CN108797929A - Ecological stone material construction - Google Patents

Ecological stone material construction Download PDF

Info

Publication number
CN108797929A
CN108797929A CN201810544157.9A CN201810544157A CN108797929A CN 108797929 A CN108797929 A CN 108797929A CN 201810544157 A CN201810544157 A CN 201810544157A CN 108797929 A CN108797929 A CN 108797929A
Authority
CN
China
Prior art keywords
stone material
stone
jointing
brick
paving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810544157.9A
Other languages
Chinese (zh)
Inventor
秦庆华
李义
闫立
黄磊
施丰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA UNION CENTURY BUILDING GROUP Co Ltd
Original Assignee
CHINA UNION CENTURY BUILDING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA UNION CENTURY BUILDING GROUP Co Ltd filed Critical CHINA UNION CENTURY BUILDING GROUP Co Ltd
Priority to CN201810544157.9A priority Critical patent/CN108797929A/en
Publication of CN108797929A publication Critical patent/CN108797929A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/14Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements stone or stone-like materials, e.g. ceramics concrete; of glass or with an outer layer of stone or stone-like materials or glass
    • E04F13/147Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements stone or stone-like materials, e.g. ceramics concrete; of glass or with an outer layer of stone or stone-like materials or glass with an outer layer imitating natural stone, brick work or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)

Abstract

The invention discloses a kind of ecological stone material construction, including wall plastering, base's surface treatment, optimization row's brick gap scheme, the positioning of snap the line row's brick, bonding mucilage mixing, wall in slurry and paving is scraped at the back side, seam is drawn in jointing, metope is cleared up.The present invention is easy for construction, and effect is good.

Description

Ecological stone material construction
Technical field
The present invention relates to a kind of ecological stone material constructions.
Background technology
Lithotome is widely used under construction, but limited due to resource, and exploitation stone material is to natural, ecological ring The destructiveness in border, gradually attracts people's attention.
And a kind of MCM ecologies stone material, the inorganic matters such as block and pitchers, mountain flour are abandoned as raw material, through dividing using urban construction waste soil, cement Class mixes, is composite modified, is molded at a temperature of photochemical isomery and curve.The product meet country advocate it is energy saving, section material, save land, Water-saving, environmentally protective policy.
MCM ecology stone materials have the texture and texture of lithotome, it can overcome in Bartlit exterior wall from heavy, easy The problems such as accumulation of salt in the surface soil, antidetonation be poor, easy to leak.
Invention content
The purpose of the present invention is to provide a kind of easy for construction, good ecological stone material constructions of effect.
Technical solution of the invention is:
A kind of ecology stone material construction, it is characterized in that:Include the following steps:
(One)Wall plastering
(1)Before exterior wall smears bottom ash, using corner positioning, the intermediate plastering method for determining face, the flatness of base is improved;With sharp Metope is scanned reference plane by optical measuring instrument, first looks for Founder to do ash cake external corner, then again on big face wall according to 1.5m × 1.5m Spacing does the reference plane that ash cake identifies big face wall, and openings position increases by four big angles and pastes ash cake;
(2)Coat of plaster is constructed from top to bottom completion;
(3)Check that plastering surface evenness, flatness are controlled in 2-3mm in real time;
(4)Showering curing is no less than 7 days after the completion of coat of plaster;
(Two)Base's surface treatment
(1)Laitance, dust, the dirt in base's plastering face are cleaned out;
(2)To part plastering face verticality, the undesirable position in flatness negative and positive angle, using quartz mortar filling-in;
(Three)Optimization row's brick gap scheme
(1)Entity measuring calculates the horizontal and vertical node size of each facade, by 1:50 ratio is drawn with CAD on computers Each facade drawing designs according to design drawing facade effect, multiple stone material paving typesetting conceptual schemes is drawn on facade drawing, The I-shaped seam sticking scheme of architectural modeling feature can be embodied by choosing, and carry out construction modulus examination row by prioritization scheme, and determine Joint gap;
(2)The principle of typesetting paving:
1)Ensure that Stone brick gap is uniform, meets design requirement;
2)Big metope, exceedingly high pillar and pier will arrange monoblock paving;When being unable to monoblock paving, pillar stone material is taken and is uniformly divided Block laying method;For big face wall, then non-monoblock position is discharged to unobtrusively position, and stone material is avoided to be less than 1/3 piece of area;
3)It such as meets the stone material around metope protrusion and should integrally cover and cut, it is ensured that neat in edge forbids piecing together edge patch;
(Four)Snap the line arranges brick positioning
On plaster base vertical line and horizontal line conduct are popped up using the specification of material, size as standard by optimization row's brick scheme Paste control line;
(Five)Bonding mucilage mixing
(1)According to the match ratio and its adhesion strength examining report of experiment model, stone is added using binder rubber powder cooperation latex solution Diamond stone gravel increases adhesive strength;
(2)During bonding mucilage mixing auxiliary material stirring sequence according to:Polymer emulsion → rubber powder → quartz sand sequential feeding, Idle 15 minutes or so after the completion of stirring, reacted with the further of lotion to glue powder, after carry out application work again;
(3)Bonding mucilage and pointing are stirred using motor machine in uniform sticky slurry, and avoiding stirring by hand leads to adhesive glue Starch non-uniform problem;
(Six)Scrape wall in slurry and paving in the back side
(1)Slurry is scraped in the stone material back of the body using zigzag steel trowel, ensures that back side recess is just filled and led up by polymer cement binder;
(2)To keep the cleaning of brick face, layup sequence paving from top to bottom is adhered to;Bonding mucilage is put on zigzag steel trowel Brick back, shaving must uniformly be paved with brick bottom, can not put viscous, not interspace, and ensureing completely 90% or more slurry rate and pulling out sawtooth lines Starch thickness 2-4mm;Then frame bar is pressed by stone material paving on metope, with the hands moves pressure on stone material after wall back and forth and to line, It moves die pressing product adjustment slit width blend compounds plate and uniformly pats stone material surface;Make bonding mucilage equably squeeze out stone material while while on, once have Bonding mucilage spilling should be cleaned out with clean cloth or sponge in time;Before adhesive layer initial set, position and the seam of stone material are adjusted Width, to complete solidification stages after adhesive layer initial set, the stone material for forbidding disturbance to paste;
(Seven)Seam is drawn in jointing
(1)Using special gap filler joint filling, can more times improve the speed of joint filling and jointing, and can keep cleaning;Due to stone material sheet Stature matter is relatively thin, and calking tool is poured into the gap filler being stirred in glue rifle using flexible glue rifle, and punched mouth need to be split into it is ellipse It is round;It is uniformly pressed into preset slot and pulls down soft by gap filler by extrusion handle such as gluing operation when carrying out joint filling operation Glue rifle rifle mouth, to ensure the uniform full of mortar joint;
(2)Seam and jointing are drawn using the round steel rib of mating jointing light;It may be noted that joint sealing material suitably receives water seven when jointing At it is dry when with smooth reinforcing bar round bar carry out jointing, from top to bottom, first after short seam slit sequence;Jointing round bar diameter should be than seam Roomy 2-4mm, jointing answer full, continuous, the straight, depth uniformly, flawless;
(Eight)Metope is cleared up
(1)The bonding agent that stone surface stains must not be washed with water when not dry or be wiped with aqueous article, and glue should be used after initial set Plate strikes off or is cleaned out with dry sponge;
(2)First check that whether there is or not crackings, such as cracking to repair in time for mortar joint before large area cleaning;It is solidifying that rubber cement is pasted after joint filling completion Consolidate and after reaching some strength, scrubbing brick face comprehensively from top to down with clear water until clean;
The stone material is ecological stone material.
The ecology stone material is MCM ecology stone materials.
The present invention carries out typesetting setting-out to MCM ecology stone materials on computers first with CAD drawing techniques, recycles master die Plate and horizontal vertical lattice control technology eliminate cumulative errors caused by setting-out, ensure the unification for imitating stone effect.Using corner Positioning, the intermediate plastering method for determining face, improve the flatness of base, meet MCM ecology stone materials and bond requirement.It is smeared using steel The sawtooth trowel mouth of son carries out scraping slurry in MCM ecologies back face of stone, keeps bonding mucilage well-bonded with back face of stone, and effectively control is viscous The thickness of gum deposit slurry.The plumpness of bonding mucilage is improved, ensures the adhesion strength of wall on stone material.Pass through special jointing technique Jointing operation is carried out, that is, plays waterproof effect, and keeps the visual effect of imitative stone material more true to nature.The present invention is suitable for height and is not more than 100m, seismic fortification intensity are not more than 8 degree, using the multilayer of the exposed wall facing brick stickup of full bonding construction, high building project Exterior wall.
With reference to embodiment, the invention will be further described.
Specific implementation mode
A kind of ecology stone material construction, includes the following steps:
(One)Wall plastering
(1)Before exterior wall smears bottom ash, using corner positioning, the intermediate plastering method for determining face, the flatness of base is improved;With sharp Metope is scanned reference plane by optical measuring instrument, first looks for Founder to do ash cake external corner, then again on big face wall according to 1.5m × 1.5m Spacing does the reference plane that ash cake identifies big face wall, and openings position increases by four big angles and pastes ash cake;
(2)Coat of plaster is constructed from top to bottom completion;
(3)Check that plastering surface evenness, flatness are controlled in 2-3mm in real time;
(4)Showering curing is no less than 7 days after the completion of coat of plaster;
(Two)Base's surface treatment
(1)Laitance, dust, the dirt in base's plastering face are cleaned out;
(2)To part plastering face verticality, the undesirable position in flatness negative and positive angle, using quartz mortar filling-in;
(Three)Optimization row's brick gap scheme
(1)Entity measuring calculates the horizontal and vertical node size of each facade, by 1:50 ratio is drawn with CAD on computers Each facade drawing designs according to design drawing facade effect, multiple stone material paving typesetting conceptual schemes is drawn on facade drawing, The I-shaped seam sticking scheme of architectural modeling feature can be embodied by choosing, and carry out construction modulus examination row by prioritization scheme, and determine Joint gap;
(2)The principle of typesetting paving:
1)Ensure that Stone brick gap is uniform, meets design requirement;
2)Big metope, exceedingly high pillar and pier will arrange monoblock paving;When being unable to monoblock paving, pillar stone material is taken and is uniformly divided Block laying method;For big face wall, then non-monoblock position is discharged to unobtrusively position, and stone material is avoided to be less than 1/3 piece of area;
3)It such as meets the stone material around metope protrusion and should integrally cover and cut, it is ensured that neat in edge forbids piecing together edge patch;
(Four)Snap the line arranges brick positioning
On plaster base vertical line and horizontal line conduct are popped up using the specification of material, size as standard by optimization row's brick scheme Paste control line;
(Five)Bonding mucilage mixing
(1)According to the match ratio and its adhesion strength examining report of experiment model, stone is added using binder rubber powder cooperation latex solution Diamond stone gravel increases adhesive strength;
(2)During bonding mucilage mixing auxiliary material stirring sequence according to:Polymer emulsion → rubber powder → quartz sand sequential feeding, Idle 15 minutes or so after the completion of stirring, reacted with the further of lotion to glue powder, after carry out application work again;
(3)Bonding mucilage and pointing are stirred using motor machine in uniform sticky slurry, and avoiding stirring by hand leads to adhesive glue Starch non-uniform problem;
(Six)Scrape wall in slurry and paving in the back side
(1)Slurry is scraped in the stone material back of the body using zigzag steel trowel, ensures that back side recess is just filled and led up by polymer cement binder;
(2)To keep the cleaning of brick face, layup sequence paving from top to bottom is adhered to;Bonding mucilage is put on zigzag steel trowel Brick back, shaving must uniformly be paved with brick bottom, can not put viscous, not interspace, and ensureing completely 90% or more slurry rate and pulling out sawtooth lines Starch thickness 2-4mm;Then frame bar is pressed by stone material paving on metope, with the hands moves pressure on stone material after wall back and forth and to line, It moves die pressing product adjustment slit width blend compounds plate and uniformly pats stone material surface;Make bonding mucilage equably squeeze out stone material while while on, once have Bonding mucilage spilling should be cleaned out with clean cloth or sponge in time;Before adhesive layer initial set, position and the seam of stone material are adjusted Width, to complete solidification stages after adhesive layer initial set, the stone material for forbidding disturbance to paste;
(Seven)Seam is drawn in jointing
(1)Using special gap filler joint filling, can more times improve the speed of joint filling and jointing, and can keep cleaning;Due to stone material sheet Stature matter is relatively thin, and calking tool is poured into the gap filler being stirred in glue rifle using flexible glue rifle, and punched mouth need to be split into it is ellipse It is round;It is uniformly pressed into preset slot and pulls down soft by gap filler by extrusion handle such as gluing operation when carrying out joint filling operation Glue rifle rifle mouth, to ensure the uniform full of mortar joint;
(2)Seam and jointing are drawn using the round steel rib of mating jointing light;It may be noted that joint sealing material suitably receives water seven when jointing At it is dry when with smooth reinforcing bar round bar carry out jointing, from top to bottom, first after short seam slit sequence;Jointing round bar diameter should be than seam Roomy 2-4mm, jointing answer full, continuous, the straight, depth uniformly, flawless;
(Eight)Metope is cleared up
(1)The bonding agent that stone surface stains must not be washed with water when not dry or be wiped with aqueous article, and glue should be used after initial set Plate strikes off or is cleaned out with dry sponge;
(2)First check that whether there is or not crackings, such as cracking to repair in time for mortar joint before large area cleaning;It is solidifying that rubber cement is pasted after joint filling completion Consolidate and after reaching some strength, scrubbing brick face comprehensively from top to down with clear water until clean;
The stone material is ecological stone material.The ecology stone material is MCM ecology stone materials.

Claims (2)

1. a kind of ecology stone material construction, it is characterized in that:Include the following steps:
(One)Wall plastering
(1)Before exterior wall smears bottom ash, using corner positioning, the intermediate plastering method for determining face, the flatness of base is improved;With sharp Metope is scanned reference plane by optical measuring instrument, first looks for Founder to do ash cake external corner, then again on big face wall according to 1.5m × 1.5m Spacing does the reference plane that ash cake identifies big face wall, and openings position increases by four big angles and pastes ash cake;
(2)Coat of plaster is constructed from top to bottom completion;
(3)Check that plastering surface evenness, flatness are controlled in 2-3mm in real time;
(4)Showering curing is no less than 7 days after the completion of coat of plaster;
(Two)Base's surface treatment
(1)Laitance, dust, the dirt in base's plastering face are cleaned out;
(2)To part plastering face verticality, the undesirable position in flatness negative and positive angle, using quartz mortar filling-in;
(Three)Optimization row's brick gap scheme
(1)Entity measuring calculates the horizontal and vertical node size of each facade, by 1:50 ratio is drawn with CAD on computers Each facade drawing designs according to design drawing facade effect, multiple stone material paving typesetting conceptual schemes is drawn on facade drawing, The I-shaped seam sticking scheme of architectural modeling feature can be embodied by choosing, and carry out construction modulus examination row by prioritization scheme, and determine Joint gap;
(2)The principle of typesetting paving:
1)Ensure that Stone brick gap is uniform, meets design requirement;
2)Big metope, exceedingly high pillar and pier will arrange monoblock paving;When being unable to monoblock paving, pillar stone material is taken and is uniformly divided Block laying method;For big face wall, then non-monoblock position is discharged to unobtrusively position, and stone material is avoided to be less than 1/3 piece of area;
3)It such as meets the stone material around metope protrusion and should integrally cover and cut, it is ensured that neat in edge forbids piecing together edge patch;
(Four)Snap the line arranges brick positioning
On plaster base vertical line and horizontal line conduct are popped up using the specification of material, size as standard by optimization row's brick scheme Paste control line;
(Five)Bonding mucilage mixing
(1)According to the match ratio and its adhesion strength examining report of experiment model, stone is added using binder rubber powder cooperation latex solution Diamond stone gravel increases adhesive strength;
(2)During bonding mucilage mixing auxiliary material stirring sequence according to:Polymer emulsion → rubber powder → quartz sand sequential feeding, Idle 15 minutes or so after the completion of stirring, reacted with the further of lotion to glue powder, after carry out application work again;
(3)Bonding mucilage and pointing are stirred using motor machine in uniform sticky slurry, and avoiding stirring by hand leads to adhesive glue Starch non-uniform problem;
(Six)Scrape wall in slurry and paving in the back side
(1)Slurry is scraped in the stone material back of the body using zigzag steel trowel, ensures that back side recess is just filled and led up by polymer cement binder;
(2)To keep the cleaning of brick face, layup sequence paving from top to bottom is adhered to;Bonding mucilage is put on zigzag steel trowel Brick back, shaving must uniformly be paved with brick bottom, can not put viscous, not interspace, and ensureing completely 90% or more slurry rate and pulling out sawtooth lines Starch thickness 2-4mm;Then frame bar is pressed by stone material paving on metope, with the hands moves pressure on stone material after wall back and forth and to line, It moves die pressing product adjustment slit width blend compounds plate and uniformly pats stone material surface;Make bonding mucilage equably squeeze out stone material while while on, once have Bonding mucilage spilling should be cleaned out with clean cloth or sponge in time;Before adhesive layer initial set, position and the seam of stone material are adjusted Width, to complete solidification stages after adhesive layer initial set, the stone material for forbidding disturbance to paste;
(Seven)Seam is drawn in jointing
(1)Using special gap filler joint filling, can more times improve the speed of joint filling and jointing, and can keep cleaning;Due to stone material sheet Stature matter is relatively thin, and calking tool is poured into the gap filler being stirred in glue rifle using flexible glue rifle, and punched mouth need to be split into it is ellipse It is round;It is uniformly pressed into preset slot and pulls down soft by gap filler by extrusion handle such as gluing operation when carrying out joint filling operation Glue rifle rifle mouth, to ensure the uniform full of mortar joint;
(2)Seam and jointing are drawn using the round steel rib of mating jointing light;It may be noted that joint sealing material suitably receives water seven when jointing At it is dry when with smooth reinforcing bar round bar carry out jointing, from top to bottom, first after short seam slit sequence;Jointing round bar diameter should be than seam Roomy 2-4mm, jointing answer full, continuous, the straight, depth uniformly, flawless;
(Eight)Metope is cleared up
(1)The bonding agent that stone surface stains must not be washed with water when not dry or be wiped with aqueous article, and glue should be used after initial set Plate strikes off or is cleaned out with dry sponge;
(2)First check that whether there is or not crackings, such as cracking to repair in time for mortar joint before large area cleaning;It is solidifying that rubber cement is pasted after joint filling completion Consolidate and after reaching some strength, scrubbing brick face comprehensively from top to down with clear water until clean;
The stone material is ecological stone material.
2. ecology stone material construction according to claim 1, it is characterized in that:The ecology stone material is MCM ecology stone materials.
CN201810544157.9A 2018-05-31 2018-05-31 Ecological stone material construction Pending CN108797929A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810544157.9A CN108797929A (en) 2018-05-31 2018-05-31 Ecological stone material construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810544157.9A CN108797929A (en) 2018-05-31 2018-05-31 Ecological stone material construction

Publications (1)

Publication Number Publication Date
CN108797929A true CN108797929A (en) 2018-11-13

Family

ID=64089608

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810544157.9A Pending CN108797929A (en) 2018-05-31 2018-05-31 Ecological stone material construction

Country Status (1)

Country Link
CN (1) CN108797929A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109750814A (en) * 2019-01-26 2019-05-14 广州市第三建筑装修有限公司 Anti- hollowing wall construction method
CN109779178A (en) * 2019-01-29 2019-05-21 苏州金螳螂建筑装饰股份有限公司 A kind of the joint filling structure and its method of indoor decoration surface layer
CN109898773A (en) * 2019-03-21 2019-06-18 安徽省第二建筑工程有限公司 The soft patch construction of gypsum wall vitrified tile
CN110469068A (en) * 2019-07-29 2019-11-19 安徽智恒节能材料科技有限公司 A kind of construction technology of exterior wall decorating tile
CN113323314A (en) * 2021-06-10 2021-08-31 中国建筑第八工程局有限公司 External wall paving construction method for sintered ceramic tiles in freeze-thaw environment
CN113503027A (en) * 2021-07-09 2021-10-15 中国二十冶集团有限公司 External wall construction method based on soft porcelain
CN114352056A (en) * 2021-12-23 2022-04-15 上海建工集团股份有限公司 Construction process for renovating ecological face bricks on old wall surfaces
CN114412104A (en) * 2022-01-27 2022-04-29 广州市绿化有限公司 Construction method for stone paving alkali return control flow guiding net

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101949208A (en) * 2010-09-08 2011-01-19 深圳市建设(集团)有限公司 Construction method for plastering wall and adhering plaster dough in building construction
CN103758312A (en) * 2011-12-31 2014-04-30 常熟古建园林建设集团有限公司 Laminating construction method for facing bricks

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101949208A (en) * 2010-09-08 2011-01-19 深圳市建设(集团)有限公司 Construction method for plastering wall and adhering plaster dough in building construction
CN103758312A (en) * 2011-12-31 2014-04-30 常熟古建园林建设集团有限公司 Laminating construction method for facing bricks

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
中国建筑业协会: "《创建鲁班奖工程细部做法指导》", 30 April 2014 *
陈璞: "外墙柔性饰面砖施工工艺及避免泛碱问题的探讨", 《新型建筑材料》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109750814A (en) * 2019-01-26 2019-05-14 广州市第三建筑装修有限公司 Anti- hollowing wall construction method
CN109779178A (en) * 2019-01-29 2019-05-21 苏州金螳螂建筑装饰股份有限公司 A kind of the joint filling structure and its method of indoor decoration surface layer
CN109898773A (en) * 2019-03-21 2019-06-18 安徽省第二建筑工程有限公司 The soft patch construction of gypsum wall vitrified tile
CN110469068A (en) * 2019-07-29 2019-11-19 安徽智恒节能材料科技有限公司 A kind of construction technology of exterior wall decorating tile
CN113323314A (en) * 2021-06-10 2021-08-31 中国建筑第八工程局有限公司 External wall paving construction method for sintered ceramic tiles in freeze-thaw environment
CN113503027A (en) * 2021-07-09 2021-10-15 中国二十冶集团有限公司 External wall construction method based on soft porcelain
CN114352056A (en) * 2021-12-23 2022-04-15 上海建工集团股份有限公司 Construction process for renovating ecological face bricks on old wall surfaces
CN114412104A (en) * 2022-01-27 2022-04-29 广州市绿化有限公司 Construction method for stone paving alkali return control flow guiding net

Similar Documents

Publication Publication Date Title
CN108797929A (en) Ecological stone material construction
CN109838065B (en) Floor tile ground paving construction method
CN102505831A (en) Construction method for paving plasters on ground and manmade stone
US20070071551A1 (en) Surface seeded fine aggregate concrete simulating quarried stone
CN107143111A (en) A kind of construction method of abrasion-proof terrace
CN102518216A (en) Cantilever type cover plate deformation joint structure of accessible roof and construction method for structure
CN103740156A (en) Novel low-cost easily constructed putty as well as preparation method and construction process thereof
CN109441059A (en) A kind of plastic floor laying structure and its construction method
CN108468413A (en) A kind of air-entrained concrete building block exempts from anti-hollowing construction method of plastering
CN107130766A (en) One kind crystallization envelope seamless stone floor construction method of glaze
CN106284998A (en) Plastering on inner walls completely spreads fiberglass gridding cloth construction method
CN104831926B (en) A kind of tenon joint type bulk surface layer flooring method for paving
CN109025136A (en) Glue for tile pastes tapestry brick construction method between more boiled water rooms
CN105178547A (en) Large-unit ceramic thin sheet back-suspending and gluing structure and construction method thereof
CN101008192A (en) Construction method of outer wall insulation system adopting composite insulation surface tile
CN103291024B (en) A kind of construction method of novel cement-based motar
CN105437354B (en) The method of binding face tile when a kind of prefabricated concrete floor and wallboard
CN105888084A (en) Whole outer wall internal thermal insulation system construction method by using enhanced composite thermal insulation material
CN108979034A (en) Wall surface construction technology
CN1108934C (en) Method for producing coating with decorative patterns, mineral coating and tool for implementing same
CN210597982U (en) Composite copper plate structure with back bolt on floor
CN108558305A (en) The inorganic tile gap filler and preparation method thereof of squeezing and coating construction
CN104612343A (en) Method for constructing extruded polystyrene board molding of building outer wall
CN205025042U (en) Big unit pottery sheet metal back of body kiss -coating bonds and constructs
CN205577324U (en) Vitrified tile spreads and pastes structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181113

RJ01 Rejection of invention patent application after publication