and installation of Hanging Basket are these The core of technique, the installation spelling of Hanging Basket is the whole substantial first step of Hanging Basket cantilever construction for concrete operations, It is a most important link.When some specific type bridges are run into, traditional cradle assembly scheme generally requires to make Change can adapt to construction.Especially in some bridges, 0# section box girder length is shorter, and design Hanging Basket main longitudinal grider because Some cause specifics must are fulfilled for certain length condition, and the solution generally directed to this contradiction is forced to change Hanging Basket Form is processed by the way of being connect using first having no progeny main longitudinal grider, and construction is extremely bothered.
The content of the invention
It is short and small it is an object of the invention to solve curve low-pylon cable-stayed bridge 0# beam sections, Hanging Basket cannot normal mounting problem, A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method are provided herein, existing Hanging Basket is made full use of to reach Purpose, in the case where construction input is relatively fewer, solves 0# sections of Hanging Basket of curve low-pylon cable-stayed bridge and be unable to normal mounting and ask Topic.
The present invention is achieved in that a kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement of construction and traversing construction method, It is characterized in that:Comprise the following steps:
(1)Hanging Basket is staggered installation of:No. 0 beam section is poured after completing and reaching design strength, in addition to side form Board position is constant, The overall relative design attitude transverse translation b/2+50mm of Hanging Basket is installed(B is the width of main longitudinal grider 115), Hanging Basket is according to normal sequence peace Dress, position of the skid beam suspension rod on preceding entablature direction opposite direction movement 30cm traversing relative to Hanging Basket;
(2)Hanging basket advancing:After No. 1 beam section pours and completes and reach intensity, size pile No. Hanging Basket is moved forward L/2(L is The interlaced lap of splice of the Hanging Basket of large and small mileage two), traversing space is provided to Hanging Basket, anchor after being anchored after hanging basket advancing;
(3)Long rails move forward:Before cross track is installed, long rails should be moved forward, track reach distance The installation of cross track when not blocking traversing should be reached;
(4)Drop-over steel plate is installed:At central bearing point, Hanging Basket of jack-uping installs longitudinal direction being staggered installation of with normotopia Track is installed below drop-over steel plate, and the coating lubricating oil on drop-over steel plate;
(5)Cross track is installed:Track has been transversely mounted it and has anchored in the position of rear anchor dolly, and rear anchor dolly has been rotated 90 ° are anchored on cross track;
(6)Reaction frame is installed:Reaction frame is welded at Hanging Basket fulcrum, reaction frame is welded on pre-buried good steel plate;
(7)Jack is installed:Hydraulic jack is installed at central bearing point after being welded reaction frame;
(8)Anchor constraint, makes rear anchor be separated with beam body after dismounting, transfers force on rear anchor dolly, and in each rear anchor point One 5t chain block is respectively installed;
(9)Anchor point chain block tensed with long rails at jack pushing tow fulcrum simultaneously after, makes Hanging Basket together with longitudinal rail Road slowly slides transverse translation to design attitude on drop-over steel plate, anchor fining twisted steel and is anchored after then installing;
(10)Anchor point cross track after dismounting, and move long rails afterwards and anchor, anchored after rear anchor dolly is rotated by 90 ° On long rails;
(11)Edge of a wing skid beam suspension rod is reinstalled in normotopia, and is anchored;
(12)Anchor after dismounting, two sets of Hanging Baskets symmetrically move forward to No. 2 beam section positions and anchor on request, complete No. 2 beam sections and hang Basket is in place, into next procedure construction.
Curve low-pylon cable-stayed bridge Hanging Basket of the present invention is staggered installation of and traversing construction method, in the traversing playback of Hanging Basket When, anchor point carries out track and dolly is rotated by 90 ° after Hanging Basket, and it is rolling friction to become sliding friction.
In the traversing playback of Hanging Basket, many methods of hydraulic jack are controlled using same oil pump and oil meter combination banked direction control valves Control jacking force, it is ensured that each point stress equalization, prevents larger internal force influence Hanging Basket resistance to overturning.
The advantage of the invention is that:Compared with prior art, the beneficial effects of the present invention are:
(1)The cost-effective, duration:After being such as staggered installation of using Hanging Basket, remove Hanging Basket reinstall, it is necessary to artificial, material, 200,000 yuan of the expenses such as plant equipment, reinstalling Hanging Basket need to be with 20 days time, it is necessary to pay site operation expense and administration fee Totally 10 ten thousand yuan.And after using this construction technology, it is only necessary to 20,000 yuan of the expense such as artificial, material, plant equipment, the engineering time only needs 2 It is, it is necessary to pay site operation expense and administration fee less than 10,000 yuan.
(2)Hanging Basket is staggered installation of and whole lateral moving construction stress is clear and definite, and safe and reliable, economic and practical, technology is easily mastered, The construction period can be shortened and reduced investment outlay, be a kind of construction method being worthy to be popularized.
Brief description of the drawings
Fig. 1 is Hanging Basket interlaced arrangement figure of the present invention
Fig. 2 is that Hanging Basket side of the present invention regards intention
Fig. 3 is that Hanging Basket facade of the present invention regards intention
In figure:101st, 0# beam sections, 102,1# beam sections, 103,2# beam sections, 104, side template, 105, skid beam suspension rod, 106, preceding Entablature, 107, rear anchor, 108, long rails, 109, cross track, 110, drop-over steel plate, 111, jack, 112, rear anchor it is small Car, 113, reaction frame, 114, central bearing point, 115, main longitudinal grider.
Specific embodiment
Below in conjunction with accompanying drawing, the present invention is described in detail, and the technical scheme in the embodiment of the present invention is carried out clearly Chu, it is fully described by, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments. Based on the embodiment in the present invention, it is all that those of ordinary skill in the art are obtained under the premise of creative work is not made Other embodiment, belongs to the scope of protection of the invention.
Arranged and traversing construction method on short and small 0# section box girders the invention discloses a kind of Hanging Basket of growing up, especially related to And be curve low-pylon cable-stayed bridge Hanging Basket cantilever construction technology.Solution curve low-pylon cable-stayed bridge 0# beam sections are short and small, and Hanging Basket cannot be just Often install problem, using Hanging Basket both sides respectively stagger half interlock overlap joint install, 1# beam sections construction after the completion of, first by before Hanging Basket Move, by rear anchor point particular design, will grow up the traversing playback of Hanging Basket.The present invention is by the ingenious structure to Hanging Basket traversing construction Think, rationally design, easy construction has saved cost, shortened the duration relative to conventional method.
The present invention is described in detail below in conjunction with the accompanying drawings:
(1)Hanging Basket is staggered installation of:No. 0 beam section 101 is poured after completing and reaching design strength, except the position of side template 104 not Become outer, the overall relative design attitude transverse translation b/2+50mm of Hanging Basket is installed(B is the width of main longitudinal grider 115).Hanging Basket is according to normal Order is installed, position of the skid beam suspension rod 105 on preceding entablature 106 direction opposite direction movement 30cm traversing relative to Hanging Basket.
(2)Hanging basket advancing:After No. 1 beam section 102 pours and completes and reach intensity, size pile No. Hanging Basket is moved forward L/2 (L is the interlaced lap of splice of the Hanging Basket of large and small mileage two), provides traversing space, anchor after being anchored after hanging basket advancing to Hanging Basket 107。
(3)Long rails 108 move forward:Before cross track 109 is installed, long rails 108 should be moved forward, track Reach distance should reach the installation of cross track 109 when not blocking traversing.
(4)Drop-over steel plate 110 is installed:At central bearing point 114, with the jack-up Hanging Basket of jack 111, it is being staggered installation of and normotopia Long rails 108 are installed drop-over steel plate 110, and the coating lubricating oil on drop-over steel plate 110 is installed below.
(5)Cross track 109 is installed:Track 109 has been transversely mounted in the position of rear anchor dolly 112 and anchored, and by after Anchor dolly 112 is rotated by 90 ° and is anchored on cross track 109.
(6)Reaction frame 113 is installed:Reaction frame 113 is welded at Hanging Basket fulcrum, reaction frame 113 is welded on pre-buried good Steel plate on.
(7)Jack 111 is installed:Hydraulic jack 111 is installed at central bearing point 114 after being welded reaction frame 113.
(8)Anchor 107 is constrained after dismounting, rear anchor 107 is separated with beam body, is transferred force on rear anchor dolly 112, and each Individual rear anchor point respectively installs a 5t chain block.
(9)Anchor point chain block tensed with long rails 108 at the pushing tow fulcrum of jack 111 simultaneously after, make Hanging Basket together with Long rails 108 slowly slide transverse translation to design attitude on drop-over steel plate 110, anchor fining twisted steel after then installing 107 and anchor.
(10)Anchor point cross track 109 after dismounting, and move long rails 108 afterwards and anchor, rear anchor dolly 112 is rotated It is anchored at after 90 ° on long rails 108.
(11)Edge of a wing skid beam suspension rod 105 is reinstalled in normotopia, and is anchored.
(12)Anchor after dismounting, two sets of Hanging Baskets symmetrically move forward to No. 2 positions of beam section 103 and anchor on request, complete No. 2 beam sections 103 Hanging Baskets are in place, into next procedure construction.
It is described that in the traversing playback of Hanging Basket, anchor point carries out track and dolly is rotated by 90 ° after Hanging Basket, become sliding friction into Rolling friction.It is described in the traversing playback of Hanging Basket, many hydraulic jacks are controlled using same oil pump and oil meter combination banked direction control valves The method control jacking force on top, it is ensured that each point stress equalization, prevents larger internal force influence Hanging Basket resistance to overturning.
The foregoing description of the disclosed embodiments, enables professional and technical personnel in the field to realize or uses the present invention. Various modifications to these embodiments will be apparent for those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, the present invention The embodiments shown herein is not intended to be limited to, and is to fit to and principles disclosed herein and features of novelty phase one The scope most wide for causing.

Claims (3)

1. a kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method, it is characterised in that:Comprise the following steps:
(1)Hanging Basket is staggered installation of:No. 0 beam section(101)Pour after completing and reaching design strength, except side template(104)Position is not Become outer, the overall relative design attitude transverse translation b/2+50mm of Hanging Basket is installed, and Hanging Basket is installed according to normal sequence, skid beam suspension rod (105)In preceding entablature(106)On position relative to Hanging Basket traversing direction opposite direction movement 30cm, b is main longitudinal grider(115)It is wide Degree;
(2)Hanging basket advancing:In No. 1 beam section(102)Pour after completing and reaching intensity, size pile No. Hanging Basket is moved forward L/2, give Hanging Basket provides traversing space, anchor after being anchored after hanging basket advancing(107), L is the interlaced lap of splice of Hanging Basket of large and small mileage two;
(3)Long rails(108)Reach:Cross track is being installed(109)Before, should be by long rails(108)Moved forward, rail Reach distance in road should reach cross track when not blocking traversing(109)Installation;
(4)Drop-over steel plate(110)Install:In central bearing point(114)Place, Hanging Basket of jack-uping is pacified being staggered installation of with normotopia The long rails of dress(108)Drop-over steel plate is installed below(110), and in drop-over steel plate(110)Upper coating lubricating oil;
(5)Cross track is installed(109):In rear anchor dolly(112)Position be transversely mounted cross track(109)And anchor, And by rear anchor dolly(112)It is rotated by 90 ° and is anchored at cross track(109)On;
(6)Reaction frame(113)Install:Reaction frame is welded at Hanging Basket fulcrum(113), reaction frame(113)It is welded on pre-buried On good steel plate;
(7)Hydraulic jack is installed(111):It is welded reaction frame(113)Afterwards in central bearing point(114)Place installs hydraulic jack (111);
(8)Anchor after dismounting(107)Constraint, makes rear anchor(107)Separated with beam body, transfer force to rear anchor dolly(112)On, and Each rear anchor point respectively installs a 5t chain block;
(9)Use hydraulic jack(111)Long rails at pushing tow fulcrum(108)Anchor point chain block tense simultaneously after, makes Hanging Basket Together with long rails(108)In drop-over steel plate(110)On slowly slide transverse translation to design attitude, then install after anchor essence Roll screw-thread steel and anchor;
(10)Anchor point cross track after dismounting(109), and after move long rails(108)And anchor, by rear anchor dolly(112)Rotation Long rails are anchored at after turning 90 °(108)On;
(11)By skid beam suspension rod(105)Reinstalled in normotopia, and anchored;
(12)Anchor after dismounting, two sets of Hanging Baskets symmetrically move forward to No. 2 beam sections on request(103)Position simultaneously anchors, and completes No. 2 beam sections (103)Hanging Basket is in place, into next procedure construction.
2. curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement according to claim 1 and traversing construction method, it is characterised in that: In the traversing playback of Hanging Basket, anchor point carries out track and rear anchor dolly is rotated by 90 ° after Hanging Basket, and it is rolling friction to become sliding friction.
3. curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement according to claim 1 and traversing construction method, it is characterised in that: In the traversing playback of Hanging Basket, many methods of hydraulic jack are controlled to control pushing tow using same oil pump and oil meter combination banked direction control valves Power, it is ensured that each point stress equalization, prevents larger internal force influence Hanging Basket resistance to overturning.
CN201610091967.4A 2016-02-19 2016-02-19 A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method Active CN105714691B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610091967.4A CN105714691B (en) 2016-02-19 2016-02-19 A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610091967.4A CN105714691B (en) 2016-02-19 2016-02-19 A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method

Publications (2)

Publication Number Publication Date
CN105714691A CN105714691A (en) 2016-06-29
CN105714691B true CN105714691B (en) 2017-06-09

Family

ID=56155995

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610091967.4A Active CN105714691B (en) 2016-02-19 2016-02-19 A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method

Country Status (1)

Country Link
CN (1) CN105714691B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106567343A (en) * 2016-11-10 2017-04-19 上海市基础工程集团有限公司 Alternative mounting and construction method for hanging baskets of long-span rigid frame bridge
CN108824196B (en) * 2018-06-13 2020-04-28 贵州路桥集团有限公司 Main truss curved surface installation construction method
CN110565542B (en) * 2019-09-12 2024-03-12 中交第三航务工程局有限公司 Hanging basket for cantilever casting small curvature radius continuous beam

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1123861A (en) * 1995-08-28 1996-06-05 铁道部大桥工程局 Construction of prestressed concrete stayed cable bridge
JPH11256521A (en) * 1998-03-09 1999-09-21 Sumitomo Constr Co Ltd Bridge erection device
CN201109899Y (en) * 2007-08-30 2008-09-03 中铁大桥局集团第一工程有限公司 Lower girder-sliding type construction hanging basket
CN102134834A (en) * 2011-04-29 2011-07-27 湖南中铁五新钢模有限责任公司 Small pier construction diamond cradle
CN102587293A (en) * 2012-03-22 2012-07-18 中铁大桥局股份有限公司 System and method for cradle cantilever construction of variable-width section concrete girder

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1123861A (en) * 1995-08-28 1996-06-05 铁道部大桥工程局 Construction of prestressed concrete stayed cable bridge
JPH11256521A (en) * 1998-03-09 1999-09-21 Sumitomo Constr Co Ltd Bridge erection device
CN201109899Y (en) * 2007-08-30 2008-09-03 中铁大桥局集团第一工程有限公司 Lower girder-sliding type construction hanging basket
CN102134834A (en) * 2011-04-29 2011-07-27 湖南中铁五新钢模有限责任公司 Small pier construction diamond cradle
CN102587293A (en) * 2012-03-22 2012-07-18 中铁大桥局股份有限公司 System and method for cradle cantilever construction of variable-width section concrete girder

Also Published As

Publication number Publication date
CN105714691A (en) 2016-06-29

Similar Documents

Publication Publication Date Title
CN102182147B (en) Steel box girder erection method
CN103334381B (en) Full-bracket track-bogie bearing and moving device and construction method for installing steel box girders
CN103669226B (en) River-crossing prestressed concrete continuous beam bridge box girder 0# block support construction method
CN103882812B (en) Across the construction method of girder in stayed-cable bridge
CN105714691B (en) A kind of curve low-pylon cable-stayed bridge Hanging Basket interlaced arrangement and traversing construction method
CN103669216A (en) Steel box girder scattered-splicing sliding device and installation method
CN108374296A (en) The construction method of straddle type monorail rail tracks installation
CN104328745B (en) Across the rotary body device of the little bridge beam of high ferro and construction method thereof on a kind of low-angle
CN103255726A (en) Construction method for continuous beam and arch combination bridge
CN110205938B (en) Steel pipe arch installation method of through beam-arch combination bridge
CN109610327A (en) A kind of Bridge Erector free cantilever erection construction method
CN106192755A (en) A kind of fish-bellied type shaped form cross a river double width steel box-girder steel bridge construction method of installation
CN105648917A (en) Cable-beam synchronization construction method for composite beam self-anchored suspension bridge
CN102134832B (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN108221711A (en) Across existing railway Business Line freely-supported tied arch pushing tow flat turn and high-order fall girder apparatus
CN208965416U (en) A kind of safeguard structure of large span frame bridge jack-in process existing railway
CN203654200U (en) No. 0 block support for box girder of river-crossing prestressed concrete continuous beam bridge
CN106677076B (en) The simple and fast method and device of adjacent cover back box beam is installed with across a pier gantry crane
CN103835238B (en) A kind of high pier cable stayed bridge No. 0 block non-stand construction method and the structure in constructing
CN113614322B (en) Unequal span structure subsection rail-changing accumulated slippage construction method
CN204715212U (en) A kind of guiding device for mobile formwork girder whole lateral moving
CN204224995U (en) Fortune frame railway D beam one chassis
CN203741729U (en) Pre-stress supporting system used for bridge incremental launching construction method
CN104213512B (en) Fortune frame railway D beam one chassis and D beam installation method
CN110316662A (en) A kind of large span gantry crane construction method of installation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant