CN109732768A - Building prefabricated components forming production line and production technology with central dispatch system - Google Patents
Building prefabricated components forming production line and production technology with central dispatch system Download PDFInfo
- Publication number
- CN109732768A CN109732768A CN201910144117.XA CN201910144117A CN109732768A CN 109732768 A CN109732768 A CN 109732768A CN 201910144117 A CN201910144117 A CN 201910144117A CN 109732768 A CN109732768 A CN 109732768A
- Authority
- CN
- China
- Prior art keywords
- area
- station
- processing
- die station
- stations
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
The present invention relates to a kind of building prefabricated components forming production line and production technology with central dispatch system, belongs to industrialized house technical field.The production line includes following functions area: processing one area, ferry-boat system pour area of vibrating, 2nd area of processing, displacement movement system, 3rd area of processing, the area precuring Jing Ting, 4th area of processing, stacking maintenance area, demoulding discharge zone, inclination discharge zone and die station clearing zone;It is arranged to offline mode by that will process an area, and a production line, which both may be implemented, can produce multiple types product, can also realize a production line while produce production efficiency of the different types of product without influencing respective product.
Description
Technical field
The present invention relates to a kind of building prefabricated components forming production line and production technology with central dispatch system, belongs to work
Industry residence technology field.
Background technique
The traditional house prefabricated components production line in China at present, have following problems: the product of 1. productions is more single, than
If the production line of PC prefabricated outer wall panel cannot be compatible into a line with special-shaped production line, if produced with production line more complicated
Special-shaped component, efficiency are very low;2. conventional production lines generally only have simple subprogram circuit, the flow beat of production line be easy to by
The complexity of the production technology of specific pre-manufactured product is upset, for example, product produced is than latter die station in previous die station
When product produced is more complicated, previous die station just need it is longer in a certain particular process station residence time, and it is faster complete
At the latter die station of corresponding process because of the stop of front die station, it can only be also parked in original place, until previous die station completes corresponding work
Skill.
Summary of the invention
The present invention is in order to overcome the defect of above-mentioned production line, and the purpose of the present invention is to provide a kind of band central dispatch systems
Building prefabricated components forming production line and production technology, it is arranged to offline mode by that will process an area, both can be real
An existing production line can produce multiple types product, can also realize a production line and meanwhile produce different types of product without
Influence the production efficiency of respective product.
The present invention to achieve the goals above, adopts the following technical scheme that
Building prefabricated components forming production line with central dispatch system, the production line include following functions area: one area of processing, pendulum
It crosses system, pour area of vibrating, 2nd area of processing, displacement movement system, 3rd area of processing, the area precuring Jing Ting, processing 4th area, stacking
Conserve area, demoulding discharge zone, inclination discharge zone and die station clearing zone;
The side of ferry-boat system is one area of processing, and the other side is 3rd area of processing, the area precuring Jing Ting, 4th area of processing, stacking maintenance
Area and demoulding discharge zone;
Area of vibrating is built in one end connection of ferry-boat system, builds the other side 2nd area of connection processing in area of vibrating, the other end for system of ferrying
Connect die station clearing zone, die station clearing zone connection inclination discharge zone;
Displacement movement system is provided in processing 2nd area, inclination discharge zone and die station clearing zone;
Described processing its quantity of one area is more than or equal to one, and its internal number of stations is more than or equal to one, and process has mould
Platform setting-out, side mode installation, mold oiling, installation of embedded parts and reinforcement installation;
Described its quantity of ferry-boat system is more than or equal to one, and is equipped with ferry-boat transloading equipment, and die station is transported from die station clearing zone
It is transported to from the station in one area of processing to the station in one phase area of processing or by die station and pours area of vibrating;
Described its quantity of area of vibrating that pours is more than or equal to one, and internal number of stations is more than or equal to one, and process is gelling
Material is poured and is vibrated;
Described processing its quantity of 2nd area is more than or equal to one, and internal number of stations is more than or equal to one, and process has built-in fitting peace
Dress, reinforcement installation and insulation board installation;
The displacement movement system is equipped with displacement transloading equipment, and die station is transported to the assembly line to form perforation;
Its internal number of stations of 3rd area of the processing is more than or equal to one, and is equipped with and catches up with leveling device, function be to poured
Concrete carries out catching up with flat processing or functions only as transfer passage;
Its internal number of stations of the area the precuring Jing Ting is more than or equal to one, and function is carried out in advance to prefabricated components produced
Maintenance processing functions only as transfer passage;
Described processing its number of stations of 4th area is more than or equal to one, and is equipped with galling device and Troweling press finishing device, and function is pair
Prefabricated components produced carry out hair pulling treatment or Troweling press finishing processing or function only as transfer passage;
Described stacking maintenance its number of stations of area is more than or equal to one, and process is the maintenance of prefabricated components;
Its number of stations of the demoulding discharge zone is more than or equal to one, and process is that disassembly, die station demoulding, allocation and transportation discharging are touched in side;
Its number of stations of the inclination discharge zone is more than or equal to one, and process is die station inclination demoulding, transhipment discharging;
Described its number of stations of die station clearing zone is more than or equal to one, and process is mold cleaning or functions only as transfer passage.
Further, the number of stations in one area of the processing are as follows: one area's station of processing;
The number of stations for pouring area of vibrating are as follows: pour the first station of area that vibrates, pour the area's second station or pour of vibrating and vibrate
Area's 3rd station;
The number of stations in 2nd area of the processing are as follows: two area's stations of processing;
The number of stations in 3rd area of the processing are as follows: three area's stations of processing;
The number of stations in the area the precuring Jing Ting are as follows: the area precuring Jing Ting station;
The number of stations in 4th area of the processing are as follows: four area's stations of processing;
The number of stations in stacking maintenance area are as follows: stacking system, stacking conserve area's station;
Demould the number of stations of discharge zone are as follows: demoulding the first station of discharge zone or demoulding discharge zone second station;
The number of stations of die station clearing zone are as follows: die station clearing zone station.
The step of a kind of production technology of superimposed sheet, the production technology are as follows: die station is successively by adding in one area of processing first
Any independent station in one area's station of work carries out die station setting-out, side mode installation, mold oiling, installation of embedded parts, truss bars
Installation;
Then by ferry-boat system by die station transport to pour pouring in area of vibrating vibrate the first station of area, pour area of vibrating
Two stations pour area's 3rd station of vibrating and are poured and vibrated;
Then die station into the area precuring Jing Ting, and is completed quiet in this area by three area's station of processing in 3rd area of processing
Shut-down sequence;
Then in the four area's station hair pulling treatment of processing processed in 4th area;Stacking maintenance area is transported to later to be conserved;Maintenance
After the completion, die station is transported to the first station of demoulding discharge zone in demoulding discharge zone or demoulds discharge zone second station progress side
Mould disassembly, demoulding discharging;
Then die station is delivered to die station clearing zone and carries out mold cleaning;Later by die station be delivered to processing one area in carry out it is next
A circulation.
A kind of the step of production technology of the PC wallboard of band heat preservation, the production technology are as follows:
Die station is successively by any independent station in one area's station of processing in one area of processing carries out die station setting-out, side mode is pacified first
Dress, mold oiling, steel mesh installation;
Then by ferry-boat system by die station transport to pour pouring in area of vibrating vibrate the first station of area carry out for the first time pour
It builds and vibrates;
Then two area's station of processing that die station is delivered in 2nd area of processing is subjected to insulation board installation, installation of embedded parts, reinforcing bar peace
Dress;
Then it is delivered to and pours pouring in area of vibrating area's second station or pour area's 3rd station of vibrating of vibrating and carry out secondary pour
It builds and vibrates
Then die station carries out catching up with flat process by three area's station of processing in 3rd area of processing;Die station enters that precuring is quiet to stop later
Area, and quiet shut-down sequence is completed in this area;Troweling press finishing processing is carried out in the four area's station of processing processed in 4th area later;
Then die station is transported to stacking maintenance area and is conserved;After the completion of maintenance, die station is transported to demoulding and is discharged by stacking system
The first station of demoulding discharge zone in area carries out side and touches disassembly;
Then it is delivered in inclination discharging and carries out inclination demoulding, handling discharging;Die station die station clearing zone is delivered to later to carry out
Mold cleaning;Die station is delivered in one area of processing later and carries out next circulation.
A kind of the step of production technology of abnormity component, the production technology are as follows:
Die station is successively by any independent station in one area's station of processing in one area of processing carries out die station setting-out, side mode is pacified first
Dress, mold oiling, installation of embedded parts, reinforcement installation;
Then by ferry-boat system by die station transport to pour pouring in area of vibrating vibrate the first station of area, pour area of vibrating
Two stations pour area's 3rd station of vibrating and are poured and vibrated;
Then die station into the area precuring Jing Ting, and is completed quiet in this area by three area's station of processing in 3rd area of processing
Shut-down sequence;Pass through four area's station of processing in 4th area of processing later;
Then stacking maintenance area is delivered to be conserved;After the completion of maintenance, die station is transported to the demoulding in demoulding discharge zone
Expect that the first station of area or demoulding discharge zone second station carry out side mode disassembly, demoulding discharging;
Then die station is delivered to die station clearing zone and carries out mold cleaning;Later by die station be delivered to processing one area in carry out it is next
A circulation.
Beneficial effects of the present invention:
The present invention realizes that " joint use " i.e. production line can produce a plurality of types of wallboards, reaches and reduces cost, reduces
The effect of occupation area of equipment;The present invention can be achieved while produce different types of wallboard without influencing the respective production effect of product
Rate;Compared to conventional stent platform production line, the degree of automation of the present invention is higher, less with number, more efficient, and it is right to meet country
The policy requirements of industrialized house.
Detailed description of the invention
Fig. 1 is the structural representation frame of building prefabricated components forming production line of the embodiment of the present invention one with central dispatch system
Figure;
Fig. 2 is the structural schematic block diagram of two, three, four manufacturing technique method of the embodiment of the present invention.
Specific embodiment
The present invention will be described in detail by 1-2 with reference to the accompanying drawing:
Embodiment one
The present embodiment is the building prefabricated components forming production line with central dispatch system, which includes following functions area:
Process an area 1, ferry-boat system 2, pour area 3 of vibrating, two areas 4 of processing, displacement movement system 5, three areas 6 of processing, precuring is quiet stops
Area 7, four areas 8 of processing, stacking maintenance area 9, demoulding discharge zone 10, inclination discharge zone 11 and die station clearing zone 12;
The side of ferry-boat system 2 is one area 1 of processing, and the other side is three areas 6 of processing, the area precuring Jing Ting 7, processing four areas 8, heap
Pile conserves area 9 and demoulding discharge zone 10;
Ferry-boat system 2 one end connection build area 3 of vibrating, build area 3 of vibrating the other side connection processing two areas 4, ferry-boat system 2 it is another
One end connects die station clearing zone 12, the connection inclination discharge zone 11 of die station clearing zone 12;
Displacement movement system 5 is provided in processing two areas 4, inclination discharge zone 11 and die station clearing zone 12;
One its quantity of area 1 of the processing is more than or equal to one, and its internal number of stations is more than or equal to one, and process has mould
Platform setting-out, side mode installation, mold oiling, installation of embedded parts and reinforcement installation;
Described its quantity of ferry-boat system 2 is more than or equal to one, and is equipped with ferry-boat transloading equipment, and die station is transported from die station clearing zone 12
Die station is transported to from the station in one area 1 of processing and pours area 3 of vibrating by the station that is sent in one phase of processing area 1;
Described its quantity of area 3 of vibrating that pours is more than or equal to one, and internal number of stations is more than or equal to one, and process is gelling
Material is poured and is vibrated;
Two its quantity of area 4 of the processing are more than or equal to one, and internal number of stations is more than or equal to one, and process has built-in fitting peace
Dress, reinforcement installation and insulation board installation;
The displacement movement system 5 is equipped with displacement transloading equipment, and die station is transported to the assembly line to form perforation;
Its internal number of stations of three areas 6 of the processing is more than or equal to one, and is equipped with and catches up with leveling device, function be to poured
Concrete carries out catching up with flat processing or functions only as transfer passage;
Its internal number of stations of the area the precuring Jing Ting 7 is more than or equal to one, and function is carried out to prefabricated components produced
Precuring handles or functions only as transfer passage;
Four its number of stations of area 8 of the processing are more than or equal to one, and are equipped with galling device and Troweling press finishing device, and function is pair
Prefabricated components produced carry out hair pulling treatment or Troweling press finishing processing or function only as transfer passage;
Described stacking maintenance its number of stations of area 9 is more than or equal to one, and process is the maintenance of prefabricated components;
Described 10 its number of stations of demoulding discharge zone is more than or equal to one, and process is that disassembly, die station demoulding, allocation and transportation discharging are touched in side;
Described 11 its number of stations of inclination discharge zone is more than or equal to one, and process is die station inclination demoulding, transhipment discharging;
Described its number of stations of die station clearing zone 12 is more than or equal to one, and process is mold cleaning or functions only as transfer passage.
The number of stations in one area 1 of the processing are as follows: processing one area's station 1.1 or 1.2 or 1.3 or 1.4 or 1.5 or 1.6 or 1.7
Or 1.8 or 1.9 or 1.10;
The number of stations for pouring area 3 of vibrating are as follows: pour the first station of area 3.1 that vibrates, pour to vibrate and area's second station 3.2 or pour
Build area's 3rd station 3.3 of vibrating;
The number of stations in two areas 4 of the processing are as follows: processing two area's stations 4.1 or 4.2 or 4.3 or 4.4 or 4.5 or 4.6;
The number of stations in three areas 6 of the processing are as follows: three area's stations 6.1 or 6.2 of processing;
The number of stations in the area the precuring Jing Ting 7 are as follows: the area precuring Jing Ting station 7.1 or 7.2 or 7.3 or 7.4 or 7.5 or
7.6 or 7.7 or 7.8;
The number of stations in four areas 8 of the processing are as follows: four area's stations 8.1 or 8.2 of processing;
The number of stations in stacking maintenance area 9 are as follows: stacking system 9.2, stacking conserve area's station 9.1 or 9.3;
Demould the number of stations of discharge zone 10 are as follows: demoulding the first station of discharge zone 10.1 or demoulding discharge zone second station 10.2;
The number of stations of die station clearing zone 12 are as follows: die station clearing zone station 12.1 or 12.2.
Embodiment two
The present embodiment is a kind of production technology of superimposed sheet, the production technology are as follows: die station is successively by adding in one area 1 of processing first
Any independent station in one area's station 1.1 or 1.2 of work or 1.3 or 1.4 or 1.5 or 1.6 or 1.7 or 1.8 or 1.9 or 1.10 into
The setting-out of row die station, side mode installation, mold oiling, installation of embedded parts, truss bars installation;
Then by ferry-boat system 2 by die station transport to pour pouring in area 3 of vibrating vibrate the first station of area 3.1, pour vibration
It smashes area's second station 3.2 or pours area's 3rd station 3.3 of vibrating and poured and vibrated;
Then die station is by three area's station 6.1 or 6.2 of processing in three areas 6 of processing, into the area precuring Jing Ting 7, the area Bing Ci
Quiet shut-down sequence is completed in domain;
Then in the four area's station 8.1 of processing or 8.2 hair pulling treatments processed in four areas 8;Stacking maintenance area 9 is transported to later to carry out
Maintenance;After the completion of maintenance, die station is transported to the first station of demoulding discharge zone 10.1 in demoulding discharge zone 10 or demoulds discharging
Area's second station 10.2 carries out side mode disassembly, demoulding discharging;
Then die station is delivered to die station clearing zone 12 and carries out mold cleaning;Die station is delivered in one area 1 of processing later and is carried out
Next circulation.
Embodiment three
Production technology of the present embodiment for a kind of PC wallboard of band heat preservation, the production technology:
Die station is successively by one area's station 1.1 or 1.2 of processing or 1.3 or 1.4 or 1.5 or 1.6 or 1.7 in one area 1 of processing first
Or any independent station in 1.8 or 1.9 or 1.10 carries out die station setting-out, side mode installation, mold oiling, steel mesh installation;
Then by ferry-boat system 2 by die station transport to pour pouring in area 3 of vibrating vibrate the first station of area 3.1 carry out first
It is secondary to pour and vibrate;
Then two area's station 4.1 or 4.2 of processing or 4.3 or 4.4 or 4.5 or 4.6 progress die station being delivered in two areas 4 of processing
Insulation board installation, installation of embedded parts, reinforcement installation;
Then it is delivered to and pours vibrate area's second station 3.2 or pour of pouring in area 3 of vibrating and vibrate the progress of area's 3rd station 3.3
It is secondary to pour and vibrate
Then die station carries out catching up with flat process by three area's station 6.1 or 6.2 of processing in three areas 6 of processing;Die station enters pre- later
The area Jing Ting 7 is conserved, and completes quiet shut-down sequence in this area;Later in the four area's station 8.1 or 8.2 of processing processed in four areas 8
Carry out Troweling press finishing processing;
Then die station is transported to stacking maintenance area 9 and is conserved;After the completion of maintenance, stacking system 9.2 transports die station to demoulding
The first station of demoulding discharge zone 10.1 in discharge zone 10 carries out side and touches disassembly;
Then it is delivered in inclination discharging 11 and carries out inclination demoulding, handling discharging;Die station is delivered to die station clearing zone 12 later
Carry out mold cleaning;Die station is delivered in one area 1 of processing later and carries out next circulation.
Example IV
A kind of production technology of the present embodiment for abnormity component, the production technology:
Die station is successively by one area's station 1.1 or 1.2 of processing or 1.3 or 1.4 or 1.5 or 1.6 or 1.7 in one area 1 of processing first
Or any independent station in 1.8 or 1.9 or 1.10 carries out die station setting-out, side mode installation, mold oiling, installation of embedded parts, steel
Muscle installation;
Then by ferry-boat system 2 by die station transport to pour pouring in area 3 of vibrating vibrate the first station of area 3.1, pour vibration
It smashes area's second station 3.2 or pours area's 3rd station 3.3 of vibrating and poured and vibrated;
Then die station is by three area's station 6.1 or 6.2 of processing in three areas 6 of processing, into the area precuring Jing Ting 7, the area Bing Ci
Quiet shut-down sequence is completed in domain;Pass through four area's station 8.1 or 8.2 of processing in four areas 8 of processing later;
Then stacking maintenance area 9 is delivered to be conserved;After the completion of maintenance, die station is transported to the demoulding in demoulding discharge zone 10
The first station of discharge zone 10.1 or demoulding discharge zone second station 10.2 carry out side mode disassembly, demoulding discharging;
Then die station is delivered to die station clearing zone 12 and carries out mold cleaning;Die station is delivered in one area 1 of processing later and is carried out
Next circulation.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto,
Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its
Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.
Claims (5)
1. the building prefabricated components forming production line with central dispatch system, it is characterised in that: the production line includes following functions
Area: processing one area (1), ferry-boat system (2) pour area of vibrating (3), processing 2nd area (4), displacement movement system (5), 3rd area of processing
(6), the area precuring Jing Ting (7), processing 4th area (8), stacking maintenance area (9), demoulding discharge zone (10), inclination discharge zone (11)
With die station clearing zone (12);
The side of ferry-boat system (2) is processing one area (1), and the other side is processing 3rd area (6), the area precuring Jing Ting (7), processing
4th area (8), stacking maintenance area (9) and demoulding discharge zone (10);
Area of vibrating (3) are built in one end connection of ferry-boat system (2), build the other side connection processing 2nd area (4) in area of vibrating (3), ferry-boat
The other end of system (2) connects die station clearing zone (12), die station clearing zone (12) connection inclination discharge zone (11);
Displacement movement system (5) is provided in processing 2nd area (4), inclination discharge zone (11) and die station clearing zone (12);
Described processing one area (1) its quantity is more than or equal to one, and its internal number of stations is more than or equal to one, and process has
Die station setting-out, side mode installation, mold oiling, installation of embedded parts and reinforcement installation;
Described its quantity of ferry-boat system (2) is more than or equal to one, and is equipped with ferry-boat transloading equipment, by die station from die station clearing zone
(12) it is transported to the station processed in a phase area (1) or is transported to die station from the station in processing one area (1) and pour area of vibrating
(3);
Described area of vibrating (3) its quantity that pours is more than or equal to one, and internal number of stations is more than or equal to one, and process is glue
Gel material is poured and is vibrated;
Described processing 2nd area (4) its quantity is more than or equal to one, and internal number of stations is more than or equal to one, and process has built-in fitting
Installation, reinforcement installation and insulation board installation;
The displacement movement system (5) is equipped with displacement transloading equipment, and die station is transported to the assembly line to form perforation;
Its internal number of stations of 3rd area of the processing (6) is more than or equal to one, and is equipped with and catches up with leveling device, and function is poured to institute
Concrete catch up with flat processing or function only as transfer passage;
Its internal number of stations of the area the precuring Jing Ting (7) is more than or equal to one, function be to prefabricated components produced into
Row precuring handles or functions only as transfer passage;
Described processing 4th area (8) its number of stations is more than or equal to one, and is equipped with galling device and Troweling press finishing device, function
Hair pulling treatment or Troweling press finishing processing are carried out to prefabricated components produced or function only as transfer passage;
Described stacking maintenance area (9) its number of stations is more than or equal to one, and process is the maintenance of prefabricated components;
Described its number of stations of demoulding discharge zone (10) is more than or equal to one, and process is that side is touched disassembly, die station demoulding, allocated and transported out
Material;
Described its number of stations of inclination discharge zone (11) is more than or equal to one, and process is die station inclination demoulding, transhipment discharging;
Described its number of stations of die station clearing zone (12) is more than or equal to one, and process is mold cleaning or functions only as transfer passage.
2. the building prefabricated components forming production line according to claim 1 with central dispatch system, it is characterised in that:
The number of stations of the processing one area (1) are as follows: one area's station (1.1 or 1.2 or 1.3 or 1.4 or 1.5 or 1.6 or 1.7 of processing
Or 1.8 or 1.9 or 1.10);
The number of stations for pouring area of vibrating (3) are as follows: pour the first station of area (3.1) that vibrates, pour area's second station of vibrating
(3.2) it or pours vibrate area's 3rd station (3.3);
The number of stations of the processing 2nd area (4) are as follows: processing two area's stations (4.1 or 4.2 or 4.3 or 4.4 or 4.5 or 4.6);
The number of stations of the processing 3rd area (6) are as follows: processing three area's stations (6.1 or 6.2);
The number of stations in the area the precuring Jing Ting (7) are as follows: the area precuring Jing Ting station (7.1 or 7.2 or 7.3 or 7.4 or
7.5 or 7.6 or 7.7 or 7.8);
The number of stations of the processing 4th area (8) are as follows: processing four area's stations (8.1 or 8.2);
Stacking conserves the number of stations of area (9) are as follows: stacking system (9.2), stacking maintenance area's station (9.1 or 9.3);
Demould the number of stations of discharge zone (10) are as follows: demoulding the first station of discharge zone (10.1) or demoulding discharge zone second station
(10.2);
The number of stations of die station clearing zone (12) are as follows: die station clearing zone station (12.1 or 12.2).
3. a kind of production technology of superimposed sheet, the production technology are characterized in that: die station is successively by processing one area (1) first
Process any independent work in area's station (1.1 or 1.2 or 1.3 or 1.4 or 1.5 or 1.6 or 1.7 or 1.8 or 1.9 or 1.10)
Position carries out die station setting-out, side mode installation, mold oiling, installation of embedded parts, truss bars installation;
Then by ferry-boat system (2) by die station transport to pour pouring in area of vibrating (3) vibrate the first station of area (3.1),
It pours to vibrate area's second station (3.2) or pour area's 3rd station (3.3) of vibrating and is poured and vibrated;
Then die station is by three area's station of processing (6.1 or 6.2) in processing 3rd area (6), into the area precuring Jing Ting (7), and
Quiet shut-down sequence is completed in this area;
Then four area's station of processing (8.1 or 8.2) hair pulling treatment in processing 4th area (8);It is transported to stacking maintenance area later
(9) it is conserved;After the completion of maintenance, die station is transported to the first station of demoulding discharge zone (10.1) in demoulding discharge zone (10)
Or demoulding discharge zone second station (10.2) carries out side mode disassembly, demoulding discharging;
Then die station is delivered to die station clearing zone (12) and carries out mold cleaning;Die station is delivered in processing one area (1) later
Carry out next circulation.
4. a kind of production technology of the PC wallboard of band heat preservation, the production technology are characterized in that:
First die station successively by processing one area (1) in one area's station of processing (1.1 or 1.2 or 1.3 or 1.4 or 1.5 or 1.6 or
1.7 or 1.8 or 1.9 or 1.10) in any independent station carry out die station setting-out, side mode installation, mold oiling, steel mesh are pacified
Dress;
Then by ferry-boat system (2) by die station transport to pour pouring in area of vibrating (3) vibrate the first station of area (3.1) into
Row is poured and is vibrated for the first time;
Then the two area's station of processing (4.1 or 4.2 or 4.3 or 4.4 or 4.5 or 4.6) die station being delivered in processing 2nd area (4)
Carry out insulation board installation, installation of embedded parts, reinforcement installation;
Then it is delivered to pour pouring in area of vibrating (3) and vibrate and area's second station (3.2) or pours area's 3rd station of vibrating
(3.3) progress is secondary pours and vibrates
Then die station carries out catching up with flat process by three area's station of processing (6.1 or 6.2) in processing 3rd area (6);Later die station into
Enter the area precuring Jing Ting (7), and completes quiet shut-down sequence in this area;Four area's station of processing in processing 4th area (8) later
(8.1 or 8.2) carry out Troweling press finishing processing;
Then die station is transported to stacking maintenance area (9) and is conserved;After the completion of maintenance, stacking system (9.2) by die station transport to
The first station of demoulding discharge zone (10.1) in demoulding discharge zone (10) carries out side and touches disassembly;
Then it is delivered in inclination discharging (11) and carries out inclination demoulding, handling discharging;Die station is delivered to die station clearing zone later
(12) mold cleaning is carried out;Die station is delivered in processing one area (1) later and carries out next circulation.
5. a kind of production technology of abnormity component, the production technology are characterized in that:
First die station successively by processing one area (1) in one area's station of processing (1.1 or 1.2 or 1.3 or 1.4 or 1.5 or 1.6 or
1.7 or 1.8 or 1.9 or 1.10) in any independent station carry out die station setting-out, side mode installation, mold oiling, built-in fitting are pacified
Dress, reinforcement installation;
Then by ferry-boat system (2) by die station transport to pour pouring in area of vibrating (3) vibrate the first station of area (3.1),
It pours to vibrate area's second station (3.2) or pour area's 3rd station (3.3) of vibrating and is poured and vibrated;
Then die station is by three area's station of processing (6.1 or 6.2) in processing 3rd area (6), into the area precuring Jing Ting (7), and
Quiet shut-down sequence is completed in this area;Pass through four area's station of processing (8.1 or 8.2) in processing 4th area (8) later;
Then stacking maintenance area (9) is delivered to be conserved;After the completion of maintenance, die station is transported to demoulding discharge zone (10)
It demoulds the first station of discharge zone (10.1) or demoulding discharge zone second station (10.2) carries out side mode disassembly, demoulding discharging;
Then die station is delivered to die station clearing zone (12) and carries out mold cleaning;Die station is delivered in processing one area (1) later
Carry out next circulation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910144117.XA CN109732768A (en) | 2019-02-27 | 2019-02-27 | Building prefabricated components forming production line and production technology with central dispatch system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910144117.XA CN109732768A (en) | 2019-02-27 | 2019-02-27 | Building prefabricated components forming production line and production technology with central dispatch system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109732768A true CN109732768A (en) | 2019-05-10 |
Family
ID=66368500
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910144117.XA Pending CN109732768A (en) | 2019-02-27 | 2019-02-27 | Building prefabricated components forming production line and production technology with central dispatch system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109732768A (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110053151A (en) * | 2019-05-23 | 2019-07-26 | 长沙远大住宅工业集团股份有限公司 | A kind of prefabricated components production line with temporary function |
CN110076897A (en) * | 2019-05-23 | 2019-08-02 | 长沙远大住宅工业集团股份有限公司 | A kind of prefabricated components production line with platform mould temporary storage location |
CN110228134A (en) * | 2019-06-20 | 2019-09-13 | 中国二十二冶集团有限公司 | Interior wall board member production line double-cycle process method for arranging |
CN110370447A (en) * | 2019-06-20 | 2019-10-25 | 中国二十二冶集团有限公司 | Overlap board member production line double-cycle process method for arranging |
CN110405932A (en) * | 2019-06-20 | 2019-11-05 | 中国二十二冶集团有限公司 | Double skin wall member production line double-cycle process method for arranging |
CN110450275A (en) * | 2019-06-20 | 2019-11-15 | 中国二十二冶集团有限公司 | PC component integrated production line double-cycle process method for arranging |
CN111873164A (en) * | 2020-07-29 | 2020-11-03 | 江苏蓝海住宅工业有限公司 | Production system of concrete prefabricated part and production process of production system |
CN113829487A (en) * | 2021-09-29 | 2021-12-24 | 广州市市政工程机械施工有限公司 | Extensible discrete flexible PC digital production line based on heavy-load AGV technology |
CN117124430A (en) * | 2023-10-27 | 2023-11-28 | 湖南恒运建筑科技发展有限公司 | Prefabricated equipment is used in processing of haydite concrete prefabricated wallboard |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205219397U (en) * | 2015-10-27 | 2016-05-11 | 沈阳卫德住宅工业化科技有限公司 | Ferry -boat formula precast concrete of central authorities component production line |
WO2016078610A1 (en) * | 2014-11-21 | 2016-05-26 | 天津银龙预应力材料股份有限公司 | Production line of track plate |
CN107322779A (en) * | 2017-07-18 | 2017-11-07 | 江苏汤辰机械装备制造股份有限公司 | A kind of PC components automatic production line and production procedure technique |
CN108890850A (en) * | 2018-06-22 | 2018-11-27 | 美好建筑装配科技有限公司 | A kind of intelligent production line and production technology producing multi items standard PC component |
CN109203215A (en) * | 2018-11-09 | 2019-01-15 | 长沙英平机械制造有限责任公司 | Concrete prefabricated element production line |
CN210210841U (en) * | 2019-02-27 | 2020-03-31 | 中清大装配式建筑有限公司 | Take central dispatching system's building prefabricated component shaping production line |
-
2019
- 2019-02-27 CN CN201910144117.XA patent/CN109732768A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2016078610A1 (en) * | 2014-11-21 | 2016-05-26 | 天津银龙预应力材料股份有限公司 | Production line of track plate |
CN205219397U (en) * | 2015-10-27 | 2016-05-11 | 沈阳卫德住宅工业化科技有限公司 | Ferry -boat formula precast concrete of central authorities component production line |
CN107322779A (en) * | 2017-07-18 | 2017-11-07 | 江苏汤辰机械装备制造股份有限公司 | A kind of PC components automatic production line and production procedure technique |
CN108890850A (en) * | 2018-06-22 | 2018-11-27 | 美好建筑装配科技有限公司 | A kind of intelligent production line and production technology producing multi items standard PC component |
CN109203215A (en) * | 2018-11-09 | 2019-01-15 | 长沙英平机械制造有限责任公司 | Concrete prefabricated element production line |
CN210210841U (en) * | 2019-02-27 | 2020-03-31 | 中清大装配式建筑有限公司 | Take central dispatching system's building prefabricated component shaping production line |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110053151A (en) * | 2019-05-23 | 2019-07-26 | 长沙远大住宅工业集团股份有限公司 | A kind of prefabricated components production line with temporary function |
CN110076897A (en) * | 2019-05-23 | 2019-08-02 | 长沙远大住宅工业集团股份有限公司 | A kind of prefabricated components production line with platform mould temporary storage location |
CN110228134A (en) * | 2019-06-20 | 2019-09-13 | 中国二十二冶集团有限公司 | Interior wall board member production line double-cycle process method for arranging |
CN110370447A (en) * | 2019-06-20 | 2019-10-25 | 中国二十二冶集团有限公司 | Overlap board member production line double-cycle process method for arranging |
CN110405932A (en) * | 2019-06-20 | 2019-11-05 | 中国二十二冶集团有限公司 | Double skin wall member production line double-cycle process method for arranging |
CN110450275A (en) * | 2019-06-20 | 2019-11-15 | 中国二十二冶集团有限公司 | PC component integrated production line double-cycle process method for arranging |
CN111873164A (en) * | 2020-07-29 | 2020-11-03 | 江苏蓝海住宅工业有限公司 | Production system of concrete prefabricated part and production process of production system |
CN111873164B (en) * | 2020-07-29 | 2021-08-10 | 江苏蓝海住宅工业有限公司 | Production system of concrete prefabricated part and production process of production system |
CN113829487A (en) * | 2021-09-29 | 2021-12-24 | 广州市市政工程机械施工有限公司 | Extensible discrete flexible PC digital production line based on heavy-load AGV technology |
CN117124430A (en) * | 2023-10-27 | 2023-11-28 | 湖南恒运建筑科技发展有限公司 | Prefabricated equipment is used in processing of haydite concrete prefabricated wallboard |
CN117124430B (en) * | 2023-10-27 | 2024-01-05 | 湖南恒运建筑科技发展有限公司 | Prefabricated equipment is used in processing of haydite concrete prefabricated wallboard |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109732768A (en) | Building prefabricated components forming production line and production technology with central dispatch system | |
CN109732767A (en) | Multipurpose assembled architecture prefabricated components forming production line and its production technology | |
CN104723449B (en) | A kind of automatic assembly line of building industrialization concrete prefabricated element | |
CN104626348B (en) | Prefabricated components production line | |
CN108890850B (en) | Intelligent production line and production process capable of producing various standard PC components | |
CN108058266A (en) | Prefabricated components integrated production line | |
CN107263697A (en) | A kind of intelligent production line of two-way expansible prefabricated components and control method | |
CN108536933A (en) | A kind of system and method for automatic arrangement reinforcing bar | |
CN106639317A (en) | Prefabricated building complete set constructing technology | |
RU2471620C2 (en) | Method of making hollow prismatic modular reinforced concrete elements and plant to this end | |
CN111975974A (en) | Double-circulation production line and production process of prefabricated components of fabricated building | |
CN204382485U (en) | Prefabricated components production system | |
CN108316532A (en) | Plate laminated floor slab drops in electromechanical integration laminated floor slab and its production method, toilet | |
CN105563623A (en) | Production method for prefabricated wall boards | |
CN110682434A (en) | Composite floor slab and double-skin wall single-circulation prefabrication comprehensive production line and production method thereof | |
WO2020232744A1 (en) | Prefabricated component production line having temporary storage function | |
CN109227921A (en) | A kind of prefabricated components production line | |
CN107627436A (en) | The production technology and production facility of concrete prefabricated element | |
CN108428036A (en) | A kind of collaborative management method of assembled plant, apparatus and system | |
CN109333800A (en) | A kind of prefabricated components production line | |
CN208629675U (en) | Concrete prefabricated element process units | |
CN111186009A (en) | Preparation method of PC prefabricated part double-circulation production line | |
CN212498269U (en) | Double-circulation production line for prefabricated components of fabricated building | |
CN108748643B (en) | Novel intelligent production line of assembled building material | |
CN109719843A (en) | It concrete prefabricated element production line and its pours and smashes device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |