CN206569235U - A kind of ship hanger bracket and boat scaffold - Google Patents
A kind of ship hanger bracket and boat scaffold Download PDFInfo
- Publication number
- CN206569235U CN206569235U CN201621460906.2U CN201621460906U CN206569235U CN 206569235 U CN206569235 U CN 206569235U CN 201621460906 U CN201621460906 U CN 201621460906U CN 206569235 U CN206569235 U CN 206569235U
- Authority
- CN
- China
- Prior art keywords
- column
- ship
- hanger bracket
- board support
- jump board
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model discloses a kind of ship hanger bracket, it is related to shipbuilding field, the hanging plate of " U " type that the device includes column and Open Side Down and is fixed on the upside of the column, many are further fixed on the column in the jump board support pipe being spaced apart up and down, the jump board support pipe and hanging plate are located at the relative both sides of column respectively, and are mutually perpendicular between the jump board support pipe and column.Side of the column provided with hanging plate is fixed with many in the support tube being spaced apart up and down, and is mutually perpendicular between the support tube and column.The utility model can effectively improve the convenience of scaffold building.
Description
Technical field
The utility model is related to shipbuilding field, and in particular to a kind of ship is with hanger bracket and a kind of ship suspension type
Scaffold.
Background technology
Building berth during shipbuilding is built and the harbour installation and debugging stage is, it is necessary in the stem or some lines of ship
The operations such as the place of type big rise and fall is polished, touch-up paint, it is some because these position line styles fluctuatings and upper-lower height difference are larger
Even up to more than 20 meters of position upper-lower height difference, when carrying out operation, for the larger position of difference in height, it is necessary to set up temporarily
Super-high scaffold, not only wastes time and energy, meanwhile, with the increase of scaffold building height, the high-altitude of scaffold building personnel
Task difficulty and danger are consequently increased, the serious danger that even personnel of setting up slip.
Utility model content
For defect present in prior art, the purpose of this utility model is to provide a kind of ship hanger bracket and one
Ship boat scaffold is planted, the convenience of scaffold building is effectively improved.
To achieve the above objectives, the utility model is adopted the technical scheme that:Including column and Open Side Down and is fixed on
Many are further fixed on the hanging plate of " U " type on the upside of the column, the column in the jump board support pipe being spaced apart up and down, institute
State jump board support pipe and hanging plate and be located at the relative both sides of column respectively, and be mutually perpendicular between the jump board support pipe and column.
On the basis of above-mentioned technical proposal, side of the column provided with hanging plate is fixed with many and is spaced apart above and below
Support tube, and be mutually perpendicular between the support tube and column.
On the basis of above-mentioned technical proposal, the support pipe end is provided with steel pipe seal plate.
On the basis of above-mentioned technical proposal, connecting tube is additionally provided with the column, one end connection of the connecting tube is vertical
Post, other end connection hanging plate.
On the basis of above-mentioned technical proposal, the described one end of jump board support pipe away from the column is fixed with and springboard branch
The vertical guardrail pipe of stay tube.
On the basis of above-mentioned technical proposal, a reinforcing plate is provided with below the jump board support pipe between column.
On the basis of above-mentioned technical proposal, the jump board support pipe connects below one end away from the column between column
It is connected to down tube.
The utility model also provides a kind of ship boat scaffold, including multiple ships with hanger bracket hanging side by side in
On the ship side of ship, and a springboard is placed with the jump board support pipe of sustained height layer.
On the basis of above-mentioned technical proposal, the width of the springboard is identical with the length of jump board support pipe.
Compared with prior art, a kind of ship of the utility model is with the advantage of hanger bracket:
(1) hanging plate of " U " type is provided with above column, hanger bracket is fixed on ship side by hang, operation is simple
It is single, the danger of scaffold building personal height operation is effectively reduced, meanwhile, when hanging plate is hung on ship side, hanger bracket suspension is solid
Due to after ship side, springboard is positioned on the jump board support pipe of hanging plate, that is, completes the work of setting up of whole scaffold, greatly drops
It is low to set up the time, improve operating efficiency.
(2) many are fixed with column in the support tube for being used to support hull being spaced apart up and down, protect column
Vertical state is held, is easy to follow-up construction requirement.
(3) reinforcing plate and down tube, structure between increase jump board support pipe and column are connected between jump board support pipe and column
Stability.
A kind of ship of the utility model is with the advantage of boat scaffold:By the way that multiple ships are hung with hanger bracket
In on ship side, then springboard is placed on jump board support pipe, you can quickly build construction scaffold, it is time saving and energy saving, and
The security of staff's construction can be improved.
Brief description of the drawings
Fig. 1 is a kind of structural representation of ship hanger bracket of the utility model.
In figure:1- columns, 2- hanging plates, 3- jump board support pipes, 4- support tubes, 5- steel pipe seal plates, 6- connecting tubes, 7- guardrails
Pipe, 8- reinforcing plates, 9- down tubes.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
Shown in Figure 1, the utility model provides a kind of ship hanger bracket, for meeting pin hand during shipbuilding
Frame sets up demand, and the ship hanger bracket includes column 1 and Open Side Down and is fixed on the hanging plate of " U " type of the upside of column 1
2, hanging plate 2 is typically secured on the one side on the top of column 1, and the opening of " U " type of hanging plate 2 is easy to be fastened on ship side, without
By other auxiliary fixing equipments, you can hanger bracket of the present utility model is fixed on ship.Connecting tube is additionally provided with column 1
6, one end connection column 1 of connecting tube 6, other end connection hanging plate 2 is vertical between connecting tube 6 and column 1, is controlled by connecting tube 6
The distance between column 1 and ship hull.
Side of the column 1 provided with hanging plate 2 is fixed with many in the support tube for being used to support hull being spaced apart up and down
4, support tube 4 is general to be uniformly distributed up and down on column 1, between adjacent supports pipe 4 between the upper and lower away from the same, support tube 4 and column 1
On the homonymy of hanging plate 2, i.e. support tube 4 and hanging plate 2 is located on the same side of column 1, and is mutually hung down between support tube 4 and column 1
Directly, the end of support tube 4 is provided with steel pipe seal plate 5, it is to avoid the scratch hull of support tube 4.The length of support tube 4 and connecting tube 6 can
According to real work scene smart, to make when hanging plate 2 is fastened on ship side, support tube 4 is held in after hull, column 1
Vertical state can be kept.
Many are further fixed on column 1 in the jump board support pipe 3 being spaced apart up and down, jump board support pipe 3 is general in column 1
It is upper in being uniformly distributed up and down, adjacent springboard support tube 3 between the upper and lower away from identical, jump board support pipe 3 is located at column respectively with hanging plate 2
1 relative both sides, and be mutually perpendicular between jump board support pipe 3 and column 1, it is used to place springboard on jump board support pipe 3, is jumped to improve
The stability of structure between plate support tube 3 and column 1, junction is provided with a reinforcing plate 8 between the lower section of jump board support pipe 3 and column 1, plus
Strong plate 8 is a right angled triangle, and two right-angle sides of reinforcing plate 8 are connected and fixed with jump board support pipe 3 and column 1 respectively, springboard
Support tube 3 is also associated with down tube 9 below one end away from column 1 between column 1.
The one end of jump board support pipe 3 away from column 1 is fixed with the guardrail pipe 7 vertical with jump board support pipe 3, to operating personnel
Play a protective effect.
The utility model also includes a kind of ship boat scaffold being made up of multiple above-mentioned ships with hanger bracket, many
Individual ship on the ship side of ship with hanger bracket hanging side by side in constituting, i.e., ship boat scaffold of the present utility model makes
Used time, by multiple ship hanger bracket hanging side by side on the ship side of ship i.e. constitute boat scaffold of the present utility model,
Support tube 4 is held on the hull of ship, and the column 1 made keeps placing on vertical state, the jump board support pipe 3 of sustained height layer
There is a springboard, staff, which stands on, can carry out operation on springboard, because ship with boat scaffold is by multiple hanging side by side
Ship constituted with hanger bracket, therefore each ship can be with other ship hanger brackets with the jump board support pipe 3 in hanger bracket
In jump board support pipe 3 be in sustained height, that is, presenting has multiple jump board support pipes 3 on multiple height layers, each height layer,
Springboard is positioned on the jump board support pipe 3 of sustained height layer, you can is kept horizontality, is easy to the operation of staff, springboard
Width it is identical with the length of jump board support pipe 3, it can use bolt or other fixed forms by springboard and jump board support pipe 3
Between be fixed.
Guardrail pipe 7 in each ship hanger bracket coordinates with the guardrail pipe 7 in other ship hanger brackets, forms shield
Column, and protection network can be laid on guardrail, to ensure workmen's safety.
It is time saving by the way that multiple ships are hung on ship side with hanger bracket, you can quickly build construction scaffold
It is laborsaving, and the security of staff's construction can be improved.
The utility model is not only limited to above-mentioned preferred forms, and anyone can obtain under enlightenment of the present utility model
Go out other various forms of products, however, make any change in its shape or structure, it is every to have and the utility model phase
Same or close technical scheme, within its protection domain.
Claims (9)
1. a kind of ship hanger bracket, it is characterised in that:Including column (1) and Open Side Down and is fixed on the column (1)
Many are further fixed on the hanging plate (2) of " U " type of side, the column (1) in the jump board support pipe (3) being spaced apart up and down, institute
State jump board support pipe (3) and be located at the relative both sides of column (1), and the jump board support pipe (3) and column respectively with hanging plate (2)
(1) it is mutually perpendicular between.
2. a kind of ship hanger bracket as claimed in claim 1, it is characterised in that:The column (1) is provided with the one of hanging plate (2)
Side is fixed with many in the support tube (4) being spaced apart up and down, and is mutually perpendicular between the support tube (4) and column (1).
3. a kind of ship hanger bracket as claimed in claim 2, it is characterised in that:Support tube (4) end is provided with steel pipe
Hush panel (5).
4. a kind of ship hanger bracket as claimed in claim 1, it is characterised in that:Connecting tube is additionally provided with the column (1)
(6), one end connection column (1) of the connecting tube (6), other end connection hanging plate (2).
5. a kind of ship hanger bracket as claimed in claim 1, it is characterised in that:The jump board support pipe (3) is away from described
One end of column (1) is fixed with the guardrail pipe (7) vertical with jump board support pipe (3).
6. a kind of ship hanger bracket as claimed in claim 1, it is characterised in that:With standing below the jump board support pipe (3)
A reinforcing plate (8) is provided between post (1).
7. a kind of ship hanger bracket as claimed in claim 1, it is characterised in that:The jump board support pipe (3) is away from described
Below one end of column (1) down tube (9) is connected between column (1).
8. a kind of ship that ship by any one of multiple claims 1 to 7 is constituted with hanger bracket suspension type pin hand
Frame, it is characterised in that:Multiple ships with hanger bracket hanging side by side on the ship side of ship, and the jump board support pipe of sustained height layer
(3) springboard is placed with.
9. a kind of ship boat scaffold as claimed in claim 8, it is characterised in that:The width and springboard of the springboard
The length of support tube (3) is identical.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621460906.2U CN206569235U (en) | 2016-12-28 | 2016-12-28 | A kind of ship hanger bracket and boat scaffold |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621460906.2U CN206569235U (en) | 2016-12-28 | 2016-12-28 | A kind of ship hanger bracket and boat scaffold |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206569235U true CN206569235U (en) | 2017-10-20 |
Family
ID=60061473
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621460906.2U Active CN206569235U (en) | 2016-12-28 | 2016-12-28 | A kind of ship hanger bracket and boat scaffold |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206569235U (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107600361A (en) * | 2017-10-25 | 2018-01-19 | 台山市东扩钢构有限公司 | A kind of underslung scaffold peculiar to vessel |
CN107672761A (en) * | 2017-10-25 | 2018-02-09 | 台山市东扩钢构有限公司 | A kind of scaffold peculiar to vessel |
CN107757842A (en) * | 2017-10-25 | 2018-03-06 | 台山市东扩钢构有限公司 | A kind of orientable scaffold |
CN107824355A (en) * | 2017-11-09 | 2018-03-23 | 江苏新扬子造船有限公司 | The spraying equipment of the glass flake paint of large ship |
CN109319040A (en) * | 2018-10-10 | 2019-02-12 | 上海江南长兴造船有限责任公司 | A kind of scaffold building method for hull turn of the bilge region |
CN112009644A (en) * | 2020-08-31 | 2020-12-01 | 涡阳县信隆船舶附件有限公司 | Scaffold for boats and ships |
CN112478102A (en) * | 2020-11-27 | 2021-03-12 | 中船澄西船舶修造有限公司 | Ship floating repairing suspension scaffold assembly |
-
2016
- 2016-12-28 CN CN201621460906.2U patent/CN206569235U/en active Active
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107600361A (en) * | 2017-10-25 | 2018-01-19 | 台山市东扩钢构有限公司 | A kind of underslung scaffold peculiar to vessel |
CN107672761A (en) * | 2017-10-25 | 2018-02-09 | 台山市东扩钢构有限公司 | A kind of scaffold peculiar to vessel |
CN107757842A (en) * | 2017-10-25 | 2018-03-06 | 台山市东扩钢构有限公司 | A kind of orientable scaffold |
CN107824355A (en) * | 2017-11-09 | 2018-03-23 | 江苏新扬子造船有限公司 | The spraying equipment of the glass flake paint of large ship |
CN109319040A (en) * | 2018-10-10 | 2019-02-12 | 上海江南长兴造船有限责任公司 | A kind of scaffold building method for hull turn of the bilge region |
CN112009644A (en) * | 2020-08-31 | 2020-12-01 | 涡阳县信隆船舶附件有限公司 | Scaffold for boats and ships |
CN112478102A (en) * | 2020-11-27 | 2021-03-12 | 中船澄西船舶修造有限公司 | Ship floating repairing suspension scaffold assembly |
CN112478102B (en) * | 2020-11-27 | 2022-02-08 | 中船澄西船舶修造有限公司 | Ship floating repairing suspension scaffold assembly |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206569235U (en) | A kind of ship hanger bracket and boat scaffold | |
CN201261942Y (en) | Stand platform for cantilevered concrete structure construction | |
CN204401997U (en) | A kind of suspension type ceiling construction scaffold | |
CN204126230U (en) | Assembly scaffold unit | |
CN105350759A (en) | Suspended scaffold | |
CN204552054U (en) | A kind of telescopic work high above the ground hanger bracket | |
CN205477339U (en) | A cage ladder that is used for steel construction factory building shingle nail to install | |
CN206664894U (en) | One kind auxiliary hatch board middle hinge latch mounting operation platform | |
CN102635226A (en) | Flexible hanging self-expansion operating platform and construction method | |
CN211689948U (en) | Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge | |
CN205956559U (en) | Pipeline gallows | |
CN104264781A (en) | Grid-shaped, cylindrical-surface and steel structured latticed shell and construction method thereof | |
CN104533092A (en) | Truss roof ceiling construction method | |
CN204040441U (en) | Combination assembled operating platform | |
CN201864018U (en) | Temporary scaffold device used in cross bulkhead subsection closure | |
CN204038917U (en) | Dismountable external hanging service platform | |
CN205472340U (en) | People's passageway on instrument formula tower crane | |
CN204056256U (en) | A kind of boats and ships and ocean engineering structure close up uses scaffold | |
CN204662926U (en) | A kind of operating platform for steel pipe column top construction operation | |
CN204826727U (en) | Reinforcing bar processing protection canopy that can dismantle, has enough to meet need | |
CN204370828U (en) | Tool-type protective screening | |
CN212337125U (en) | Combined type climbing tool for straight bulkhead of cargo hold | |
CN101597956B (en) | Suspended scaffold | |
CN203514813U (en) | Novel overhanging discharging platform | |
CN207362706U (en) | Load carrying type hanging basket operating platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |