CN201864019U - Temporary scaffold device used in broadside subsection closure - Google Patents

Temporary scaffold device used in broadside subsection closure Download PDF

Info

Publication number
CN201864019U
CN201864019U CN2010206022177U CN201020602217U CN201864019U CN 201864019 U CN201864019 U CN 201864019U CN 2010206022177 U CN2010206022177 U CN 2010206022177U CN 201020602217 U CN201020602217 U CN 201020602217U CN 201864019 U CN201864019 U CN 201864019U
Authority
CN
China
Prior art keywords
scaffold
subsection
closure
suspension
broadside
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010206022177U
Other languages
Chinese (zh)
Inventor
周科伟
周文明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangzijiang Shipbuilding Holdings Ltd Jiangsu
Original Assignee
Yangzijiang Shipbuilding Holdings Ltd Jiangsu
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangzijiang Shipbuilding Holdings Ltd Jiangsu filed Critical Yangzijiang Shipbuilding Holdings Ltd Jiangsu
Priority to CN2010206022177U priority Critical patent/CN201864019U/en
Application granted granted Critical
Publication of CN201864019U publication Critical patent/CN201864019U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model relates to a temporary scaffold device used in broadside subsection closure in the ship building process. The device comprises a hanging ring (1), a hanging bracket (2), a scaffold tube (3), a scaffold floor (4) and a hung straight ladder (5), wherein the hanging bracket (2) and the hung straight ladder (5) are vertically arranged; the hanging ring (1) is arranged at the upper end of the hanging bracket (2); the scaffold tube (3) is longitudinally arranged at the sides of the scaffold tube (3) and the hung straight ladder (5); and the scaffold floor (4) is transversally paved between the hung straight ladder (5) and the scaffold tube (3) on the hanging bracket (2). The temporary scaffold device is simple, reliable and practical in the subsection closure and can achieve the same effect when using the fewest scaffold tubes and the least amount of building work.

Description

Employed cripple device in the topside segment folding
Technical field
The utility model relates in a kind of ship building process, the cripple device that uses during the segment folding.Belong to the shipbuilding technical field.
Background technology
According to the shipyard convention, the scaffolding erecting of general large tracts of land, full ship during boat segmental closes up is convenient to construction and safety.Because this scaffold One's name is legion, the work capacity of building is big, and large tracts of land scaffolds erecting dangerous big, and the building berth operating cycles is long.And install and the dismounting inconvenience, can not recycle again.
Summary of the invention
The purpose of this utility model is to overcome above-mentioned deficiency, provides a kind of and satisfies when closing up work requirements, employed cripple device in the topside segment folding of the quantity of minimizing scaffold.
The purpose of this utility model is achieved in that employed cripple device in a kind of topside segment folding, it is characterized in that described device comprises suspension ring, suspension bracket, scaffold tubes, foot plank and suspension vertical ladder, described suspension bracket and suspension vertical ladder vertically are provided with, suspension ring are arranged at the suspension bracket upper end, scaffold tubes vertically is arranged at scaffold tubes and hangs the side of vertical ladder, and foot plank laterally is layed between the scaffold tubes that hangs on vertical ladder and the suspension bracket.
The cripple platform that suspension ring, suspension bracket, foot plank and suspension vertical ladder are formed directly hangs on ship
On the body structure, so that close up construction.
The beneficial effects of the utility model are:
The cripple of utilization of the present utility model, do not need to scaffold erecting in the full ship scope of large tracts of land, only need build part, zonal scaffold at segment folding seam place, satisfy when closing up work requirements, reduce the quantity of scaffold and the work capacity of building, and having reduced the danger that large tracts of land scaffolds erecting, these scaffolds can be pre-installed in segmentation simultaneously, have shortened time on building berth greatly.And it is convenient that these scaffolds are installed and removed, and can recycle.
To sum up, adopt the utility model device simple when segment folding, reliable and practical, can when using minimum scaffold tube and building amount, reach same effect.
Description of drawings
Fig. 1 is the structural representation of employed cripple device in the utility model topside segment folding.
Fig. 2 is an Application Example scheme drawing of the present utility model.
Fig. 3 is that the A of Fig. 2 is to view.
Reference numeral among the figure:
Comprise suspension ring 1, suspension bracket 2, scaffold tubes 3, foot plank 4, hang vertical ladder 5, root plate 6, top side tank 7, bottom side tank 8, close up seam 9, rib position 10 greatly.
The specific embodiment
Referring to Fig. 1, Fig. 1 is the structural representation of employed cripple device in the utility model topside segment folding.As seen from Figure 1, employed cripple device in the utility model topside segment folding comprises suspension ring 1, suspension bracket 2, scaffold tubes 3, foot plank 4 and hangs vertical ladder 5,
Described suspension bracket 2 and suspension vertical ladder 5 vertically are provided with, and suspension ring 1 are arranged at suspension bracket 2 upper ends, and scaffold tubes 3 vertically is arranged at scaffold tubes 3 and hangs the side of vertical ladder 5, and foot plank 4 laterally is layed between the scaffold tubes 3 that hangs on vertical ladder 5 and the suspension bracket 2.
After the segmentation completion, hanger supports is fixed.Again foot plank and suspension ladder are installed and fixed when treating segment folding.
Specific operation process is as follows:
1, be contained in suspension ring height and spacing as required in the segmental structure in advance;
2, treat that segmentation paint finishes after, suspension bracket and scaffold tubes and auxiliary scaffold tubes etc. are fixed, and will hang ladder and also fix;
3, during the topside segment folding, by Fig. 2 with shown in Figure 3ly successively lay foot plank from bottom to top closing up position, seam place greatly;
4, after the whole paint of hull finishes, scaffold complete removal does not the most at last destroy paint again.

Claims (1)

1. employed cripple device in the topside segment folding, it is characterized in that described device comprises suspension ring (1), suspension bracket (2), scaffold tubes (3), foot plank (4) and hangs vertical ladder (5), described suspension bracket (2) and suspension vertical ladder (5) vertically are provided with, suspension ring (1) are arranged at suspension bracket (2) upper end, scaffold tubes (3) vertically is arranged at scaffold tubes (3) and hangs the side of vertical ladder (5), and foot plank (4) laterally is layed between the scaffold tubes (3) that hangs on vertical ladder (5) and the suspension bracket (2).
CN2010206022177U 2010-11-11 2010-11-11 Temporary scaffold device used in broadside subsection closure Expired - Fee Related CN201864019U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206022177U CN201864019U (en) 2010-11-11 2010-11-11 Temporary scaffold device used in broadside subsection closure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206022177U CN201864019U (en) 2010-11-11 2010-11-11 Temporary scaffold device used in broadside subsection closure

Publications (1)

Publication Number Publication Date
CN201864019U true CN201864019U (en) 2011-06-15

Family

ID=44135181

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206022177U Expired - Fee Related CN201864019U (en) 2010-11-11 2010-11-11 Temporary scaffold device used in broadside subsection closure

Country Status (1)

Country Link
CN (1) CN201864019U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103482043A (en) * 2013-09-23 2014-01-01 浙江海洋学院 Marine used fixture for erecting scaffold
CN108341033A (en) * 2018-03-09 2018-07-31 上海外高桥造船有限公司 Topside always organizes weld seam job platform

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103482043A (en) * 2013-09-23 2014-01-01 浙江海洋学院 Marine used fixture for erecting scaffold
CN108341033A (en) * 2018-03-09 2018-07-31 上海外高桥造船有限公司 Topside always organizes weld seam job platform

Similar Documents

Publication Publication Date Title
CN201261942Y (en) Stand platform for cantilevered concrete structure construction
CN206569235U (en) A kind of ship hanger bracket and boat scaffold
CN107161282A (en) A kind of propeller shrouding erecting device
CN201635379U (en) Safety platform for installation and construction of roof contour plate hang ceiling
CN104420640B (en) Abnormity chimney construction platform
CN103352559A (en) Hanging type movable working platform for storage tank maintenance
CN201864019U (en) Temporary scaffold device used in broadside subsection closure
CN208056596U (en) A kind of Novel engineering exterior wall scaffold
CN204299145U (en) For the operating platform that external climbing tower crane support frame is installed
CN201864018U (en) Temporary scaffold device used in cross bulkhead subsection closure
CN203113793U (en) Large formwork installation system of oblique structure
CN203947755U (en) A kind of large Steel Cantilever trussed construction high-altitude construction first floor steel truss erecting device
CN203531352U (en) Hanging type movable working platform for storage tank maintenance
CN204001658U (en) A kind of movable hanging frame of installing for cornice decorative ceiling
CN203905433U (en) Detachable elevator shaft operating platform
CN201843323U (en) Corrosion-prevention thermal-insulation flexible scaffold adapted to large-size storage tank wall
CN204983692U (en) Concrete panel's hoist device
CN208844900U (en) A kind of suspension mechanism for hanging basket
CN205711761U (en) A kind of Novel hanging basket of convenience and safety
CN201863994U (en) Ship hanging basket suspension mechanism
CN204126237U (en) A kind of elevator hoistway construction platform
CN204056256U (en) A kind of boats and ships and ocean engineering structure close up uses scaffold
CN204456811U (en) A kind of Portable scaffold
CN207228603U (en) One kind is used for interior decoration scaffold
CN203924663U (en) Guide-rail attached lifting discharge platform device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110615

Termination date: 20141111