CN201635379U - Safety platform for installation and construction of roof contour plate hang ceiling - Google Patents
Safety platform for installation and construction of roof contour plate hang ceiling Download PDFInfo
- Publication number
- CN201635379U CN201635379U CN2009202131859U CN200920213185U CN201635379U CN 201635379 U CN201635379 U CN 201635379U CN 2009202131859 U CN2009202131859 U CN 2009202131859U CN 200920213185 U CN200920213185 U CN 200920213185U CN 201635379 U CN201635379 U CN 201635379U
- Authority
- CN
- China
- Prior art keywords
- installation
- platform
- construction
- contour plate
- hang ceiling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009434 installation Methods 0.000 title claims abstract description 17
- 238000010276 construction Methods 0.000 title abstract description 9
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 13
- 239000010959 steel Substances 0.000 claims abstract description 13
- 239000004677 Nylon Substances 0.000 claims abstract description 5
- 229920001778 nylon Polymers 0.000 claims abstract description 5
- 239000011248 coating agent Substances 0.000 abstract description 3
- 238000000576 coating method Methods 0.000 abstract description 3
- 238000005096 rolling process Methods 0.000 abstract 1
- 238000000034 method Methods 0.000 description 4
- 238000009435 building construction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model relates to installation and construction of roof hang ceiling, in particular to a safety device for installation and construction of roof hang ceiling. The safety platform for installation and construction of roof contour plate hang ceiling comprises a quadrilateral platform with the surrounding being provided with guardrails; all the guardrails are connected through safety ropes; the four corners of the quadrilateral platform are respectively provided with a steel tube downwards; and the bottom of each steel tube is connected with a nylon wheel which is connected with the building structure top tie bar in a rolling way. The safety platform has simple processing and convenient installation. The device leads to stable sliding, does not damage the structure coating, saves scaffold expense and reduces construction cost.
Description
Technical field
The utility model relates to roof ceiling board installation, relates in particular to the safety device that the ceiling board installation of a kind of roof is used.
Background technology
In the steel building construction, the operating platform that roofing profiled sheet ceiling board is installed usefulness generally has two kinds of methods, and a kind of is that scaffold (have fixing or move) is set up on ground.Another kind method hangs suspension bracket exactly on roof structure.But above-mentioned two kinds of methods are subjected to place restriction and form of structure restriction can't use said method.
Summary of the invention
The utility model is intended to address the aforementioned drawbacks, and a kind of roofing contour plate ceiling board installation security platform is provided.The utility model processing is simple, easy for installation.Adopt this device to slide steadily, not the damaged structure coating; Save the scaffold expense, reduce construction cost.
The utility model is achieved in that
A kind of roofing contour plate ceiling board installation security platform, it comprises that one four limit is provided with the quadrangle platform of guardrail, each guardrail connects with safety rope, four jiaos of described quadrangle platform separately to having a steel pipe, and each steel pipe bottom is connected with one and rolls and connect the nylon wheel of building structure top tie-rod.
Described roofing contour plate ceiling board installation security platform also is provided with the traction ear on described each steel pipe.
Operating principle of the present utility model is to utilize the mounted structure of factory building as supporting skid rail, according to profiled sheet length setting operation platform quantity and appearance and size, adopts the traction of chain hoist or small winch.The utility model has solved the installation of ceiling board when facility floor has equipment or obstruction to set up scaffold effectively; Can save the scaffold expense that the roof panel lifting is used; The ceiling board handling frame slides on the structure depression bar and adopts the I of nylon wheel frictional resistance to avoid the structure coating damage.
The utility model is simple in structure, is convenient to make, install, and cost is low, and is reusable; Easy and simple to handle, safe in utilization.Under cooperation of the present utility model, the constructor can finish the installation of color steel ceiling board safely, fast, efficiently, has reduced the danger and the construction cost of construction, has guaranteed the construction period.
Description of drawings
Below, further specify the utility model in conjunction with the accompanying drawings:
Fig. 1 is a structural representation of the present utility model.
Fig. 2 is an elevation of the present utility model.
The specific embodiment
As depicted in figs. 1 and 2:
A kind of roofing contour plate ceiling board installation security platform, it comprises that one four limit is provided with the quadrangle platform 1 of guardrail 2, each guardrail 2 connects with safety rope 3, four jiaos of described quadrangle platform separately to having a steel pipe 4, each steel pipe 4 bottom is connected with the nylon wheel 6 of the connection building structure top tie-rod 5 that rolls, and also is provided with traction ear 7 on described each steel pipe 4.Adopt the traction of chain hoist or small winch promptly to can be the roof constructor safe operating platform is provided.
Claims (2)
1. roofing contour plate ceiling board installation security platform, it comprises that one four limit is provided with the quadrangle platform of guardrail, each guardrail connects with safety rope, it is characterized in that, four jiaos of described quadrangle platform separately to having a steel pipe, and each steel pipe bottom is connected with one and rolls and connect the nylon wheel of building structure top tie-rod.
2. roofing contour plate ceiling board installation security platform according to claim 1 is characterized in that, also is provided with the traction ear on described each steel pipe.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009202131859U CN201635379U (en) | 2009-12-16 | 2009-12-16 | Safety platform for installation and construction of roof contour plate hang ceiling |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009202131859U CN201635379U (en) | 2009-12-16 | 2009-12-16 | Safety platform for installation and construction of roof contour plate hang ceiling |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN201635379U true CN201635379U (en) | 2010-11-17 |
Family
ID=43079867
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2009202131859U Expired - Fee Related CN201635379U (en) | 2009-12-16 | 2009-12-16 | Safety platform for installation and construction of roof contour plate hang ceiling |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN201635379U (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102277956A (en) * | 2011-04-28 | 2011-12-14 | 浙江鼎力机械有限公司 | Extensible high-altitude standing platform |
| CN102493634A (en) * | 2011-11-29 | 2012-06-13 | 上海市第四建筑有限公司 | Suspended ceiling steel platform device for rebuilding wood structure |
| CN106193476A (en) * | 2015-05-05 | 2016-12-07 | 五冶集团上海有限公司 | A kind of concealed roofing tile mounting platform |
| CN106437179A (en) * | 2016-11-16 | 2017-02-22 | 上海通用金属结构工程有限公司 | Device for steel structure roof ceiling floor construction |
| CN106522565A (en) * | 2016-11-16 | 2017-03-22 | 上海通用金属结构工程有限公司 | Operation platform for steel structure roof ceiling board construction |
| CN107447931A (en) * | 2016-05-31 | 2017-12-08 | 中国二十冶集团有限公司 | The closed factory building roof skylight frame installation method of overlarge area |
| CN108316540A (en) * | 2018-03-08 | 2018-07-24 | 四川泰兴装饰工程有限责任公司 | Furred ceiling stone material dry suspending constructs and its construction method |
| CN108978926A (en) * | 2017-05-31 | 2018-12-11 | 五冶集团上海有限公司 | A kind of installation method of Double-layer profiled steel sheet composite thermal-insulating wall inside profiled sheet |
-
2009
- 2009-12-16 CN CN2009202131859U patent/CN201635379U/en not_active Expired - Fee Related
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102277956A (en) * | 2011-04-28 | 2011-12-14 | 浙江鼎力机械有限公司 | Extensible high-altitude standing platform |
| CN102493634A (en) * | 2011-11-29 | 2012-06-13 | 上海市第四建筑有限公司 | Suspended ceiling steel platform device for rebuilding wood structure |
| CN102493634B (en) * | 2011-11-29 | 2014-03-05 | 上海建工四建集团有限公司 | Suspended ceiling steel platform installation for reconstruction of timber structure |
| CN106193476A (en) * | 2015-05-05 | 2016-12-07 | 五冶集团上海有限公司 | A kind of concealed roofing tile mounting platform |
| CN107447931A (en) * | 2016-05-31 | 2017-12-08 | 中国二十冶集团有限公司 | The closed factory building roof skylight frame installation method of overlarge area |
| CN107447931B (en) * | 2016-05-31 | 2019-06-14 | 中国二十冶集团有限公司 | The closed factory building roof skylight frame installation method of overlarge area |
| CN106437179A (en) * | 2016-11-16 | 2017-02-22 | 上海通用金属结构工程有限公司 | Device for steel structure roof ceiling floor construction |
| CN106522565A (en) * | 2016-11-16 | 2017-03-22 | 上海通用金属结构工程有限公司 | Operation platform for steel structure roof ceiling board construction |
| CN108978926A (en) * | 2017-05-31 | 2018-12-11 | 五冶集团上海有限公司 | A kind of installation method of Double-layer profiled steel sheet composite thermal-insulating wall inside profiled sheet |
| CN108316540A (en) * | 2018-03-08 | 2018-07-24 | 四川泰兴装饰工程有限责任公司 | Furred ceiling stone material dry suspending constructs and its construction method |
| CN108316540B (en) * | 2018-03-08 | 2020-01-24 | 四川泰兴装饰工程有限责任公司 | Suspended ceiling stone dry hanging structure and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CA2713161A1 (en) | Load transportation system | |
| CN103711301A (en) | Construction method and device for two-track movable electric basket and lifting hoist | |
| CN101177959A (en) | Curtain wall unit hanging equipment and construction method thereof | |
| CN208454342U (en) | A kind of safety of tower crane platform and standard knot install conjoined device | |
| CN212251443U (en) | Special pipeline of old factory building dust removal pipeline transformation installation removes hoist device | |
| CN202370234U (en) | Tool type elevator hoistway construction platform | |
| CN213268983U (en) | Self-climbing discharging platform | |
| CN104153586B (en) | A kind of suspension cable hangs the construction method of mounting purlines | |
| CN205773024U (en) | Convenient pipeline promotes auxiliary device | |
| CN202441045U (en) | Rail-type electric attached lifting scaffold | |
| CN203834369U (en) | Device capable of being rotated by 360 degrees and vertically lifted for bridge | |
| CN203359889U (en) | Wall plate lifting and installation integrated operation platform | |
| CN202787991U (en) | Overhanging passageway for tower crane | |
| CN202544379U (en) | Automatic climbing device | |
| CN203461720U (en) | Simple cantilever hoisting machine | |
| CN203865929U (en) | Portable crane | |
| CN202000647U (en) | Base device for lifting scaffold in elevator shaft | |
| CN102733612B (en) | Mounting method of electric hoist orbit | |
| CN103470057B (en) | A kind of high-altitude component hoisting construction method | |
| CN202831591U (en) | Special-shaped truss operation platform capable of hoisting to super high space | |
| CN202864771U (en) | Hoisting system for glass curtain wall construction | |
| CN204038917U (en) | Detachable external hanging type operating platform | |
| CN201485204U (en) | Gas tank hanging device | |
| CN203531354U (en) | Underneath type lifting scaffold for high-rise building | |
| CN204850396U (en) | Foldable elevartor shaft construction support |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20101117 Termination date: 20141216 |
|
| EXPY | Termination of patent right or utility model |