CN108797929A - Ecological stone material construction - Google Patents
Ecological stone material construction Download PDFInfo
- Publication number
- CN108797929A CN108797929A CN201810544157.9A CN201810544157A CN108797929A CN 108797929 A CN108797929 A CN 108797929A CN 201810544157 A CN201810544157 A CN 201810544157A CN 108797929 A CN108797929 A CN 108797929A
- Authority
- CN
- China
- Prior art keywords
- stone material
- stone
- jointing
- brick
- paving
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/14—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements stone or stone-like materials, e.g. ceramics concrete; of glass or with an outer layer of stone or stone-like materials or glass
- E04F13/147—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements stone or stone-like materials, e.g. ceramics concrete; of glass or with an outer layer of stone or stone-like materials or glass with an outer layer imitating natural stone, brick work or the like
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Repair (AREA)
Abstract
The invention discloses a kind of ecological stone material construction, including wall plastering, base's surface treatment, optimization row's brick gap scheme, the positioning of snap the line row's brick, bonding mucilage mixing, wall in slurry and paving is scraped at the back side, seam is drawn in jointing, metope is cleared up.The present invention is easy for construction, and effect is good.
Description
Technical field
The present invention relates to a kind of ecological stone material constructions.
Background technology
Lithotome is widely used under construction, but limited due to resource, and exploitation stone material is to natural, ecological ring
The destructiveness in border, gradually attracts people's attention.
And a kind of MCM ecologies stone material, the inorganic matters such as block and pitchers, mountain flour are abandoned as raw material, through dividing using urban construction waste soil, cement
Class mixes, is composite modified, is molded at a temperature of photochemical isomery and curve.The product meet country advocate it is energy saving, section material, save land,
Water-saving, environmentally protective policy.
MCM ecology stone materials have the texture and texture of lithotome, it can overcome in Bartlit exterior wall from heavy, easy
The problems such as accumulation of salt in the surface soil, antidetonation be poor, easy to leak.
Invention content
The purpose of the present invention is to provide a kind of easy for construction, good ecological stone material constructions of effect.
Technical solution of the invention is:
A kind of ecology stone material construction, it is characterized in that:Include the following steps:
(One)Wall plastering
(1)Before exterior wall smears bottom ash, using corner positioning, the intermediate plastering method for determining face, the flatness of base is improved;With sharp
Metope is scanned reference plane by optical measuring instrument, first looks for Founder to do ash cake external corner, then again on big face wall according to 1.5m × 1.5m
Spacing does the reference plane that ash cake identifies big face wall, and openings position increases by four big angles and pastes ash cake;
(2)Coat of plaster is constructed from top to bottom completion;
(3)Check that plastering surface evenness, flatness are controlled in 2-3mm in real time;
(4)Showering curing is no less than 7 days after the completion of coat of plaster;
(Two)Base's surface treatment
(1)Laitance, dust, the dirt in base's plastering face are cleaned out;
(2)To part plastering face verticality, the undesirable position in flatness negative and positive angle, using quartz mortar filling-in;
(Three)Optimization row's brick gap scheme
(1)Entity measuring calculates the horizontal and vertical node size of each facade, by 1:50 ratio is drawn with CAD on computers
Each facade drawing designs according to design drawing facade effect, multiple stone material paving typesetting conceptual schemes is drawn on facade drawing,
The I-shaped seam sticking scheme of architectural modeling feature can be embodied by choosing, and carry out construction modulus examination row by prioritization scheme, and determine
Joint gap;
(2)The principle of typesetting paving:
1)Ensure that Stone brick gap is uniform, meets design requirement;
2)Big metope, exceedingly high pillar and pier will arrange monoblock paving;When being unable to monoblock paving, pillar stone material is taken and is uniformly divided
Block laying method;For big face wall, then non-monoblock position is discharged to unobtrusively position, and stone material is avoided to be less than 1/3 piece of area;
3)It such as meets the stone material around metope protrusion and should integrally cover and cut, it is ensured that neat in edge forbids piecing together edge patch;
(Four)Snap the line arranges brick positioning
On plaster base vertical line and horizontal line conduct are popped up using the specification of material, size as standard by optimization row's brick scheme
Paste control line;
(Five)Bonding mucilage mixing
(1)According to the match ratio and its adhesion strength examining report of experiment model, stone is added using binder rubber powder cooperation latex solution
Diamond stone gravel increases adhesive strength;
(2)During bonding mucilage mixing auxiliary material stirring sequence according to:Polymer emulsion → rubber powder → quartz sand sequential feeding,
Idle 15 minutes or so after the completion of stirring, reacted with the further of lotion to glue powder, after carry out application work again;
(3)Bonding mucilage and pointing are stirred using motor machine in uniform sticky slurry, and avoiding stirring by hand leads to adhesive glue
Starch non-uniform problem;
(Six)Scrape wall in slurry and paving in the back side
(1)Slurry is scraped in the stone material back of the body using zigzag steel trowel, ensures that back side recess is just filled and led up by polymer cement binder;
(2)To keep the cleaning of brick face, layup sequence paving from top to bottom is adhered to;Bonding mucilage is put on zigzag steel trowel
Brick back, shaving must uniformly be paved with brick bottom, can not put viscous, not interspace, and ensureing completely 90% or more slurry rate and pulling out sawtooth lines
Starch thickness 2-4mm;Then frame bar is pressed by stone material paving on metope, with the hands moves pressure on stone material after wall back and forth and to line,
It moves die pressing product adjustment slit width blend compounds plate and uniformly pats stone material surface;Make bonding mucilage equably squeeze out stone material while while on, once have
Bonding mucilage spilling should be cleaned out with clean cloth or sponge in time;Before adhesive layer initial set, position and the seam of stone material are adjusted
Width, to complete solidification stages after adhesive layer initial set, the stone material for forbidding disturbance to paste;
(Seven)Seam is drawn in jointing
(1)Using special gap filler joint filling, can more times improve the speed of joint filling and jointing, and can keep cleaning;Due to stone material sheet
Stature matter is relatively thin, and calking tool is poured into the gap filler being stirred in glue rifle using flexible glue rifle, and punched mouth need to be split into it is ellipse
It is round;It is uniformly pressed into preset slot and pulls down soft by gap filler by extrusion handle such as gluing operation when carrying out joint filling operation
Glue rifle rifle mouth, to ensure the uniform full of mortar joint;
(2)Seam and jointing are drawn using the round steel rib of mating jointing light;It may be noted that joint sealing material suitably receives water seven when jointing
At it is dry when with smooth reinforcing bar round bar carry out jointing, from top to bottom, first after short seam slit sequence;Jointing round bar diameter should be than seam
Roomy 2-4mm, jointing answer full, continuous, the straight, depth uniformly, flawless;
(Eight)Metope is cleared up
(1)The bonding agent that stone surface stains must not be washed with water when not dry or be wiped with aqueous article, and glue should be used after initial set
Plate strikes off or is cleaned out with dry sponge;
(2)First check that whether there is or not crackings, such as cracking to repair in time for mortar joint before large area cleaning;It is solidifying that rubber cement is pasted after joint filling completion
Consolidate and after reaching some strength, scrubbing brick face comprehensively from top to down with clear water until clean;
The stone material is ecological stone material.
The ecology stone material is MCM ecology stone materials.
The present invention carries out typesetting setting-out to MCM ecology stone materials on computers first with CAD drawing techniques, recycles master die
Plate and horizontal vertical lattice control technology eliminate cumulative errors caused by setting-out, ensure the unification for imitating stone effect.Using corner
Positioning, the intermediate plastering method for determining face, improve the flatness of base, meet MCM ecology stone materials and bond requirement.It is smeared using steel
The sawtooth trowel mouth of son carries out scraping slurry in MCM ecologies back face of stone, keeps bonding mucilage well-bonded with back face of stone, and effectively control is viscous
The thickness of gum deposit slurry.The plumpness of bonding mucilage is improved, ensures the adhesion strength of wall on stone material.Pass through special jointing technique
Jointing operation is carried out, that is, plays waterproof effect, and keeps the visual effect of imitative stone material more true to nature.The present invention is suitable for height and is not more than
100m, seismic fortification intensity are not more than 8 degree, using the multilayer of the exposed wall facing brick stickup of full bonding construction, high building project
Exterior wall.
With reference to embodiment, the invention will be further described.
Specific implementation mode
A kind of ecology stone material construction, includes the following steps:
(One)Wall plastering
(1)Before exterior wall smears bottom ash, using corner positioning, the intermediate plastering method for determining face, the flatness of base is improved;With sharp
Metope is scanned reference plane by optical measuring instrument, first looks for Founder to do ash cake external corner, then again on big face wall according to 1.5m × 1.5m
Spacing does the reference plane that ash cake identifies big face wall, and openings position increases by four big angles and pastes ash cake;
(2)Coat of plaster is constructed from top to bottom completion;
(3)Check that plastering surface evenness, flatness are controlled in 2-3mm in real time;
(4)Showering curing is no less than 7 days after the completion of coat of plaster;
(Two)Base's surface treatment
(1)Laitance, dust, the dirt in base's plastering face are cleaned out;
(2)To part plastering face verticality, the undesirable position in flatness negative and positive angle, using quartz mortar filling-in;
(Three)Optimization row's brick gap scheme
(1)Entity measuring calculates the horizontal and vertical node size of each facade, by 1:50 ratio is drawn with CAD on computers
Each facade drawing designs according to design drawing facade effect, multiple stone material paving typesetting conceptual schemes is drawn on facade drawing,
The I-shaped seam sticking scheme of architectural modeling feature can be embodied by choosing, and carry out construction modulus examination row by prioritization scheme, and determine
Joint gap;
(2)The principle of typesetting paving:
1)Ensure that Stone brick gap is uniform, meets design requirement;
2)Big metope, exceedingly high pillar and pier will arrange monoblock paving;When being unable to monoblock paving, pillar stone material is taken and is uniformly divided
Block laying method;For big face wall, then non-monoblock position is discharged to unobtrusively position, and stone material is avoided to be less than 1/3 piece of area;
3)It such as meets the stone material around metope protrusion and should integrally cover and cut, it is ensured that neat in edge forbids piecing together edge patch;
(Four)Snap the line arranges brick positioning
On plaster base vertical line and horizontal line conduct are popped up using the specification of material, size as standard by optimization row's brick scheme
Paste control line;
(Five)Bonding mucilage mixing
(1)According to the match ratio and its adhesion strength examining report of experiment model, stone is added using binder rubber powder cooperation latex solution
Diamond stone gravel increases adhesive strength;
(2)During bonding mucilage mixing auxiliary material stirring sequence according to:Polymer emulsion → rubber powder → quartz sand sequential feeding,
Idle 15 minutes or so after the completion of stirring, reacted with the further of lotion to glue powder, after carry out application work again;
(3)Bonding mucilage and pointing are stirred using motor machine in uniform sticky slurry, and avoiding stirring by hand leads to adhesive glue
Starch non-uniform problem;
(Six)Scrape wall in slurry and paving in the back side
(1)Slurry is scraped in the stone material back of the body using zigzag steel trowel, ensures that back side recess is just filled and led up by polymer cement binder;
(2)To keep the cleaning of brick face, layup sequence paving from top to bottom is adhered to;Bonding mucilage is put on zigzag steel trowel
Brick back, shaving must uniformly be paved with brick bottom, can not put viscous, not interspace, and ensureing completely 90% or more slurry rate and pulling out sawtooth lines
Starch thickness 2-4mm;Then frame bar is pressed by stone material paving on metope, with the hands moves pressure on stone material after wall back and forth and to line,
It moves die pressing product adjustment slit width blend compounds plate and uniformly pats stone material surface;Make bonding mucilage equably squeeze out stone material while while on, once have
Bonding mucilage spilling should be cleaned out with clean cloth or sponge in time;Before adhesive layer initial set, position and the seam of stone material are adjusted
Width, to complete solidification stages after adhesive layer initial set, the stone material for forbidding disturbance to paste;
(Seven)Seam is drawn in jointing
(1)Using special gap filler joint filling, can more times improve the speed of joint filling and jointing, and can keep cleaning;Due to stone material sheet
Stature matter is relatively thin, and calking tool is poured into the gap filler being stirred in glue rifle using flexible glue rifle, and punched mouth need to be split into it is ellipse
It is round;It is uniformly pressed into preset slot and pulls down soft by gap filler by extrusion handle such as gluing operation when carrying out joint filling operation
Glue rifle rifle mouth, to ensure the uniform full of mortar joint;
(2)Seam and jointing are drawn using the round steel rib of mating jointing light;It may be noted that joint sealing material suitably receives water seven when jointing
At it is dry when with smooth reinforcing bar round bar carry out jointing, from top to bottom, first after short seam slit sequence;Jointing round bar diameter should be than seam
Roomy 2-4mm, jointing answer full, continuous, the straight, depth uniformly, flawless;
(Eight)Metope is cleared up
(1)The bonding agent that stone surface stains must not be washed with water when not dry or be wiped with aqueous article, and glue should be used after initial set
Plate strikes off or is cleaned out with dry sponge;
(2)First check that whether there is or not crackings, such as cracking to repair in time for mortar joint before large area cleaning;It is solidifying that rubber cement is pasted after joint filling completion
Consolidate and after reaching some strength, scrubbing brick face comprehensively from top to down with clear water until clean;
The stone material is ecological stone material.The ecology stone material is MCM ecology stone materials.
Claims (2)
1. a kind of ecology stone material construction, it is characterized in that:Include the following steps:
(One)Wall plastering
(1)Before exterior wall smears bottom ash, using corner positioning, the intermediate plastering method for determining face, the flatness of base is improved;With sharp
Metope is scanned reference plane by optical measuring instrument, first looks for Founder to do ash cake external corner, then again on big face wall according to 1.5m × 1.5m
Spacing does the reference plane that ash cake identifies big face wall, and openings position increases by four big angles and pastes ash cake;
(2)Coat of plaster is constructed from top to bottom completion;
(3)Check that plastering surface evenness, flatness are controlled in 2-3mm in real time;
(4)Showering curing is no less than 7 days after the completion of coat of plaster;
(Two)Base's surface treatment
(1)Laitance, dust, the dirt in base's plastering face are cleaned out;
(2)To part plastering face verticality, the undesirable position in flatness negative and positive angle, using quartz mortar filling-in;
(Three)Optimization row's brick gap scheme
(1)Entity measuring calculates the horizontal and vertical node size of each facade, by 1:50 ratio is drawn with CAD on computers
Each facade drawing designs according to design drawing facade effect, multiple stone material paving typesetting conceptual schemes is drawn on facade drawing,
The I-shaped seam sticking scheme of architectural modeling feature can be embodied by choosing, and carry out construction modulus examination row by prioritization scheme, and determine
Joint gap;
(2)The principle of typesetting paving:
1)Ensure that Stone brick gap is uniform, meets design requirement;
2)Big metope, exceedingly high pillar and pier will arrange monoblock paving;When being unable to monoblock paving, pillar stone material is taken and is uniformly divided
Block laying method;For big face wall, then non-monoblock position is discharged to unobtrusively position, and stone material is avoided to be less than 1/3 piece of area;
3)It such as meets the stone material around metope protrusion and should integrally cover and cut, it is ensured that neat in edge forbids piecing together edge patch;
(Four)Snap the line arranges brick positioning
On plaster base vertical line and horizontal line conduct are popped up using the specification of material, size as standard by optimization row's brick scheme
Paste control line;
(Five)Bonding mucilage mixing
(1)According to the match ratio and its adhesion strength examining report of experiment model, stone is added using binder rubber powder cooperation latex solution
Diamond stone gravel increases adhesive strength;
(2)During bonding mucilage mixing auxiliary material stirring sequence according to:Polymer emulsion → rubber powder → quartz sand sequential feeding,
Idle 15 minutes or so after the completion of stirring, reacted with the further of lotion to glue powder, after carry out application work again;
(3)Bonding mucilage and pointing are stirred using motor machine in uniform sticky slurry, and avoiding stirring by hand leads to adhesive glue
Starch non-uniform problem;
(Six)Scrape wall in slurry and paving in the back side
(1)Slurry is scraped in the stone material back of the body using zigzag steel trowel, ensures that back side recess is just filled and led up by polymer cement binder;
(2)To keep the cleaning of brick face, layup sequence paving from top to bottom is adhered to;Bonding mucilage is put on zigzag steel trowel
Brick back, shaving must uniformly be paved with brick bottom, can not put viscous, not interspace, and ensureing completely 90% or more slurry rate and pulling out sawtooth lines
Starch thickness 2-4mm;Then frame bar is pressed by stone material paving on metope, with the hands moves pressure on stone material after wall back and forth and to line,
It moves die pressing product adjustment slit width blend compounds plate and uniformly pats stone material surface;Make bonding mucilage equably squeeze out stone material while while on, once have
Bonding mucilage spilling should be cleaned out with clean cloth or sponge in time;Before adhesive layer initial set, position and the seam of stone material are adjusted
Width, to complete solidification stages after adhesive layer initial set, the stone material for forbidding disturbance to paste;
(Seven)Seam is drawn in jointing
(1)Using special gap filler joint filling, can more times improve the speed of joint filling and jointing, and can keep cleaning;Due to stone material sheet
Stature matter is relatively thin, and calking tool is poured into the gap filler being stirred in glue rifle using flexible glue rifle, and punched mouth need to be split into it is ellipse
It is round;It is uniformly pressed into preset slot and pulls down soft by gap filler by extrusion handle such as gluing operation when carrying out joint filling operation
Glue rifle rifle mouth, to ensure the uniform full of mortar joint;
(2)Seam and jointing are drawn using the round steel rib of mating jointing light;It may be noted that joint sealing material suitably receives water seven when jointing
At it is dry when with smooth reinforcing bar round bar carry out jointing, from top to bottom, first after short seam slit sequence;Jointing round bar diameter should be than seam
Roomy 2-4mm, jointing answer full, continuous, the straight, depth uniformly, flawless;
(Eight)Metope is cleared up
(1)The bonding agent that stone surface stains must not be washed with water when not dry or be wiped with aqueous article, and glue should be used after initial set
Plate strikes off or is cleaned out with dry sponge;
(2)First check that whether there is or not crackings, such as cracking to repair in time for mortar joint before large area cleaning;It is solidifying that rubber cement is pasted after joint filling completion
Consolidate and after reaching some strength, scrubbing brick face comprehensively from top to down with clear water until clean;
The stone material is ecological stone material.
2. ecology stone material construction according to claim 1, it is characterized in that:The ecology stone material is MCM ecology stone materials.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810544157.9A CN108797929A (en) | 2018-05-31 | 2018-05-31 | Ecological stone material construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810544157.9A CN108797929A (en) | 2018-05-31 | 2018-05-31 | Ecological stone material construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108797929A true CN108797929A (en) | 2018-11-13 |
Family
ID=64089608
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810544157.9A Pending CN108797929A (en) | 2018-05-31 | 2018-05-31 | Ecological stone material construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108797929A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109750814A (en) * | 2019-01-26 | 2019-05-14 | 广州市第三建筑装修有限公司 | Anti- hollowing wall construction method |
CN109779178A (en) * | 2019-01-29 | 2019-05-21 | 苏州金螳螂建筑装饰股份有限公司 | A kind of the joint filling structure and its method of indoor decoration surface layer |
CN109898773A (en) * | 2019-03-21 | 2019-06-18 | 安徽省第二建筑工程有限公司 | The soft patch construction of gypsum wall vitrified tile |
CN110469068A (en) * | 2019-07-29 | 2019-11-19 | 安徽智恒节能材料科技有限公司 | A kind of construction technology of exterior wall decorating tile |
CN113323314A (en) * | 2021-06-10 | 2021-08-31 | 中国建筑第八工程局有限公司 | External wall paving construction method for sintered ceramic tiles in freeze-thaw environment |
CN113503027A (en) * | 2021-07-09 | 2021-10-15 | 中国二十冶集团有限公司 | External wall construction method based on soft porcelain |
CN114352056A (en) * | 2021-12-23 | 2022-04-15 | 上海建工集团股份有限公司 | Construction process for renovating ecological face bricks on old wall surfaces |
CN114412104A (en) * | 2022-01-27 | 2022-04-29 | 广州市绿化有限公司 | Construction method for stone paving alkali return control flow guiding net |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101949208A (en) * | 2010-09-08 | 2011-01-19 | 深圳市建设(集团)有限公司 | Construction method for plastering wall and adhering plaster dough in building construction |
CN103758312A (en) * | 2011-12-31 | 2014-04-30 | 常熟古建园林建设集团有限公司 | Laminating construction method for facing bricks |
-
2018
- 2018-05-31 CN CN201810544157.9A patent/CN108797929A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101949208A (en) * | 2010-09-08 | 2011-01-19 | 深圳市建设(集团)有限公司 | Construction method for plastering wall and adhering plaster dough in building construction |
CN103758312A (en) * | 2011-12-31 | 2014-04-30 | 常熟古建园林建设集团有限公司 | Laminating construction method for facing bricks |
Non-Patent Citations (2)
Title |
---|
中国建筑业协会: "《创建鲁班奖工程细部做法指导》", 30 April 2014 * |
陈璞: "外墙柔性饰面砖施工工艺及避免泛碱问题的探讨", 《新型建筑材料》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109750814A (en) * | 2019-01-26 | 2019-05-14 | 广州市第三建筑装修有限公司 | Anti- hollowing wall construction method |
CN109779178A (en) * | 2019-01-29 | 2019-05-21 | 苏州金螳螂建筑装饰股份有限公司 | A kind of the joint filling structure and its method of indoor decoration surface layer |
CN109898773A (en) * | 2019-03-21 | 2019-06-18 | 安徽省第二建筑工程有限公司 | The soft patch construction of gypsum wall vitrified tile |
CN110469068A (en) * | 2019-07-29 | 2019-11-19 | 安徽智恒节能材料科技有限公司 | A kind of construction technology of exterior wall decorating tile |
CN113323314A (en) * | 2021-06-10 | 2021-08-31 | 中国建筑第八工程局有限公司 | External wall paving construction method for sintered ceramic tiles in freeze-thaw environment |
CN113503027A (en) * | 2021-07-09 | 2021-10-15 | 中国二十冶集团有限公司 | External wall construction method based on soft porcelain |
CN114352056A (en) * | 2021-12-23 | 2022-04-15 | 上海建工集团股份有限公司 | Construction process for renovating ecological face bricks on old wall surfaces |
CN114412104A (en) * | 2022-01-27 | 2022-04-29 | 广州市绿化有限公司 | Construction method for stone paving alkali return control flow guiding net |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108797929A (en) | Ecological stone material construction | |
CN109838065B (en) | Floor tile ground paving construction method | |
CN102505831A (en) | Construction method for paving plasters on ground and manmade stone | |
US20070071551A1 (en) | Surface seeded fine aggregate concrete simulating quarried stone | |
CN107143111A (en) | A kind of construction method of abrasion-proof terrace | |
CN102518216A (en) | Cantilever type cover plate deformation joint structure of accessible roof and construction method for structure | |
CN103740156A (en) | Novel low-cost easily constructed putty as well as preparation method and construction process thereof | |
CN109441059A (en) | A kind of plastic floor laying structure and its construction method | |
CN108468413A (en) | A kind of air-entrained concrete building block exempts from anti-hollowing construction method of plastering | |
CN107130766A (en) | One kind crystallization envelope seamless stone floor construction method of glaze | |
CN106284998A (en) | Plastering on inner walls completely spreads fiberglass gridding cloth construction method | |
CN104831926B (en) | A kind of tenon joint type bulk surface layer flooring method for paving | |
CN109025136A (en) | Glue for tile pastes tapestry brick construction method between more boiled water rooms | |
CN105178547A (en) | Large-unit ceramic thin sheet back-suspending and gluing structure and construction method thereof | |
CN101008192A (en) | Construction method of outer wall insulation system adopting composite insulation surface tile | |
CN103291024B (en) | A kind of construction method of novel cement-based motar | |
CN105437354B (en) | The method of binding face tile when a kind of prefabricated concrete floor and wallboard | |
CN105888084A (en) | Whole outer wall internal thermal insulation system construction method by using enhanced composite thermal insulation material | |
CN108979034A (en) | Wall surface construction technology | |
CN1108934C (en) | Method for producing coating with decorative patterns, mineral coating and tool for implementing same | |
CN210597982U (en) | Composite copper plate structure with back bolt on floor | |
CN108558305A (en) | The inorganic tile gap filler and preparation method thereof of squeezing and coating construction | |
CN104612343A (en) | Method for constructing extruded polystyrene board molding of building outer wall | |
CN205025042U (en) | Big unit pottery sheet metal back of body kiss -coating bonds and constructs | |
CN205577324U (en) | Vitrified tile spreads and pastes structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181113 |
|
RJ01 | Rejection of invention patent application after publication |