CN203978443U - A kind of suspension device of gob side entry retaining - Google Patents

A kind of suspension device of gob side entry retaining Download PDF

Info

Publication number
CN203978443U
CN203978443U CN201420219350.2U CN201420219350U CN203978443U CN 203978443 U CN203978443 U CN 203978443U CN 201420219350 U CN201420219350 U CN 201420219350U CN 203978443 U CN203978443 U CN 203978443U
Authority
CN
China
Prior art keywords
presplitting
side entry
entry retaining
gob side
big gun
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420219350.2U
Other languages
Chinese (zh)
Inventor
王小国
王万德
李迎
刘攀
马点友
付姗姗
杨光林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUIZHOU YONGRUN COAL INDUSTRY Co Ltd
Original Assignee
GUIZHOU YONGRUN COAL INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUIZHOU YONGRUN COAL INDUSTRY Co Ltd filed Critical GUIZHOU YONGRUN COAL INDUSTRY Co Ltd
Priority to CN201420219350.2U priority Critical patent/CN203978443U/en
Application granted granted Critical
Publication of CN203978443U publication Critical patent/CN203978443U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

The utility model discloses a kind of suspension device of gob side entry retaining, the presplitting line that comprises gob side entry retaining, the presplitting big gun hole of constructing on presplitting line, adopt hydraulic prop coordination hinge back timber to set up canopy along presplitting big gun hole trend, and by anchor pole complexed metal net, carry out supporting on top board, the utility model is eliminated approaches the working surface coal body top stress and is concentrated, reduce digging ratio, enhance productivity, simple to operate, cheap, the bump of avoiding reserved coal pillar to cause, the harm such as Gas Outburst and spontaneous combustion, the wasting of resources of also having avoided reserved coal pillar to cause, improve resource recovery, reduce digging ratio, enhance productivity, reduce tunnelling and repair project amount, simplify face end maintenance workload, reduce labor strength, can obtain significant social benefit.

Description

A kind of suspension device of gob side entry retaining
Technical field
The utility model relates to a kind of suspension device of gob side entry retaining, belongs to colliery suspension device technical field is installed.
Background technology
The former use concrete precast block build a wall+anchor net of existing coal mine fully-mechanized mining working air intake lane gob side entry retaining and Application of Combined Support with Anchor carry out gob side entry retaining, the fund input of this gob side entry retaining mode is high, construction sequence complicated (from making fragment of brick, maintenance fragment of brick, transport fragment of brick, building fragment of brick by laying bricks or stones), labour intensity is large, and can not effectively cut off top board, cause the passive pressurized of body of wall.
Summary of the invention
The object of the invention is to: a kind of supporting method and device of gob side entry retaining are provided, eliminate approaches the working surface coal body top stress and concentrate, thereby overcome the deficiencies in the prior art.
The technical solution of the utility model
A kind of supporting method of gob side entry retaining, the big gun hole of constructing on presplitting line in colliery, adopt energy-gathering device powder charge, and make cumulative direction corresponding to rock mass presplitting direction, detonation product will be at the upper cumulative shooting flow that forms of two direction initializations (being parallel to each other and vertical direction with rock mass presplitting direction), and tensile stress is concentrated in generation, presplitting big gun hole is run through along cumulative direction, form pre-broken face, along staying lane side presplitting surface construction to cut topmast protective material, propelling along with back production, stay the top board in lane under the effect of Ya Ji goaf, ore deposit pressure and self pressure, along with pre-broken face cut top be caving, impel the pressure in goaf to lay down, alleviate the roof pressure that stays lane, reached a kind of object of cutting top release gob side entry retaining.
In aforesaid deep hole cumulative borehole presplitting top board gob side entry retaining construction method, described in cut topmast protective material and comprise that individual prop coordination hinge bar timbering and anchor cable coordinate bolting with wire mesh.
In aforesaid deep hole cumulative borehole presplitting top board gob side entry retaining construction method, this individual prop coordination hinge bar timbering is specially and adopts hydraulic prop coordination hinge back timber to set up two row's canopies along the presplitting line trend in explosion place to carry out supporting.
In aforesaid deep hole cumulative borehole presplitting top board gob side entry retaining construction method, this anchor cable coordinates bolting with wire mesh to refer on the basis of original technology anchor pole complexed metal net supporting roof, along gob side entry retaining center line in roadway every an anchor cable of 2~2.5m construction, behind Ruo Liu lane, under the large increase of roadway in the roof pressure, help pressure, while making coal wall have serious wall caving, in real coal body Ce lane, help to carry additionally wire lath and add and make a call to two row's pipe seam anchor bars.
A suspension device for gob side entry retaining, comprises the presplitting line of gob side entry retaining, and the presplitting big gun hole of constructing on presplitting line adopts hydraulic prop coordination hinge back timber to set up canopy along presplitting big gun hole trend, and by anchor pole complexed metal net, carry out supporting on top board.
In the suspension device of aforesaid gob side entry retaining, along gob side entry retaining center line in roadway every 2~2.5m construction anchor cable.
Compared with prior art, the utility model is eliminated approaches the working surface coal body top stress and is concentrated, reduce digging ratio, enhance productivity, simple to operate, cheap, the bump of avoiding reserved coal pillar to cause, the harm such as Gas Outburst and spontaneous combustion, the wasting of resources of also having avoided reserved coal pillar to cause, improve resource recovery, reduce digging ratio, enhance productivity, reduce tunnelling and repair project amount, simplify face end maintenance workload, reduce labor strength, can obtain significant social benefit, above eliminating approaches the working surface coal body stress concentrated in, avoided Gas Outburst, bump hidden danger, there is obvious safety benefit, construction technology is simple simultaneously, the utility model implements only need to construct borehole, charge explosion, cheap, cost-saving, fund input is little, income is large, simple to operate, the workable technology content that not only can promote mine production, and can promote at the similar mine of geological conditions (especially highly gassy mine gob side entry retaining), can create more economy, social benefit.
Accompanying drawing explanation;
Accompanying drawing 1 is the utility model structural front view;
Accompanying drawing 2 is the utility model structure top view.
Being labeled as in accompanying drawing: 1-gob side entry retaining, 2-presplitting line, 3-presplitting big gun hole, 4-hydraulic prop, 5-articulated roof beam, 6-canopy, 7-anchor pole, 8-wire lath, 9-anchor cable.
The specific embodiment;
Below in conjunction with accompanying drawing, the utility model is described in further detail, but not as to any restriction of the present utility model.
Embodiment of the present utility model: the supporting method of a kind of gob side entry retaining of the present utility model, the big gun hole of constructing on presplitting line in colliery, adopt energy-gathering device powder charge, and make cumulative direction corresponding to rock mass presplitting direction, detonation product will be at the upper cumulative shooting flow that forms of two direction initializations (being parallel to each other and vertical direction with rock mass presplitting direction), and tensile stress is concentrated in generation, presplitting big gun hole is run through along cumulative direction, form pre-broken face, along staying lane side presplitting surface construction to cut topmast protective material, propelling along with back production, stay the top board in lane under the effect of Ya Ji goaf, ore deposit pressure and self pressure, along with pre-broken face cut top be caving, impel the pressure in goaf to lay down, alleviate the roof pressure that stays lane, reached a kind of object of cutting top release gob side entry retaining.
The described topmast protective material of cutting comprises that individual prop coordination hinge bar timbering and anchor cable coordinate bolting with wire mesh, and the specific embodiment is:.
(1), individual prop coordination hinge bar timbering: adopt DW22~DW25 type hydraulic prop to coordinate HDJB-1200 type articulated roof beam to set up two row's canopies along the presplitting line trend in explosion place and carry out supporting, and bundle wire lath (bilayer) isolation goaf with iron wire on the monomer column along goaf one side.
(2), anchor cable coordinates bolting with wire mesh: on the basis of original anchor pole complexed metal net supporting roof, along gob side entry retaining center line in roadway every an anchor cable that specification is diameter * length=0.01524m * 6.0m of 2.4m construction, if help pressure under the large increase of roadway in the roof pressure behind Liu lane, while making coal wall have serious wall caving, can help in real coal body Ce lane to carry additionally wire lath and add and make a call to two row's pipe seam anchor bars, anchor pole specification is diameter * length=0.042m * 1.4m, and an array pitch is 1.0m * 1.0m.
According to the suspension device of the constructed a kind of gob side entry retaining of above-mentioned supporting method, as shown in the figure: the presplitting line 3 that comprises gob side entry retaining 1, it is characterized in that: the presplitting big gun hole 3 of constructing on presplitting line 2, adopt hydraulic prop 4 coordination hinge back timbers 5 along presplitting big gun hole 3 trends set up canopy 6, and on top board, by anchor pole 7 complexed metal nets 8, carry out supporting, along gob side entry retaining center line in roadway every 2~2.5m construction anchor cable 9.

Claims (2)

1. the suspension device of a gob side entry retaining, the presplitting line (3) that comprises gob side entry retaining (1), it is characterized in that: in the upper construction of presplitting line (2) presplitting big gun hole (3), adopt hydraulic prop (4) coordination hinge back timber (5) to set up canopy (6) along presplitting big gun hole (3) trend, and by anchor pole (7) complexed metal net (8), carry out supporting on top board.
2. the suspension device of gob side entry retaining according to claim 1, is characterized in that: along gob side entry retaining center line in roadway every 2~2.5m construction anchor cable (9).
CN201420219350.2U 2014-04-30 2014-04-30 A kind of suspension device of gob side entry retaining Expired - Fee Related CN203978443U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420219350.2U CN203978443U (en) 2014-04-30 2014-04-30 A kind of suspension device of gob side entry retaining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420219350.2U CN203978443U (en) 2014-04-30 2014-04-30 A kind of suspension device of gob side entry retaining

Publications (1)

Publication Number Publication Date
CN203978443U true CN203978443U (en) 2014-12-03

Family

ID=51975902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420219350.2U Expired - Fee Related CN203978443U (en) 2014-04-30 2014-04-30 A kind of suspension device of gob side entry retaining

Country Status (1)

Country Link
CN (1) CN203978443U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106121676A (en) * 2016-08-26 2016-11-16 百色百矿集团有限公司 A kind of supporting construction and method for protecting support thereof protecting lane for gob side entry retaining
CN109488353A (en) * 2018-10-23 2019-03-19 新汶矿业集团有限责任公司 A kind of stope advance support system and method
CN110411840A (en) * 2019-08-29 2019-11-05 安徽理工大学 Simulate experimental rig and method that the earth's surface soil body in goaf generates tension crack
CN113417640A (en) * 2021-08-10 2021-09-21 湖南科技大学 Gob-side entry retaining supporting method in reserved extremely-close thin coal seam separate mining-combined mining

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106121676A (en) * 2016-08-26 2016-11-16 百色百矿集团有限公司 A kind of supporting construction and method for protecting support thereof protecting lane for gob side entry retaining
CN109488353A (en) * 2018-10-23 2019-03-19 新汶矿业集团有限责任公司 A kind of stope advance support system and method
CN110411840A (en) * 2019-08-29 2019-11-05 安徽理工大学 Simulate experimental rig and method that the earth's surface soil body in goaf generates tension crack
CN110411840B (en) * 2019-08-29 2023-12-26 安徽理工大学 Test device and method for simulating tension fracture generated by goaf earth surface soil body
CN113417640A (en) * 2021-08-10 2021-09-21 湖南科技大学 Gob-side entry retaining supporting method in reserved extremely-close thin coal seam separate mining-combined mining
CN113417640B (en) * 2021-08-10 2023-01-03 湖南科技大学 Gob-side entry retaining supporting method in reserved extremely-close thin coal seam separate mining-combined mining

Similar Documents

Publication Publication Date Title
CN103410515B (en) It is a kind of that three-soft seam is reciprocating combines mining method without coal column
CN101761338B (en) Gob-side entry retaining method of a solid filling coal mining half-section one-leg shed
CN104061001B (en) Gob side entry retaining exploitation support process method
CN103161480B (en) Initiatively support the method for roadside packing gob side entry retaining
CN101864956B (en) Sectional coal pillar-free exploitation method
CN202064981U (en) Soft coal layer roadway supporting structure
CN100554642C (en) A kind of method of long-wall integrated-extraction reclaiming room-type coal column mining
CN102661169B (en) Gob-side entry retaining method for anchor bolt network gangue bag wall body for coal mining without pillars
CN103306714B (en) Coal seam group with near interval Di Chou holes in lane the mash gas harnessing method in a hole three
CN108661643A (en) It a kind of coal working face end adopts return channel and cuts top release shield lane method
CN103628911B (en) Work plane segmented gob-side entry retaining method is adopted/put to a kind of combining
CN203978443U (en) A kind of suspension device of gob side entry retaining
CN103147793B (en) Girdle roadside packing non chain pillar entryprotection method
CN104806246B (en) Gob-side entry retaining method for coal mine gateway by directional-predetermined crack blasting and truncating crest and pressure relief mode
AU2014393189B2 (en) Method for filling open stope with aeolian sand in shallow coal seam in western desertified mining areas
CN102852528A (en) Method for controlling floor heave through inverted arch anchoring beam
CN104453900A (en) Filling mining method of near-horizontal ore body
CN104074534B (en) A kind of combining adopts/the gob-side entry retaining method of fully mechanized coal face
CN110529151A (en) A kind of fully mechanized workface Grading And Zoning integrative consolidation passing sunk pillars on full method
CN102587962A (en) Methods for arranging and supporting wall-expanded gas extraction drill sites
CN105003288A (en) Medium-thickness coal seam gob-side entry retaining method and support system
CN105545321A (en) Method for supporting retained gob-side entry of blasting-mining working faces of small-area thin seam
CN104863588A (en) Advanced pier column pre-arranging gob-side entry retaining method
CN109630168A (en) Comprehensive extracting and caving face tunnel is arranged along floor strata and support pattern
CN103114854B (en) Pillar robbing method of reconstructed artificial stud

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141203

Termination date: 20150430

EXPY Termination of patent right or utility model