CN108277894A - A kind of plate heat preserving formwork mounting process of concrete shear force wall - Google Patents

A kind of plate heat preserving formwork mounting process of concrete shear force wall Download PDF

Info

Publication number
CN108277894A
CN108277894A CN201710006642.6A CN201710006642A CN108277894A CN 108277894 A CN108277894 A CN 108277894A CN 201710006642 A CN201710006642 A CN 201710006642A CN 108277894 A CN108277894 A CN 108277894A
Authority
CN
China
Prior art keywords
formwork
shear force
concrete shear
force wall
heat preserving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710006642.6A
Other languages
Chinese (zh)
Inventor
王涛
隋群
邵云波
彭军
刘日伍
解华
李凤龙
吕海亮
王锡强
郑学高
韩晓娜
赵功江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Energy-Saving Building Material Device Fabrication Co Ltd Is Led In Yantai Political Affairs
Original Assignee
Energy-Saving Building Material Device Fabrication Co Ltd Is Led In Yantai Political Affairs
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Energy-Saving Building Material Device Fabrication Co Ltd Is Led In Yantai Political Affairs filed Critical Energy-Saving Building Material Device Fabrication Co Ltd Is Led In Yantai Political Affairs
Priority to CN201710006642.6A priority Critical patent/CN108277894A/en
Publication of CN108277894A publication Critical patent/CN108277894A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/762Exterior insulation of exterior walls
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/762Exterior insulation of exterior walls
    • E04B1/7625Details of the adhesive connection of the insulation to the wall
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/762Exterior insulation of exterior walls
    • E04B1/7641Elements for window or door openings, or for corners of the building
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/78Heat insulating elements
    • E04B1/80Heat insulating elements slab-shaped

Abstract

The invention discloses a kind of plate heat preserving formwork mounting process of concrete shear force wall, include the following steps:Concrete shear force wall formwork installs preparatory process, the installation procedure of concrete shear force wall formwork thermal insulation board, and concrete shear force wall formwork keeps the temperature the levelling process of board finish, smears anticracking grout protective layer process.Addition auxiliary external member, improves construction efficiency in work progress, reduces difficulty of construction, prevents tablet formwork from falling off.

Description

A kind of plate heat preserving formwork mounting process of concrete shear force wall
Technical field
The present invention relates to formwork construction techniques, are exactly a kind of plate heat preserving formwork erectors of concrete shear force wall Skill.
Background technology
Cement polyphenyl mould case lattice type concrete wall is more work(such as a kind of light set, moisturizing, fire prevention, sound insulation, load-bearing, antidetonation It can be used for multilayer residential houses in the completely new energy conservation and environmental protection composite building wall construction material of one, can be used for load-bearing, non- Load bearing heat preserving wall.A kind of devices of connecting building structural shear wall and concrete floor of CN104153467B, intensive drilling meeting Many cracks are caused inside shear wall, reduce its bearing capacity line, use poly- ammonia more in plate formwork technique in the prior art Ester foaming glue, when installation, lack auxiliary tool, need construction personnel carefully to dock, and be easy to fall off.
Invention content
The technical problem to be solved by the present invention is to reduce polyurethane foam glue in heat preserving formwork mounting process to use, it is anti-to improve fire prevention Shock stability, according to engineering practice increase beam, at column and shear wall formwork surface cracking resistance construction measure, plate heat preserving formwork The composite thermal-insulating wall formed with cast-in-place concretes such as beam columns does not need anchor bolt and does supplementary anchorage measure, uses Auxiliary support set Part facilitates installation, not easily to fall off.
In order to solve the above technical problems, the present invention uses following technological means:
A kind of plate heat preserving formwork mounting process of concrete shear force wall, feature include the following steps:
1)Concrete shear force wall formwork installs preparatory process:Concrete shear force wall substrate surface is cleared up, greasy dirt attachment is removed, if Screed-coat is set, screed-coat is that polymer cement mortar is levelling to surface progress, removes protrusion, hollowing and porous spot, it is fixed to place Bit line;
2)The installation procedure of concrete shear force wall formwork thermal insulation board:The stickup erection sequence of formwork thermal insulation board is opened from exterior wall corner Begin, to both sides sequence carry out, by bottom, successively install from bottom to top, paste installation before, first polyurethane is sent out by flush coater Glue even application is steeped on concrete shear force wall surface and auxiliary external member, formwork thermal insulation board is pasted, by assisting external member to be determined Position, formwork thermal insulation board should be immediately to carrying out joint filling processing after pasting at plate stitch with polyurethane foam glue;
3)Concrete shear force wall formwork keeps the temperature the levelling process of board finish:Formwork thermal insulation board surface smoothness differs within 10mm, Levelling with flat washboard filing, flatness is levelling with polymer cement mortar other than 10mm, and depth of plastering is less than 10mm, is more than 10mm needs to be layered plastering, and layering plastering interval time must not be less than 3 days, and follow-up work can be carried out within 7 days after the completion of levelling process Sequence;
4)Smear anticracking grout protective layer process:Leveling mortar parches, cracks, and smears first of cracking resistance sand, spreads alkali-resisting glass fiber screen cloth, Grid cloth is packed in exterior wall mouth at door-window opening, with beam, the plug-in steel fabric sheet of column seam areas, is overlapped with exterior wall grid cloth, cracking resistance After mortar parches, thermal insulation board Special anchor bolt is installed and smears second cracking resistance sand after anchor bolt is fixed.
Preferably, the further technical solution of the present invention is:
Base course wall screed-coat in the concrete shear force wall formwork installation preparatory process, curing time are not less than 14 days, put down Whole degree deviation is less than or equal to 4mm, and structure boundary hangs steel wire and carries out cracking resistance reinforcement processing.
In the installation procedure of the concrete shear force wall formwork thermal insulation board at wall handing-over and door-window opening, formwork is protected Warm plate should be carried out assembly by design requirement, should uniformly be contacted with polyurethane foam glue by squeezing when formwork thermal insulation board pastes installation, Adhesive surface plumpness should reach 80 or more percent, by assisting external member that plate stitch is made to keep horizontal and vertical, keep the temperature plate surface It is smooth.
Polymer cement mortar in the concrete shear force wall formwork heat preservation levelling process of board finish, polymer water silt particle Paste dry powder material is directly added into suitable quantity of water, and 10 minutes are stood after stirring evenly, and carries out secondary agitation, three hour cohesions after the completion of stirring Close object cement mortar need to use finish, and any additive for helping stirring cannot be added in whipping process.
Described first of the cracking resistance sand thickness control of smearing anticracking grout protective layer process is in 2-3mm, with beam, column seam The plug-in steel fabric sheet in position, paving alkali-resisting glass fiber screen cloth overlap transverse direction 100mm, vertical 80mm, are pressed into anticracking grout superficial layer, then smear 1- 2mm anticracking grouts, alkali proof fiber screen cloth reach micro- and see that grid cloth, leakage line are not slipped through the net.
The smearing anticracking grout protective layer process installation anchor hole anomaly template formwork edge is no less than 100mm, anchor Every square metre of bolt quantity no less than 4, and every piece of plate formwork anchor bolt quantity is no less than 2, the second cracking resistance sand Thickness is in 2-3mm.
Plug-in steel fabric sheet is that horizontal steel wire and perpendicular steel wire are interwoven in the smearing anticracking grout protective layer process, horizontal Steel wire is that three braided steel wires form, and perpendicular steel wire is that two braided steel wires form, plug-in steel fabric sheet and plate heat preserving formwork Measure is auxiliarily fixed in Special anchor bolt, and anchor bolt should be mounted on the upper surface of steel fabric sheet or finishing mucilage and alkali-resisting glass fiber screen cloth.
A kind of plate heat preserving formwork that the plate heat preserving formwork mounting process of concrete shear force wall uses, the tablet Type heat preserving formwork is cuboid, is equipped with groove in plate heat preserving formwork side, the groove is L-type, is arranged plate Four angles of heat preserving formwork.
A kind of auxiliary external member that the plate heat preserving formwork mounting process of concrete shear force wall uses, the auxiliary external member are set There are a cross-brace axis and vertical supporting axis, cross-brace axis and vertical supporting axis are in cross connection, cross-brace axis and vertical Support shaft is equipped with raised item, and raised item is plugged in the groove of template heat preserving formwork side.
A kind of production equipment for the plate heat preserving formwork that the plate heat preserving formwork mounting process of concrete shear force wall uses, Including automatic charging storehouse, formwork molding die, ballast consolidating machine;It is set on the outside of the formwork molding die there are four supporting rack, is propped up The other side of support side connecting mold, supporting rack is equipped with shaped support, and shaped support is L-type.
In concrete frame shear wall structure system, beams of concrete, column, floor and shear wall exterior wall isothermal holding, It is all made of plate heat preserving formwork and is pasted on outer surface, thickness is selected according to design requirement, and thick with standard type form wall It spends harmonious.The installation of plate formwork is divided to two kinds of construction technologies to carry out, one is using cast in place process, i.e., in concrete knot It is mounted on the inside of concrete blinding when structure is constructed, is poured together with structural concrete;Another kind be using viscous anchor technique, be After the completion of concrete structure construction, wall outer side is pasted on using bonding and anchorage style, and same with the installation of formwork filled wall Step carries out.Concrete construction method is first by concrete shear force wall outer surface(Part)Levelling and interface processing is carried out, then sprays hair Plate form boarding is simultaneously pasted onto shear wall surface by bubble polyurethane adhesive, and the gap between form boarding is filled out with polyurethane foam glue It is full, after adhesives solidification with polymer cement mortar it is levelling, do anticracking grout indentation alkali-resisting glass fiber screen cloth, installation thermal insulation board Special anchor bolt, then second time anticracking grout protective layer is done, finally exterior wall finish layer is done by design requirement.It is increased in installation process External member is assisted, installation effectiveness is improved, promotes the quality of installation, personnel is facilitated to construct, promotes formwork support effect, anti-anti-avulsion It falls.
Description of the drawings
Fig. 1 is a kind of plate heat preserving formwork construction process figure of concrete shear force wall of the present invention.
Fig. 2 is the plate heat preserving formwork installation flow chart of the present invention.
Fig. 3 is the plate heat preserving formwork structural schematic diagram of the present invention.
Fig. 4 is present invention auxiliary external member structural schematic diagram.
Reference sign:The plate heat preserving formworks of 1-;2- grooves;3- cross-brace axis;4- vertical supporting axis.
Specific implementation mode
With reference to embodiment, further illustrate the present invention.
Specific embodiment 1:
According to Fig. 1 and Fig. 2 it is found that a kind of plate 1 mounting process of heat preserving formwork of concrete shear force wall of the present invention, feature include Following steps:
1)Concrete shear force wall formwork installs preparatory process:Concrete shear force wall substrate surface is cleared up, greasy dirt, releasing agent etc. are removed Screed-coat is arranged in attachment, and screed-coat is that polymer cement mortar is levelling to surface progress, removes protrusion, hollowing and puff Position, according to formwork mounting plane construction diagrams placement positioning line;Curing time is not less than 14 days, and flatness deviation is less than or equal to 4mm, Structure boundary hangs steel wire and carries out cracking resistance reinforcement processing;It is levelling that concrete shear force wall formwork installs base course wall in preparatory process Layer, curing time are not less than 14 days, and flatness deviation is less than or equal to 4mm, and structure boundary is hung steel wire and carried out at cracking resistance reinforcement Reason.
2)The installation procedure of concrete shear force wall formwork thermal insulation board:The stickup erection sequence of formwork thermal insulation board is from exterior wall corner Start, carried out to both sides sequence, by bottom, successively install from bottom to top, before pasting installation, first by flush coater by polyurethane Foamed glue even application pastes formwork thermal insulation board on concrete shear force wall surface, according still further to the assembled arrangement figure of design, and is determined Position, formwork thermal insulation board should be immediately to carrying out joint filling processing after pasting at plate stitch with polyurethane foam glue;Wall joins and door and window hole At mouth, formwork thermal insulation board should be carried out assembly by design requirement, should pass through extruding and polyurethane foam when formwork thermal insulation board pastes installation Glue uniformly contacts, and adhesive surface plumpness should reach 80 or more percent, and plate stitch should keep horizontal and vertical and be flushed with unwrapping wire, Thermal insulation board surfacing;In the installation procedure of concrete shear force wall formwork thermal insulation board at wall handing-over and door-window opening, formwork Thermal insulation board should be carried out assembly by design requirement, should uniformly be connect with polyurethane foam glue by squeezing when formwork thermal insulation board pastes installation It touches, adhesive surface plumpness should reach 80 or more percent, and plate stitch should keep horizontal and vertical and be flushed with unwrapping wire, thermal insulation board table Face is smooth, and levels take the fissure of displacement to overlap.
3)Concrete shear force wall formwork keeps the temperature the levelling process of board finish:Formwork thermal insulation board surface irregularity degree is differed in 10mm Within, levelling with flat washboard filing, flatness is levelling with polymer cement mortar other than 10mm, and depth of plastering is less than 10mm, It needs to be layered plastering more than 10mm, layering plastering interval time must not be less than 3 days, after can carrying out within 7 days after the completion of levelling process Continuous process;Polymer cement mortar dry mash is directly added into suitable quantity of water, and 10 minutes are stood after stirring evenly, and is carried out secondary agitation, is stirred After the completion of mixing three hour interpolymer cement mortar need to use finish, and cannot be added in whipping process and any help stirring Additive;Concrete shear force wall formwork keeps the temperature polymer cement mortar in the levelling process of board finish, polymer cement mortar dry powder Material is directly added into suitable quantity of water, and 10 minutes are stood after stirring evenly, and carries out secondary agitation, three hour interpolymer water after the completion of stirring Cement mortar need to use finish, and any additive for helping stirring cannot be added in whipping process.
4)Smear anticracking grout protective layer process:Leveling mortar parches, cracks, and smears first of cracking resistance sand, spreads alkali-resisting glass fiber Screen cloth, grid cloth is packed in exterior wall mouth at door-window opening, with beam, the plug-in steel fabric sheet of column seam areas, is overlapped with exterior wall grid cloth, After anticracking grout parches, thermal insulation board Special anchor bolt is installed and smears second cracking resistance sand after anchor bolt is fixed;First of cracking resistance sand thickness Control is in 2-3mm, and with beam, the plug-in steel fabric sheet of column seam areas, paving alkali-resisting glass fiber screen cloth overlaps transverse direction 100mm, vertical 80mm, It is pressed into anticracking grout superficial layer, then smears 1-2mm anticracking grouts, alkali proof fiber screen cloth reaches micro- and sees that grid cloth, leakage line are not slipped through the net;Peace Dress anchor hole anomaly template formwork edge is no less than 100mm, every square metre of anchor bolt quantity no less than 4, and every piece of tablet pattern Shell anchor bolt quantity is no less than 2, and the second cracking resistance sand thickness is in 2-3mm;Plug-in steel fabric sheet is horizontal steel wire and perpendicular steel Silk is interwoven, and horizontal steel wire is that three braided steel wires form, and perpendicular steel wire is that two braided steel wires form, plug-in steel fabric sheet peace Measure is auxiliarily fixed in 1 Special anchor bolt of template heat preserving formwork, and anchor bolt should be mounted on steel fabric sheet or finishing mucilage and alkali-resisting glass fiber First of cracking resistance sand thickness control of anticracking grout protective layer process is smeared in 2-3mm, with beam, column seam in the upper surface of screen cloth The plug-in steel fabric sheet in position, paving alkali-resisting glass fiber screen cloth overlap transverse direction 100mm, vertical 80mm, are pressed into anticracking grout superficial layer, then smear 1- 2mm anticracking grouts, alkali proof fiber screen cloth reach micro- and see that grid cloth, leakage line are not slipped through the net, and smear the installation of anticracking grout protective layer process Anchor hole anomaly template formwork edge is no less than 100mm, every square metre of anchor bolt quantity no less than 4, and every piece of plate formwork Anchor bolt quantity is no less than 2, and for the second cracking resistance sand thickness in 2-3mm, plug-in steel fabric sheet is horizontal steel wire and perpendicular steel wire It is interwoven, horizontal steel wire is that three braided steel wires form, and perpendicular steel wire is that two braided steel wires form, plug-in steel fabric sheet and tablet Measure is auxiliarily fixed in 1 Special anchor bolt of type heat preserving formwork, and anchor bolt should be mounted on steel fabric sheet or finishing mucilage and alkali-resistant glass fiber mesh The upper surface of cloth.
Specific embodiment 2:
A kind of plate 1 mounting process of heat preserving formwork of concrete shear force wall, feature include the following steps:
1)Concrete shear force wall formwork installs preparatory process:Concrete shear force wall substrate surface is cleared up, greasy dirt attachment is removed, if Screed-coat is set, screed-coat is that polymer cement mortar is levelling to surface progress, removes protrusion, hollowing and porous spot, it is fixed to place Bit line;Concrete shear force wall formwork installs base course wall screed-coat in preparatory process, and curing time is not less than 14 days, and flatness is inclined Difference is less than or equal to 4mm, and structure boundary hangs steel wire and carries out cracking resistance reinforcement processing.
2)The installation procedure of concrete shear force wall formwork thermal insulation board:The stickup erection sequence of formwork thermal insulation board is from exterior wall corner Start, carried out to both sides sequence, by bottom, successively install from bottom to top, before pasting installation, first by flush coater by polyurethane Foamed glue even application pastes formwork thermal insulation board on concrete shear force wall surface and auxiliary external member, by assisting external member to carry out Positioning, formwork thermal insulation board should be immediately to carrying out joint filling processing after pasting at plate stitch with polyurethane foam glue;Concrete shear force wall mould In the installation procedure of shell thermal insulation board at wall handing-over and door-window opening, formwork thermal insulation board should be carried out assembled, mould by design requirement Shell thermal insulation board should uniformly be contacted by squeezing with polyurethane foam glue when pasting installation, and adhesive surface plumpness should reach 80 percent More than, by assisting external member that plate stitch is made to keep horizontal and vertical, thermal insulation board surfacing.
3)Concrete shear force wall formwork keeps the temperature the levelling process of board finish:Formwork thermal insulation board surface smoothness difference 10mm with Interior, levelling with flat washboard filing, flatness is levelling with polymer cement mortar other than 10mm, and depth of plastering is less than 10mm, greatly It needs to be layered plastering in 10mm, layering plastering interval time must not be less than 3 days, can carry out within 7 days after the completion of levelling process follow-up Process;Concrete shear force wall formwork keeps the temperature polymer cement mortar in the levelling process of board finish, polymer cement mortar dry mash It is directly added into suitable quantity of water, 10 minutes is stood after stirring evenly, carry out secondary agitation, three hour interpolymer cement after the completion of stirring Mortar need to use finish, and any additive for helping stirring cannot be added in whipping process.
4)Smear anticracking grout protective layer process:Leveling mortar parches, cracks, and smears first of cracking resistance sand, spreads alkali-resisting glass fiber Screen cloth, grid cloth is packed in exterior wall mouth at door-window opening, with beam, the plug-in steel fabric sheet of column seam areas, is overlapped with exterior wall grid cloth, After anticracking grout parches, thermal insulation board Special anchor bolt is installed and smears second cracking resistance sand after anchor bolt is fixed.Smear anticracking grout protection Layer first of cracking resistance sand thickness control of process spreads alkali-resisting glass fiber screen cloth in 2-3mm with beam, the plug-in steel fabric sheet of column seam areas Transverse direction 100mm, vertical 80mm are overlapped, is pressed into anticracking grout superficial layer, then smear 1-2mm anticracking grouts, alkali proof fiber screen cloth reaches It is micro- to see that grid cloth, leakage line are not slipped through the net.Anticracking grout protective layer process installation anchor hole anomaly template formwork edge is smeared to be no less than 100mm, every square metre of anchor bolt quantity no less than 4, and every piece of plate formwork anchor bolt quantity are no less than 2, and described second Road cracking resistance sand thickness is in 2-3mm.It is that horizontal steel wire and perpendicular steel wire interweave to smear plug-in steel fabric sheet in anticracking grout protective layer process It forms, horizontal steel wire is that three braided steel wires form, and perpendicular steel wire is that two braided steel wires form, plug-in steel fabric sheet and plate guarantor 1 Special anchor bolt of warm formwork is auxiliarily fixed measure, and anchor bolt should be mounted on steel fabric sheet or finishing mucilage and alkali-resisting glass fiber screen cloth Upper surface.
Specific embodiment 3:
According to fig. 3 with Fig. 4 it is found that the plate heat preservation that a kind of plate 1 mounting process of heat preserving formwork of concrete shear force wall uses Formwork 1, plate heat preserving formwork 1 are cuboid, are equipped with groove 2 in 1 side of plate heat preserving formwork, the groove 2 is L Type is arranged in four angles of plate heat preserving formwork 1.
Specific embodiment 4:
A kind of auxiliary external member that plate 1 mounting process of heat preserving formwork of concrete shear force wall uses, auxiliary external member, which is equipped with, laterally props up Axis 3 and vertical supporting axis 4 are supportted, cross-brace axis 3 and vertical supporting axis 4 are in cross connection, cross-brace axis 3 and vertical supporting Axis 4 is equipped with raised item, and raised item is plugged in the groove 2 of template heat preserving formwork side.
Specific embodiment 5:
A kind of production equipment for the plate heat preserving formwork 1 that plate 1 mounting process of heat preserving formwork of concrete shear force wall uses, packet Include automatic charging storehouse, formwork molding die, ballast consolidating machine;Supporting rack there are four being set on the outside of formwork molding die, supporting rack side The other side of connecting mold, supporting rack is equipped with shaped support, and shaped support is L-type.
Since the foregoing is merely the specific implementation modes of the present invention, but the protection of the present invention is without being limited thereto, any skill The technical staff in art field it is contemplated that the equivalent variation or replacement of the technical program technical characteristic, all cover the present invention's Within protection domain.

Claims (10)

1. a kind of plate heat preserving formwork mounting process of concrete shear force wall, feature include the following steps:
1)Concrete shear force wall formwork installs preparatory process:Concrete shear force wall substrate surface is cleared up, greasy dirt attachment is removed, if Screed-coat is set, screed-coat is that polymer cement mortar is levelling to surface progress, removes protrusion, hollowing and porous spot, it is fixed to place Bit line;
2)The installation procedure of concrete shear force wall formwork thermal insulation board:The stickup erection sequence of formwork thermal insulation board is opened from exterior wall corner Begin, to both sides sequence carry out, by bottom, successively install from bottom to top, paste installation before, first polyurethane is sent out by flush coater Glue even application is steeped on concrete shear force wall surface and auxiliary external member, formwork thermal insulation board is pasted, by assisting external member to be determined Position, formwork thermal insulation board should be immediately to carrying out joint filling processing after pasting at plate stitch with polyurethane foam glue;
3)Concrete shear force wall formwork keeps the temperature the levelling process of board finish:Formwork thermal insulation board surface smoothness differs within 10mm, Levelling with flat washboard filing, flatness is levelling with polymer cement mortar other than 10mm, and depth of plastering is less than 10mm, is more than 10mm needs to be layered plastering, and layering plastering interval time must not be less than 3 days, and follow-up work can be carried out within 7 days after the completion of levelling process Sequence;
4)Smear anticracking grout protective layer process:Leveling mortar parches, cracks, and smears first of cracking resistance sand, spreads alkali-resisting glass fiber screen cloth, Grid cloth is packed in exterior wall mouth at door-window opening, with beam, the plug-in steel fabric sheet of column seam areas, is overlapped with exterior wall grid cloth, cracking resistance After mortar parches, thermal insulation board Special anchor bolt is installed and smears second cracking resistance sand after anchor bolt is fixed.
2. the plate heat preserving formwork mounting process of a kind of concrete shear force wall according to claim 1, it is characterised in that:Institute Base course wall screed-coat in the concrete shear force wall formwork installation preparatory process stated, curing time are not less than 14 days, and flatness is inclined Difference is less than or equal to 4mm, and structure boundary hangs steel wire and carries out cracking resistance reinforcement processing.
3. the plate heat preserving formwork mounting process of a kind of concrete shear force wall according to claim 1, it is characterised in that:Institute In the installation procedure for the concrete shear force wall formwork thermal insulation board stated at wall handing-over and door-window opening, formwork thermal insulation board should be by setting Meter requires to carry out assembly, should uniformly be contacted with polyurethane foam glue by squeezing when formwork thermal insulation board pastes installation, adhesive surface is full Degree should reach 80 or more percent, by assisting external member that plate stitch is made to keep horizontal and vertical, thermal insulation board surfacing.
4. the plate heat preserving formwork mounting process of a kind of concrete shear force wall according to claim 1, it is characterised in that:Institute Polymer cement mortar in the concrete shear force wall formwork heat preservation levelling process of board finish stated, polymer cement mortar dry mash are straight It connects and is added in suitable quantity of water, 10 minutes are stood after stirring evenly, carry out secondary agitation, three hour interpolymer cement bonded sands after the completion of stirring Slurry need to use finish, and any additive for helping stirring cannot be added in whipping process.
5. the plate heat preserving formwork mounting process of a kind of concrete shear force wall according to claim 1, it is characterised in that:Institute First of the cracking resistance sand thickness control of smearing anticracking grout protective layer process stated is in 2-3mm, with beam, the plug-in steel wire of column seam areas Mesh sheet, paving alkali-resisting glass fiber screen cloth overlap transverse direction 100mm, vertical 80mm, are pressed into anticracking grout superficial layer, then smear 1-2mm cracking resistance sand Slurry, alkali proof fiber screen cloth reach micro- and see that grid cloth, leakage line are not slipped through the net.
6. the plate heat preserving formwork mounting process of a kind of concrete shear force wall according to claim 1, it is characterised in that:Institute The smearing anticracking grout protective layer process installation anchor hole anomaly template formwork edge stated is no less than 100mm, and anchor bolt quantity is often put down Square rice is no less than 4, and every piece of plate formwork anchor bolt quantity is no less than 2, and the second cracking resistance sand thickness is in 2- 3mm。
7. wanting a kind of plate heat preserving formwork mounting process of concrete shear force wall described in 5 according to right, it is characterised in that:It is described Smearing anticracking grout protective layer process in plug-in steel fabric sheet be that horizontal steel wire and perpendicular steel wire are interwoven, plug-in steel fabric sheet and Measure is auxiliarily fixed in plate heat preserving formwork Special anchor bolt, and anchor bolt should be mounted on steel fabric sheet or finishing mucilage and alkali-resisting glass fiber The upper surface of screen cloth.
8. the plate guarantor that the plate heat preserving formwork mounting process of a kind of concrete shear force wall according to claim 1 uses Warm formwork, it is characterised in that:The plate heat preserving formwork is cuboid, and groove is equipped in plate heat preserving formwork side, The groove is L-type, is arranged in four angles of plate heat preserving formwork.
9. the auxiliary sleeve that the plate heat preserving formwork mounting process of a kind of concrete shear force wall according to claim 8 uses Part, it is characterised in that:The auxiliary external member is equipped with cross-brace axis and vertical supporting axis, cross-brace axis and vertical supporting axis In cross connection, cross-brace axis and vertical supporting axis are equipped with raised item, and raised item is plugged on template heat preserving formwork side Groove in.
10. the plate heat preserving formwork mounting process of a kind of concrete shear force wall according to claim 8 uses plate The production equipment of heat preserving formwork, including automatic charging storehouse, formwork molding die, ballast consolidating machine;It is characterized in that:The formwork It is set on the outside of molding die there are four supporting rack, supporting rack side connecting mold, the other side of supporting rack is equipped with shaped support, molding Holder is L-type.
CN201710006642.6A 2017-01-05 2017-01-05 A kind of plate heat preserving formwork mounting process of concrete shear force wall Pending CN108277894A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710006642.6A CN108277894A (en) 2017-01-05 2017-01-05 A kind of plate heat preserving formwork mounting process of concrete shear force wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710006642.6A CN108277894A (en) 2017-01-05 2017-01-05 A kind of plate heat preserving formwork mounting process of concrete shear force wall

Publications (1)

Publication Number Publication Date
CN108277894A true CN108277894A (en) 2018-07-13

Family

ID=62800271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710006642.6A Pending CN108277894A (en) 2017-01-05 2017-01-05 A kind of plate heat preserving formwork mounting process of concrete shear force wall

Country Status (1)

Country Link
CN (1) CN108277894A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236471A (en) * 2020-01-19 2020-06-05 江西海鑫建设有限公司 Construction method of energy-saving wall
CN111827511A (en) * 2020-07-03 2020-10-27 广东恒实建设工程有限公司 Method for mounting prefabricated wall

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200999438Y (en) * 2007-01-16 2008-01-02 廖炎 Multifunctional combined type splice plate
WO2008110818A1 (en) * 2007-03-14 2008-09-18 A. Proctor Group Ltd Wall insulation system
CN103276831A (en) * 2013-06-28 2013-09-04 安徽中瑞节能装饰材料集团有限公司 Inorganic composite A-class non-combustible insulation board wall thermal insulation system and construction method
CN104196135A (en) * 2014-09-15 2014-12-10 中天联合节能建设发展(天津)股份有限公司 Heat-insulation construction and energy conservation process for exterior walls
CN104674962A (en) * 2015-01-27 2015-06-03 安徽同济建设集团有限责任公司 Method for constructing external heat-insulation systems of external walls from expanded perlite heat-insulation plates
KR20150061735A (en) * 2013-11-28 2015-06-05 김경훈 Panel for prefabricated building
CN105839842A (en) * 2016-04-28 2016-08-10 邹城市兴企新型建材有限公司 Slab cross buckle type composite board formed at time

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200999438Y (en) * 2007-01-16 2008-01-02 廖炎 Multifunctional combined type splice plate
WO2008110818A1 (en) * 2007-03-14 2008-09-18 A. Proctor Group Ltd Wall insulation system
CN103276831A (en) * 2013-06-28 2013-09-04 安徽中瑞节能装饰材料集团有限公司 Inorganic composite A-class non-combustible insulation board wall thermal insulation system and construction method
KR20150061735A (en) * 2013-11-28 2015-06-05 김경훈 Panel for prefabricated building
CN104196135A (en) * 2014-09-15 2014-12-10 中天联合节能建设发展(天津)股份有限公司 Heat-insulation construction and energy conservation process for exterior walls
CN104674962A (en) * 2015-01-27 2015-06-03 安徽同济建设集团有限责任公司 Method for constructing external heat-insulation systems of external walls from expanded perlite heat-insulation plates
CN105839842A (en) * 2016-04-28 2016-08-10 邹城市兴企新型建材有限公司 Slab cross buckle type composite board formed at time

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨永起等: "《中国建筑保温防火产品及应用技术》", 28 February 2015, 中国建材工业出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236471A (en) * 2020-01-19 2020-06-05 江西海鑫建设有限公司 Construction method of energy-saving wall
CN111827511A (en) * 2020-07-03 2020-10-27 广东恒实建设工程有限公司 Method for mounting prefabricated wall

Similar Documents

Publication Publication Date Title
CN101818527B (en) Assembled integral shear wall structure system and construction method thereof
CN106436893A (en) Fully-prefabricated structure and construction method thereof
CN201801979U (en) Aerated concrete building block heat insulating wall
CN100396860C (en) Concrete building combined with heat insulating framework and its construction method
CN103866885B (en) The construction method of the energy-saving heat preserving structure of light inlet window
CN100584560C (en) Method for manufacturing external wallboard, internal wallboard, floor and roof board
CN104405062A (en) Integrated column-equipped heat preservation wallboard, production and building techniques and matched equipment
CN102644382B (en) Mounting technology of large-module wall
CN103352537B (en) Overall load bearing heat preserving wallboard and production construction process thereof
CN106120870A (en) The advanced enclosed construction of poured band of outer wall of basement and construction method
CN107447893A (en) A kind of lightgage steel joist concrete anticracking filling wall and its construction method
CN109138227A (en) Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology
CN104499614B (en) Wall heat-preservation integration point hanging system and mounting method thereof
CN112459291A (en) Prefabricated heat insulation structure integrated wall structure and construction process thereof
CN108589975A (en) Assembling cladding and construction technology
CN108915107A (en) A kind of inorganic infiltration heat preservation board construction method of EPS
CN111608280A (en) External wall heat insulation construction method
CN108277894A (en) A kind of plate heat preserving formwork mounting process of concrete shear force wall
CN104110082B (en) The built-in composite insulation boards Cast-in-place concrete integration wall body structure of external mold and manufacture method thereof
CN104196135A (en) Heat-insulation construction and energy conservation process for exterior walls
CN102561691A (en) Method for eliminating cracking of joint between fair-faced concrete shear wall and masonry
CN103883022B (en) The construction method of space enclosing structure inner-outer wall antidetonation and sound insulation cracking resistance integrated structure
CN205502373U (en) Evaporate and press whole wallboard that keeps warm of aerated concrete
CN205954707U (en) Leading enclosed construction in basement outer wall post -cast strip
CN106759993A (en) A kind of external heat insulating wall and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180713