CN208965416U - A kind of safeguard structure of large span frame bridge jack-in process existing railway - Google Patents

A kind of safeguard structure of large span frame bridge jack-in process existing railway Download PDF

Info

Publication number
CN208965416U
CN208965416U CN201821146446.5U CN201821146446U CN208965416U CN 208965416 U CN208965416 U CN 208965416U CN 201821146446 U CN201821146446 U CN 201821146446U CN 208965416 U CN208965416 U CN 208965416U
Authority
CN
China
Prior art keywords
steel
horizontal lift
pontic
large span
existing railway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821146446.5U
Other languages
Chinese (zh)
Inventor
方真貌
赵原
张海鹏
景斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
The Third Railway Survey and Design Institute Co., Ltd
Original Assignee
JINZHOU RAILWAY SURVEY DESIGN CONSULTING CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JINZHOU RAILWAY SURVEY DESIGN CONSULTING CO Ltd filed Critical JINZHOU RAILWAY SURVEY DESIGN CONSULTING CO Ltd
Priority to CN201821146446.5U priority Critical patent/CN208965416U/en
Application granted granted Critical
Publication of CN208965416U publication Critical patent/CN208965416U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The highway midline position of a kind of safeguard structure of large span frame bridge jack-in process existing railway, pontic is equipped with horizontal lift beam, is covered with steel plate between horizontal lift beam and pontic;The strong ties such as just beam sides by connecting plate and bracket frame is connected to stringer to D fashioned iron, and the stringer of two width D fashioned iron just beam is docked and used by high-strength burnished bolt, form steel just beam group;Just beam group rides upon on horizontal lift beam and across pontic steel, and in steel, just beam group both ends lower part is equipped with well foundation, and to steel, just beam group is supported.Pass through above structure, the utility model solves protects the existing track strengthening period long using I-steel in the prior art, it is long to both wired driving interference times, steel using amount is big, transport is inconvenient, the high technical problem of cost, providing one kind not only can guarantee existing line operation security but also, the safeguard structure of construct convenient and fast large span frame bridge jack-in process existing railway short to both wired driving interference times.

Description

A kind of safeguard structure of large span frame bridge jack-in process existing railway
Technical field
The utility model relates to add viaduct line protection technical field under existing railway, especially a kind of large span frame The means of defence structure of structure bridge jack-in process existing railway.
Background technique
In engineering construction field, existing railway gradually carries out highway usual friendship and transform as down to wear grade separation, add viaduct or Expand the engineering constructions such as existing bridges and culverts aperture, be predominantly located in the busy location of railway transportation, railways train operation can not be interrupted for a long time, Closed-loop construction.Consider expropriation of land and economic cause, just line detour scheme is also difficult to carry out building railway, therefore undercrossing tunnel grade separation Bridge is all made of aerial existing railway pipe jacking method.At this stage, it makes somebody a mere figurehead the method for existing railway: wearing road under viaduct instantly and have a lot of social connections When spending smaller, using D fashioned iron just beam;When road width is larger under viaduct, D fashioned iron is when just beam can not protect, using work in length and breadth Word steel.Although I-steel protection is able to satisfy the requirement of large span in length and breadth, the track strengthening period is long, interferes both wired drivings Time is long, and steel using amount is big, and transport is inconvenient, and cost is high.
Summary of the invention
In view of the above problems, the utility model proposes a kind of protection knots of large span frame bridge jack-in process existing railway The highway midline position of structure, pontic is equipped with horizontal lift beam, is covered with steel plate between horizontal lift beam and pontic;Just beam sides passes through D fashioned iron Connecting plate and bracket frame are connected to stringer, and the stringer of two width D fashioned iron just beam is docked and used by high-strength burnished bolt Strong ties form steel just beam group;Just beam group rides upon on horizontal lift beam and across pontic steel, steel just beam group both ends lower part be equipped with it is heavy Well basis, to steel, just beam group is supported.By above structure, the utility model solves anti-using I-steel in the prior art The track strengthening period existing for protecting is long, and long to both wired driving interference times, steel using amount is big, and transport is inconvenient, the high technology of cost Problem.
To achieve the goals above, a kind of the technical solution adopted in the utility model are as follows: large span frame bridge jack-in process The safeguard structure of existing railway, it is characterised in that: the highway midline position of pontic is equipped with horizontal lift beam, between horizontal lift beam and pontic It is covered with steel plate;Just beam sides by connecting plate and bracket frame is connected to stringer to D fashioned iron, and the stringer of two width D fashioned iron just beam passes through height Strong burnished bolt such as is docked and use at the strong ties, formation steel just beam group;Just beam group rides upon on horizontal lift beam and across bridge steel Body, in steel, just beam group both ends lower part is equipped with well foundation, and to steel, just beam group is supported.
Mutual foundation is equipped with below horizontal lift beam at the highway midline position.
It is equipped with rolling bar between the horizontal lift beam and steel plate, reduces the frictional force between horizontal lift beam and steel plate in the jacking phase.
Just beam is 24m D fashioned iron just beam to the D fashioned iron, and just beam group entire length is 48m to steel.
The utility model has the following beneficial effects: on-site consolidation, in conjunction with steel, just beam is protected due to D fashioned iron just beam prefabrication Existing line stability, in terms of experience and data, have stable structure, protection span it is big, construction method letter Single, route is gone slowly time short and economic and practical advantage.
Detailed description of the invention
Fig. 1 is just erection floor map.
Fig. 2 is the schematic diagram of the section structure along Fig. 1 among pontic highway.
Specific embodiment
A kind of safeguard structure of large span frame bridge jack-in process existing railway, structure are as follows: the highway middle line position of pontic 4 It sets and is equipped with horizontal lift beam 2, steel plate 5 is covered between horizontal lift beam 2 and pontic 4, the effect of steel plate 5 is to guarantee pontic not because of horizontal lift Beam concentrates symbol to carry and destroyed;Just 1 side of beam by connecting plate 1-1 and bracket frame 1-2 is connected to stringer 1-3, two width to D fashioned iron The stringer 1-3 of D fashioned iron just beam 1 such as is docked and is used by high-strength burnished bolt at the strong ties, forms steel just beam group;Steel just beam Group rides upon on horizontal lift beam 2 and across pontic 4, and in steel, just beam group both ends lower part is equipped with well foundation 3, and to steel, just beam group is propped up Support.
Mutual foundation 6 is equipped with below horizontal lift beam 2 at the highway midline position.The size of specific well foundation 3 For φ 1.5m, the size of mutual foundation 6 is 1.5m × 2.1m.Make mutual foundation 6 field of load be greater than well foundation 3 by Power range.Mutual foundation 6 and 3 collective effect of well foundation, play a supporting role to total.
It is equipped with rolling bar between the horizontal lift beam 2 and steel plate 5, reduces the friction between horizontal lift beam 2 and steel plate 5 in the jacking phase Power.
Just beam 1 is 24m D fashioned iron just beam to the D fashioned iron, and just beam group entire length is 48m to steel.The length of 48m is entirely capable of Enough meet the construction requirement of various pontics.Structure is applied widely.
The utility model, which provides one kind, as a result, not only can guarantee existing line operation security but also to both wired driving interference times It is short, the safeguard structure for convenient and fast large span frame bridge jack-in process existing railway of constructing.

Claims (4)

1. a kind of safeguard structure of large span frame bridge jack-in process existing railway, it is characterised in that: the highway middle line of pontic (4) Position is equipped with horizontal lift beam (2), is covered with steel plate (5) between horizontal lift beam (2) and pontic (4);Just beam (1) side passes through company to D fashioned iron Fishplate bar (1-1) and bracket frame (1-2) are connected to stringer, and the stringer (1-3) of two width D fashioned iron just beam (1) passes through high-strength burnished bolt It the strong ties such as is docked and is used, form steel just beam group;Just beam group rides upon on horizontal lift beam (2) and across pontic (4) steel, Just beam group both ends lower part is equipped with well foundation (3) to steel, and to steel, just beam group is supported.
2. a kind of safeguard structure of large span frame bridge jack-in process existing railway according to claim 1, feature exist In: mutual foundation (6) are equipped with below the horizontal lift beam (2) at the highway midline position.
3. a kind of safeguard structure of large span frame bridge jack-in process existing railway according to claim 1, feature exist In: it is equipped with rolling bar between the horizontal lift beam (2) and steel plate (5), is reduced between horizontal lift beam (2) and steel plate (5) in the jacking phase Frictional force.
4. a kind of safeguard structure of large span frame bridge jack-in process existing railway according to claim 1, feature exist In: just beam (1) is 24m D fashioned iron just beam to the D fashioned iron, and just beam group entire length is 48m to steel.
CN201821146446.5U 2018-07-19 2018-07-19 A kind of safeguard structure of large span frame bridge jack-in process existing railway Active CN208965416U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821146446.5U CN208965416U (en) 2018-07-19 2018-07-19 A kind of safeguard structure of large span frame bridge jack-in process existing railway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821146446.5U CN208965416U (en) 2018-07-19 2018-07-19 A kind of safeguard structure of large span frame bridge jack-in process existing railway

Publications (1)

Publication Number Publication Date
CN208965416U true CN208965416U (en) 2019-06-11

Family

ID=66748714

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821146446.5U Active CN208965416U (en) 2018-07-19 2018-07-19 A kind of safeguard structure of large span frame bridge jack-in process existing railway

Country Status (1)

Country Link
CN (1) CN208965416U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374018A (en) * 2019-06-17 2019-10-25 中铁六局集团呼和浩特铁路建设有限公司 A kind of combined steel cross bearer sets up multispan just beam track strengthening method
CN110468735A (en) * 2019-08-23 2019-11-19 中铁第六勘察设计院集团有限公司 Frame core-tube system jacking engineering middle orbit construction method under existing railway operation state
CN110512474A (en) * 2019-09-12 2019-11-29 中铁二局第二工程有限公司 A kind of railroad track makes somebody a mere figurehead ruggedized construction and method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374018A (en) * 2019-06-17 2019-10-25 中铁六局集团呼和浩特铁路建设有限公司 A kind of combined steel cross bearer sets up multispan just beam track strengthening method
CN110468735A (en) * 2019-08-23 2019-11-19 中铁第六勘察设计院集团有限公司 Frame core-tube system jacking engineering middle orbit construction method under existing railway operation state
CN110512474A (en) * 2019-09-12 2019-11-29 中铁二局第二工程有限公司 A kind of railroad track makes somebody a mere figurehead ruggedized construction and method

Similar Documents

Publication Publication Date Title
CN102926299B (en) Railway elevating and fixing device and railway bridge and culvert construction method adopting railway elevating and fixing device
CN208965416U (en) A kind of safeguard structure of large span frame bridge jack-in process existing railway
CN103321151B (en) Long span continuous box girder spanning existing railway stand construction method
CN103938538A (en) Railroad bridge evacuation platform
CN206680871U (en) Boom device is transported on a kind of four rail beams
CN103774543B (en) A kind of deck type rope arch combination bridge
CN205775786U (en) A kind of novel railway curve Cable-stayed Bridge with Slanted Pylon
CN204676374U (en) A kind of strengthening mechanism of rail track
CN202148493U (en) Existing line reinforcing device in inclined jacking construction of penetrating railway frame bridge from the lower part with small incline angle and large height
CN203716044U (en) Low bearing or middle bearing cable arch combined structural bridge
CN209039945U (en) A kind of trapezoidal bracket simple beam structure used under the conditions of heavy grade
CN207032000U (en) The arch bridge that a kind of oblique is crossed over
Gao et al. Dashengguan bridge—the largest span steel arch bridge for high-speed railway
CN206486798U (en) The bridgehead structures of overpass above underground rail
Hayward The construction of railway bridges then and now
CN107142836A (en) A kind of large span high-speed railway suspension bridge
CN203716045U (en) Deck type cable-arch combined structure bridge
CN202865708U (en) Railway aerial fixing device
CN205062647U (en) Track top overpass abutment structure
CN205636464U (en) Novel modular bridge structures
CN109797609A (en) Sharp radius curve railway entirety broken line overhead device and method
CN204311360U (en) A kind of traversing carriage being applied to the simple supported box beam section assembling of bridge construction
CN203229863U (en) Large-span plate girder bridge frame
CN206616466U (en) A kind of road and bridge combined type construction equipment
CN102877406B (en) The double-deck city overhead road of the continuous Beam of rigid frame

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200630

Address after: No.10, Zhongshan Road, Hongshunli street, Hebei District, Tianjin

Patentee after: The Third Railway Survey and Design Institute Co., Ltd

Address before: 121002 No. 20, Section 4, Heping Road, Linghe Street, Jinzhou City, Liaoning Province

Patentee before: JINZHOU RAILWAY SURVEY & DESIGN INSTITUTE Co.,Ltd.

TR01 Transfer of patent right