CN112211106A - 一种高架桥预制盖梁安装方法 - Google Patents
一种高架桥预制盖梁安装方法 Download PDFInfo
- Publication number
- CN112211106A CN112211106A CN202011180167.2A CN202011180167A CN112211106A CN 112211106 A CN112211106 A CN 112211106A CN 202011180167 A CN202011180167 A CN 202011180167A CN 112211106 A CN112211106 A CN 112211106A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- bent cap
- capping beam
- column
- elevation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
Abstract
本发明公开了一种高架桥预制盖梁安装方法,包括以下步骤:S1、粘贴观测标:在预制盖梁的端头、预制盖梁侧面中心点、立柱中心点粘贴观测标;S2、预拼装;将预制盖梁吊装到立柱上端,然后通过观察观测标调整预制盖梁在立柱上的位置,调整至所需位置后对预制盖梁位置进行标记;S3、正式拼装:将标记后的预制盖梁吊起,然后进行立柱顶座浆,座浆后将盖梁吊装至立柱顶,并根据观测标、标记进行校正,进而完成预制盖梁与立柱的正式拼接,本发明通过在预制盖梁以及立柱上设置多处观察标志,同时对预制盖梁进行预拼接、正式拼接,而且在拼接的过程中通过观察标志对盖梁的垂直度、平面度、标高进行预定位以及复核,进而极大的提高了拼装精度。
Description
技术领域
本发明涉及盖梁瓶装方法,具体是一种高架桥预制盖梁安装方法。
背景技术
目前装配式高架桥预制拼装施工工艺逐渐成为智慧快速路施工的主要方法,预制拼装施工工艺取代了传统现浇混凝土施工工艺,可以提高施工质量,缩短工期,减少现场施工人员数量,同时可以降低施工对交通和环境的影响。目前高架桥预制拼装施工工艺主要适用于预制立柱、预制盖梁施工,预制盖梁拼装直接制约着高架桥预制拼装施工。
然而在现场实际施工过程中,对预制盖梁拼装精度要求很高,预制盖梁拼装时需要多次复核其垂直度、平面位置、标高等;因此预制盖梁拼装难度很高。
发明内容
本发明的目的在于提供一种高架桥预制盖梁安装方法,以解决上述背景技术中提出的问题。
为实现上述目的,本发明提供如下技术方案:
一种高架桥预制盖梁安装方法,包括以下步骤:
S1、粘贴观测标:在预制盖梁的端头、预制盖梁侧面中心点、立柱中心点粘贴观测标;
S2、预拼装;将预制盖梁吊装到立柱上端,然后通过观察观测标调整预制盖梁在立柱上的位置,调整至所需位置后对预制盖梁位置进行标记;
S3、正式拼装:将标记后的预制盖梁吊起,然后进行立柱顶座浆,座浆后将盖梁吊装至立柱顶,并根据观测标、标记进行校正,进而完成预制盖梁与立柱的正式拼接。
作为本发明进一步的方案:所述步骤S1包括以下步骤:
S1.1、在盖梁端头与全站仪架设点的正对面立柱侧弹出其中心十字墨线,并在十字线中心贴上观测标;
S1.2、使用全站仪设站放出线路左侧及右侧立柱顶处的中心点,并粘贴观测标;
S1.3、并通过卷尺量出预制盖梁相对于立柱左右侧中心点的侧面设计位置,并粘贴观测标。
作为本发明进一步的方案:所述步骤S2包括以下步骤:
S2.1、在立柱外围架设观测仪器;
S2.2、在立柱顶端安装立柱调节垫块;
S2.3、在立柱两侧安装预制盖梁支撑装置;
S2.4、将预制盖梁吊装至立柱上端,且预制盖梁远离立柱的一端通过预制盖梁支撑装置进行支撑;
S2.5、调整预制立柱调节垫块的高度以及预制盖梁的位置,使得预制盖梁至所需位置,然后在预制盖梁与预制盖梁支撑装置的连接处做定位标记。
作为本发明进一步的方案:所述观测仪器通过惯导RTK放样出轴线及平面控制全站仪架设的架设点,距离立柱边的间距为25-30m,精度为0-10mm。
作为本发明进一步的方案:所述立柱调节垫块安装在立柱顶端,通过全站仪设置高程站测量出左右侧立柱顶四角标高,使用调节垫块调节立柱顶标高与设计立柱顶标高一致,垫块放置完成后,再使用全站仪对高程进行复核,两侧立柱顶达到设计高程且相对高差不超过2mm,以保证后续湿接缝施工直螺纹套筒的有效连接。
作为本发明进一步的方案:所述盖梁支撑装置采用钢支撑架,通过惯导RTK放样出两侧钢支撑条形基础平面位置,使用全站仪设置高程站观测条形基础预埋底座四角高程,使其四角高程一致,通过全站仪观测钢支撑顶面高程,与计算设计钢支撑支点高程对比,计算出砂箱高度,砂箱根据现场实际砂质情况预留1-2cm沉降量,然后放置双拼45工字钢及楔形钢板。
作为本发明进一步的方案:所述步骤S2.5中预制盖梁完全落在立柱顶面、钢支撑顶面的楔形钢板上时,对预制盖梁的垂直度、平面位置、标高进行调整。
作为本发明进一步的方案:所述预制盖梁与立柱、预制盖梁支撑装置的位置调整包括以下步骤:
S2.5.1、使用全站仪复核预制盖梁竖向墨线是否与立柱竖向墨线在同一垂线上,如有偏差再对预制盖梁垂直度进行微调;
S2.5.2、使用两台全站仪分别架至盖梁横桥向与纵桥向,观测立柱中心观测标与预制盖梁中心观测标是否在处同一水平面上,如有偏差再对预制盖梁平面位置进行水平调整;
S2.5.3、观察盖梁与立柱的竖向墨线是否重合。最后通过全站仪对预制盖梁上的观测标进行标高测量,偏差如果超过2mm可以将预制盖梁吊起后,调节标高垫块直至标高符合要求。
作为本发明进一步的方案:所述步骤S3包括以下步骤
S3.1、将预制盖梁缓慢提起且不超过立柱顶面预埋钢筋,再进行座浆,待立柱顶面座浆完成之后开始正式拼装;
S3.2、缓慢将预制盖梁落至距离座浆面2-3cm的高度并用全站仪观测预制盖梁与立柱上观测标是否处于同一垂直线上来确认预制盖梁垂直度是否符合要求,待垂直度符合无误之后,方可将预制盖梁落至设计位置并观测与座浆面的接触面是否饱满;
S3.3、预制盖梁完全落下之后,观察预制盖梁上的定位标记与预制盖梁支撑装置端部是否重合,再使用两台全站仪观测横桥向与顺桥向的盖梁和立柱的观测标相对位置进行复核并观察其中心墨线是否重合,同时对预制盖梁顶标高进行复核,确保无误之后即可进行松钩,完成预制盖梁的正式拼装。
与现有技术相比,本发明的有益效果是:
1、本发明通过在预制盖梁以及立柱上设置多处观察标志,同时对预制盖梁进行预拼接、正式拼接,而且在拼接的过程中通过观察标志对盖梁的垂直度、平面度、标高进行预定位以及复核,进而极大的提高了拼装精度;
2、本发明通过钢支撑体系作为预制盖梁临时支撑系统,同时在预拼接过程中还通过座定位标记,通过定位标记在正式拼接过程中对拼接的精度进行反馈,以便提高拼接装的。
具体实施方式
下面将对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
本发明实施例中,一种高架桥预制盖梁安装方法,包括以下步骤:
S1、粘贴观测标:在预制盖梁的端头、预制盖梁侧面中心点、立柱中心点粘贴观测标,步骤S1包括以下步骤:
S1.1、在盖梁端头与全站仪架设点的正对面立柱侧弹出其中心十字墨线,并在十字线中心贴上观测标,用于盖梁拼装时的轴线复核控制,确保立柱与盖梁在同一轴线断面上;
S1.2、使用全站仪设站放出线路左侧及右侧立柱顶处的中心点,并粘贴观测标;
S1.3、并通过卷尺量出预制盖梁相对于立柱左右侧中心点的侧面设计位置,并粘贴观测标;
立柱顶处的中心点、立柱左右侧中心点的侧面设计位置点的观测标,用于控制预制盖梁平面位置,以确保两节块预制盖梁的预埋主筋间距,使其直螺纹套筒连接符合设计要求,保证后续湿接缝施工质量。
S2、预拼装;将预制盖梁吊装到立柱上端,然后通过观察观测标调整预制盖梁在立柱上的位置,调整至所需位置后对预制盖梁位置进行标记,步骤S2包括以下步骤:
S2.1、在立柱外围架设观测仪器,观测仪器通过惯导RTK放样出轴线及平面控制全站仪架设的架设点,距离立柱边的间距为25-30m,精度为0-10mm;
S2.2、在立柱顶端安装立柱调节垫块,立柱调节垫块安装在立柱顶端,通过全站仪设置高程站测量出左右侧立柱顶四角标高,使用调节垫块调节立柱顶标高与设计立柱顶标高一致,垫块放置完成后,再使用全站仪对高程进行复核,两侧立柱顶达到设计高程且相对高差不超过2mm,以保证后续湿接缝施工直螺纹套筒的有效连接;
S2.3、在立柱两侧安装预制盖梁支撑装置,选择钢支撑体系作为预制盖梁临时支撑系统,通过惯导RTK放样出两侧钢支撑条形基础平面位置,使用全站仪设置高程站观测条形基础预埋底座四角高程,使其四角高程一致,以确保整体钢支撑的垂直度符合要求,钢支撑搭设至钢围檩处,通过全站仪观测钢支撑顶面高程,与计算设计钢支撑支点高程对比,计算出砂箱高度,砂箱根据现场实际砂质情况预留1-2cm沉降量,然后放置双拼45工字钢及楔形钢板;
S2.4、将预制盖梁吊装至立柱上端,且预制盖梁远离立柱的一端通过预制盖梁支撑装置进行支撑;
S2.5、调整预制立柱调节垫块的高度以及预制盖梁的位置,使得预制盖梁至所需位置,然后在预制盖梁与预制盖梁支撑装置的连接处做定位标记,预制盖梁完全落在立柱顶面、钢支撑顶面的楔形钢板上时,对预制盖梁的垂直度、平面位置、标高进行调整,预制盖梁与立柱、预制盖梁支撑装置的位置调整包括以下步骤:
S2.5.1、使用全站仪复核预制盖梁竖向墨线是否与立柱竖向墨线在同一垂线上,如有偏差再对预制盖梁垂直度进行微调;
S2.5.2、使用两台全站仪分别架至盖梁横桥向与纵桥向,观测立柱中心观测标与预制盖梁中心观测标是否在处同一水平面上,如有偏差再对预制盖梁平面位置进行水平调整;
S2.5.3、观察盖梁与立柱的竖向墨线是否重合。最后通过全站仪对预制盖梁上的观测标进行标高测量,偏差如果超过2mm可以将预制盖梁吊起后,调节标高垫块直至标高符合要求。
在盖梁与楔形钢板的接触边上绘制出盖梁定位标记,同时对盖梁的顶面垫石边线进行测量放样并观察垫石预埋筋是否位于边线之中并符合垫石预埋筋保护层的误差范围以复核预制盖梁是否偏位。待预制盖梁的垂直度、平面位置、标高均符合要求之后,即完成预制盖梁的预拼装
S3、正式拼装:将标记后的预制盖梁吊起,然后进行立柱顶座浆,座浆后将盖梁吊装至立柱顶,并根据观测标、标记进行校正,进而完成预制盖梁与立柱的正式拼接,步骤S3包括以下步骤
S3.1、将预制盖梁缓慢提起且不超过立柱顶面预埋钢筋,再进行座浆,待立柱顶面座浆完成之后开始正式拼装;
S3.2、缓慢将预制盖梁落至距离座浆面2-3cm的高度并用全站仪观测预制盖梁与立柱上观测标是否处于同一垂直线上来确认预制盖梁垂直度是否符合要求,待垂直度符合无误之后,方可将预制盖梁落至设计位置并观测与座浆面的接触面是否饱满;
S3.3、预制盖梁完全落下之后,观察预制盖梁上的定位标记与楔形钢板接触边的是否重合,再使用两台全站仪观测横桥向与顺桥向的盖梁和立柱的观测标相对位置进行复核并观察其中心墨线是否重合,同时对预制盖梁顶标高进行复核,确保无误之后即可进行松钩,完成预制盖梁的正式拼装。
本实施例的拼装方法,大幅度的提高了装配式高架桥预制盖梁拼装的精度,确保了预制盖梁拼装的质量,取得了良好的社会效益。随着装配式高架桥施工工艺的推广与普及,预制盖梁拼装将更多的实施到现场施工中去,采用上述预制盖梁拼装精度控制方法,可以更精准的完成预制盖梁拼装,提升预制盖梁施工质量
对于本领域技术人员而言,显然本发明不限于上述示范性实施例的细节,而且在不背离本发明的精神或基本特征的情况下,能够以其他的具体形式实现本发明。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本发明的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本发明内。
此外,应当理解,虽然本说明书按照实施方式加以描述,但并非每个实施方式仅包含一个独立的技术方案,说明书的这种叙述方式仅仅是为清楚起见,本领域技术人员应当将说明书作为一个整体,各实施例中的技术方案也可以经适当组合,形成本领域技术人员可以理解的其他实施方式。
Claims (9)
1.一种高架桥预制盖梁安装方法,其特征在于,包括以下步骤:
S1、粘贴观测标:在预制盖梁的端头、预制盖梁侧面中心点、立柱中心点粘贴观测标;
S2、预拼装;将预制盖梁吊装到立柱上端,然后通过观察观测标调整预制盖梁在立柱上的位置,调整至所需位置后对预制盖梁位置进行标记;
S3、正式拼装:将标记后的预制盖梁吊起,然后进行立柱顶座浆,座浆后将盖梁吊装至立柱顶,并根据观测标、标记进行校正,进而完成预制盖梁与立柱的正式拼接。
2.根据权利要求1所述的一种高架桥预制盖梁安装方法,其特征在于,所述步骤S1包括以下步骤:
S1.1、在盖梁端头与全站仪架设点的正对面立柱侧弹出其中心十字墨线,并在十字线中心贴上观测标;
S1.2、使用全站仪设站放出线路左侧及右侧立柱顶处的中心点,并粘贴观测标;
S1.3、并通过卷尺量出预制盖梁相对于立柱左右侧中心点的侧面设计位置,并粘贴观测标。
3.根据权利要求1所述的一种高架桥预制盖梁安装方法,其特征在于,所述步骤S2包括以下步骤:
S2.1、在立柱外围架设观测仪器;
S2.2、在立柱顶端安装立柱调节垫块;
S2.3、在立柱两侧安装预制盖梁支撑装置;
S2.4、将预制盖梁吊装至立柱上端,且预制盖梁远离立柱的一端通过预制盖梁支撑装置进行支撑;
S2.5、调整预制立柱调节垫块的高度以及预制盖梁的位置,使得预制盖梁至所需位置,然后在预制盖梁与预制盖梁支撑装置的连接处做定位标记。
4.根据权利要求3所述的一种高架桥预制盖梁安装方法,其特征在于,所述观测仪器通过惯导RTK放样出轴线及平面控制全站仪架设的架设点,距离立柱边的间距为25-30m,精度为0-10mm。
5.根据权利要求3所述的一种高架桥预制盖梁安装方法,其特征在于,所述立柱调节垫块安装在立柱顶端,通过全站仪设置高程站测量出左右侧立柱顶四角标高,使用调节垫块调节立柱顶标高与设计立柱顶标高一致,垫块放置完成后,再使用全站仪对高程进行复核,两侧立柱顶达到设计高程且相对高差不超过2mm,以保证后续湿接缝施工直螺纹套筒的有效连接。
6.根据权利要求3所述的一种高架桥预制盖梁安装方法,其特征在于,所述盖梁支撑装置采用钢支撑架,通过惯导RTK放样出两侧钢支撑条形基础平面位置,使用全站仪设置高程站观测条形基础预埋底座四角高程,使其四角高程一致,通过全站仪观测钢支撑顶面高程,与计算设计钢支撑支点高程对比,计算出砂箱高度,砂箱根据现场实际砂质情况预留1-2cm沉降量,然后放置双拼45工字钢及楔形钢板。
7.根据权利要求3所述的一种高架桥预制盖梁安装方法,其特征在于,所述步骤S2.5中预制盖梁完全落在立柱顶面、钢支撑顶面的楔形钢板上时,对预制盖梁的垂直度、平面位置、标高进行调整。
8.根据权利要求7所述的一种高架桥预制盖梁安装方法,其特征在于,所述预制盖梁与立柱、预制盖梁支撑装置的位置调整包括以下步骤:
S2.5.1、使用全站仪复核预制盖梁竖向墨线是否与立柱竖向墨线在同一垂线上,如有偏差再对预制盖梁垂直度进行微调;
S2.5.2、使用两台全站仪分别架至盖梁横桥向与纵桥向,观测立柱中心观测标与预制盖梁中心观测标是否在处同一水平面上,如有偏差再对预制盖梁平面位置进行水平调整;
S2.5.3、观察盖梁与立柱的竖向墨线是否重合。最后通过全站仪对预制盖梁上的观测标进行标高测量,偏差如果超过2mm可以将预制盖梁吊起后,调节标高垫块直至标高符合要求。
9.根据权利要求1所述的一种高架桥预制盖梁安装方法,其特征在于,所述步骤S3包括以下步骤
S3.1、将预制盖梁缓慢提起且不超过立柱顶面预埋钢筋,再进行座浆,待立柱顶面座浆完成之后开始正式拼装;
S3.2、缓慢将预制盖梁落至距离座浆面2-3cm的高度并用全站仪观测预制盖梁与立柱上观测标是否处于同一垂直线上来确认预制盖梁垂直度是否符合要求,待垂直度符合无误之后,方可将预制盖梁落至设计位置并观测与座浆面的接触面是否饱满;
S3.3、预制盖梁完全落下之后,观察预制盖梁上的定位标记与预制盖梁支撑装置端部是否重合,再使用两台全站仪观测横桥向与顺桥向的盖梁和立柱的观测标相对位置进行复核并观察其中心墨线是否重合,同时对预制盖梁顶标高进行复核,确保无误之后即可进行松钩,完成预制盖梁的正式拼装。
Priority Applications (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011180167.2A CN112211106B (zh) | 2020-10-29 | 2020-10-29 | 一种高架桥预制盖梁安装方法 |
PCT/CN2021/096138 WO2022088664A1 (zh) | 2020-10-29 | 2021-05-26 | 一种高架桥预制盖梁安装方法 |
LU502065A LU502065B1 (en) | 2020-10-29 | 2021-05-26 | Installation method for prefabricated bent cap of viaduct |
ZA2022/00899A ZA202200899B (en) | 2020-10-29 | 2022-01-19 | Method for installing viaduct prefabricated cover beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011180167.2A CN112211106B (zh) | 2020-10-29 | 2020-10-29 | 一种高架桥预制盖梁安装方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112211106A true CN112211106A (zh) | 2021-01-12 |
CN112211106B CN112211106B (zh) | 2023-01-10 |
Family
ID=74057409
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011180167.2A Active CN112211106B (zh) | 2020-10-29 | 2020-10-29 | 一种高架桥预制盖梁安装方法 |
Country Status (4)
Country | Link |
---|---|
CN (1) | CN112211106B (zh) |
LU (1) | LU502065B1 (zh) |
WO (1) | WO2022088664A1 (zh) |
ZA (1) | ZA202200899B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113005903A (zh) * | 2021-02-09 | 2021-06-22 | 浙江交工集团股份有限公司 | 灌浆套筒连接式盖梁拼装施工工艺 |
CN113047637A (zh) * | 2021-03-30 | 2021-06-29 | 上海公路桥梁(集团)有限公司 | 一种预制立柱导向定位的调整方法 |
WO2022088664A1 (zh) * | 2020-10-29 | 2022-05-05 | 中铁四局集团第一工程有限公司 | 一种高架桥预制盖梁安装方法 |
CN114440848A (zh) * | 2022-01-19 | 2022-05-06 | 中建安装集团有限公司 | 一种适用于装配式桥梁施工的大体积盖梁吊装测量控制方法及装置 |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115126267A (zh) * | 2022-07-25 | 2022-09-30 | 中建八局第三建设有限公司 | 一种应用于混凝土构件预埋插筋对位的光学定位控制系统及方法 |
Citations (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050217185A1 (en) * | 2004-03-31 | 2005-10-06 | Mitek Holdings, Inc. | Building framework, method for making the same and components used in the framework |
CN102418317A (zh) * | 2011-11-10 | 2012-04-18 | 中铁二十三局集团有限公司 | 一种格构墩的现场制造方法 |
US8340016B1 (en) * | 2011-07-29 | 2012-12-25 | Viasat, Inc. | Flexible forward and return capacity allocation in a hub-spoke satellite communication system |
CN206448151U (zh) * | 2017-01-06 | 2017-08-29 | 江苏省科佳工程设计有限公司 | 城市高架用预制桥墩 |
CN107953970A (zh) * | 2017-11-21 | 2018-04-24 | 中船黄埔文冲船舶有限公司 | 一种无底座的船舶大型门架的安装方法 |
CN108103936A (zh) * | 2017-11-03 | 2018-06-01 | 上海公路桥梁(集团)有限公司 | 预制盖梁安装于立柱的方法 |
JP6425848B1 (ja) * | 2018-05-15 | 2018-11-21 | 株式会社横河住金ブリッジ | 橋梁の架け替え方法 |
CN109214099A (zh) * | 2018-09-20 | 2019-01-15 | 中建三局基础设施建设投资有限公司 | 一种拱肋钢管定位计算及施工方法 |
CN109610344A (zh) * | 2018-12-31 | 2019-04-12 | 中铁六局集团太原铁路建设有限公司 | 桥梁转体支座安装施工方法 |
CN109881898A (zh) * | 2019-02-21 | 2019-06-14 | 深圳市建筑设计研究总院有限公司 | 一种高层连体结构的拼装修正方法 |
CN109944165A (zh) * | 2019-04-24 | 2019-06-28 | 中铁二十四局集团有限公司 | 一种用于预制盖梁安装的模块化可调姿态的临时支撑方法 |
CN110744269A (zh) * | 2019-11-25 | 2020-02-04 | 南通振华重型装备制造有限公司 | 轮胎吊支腿法兰制作以及安装方法 |
CN110777669A (zh) * | 2019-11-15 | 2020-02-11 | 中铁北京工程局集团有限公司 | 高铁连续梁短线匹配预制悬臂拼装线形控制方法 |
CN111622110A (zh) * | 2020-04-24 | 2020-09-04 | 中交第二航务工程局有限公司 | 基于三维测量放样技术的预制盖梁智能化安装施工方法 |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100547591B1 (ko) * | 2002-11-04 | 2006-01-31 | 지에스건설 주식회사 | 교각 코핑부 선조립 공법 |
CN106400692A (zh) * | 2016-10-28 | 2017-02-15 | 上海市政工程设计研究总院(集团)有限公司 | 一种立柱与盖梁拼装结构的施工方法 |
CN107100078B (zh) * | 2017-05-19 | 2019-01-08 | 中国五冶集团有限公司 | 一种装配式桥梁预制墩柱构件安装方法 |
CN110387825B (zh) * | 2019-07-17 | 2021-10-19 | 中铁二十四局集团有限公司 | 一种预制立柱快速对孔和姿态调整的施工方法 |
CN112211106B (zh) * | 2020-10-29 | 2023-01-10 | 中铁四局集团第一工程有限公司 | 一种高架桥预制盖梁安装方法 |
-
2020
- 2020-10-29 CN CN202011180167.2A patent/CN112211106B/zh active Active
-
2021
- 2021-05-26 LU LU502065A patent/LU502065B1/en active IP Right Grant
- 2021-05-26 WO PCT/CN2021/096138 patent/WO2022088664A1/zh active Application Filing
-
2022
- 2022-01-19 ZA ZA2022/00899A patent/ZA202200899B/en unknown
Patent Citations (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050217185A1 (en) * | 2004-03-31 | 2005-10-06 | Mitek Holdings, Inc. | Building framework, method for making the same and components used in the framework |
US8340016B1 (en) * | 2011-07-29 | 2012-12-25 | Viasat, Inc. | Flexible forward and return capacity allocation in a hub-spoke satellite communication system |
CN102418317A (zh) * | 2011-11-10 | 2012-04-18 | 中铁二十三局集团有限公司 | 一种格构墩的现场制造方法 |
CN206448151U (zh) * | 2017-01-06 | 2017-08-29 | 江苏省科佳工程设计有限公司 | 城市高架用预制桥墩 |
CN108103936A (zh) * | 2017-11-03 | 2018-06-01 | 上海公路桥梁(集团)有限公司 | 预制盖梁安装于立柱的方法 |
CN107953970A (zh) * | 2017-11-21 | 2018-04-24 | 中船黄埔文冲船舶有限公司 | 一种无底座的船舶大型门架的安装方法 |
JP6425848B1 (ja) * | 2018-05-15 | 2018-11-21 | 株式会社横河住金ブリッジ | 橋梁の架け替え方法 |
CN109214099A (zh) * | 2018-09-20 | 2019-01-15 | 中建三局基础设施建设投资有限公司 | 一种拱肋钢管定位计算及施工方法 |
CN109610344A (zh) * | 2018-12-31 | 2019-04-12 | 中铁六局集团太原铁路建设有限公司 | 桥梁转体支座安装施工方法 |
CN109881898A (zh) * | 2019-02-21 | 2019-06-14 | 深圳市建筑设计研究总院有限公司 | 一种高层连体结构的拼装修正方法 |
CN109944165A (zh) * | 2019-04-24 | 2019-06-28 | 中铁二十四局集团有限公司 | 一种用于预制盖梁安装的模块化可调姿态的临时支撑方法 |
CN110777669A (zh) * | 2019-11-15 | 2020-02-11 | 中铁北京工程局集团有限公司 | 高铁连续梁短线匹配预制悬臂拼装线形控制方法 |
CN110744269A (zh) * | 2019-11-25 | 2020-02-04 | 南通振华重型装备制造有限公司 | 轮胎吊支腿法兰制作以及安装方法 |
CN111622110A (zh) * | 2020-04-24 | 2020-09-04 | 中交第二航务工程局有限公司 | 基于三维测量放样技术的预制盖梁智能化安装施工方法 |
Non-Patent Citations (4)
Title |
---|
华文健: "预制盖梁安装工艺在城市轨道交通施工中的应用", 《建筑技术开发》 * |
康明等: "轨道梁精确定位测量方法分析", 《江西测绘》 * |
石剑: "装配式大悬臂盖梁分段预制安装施工技术", 《城市道桥与防洪》 * |
臧立娟等: "《测量学》", 31 January 2018, 武汉大学出版社 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2022088664A1 (zh) * | 2020-10-29 | 2022-05-05 | 中铁四局集团第一工程有限公司 | 一种高架桥预制盖梁安装方法 |
CN113005903A (zh) * | 2021-02-09 | 2021-06-22 | 浙江交工集团股份有限公司 | 灌浆套筒连接式盖梁拼装施工工艺 |
CN113047637A (zh) * | 2021-03-30 | 2021-06-29 | 上海公路桥梁(集团)有限公司 | 一种预制立柱导向定位的调整方法 |
CN113047637B (zh) * | 2021-03-30 | 2022-06-03 | 上海公路桥梁(集团)有限公司 | 一种预制立柱导向定位的调整方法 |
CN114440848A (zh) * | 2022-01-19 | 2022-05-06 | 中建安装集团有限公司 | 一种适用于装配式桥梁施工的大体积盖梁吊装测量控制方法及装置 |
Also Published As
Publication number | Publication date |
---|---|
CN112211106B (zh) | 2023-01-10 |
LU502065B1 (en) | 2022-11-02 |
WO2022088664A1 (zh) | 2022-05-05 |
ZA202200899B (en) | 2022-07-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112211106B (zh) | 一种高架桥预制盖梁安装方法 | |
CN103437279B (zh) | 高空现浇箱梁承压支柱及其施工工艺 | |
CN102888865A (zh) | 立柱桩施工中钢构件垂直度的校正方法及装置 | |
CN108330974B (zh) | 一种接桩对中定位装置 | |
CN206562667U (zh) | 一种快速就位的柱脚锚栓结构 | |
CN110700083A (zh) | 一种预制桥梁墩柱的安装测量控制方法 | |
CN111877814A (zh) | 预制清水混凝土看台板的施工方法 | |
CN112323654A (zh) | 桥梁全预制加宽方法 | |
CN110158951A (zh) | 一种框架结构全木质模板施工方法 | |
CN108560369A (zh) | 一种用于高速环道曲面摊铺的放样施工方法 | |
CN110685306B (zh) | 地铁明挖车站y型钢结构柱定位测量方法 | |
CN113106821A (zh) | 一种用于装配式水泥混凝土铺面板的吊装定位装置及方法 | |
CN113897821A (zh) | 一种地铁轨道板精调系统及方法 | |
CN210622423U (zh) | 一种焊接连接的接触网硬横梁 | |
CN111441238A (zh) | 一种装配式盖梁辅助安装结构及施工方法 | |
CN105544405A (zh) | 一种桥梁墩顶块采用浮吊架设安装的施工方法 | |
CN205604075U (zh) | 一种桥梁墩顶块采用浮吊架设的安装结构 | |
CN112523258A (zh) | 一种便捷式单侧模板支撑系统及其施工方法 | |
CN214738059U (zh) | 调垂基础平台 | |
CN114016751B (zh) | 垂直交叉式h型钢柱连接于钢混圆柱上的垂直度调整方法 | |
CN214783319U (zh) | 装配式桥梁系梁顶预埋钢筋定位装置 | |
CN216516497U (zh) | 一种装配式混凝土剪力墙转换层竖向钢筋定位装置 | |
CN215947896U (zh) | 一种新型端模悬吊结构 | |
CN215801777U (zh) | 一种多群组螺栓固定结构 | |
CN212223619U (zh) | 一种可精密控制节段拼装梁预制线形的观测塔 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |