CN104499614B - Wall heat-preservation integration point hanging system and mounting method thereof - Google Patents

Wall heat-preservation integration point hanging system and mounting method thereof Download PDF

Info

Publication number
CN104499614B
CN104499614B CN201410710824.8A CN201410710824A CN104499614B CN 104499614 B CN104499614 B CN 104499614B CN 201410710824 A CN201410710824 A CN 201410710824A CN 104499614 B CN104499614 B CN 104499614B
Authority
CN
China
Prior art keywords
wall
ceramic wafer
insulation material
preservation
heat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410710824.8A
Other languages
Chinese (zh)
Other versions
CN104499614A (en
Inventor
蒙政强
黎顺谋
杨仟厦
杜尔宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Green Building Technology Engineering Co ltd
Monalisa Group Co Ltd
Original Assignee
GUANGDONG GREEN BUILDING TECHNOLOGY ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG GREEN BUILDING TECHNOLOGY ENGINEERING Co Ltd filed Critical GUANGDONG GREEN BUILDING TECHNOLOGY ENGINEERING Co Ltd
Priority to CN201410710824.8A priority Critical patent/CN104499614B/en
Publication of CN104499614A publication Critical patent/CN104499614A/en
Application granted granted Critical
Publication of CN104499614B publication Critical patent/CN104499614B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/90Passive houses; Double facade technology

Landscapes

  • Finishing Walls (AREA)
  • Building Environments (AREA)

Abstract

The utility model relates to a wall heat-preservation integration point hanging system which comprises a wall, a connecting angle code, bearing hanging pieces, at least one heat-preservation material and at least one ceramic plate. The wall heat-preservation integration point hanging system is characterized in that one end of at least one bearing hanging piece is fixedly connected with the ceramic plate, and the other end of the bearing hanging piece is fixedly connected with the connecting angle code through a bolt; the connecting angle code is fixed on the wall; the plate surface of the ceramic plate is parallel to the surface of the wall, and at least one heat-preservation material is sealed between the ceramic plate and the wall. The invention further discloses a mounting method of the system and aims at realizing the heat preservation and decoration integration of the ceramic plate external wall for newly building, expanding and rebuilding civil architectures by using concrete or masonry as a basic wall. The mounting system for heat-preservation and decoration compound boards is accurately applied, the wall heat-preservation and thermal insulation performance of the energy conversation engineering for building is improved, the energy consumption of building use is reduced, the indoor comfort degree is improved, and safety, comfort and economy and application are realized.

Description

Wall thermal insulating integration point extension system and its installation method
Technical field
The present invention relates to curtain buildingses field, especially a kind of wall thermal insulating integration point extension system and its installation method.
Background technology
At present in the construction of building decoration External Wall slabstone, substantially it is divided into three major types:1. it is that (i.e. cement mortar expires wet trade class Patch slabstone);2. it is the cladding class of slabstone (i.e. the common stone curtain wall of institute or stone material dry suspending exterior wall);3. it is that slabstone point hangs class (i.e. slabstone Supporting-point by plant nail form and cancel column, crossbeam form and name).Obviously wet trade class is constructed because its construction technology falls Its building height is limited afterwards and progressively, and such as regulation can only be below 3 meters, and monolithic slabstone size is not more than 300*300mm models Enclose interior just permission construction.It is the main form of construction work of current decoration of exterior wall to the cladding of dry construction or point extension operation, and its In due to its combined ratio of point hanging construction it is cheap compared with dry hanging construction, therefore the deep extensive application by the numerous investors.Point ornament face It is certain or distinguishing between plate technique and dry hanging of veneer (or stone curtain wall), the mainly headroom in decorative cover and basic unit face Distance not should be greater than 50mm;Boundary of works area is little, and only building height is in below 28M regions and provides fortification against earthquakes to be not more than 7 grades for restriction Situation just can be suitable for;External Wall moulding, such as relating to when facing plate thickness or opposite lines are more than 35mm, separately to set Meter construction measure, just can ensure that decoration panel installation quality requirement.
The content of the invention
For the defect and deficiency of prior art, the present invention proposes a kind of install convenient, well-set wall thermal insulating one Body point hangs system and installation method.
The technical scheme is that what is be achieved in that:
A kind of wall thermal insulating integration point extension system, including body of wall, connecting corner yard, support suspension member, at least one piece thermal insulating material Material and at least one piece ceramic wafer, one end of at least one support suspension member is fixedly connected with the ceramic wafer, and described The other end of support suspension member is fixedly connected by bolt with the connecting corner yard, and the connecting corner yard is fixed on the body of wall;And The plate face of the ceramic wafer is parallel with the surface of wall, at least one block insulation material be sealed in the ceramic wafer with it is described Between body of wall.
Preferably, exist between the adjacent insulation material of the adjacent ceramic wafer of each two and/or each two Gap filling has seal.
If preferably, the one side towards the ceramic wafer and/or the body of wall of the support suspension member integrally formed with Dry projection, forms dovetail grooved gap between adjacent protrusion.
Preferably, being filled with epoxide-resin glue between the ceramic wafer and the insulation material.
Preferably, the support suspension member is fixed by epoxy structural rubber with the ceramic wafer.
Preferably, being bonded with four support suspension members, the support suspension member bonding location on per ceramic wafer described in block Apart from the ceramic wafer edge 100-300mm.
Preferably, the heat insulation material surface is enclosed with alkali-resistant glass fiber net, and it is fine in the alkali resistant glass Dimension net is coated with polymers anti-cracking mortar.
A kind of wall thermal insulating integration point hangs system installation method, comprises the following steps:
1) base treatment:Basal plane need to be cleaned out, and surface must not have dust, greasy dirt, releasing agent etc. to affect adhesive and base The material of face bonding, it is again levelling with cement mortar again after being rooted out, it is finally with broom that dust and garbage-cleaning is clean;Apply Washing moistening is carried out to basal plane before work, can be constructed after basal plane is without open fire;
2) lattice unwrapping wire, drilling are played:Installing backing or appropriate to the occasion employing of ceramic wafer is carried out from lower to upper, the root at side wall, top board According to heat insulating decorative board hang vertically, set side, play THICKNESS CONTROL line, and on metope play heat insulating decorative board install control line, subsequently exist Body of wall gets out the installation preformed hole of fixed corner code;
3) connecting corner yard is installed:Install solid with bolt on the support suspension member being fixed on by epoxy structural rubber on ceramic wafer Set connecting corner yard;
4) coating adhesive and the insulation material that bonds:Insulation material is bonded on ceramic wafer by epoxide-resin glue, meanwhile, Apply in metope and scraped cement base rubber, then ceramic wafer is bonded on body of wall, if cement-based adhesive surface is dried up after should wiping off Again apply and scrape;
5) expansion bolt is installed:After bonding ceramic wafer, expansion bolt should be in time installed and connecting corner yard is fixed on body of wall, even Connect corner brace should with wall connecting firmly, non-loosening, must not excessively move during installation, loosen the ceramic wafer for having bondd, Yi Mianying Ring the adhesion strength of adhesive;
6) fluid sealant jointing:Install and should use in time after ceramic wafer fluid sealant jointing, it is first (general with insulation material during jointing Foam strip) joint filling, then with building weather proofing sealant joint filling.Jointing should be full, closely knit, continuous, uniform, bubble-free recessed Shape groove.
Compared with prior art, the beneficial effects of enforcing the present invention are technical scheme:Solve concrete or Masonry for base course wall newly-built, the external wall thermal insulating decoration integrated problem of ceramic thin plate extending and reconstruct the building such as civilian, just Heat-insulating decorative composite board installation system should indeed be used, Energy Conservation Project in Construction wall thermal insulating heat-proof quality is improved, building is reduced and is used energy Consumption, improves indoor comfort degree, and safety and comfort are economic and practical.
Description of the drawings
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing The accompanying drawing to be used needed for having technology description is briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, without having to pay creative labor, may be used also To obtain other accompanying drawings according to these accompanying drawings.
Fig. 1 is schematic structural view of the invention;
Fig. 2 is the structural representation of support suspension member in the present invention.
Specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than the embodiment of whole.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of protection of the invention.
Wall thermal insulating integration point extension system as shown in Figure 1, including body of wall 1, connecting corner yard 5, support suspension member 6, at least One block of insulation material 3 and at least one piece ceramic wafer 2.
Wherein, to make the surface more smooth of body of wall 1, apply again on the surface of body of wall 1 and scrape one layer of screed 9, increase metope Flatness, to ensure the flatness for installing whole curtain wall after wallboard.
One end of wherein at least one support suspension member 6 is fixed together with ceramic wafer 2 in bonding mode, and support The other end of suspension member 6 is fixedly connected by bolt with connecting corner yard 5, and connecting corner yard 5 is fixed on body of wall 1;And the plate face of ceramic wafer 2 Parallel with the surface of body of wall 1, at least one block insulation material 3 is sealed between ceramic wafer 2 and body of wall 1.
Further, cement-based adhesive 12 is additionally provided between insulation material 3 and body of wall 1 to be connected with screed 9, Yi Jiwei Backing 8 between cement-based adhesive 12 and insulation material 3, it is to avoid insulation material 3 on body of wall 1, is led by directly adhesion The later stage is caused to remove trouble.
Preferably, the gap existed between the adjacent insulation material 3 of the adjacent ceramic wafer 2 of each two and/or each two Filled with seal 11, the seal 11 is fluid sealant, purport be improve adjacent ceramic plate 2 and adjacent insulation material 3 it Between air-tightness.
Preferably, if the one side towards ceramic wafer 2 and/or body of wall 1 of support suspension member 6 in Fig. 2 is integrally formed with some Raised 61, dovetail grooved gap 62 is formed between adjacent protrusion 61, to increase the bond area of bonding, improve firm intensity;Enter One step, raised 61 shape can also be swallow-tail form.
Preferably, being filled with epoxide-resin glue 4 between ceramic wafer 2 and insulation material 3, the filling of epoxide-resin glue 4 makes Both structures are more firm, turn to an entirety, when being easy to drilling that support suspension member 6 or connecting corner yard 5 and other articles are installed, Insulation material 3 will not be moved or deform.
Preferably, support suspension member 6 is fixed by epoxy structural rubber 7 with ceramic wafer 2;Cause, epoxy structural rubber 7 is solvent-free Type, liquid-state epoxy resin solid can be in normal temperature or heating cure.Hardness is waited until in solidification followed by series of strata, thus can be born The impact of extra-heavy and vibrations, following layer has a good mechanical property, good electrical insulating property, be capable of bearing temperature variation and Stripping stress is torn in flexure.Non-corrosiveness, to metal, ceramics, vulcanized rubber, glass fibre manufactured goods, and carbon fiber finished product etc., tool There is fine adherence.
Preferably, the support suspension member 6 of dovetail groove type:Support suspension member 6 is bondd using modified epoxy structural rubber 7 pre-buried On the back side of ceramic wafer 2, adhesive layer thickness is controlled in 2 ㎜ or so, it is ensured that at least four support suspension members on every ceramic wafer 2 6, each support suspension member 6 apart from ceramic wafer 2 edge 200mm or so, the control of the distance between support suspension member 6 and support suspension member 6 Within 900mm;Firmness between ceramic wafer and body of wall can so be reinforced.
Preferably, insulation material 3 is coated with alkali-resistant glass fiber net, and in alkali-resistant glass fiber net surface Coated polymer anticracking grout;Increase the heat insulating ability and air-tightness and fire protecting performance of structure.
A kind of wall thermal insulating integration point hangs system installation method, comprises the following steps:
1) base treatment:The basal plane of body of wall 1 need to be cleaned out, and it is gluing that surface must not have dust, greasy dirt, releasing agent etc. to affect The material of agent and basal plane bonding, it is again levelling with cement mortar again after being rooted out, finally with broom by dust and garbage-cleaning Totally;Washing moistening is carried out to basal plane before construction, can be constructed after basal plane is without open fire;
2) lattice unwrapping wire, drilling are played:Installing backing or appropriate to the occasion employing of ceramic wafer is carried out from lower to upper, the root at side wall, top board According to heat insulating decorative board hang vertically, set side, play THICKNESS CONTROL line, and on metope play heat insulating decorative board install control line, subsequently exist Body of wall gets out the installation preformed hole of fixed corner code;
3) connecting corner yard is installed:Install solid with bolt on the support suspension member being fixed on by epoxy structural rubber on ceramic wafer Set connecting corner yard;
4) coating adhesive and the insulation material that bonds:Insulation material is bonded on ceramic wafer by epoxide-resin glue, meanwhile, Apply in metope and scraped cement base rubber, then ceramic wafer is bonded on body of wall, if cement-based adhesive surface is dried up after should wiping off Again apply and scrape;
5) expansion bolt is installed:After bonding ceramic wafer, expansion bolt should be in time installed and connecting corner yard is fixed on body of wall, even Connect corner brace should with wall connecting firmly, non-loosening, must not excessively move during installation, loosen the ceramic wafer for having bondd, Yi Mianying Ring the adhesion strength of adhesive;
6) fluid sealant jointing:Install and should use in time after ceramic wafer fluid sealant jointing, it is first (general with insulation material during jointing Foam strip) joint filling, then with building weather proofing sealant joint filling.Jointing should be full, closely knit, continuous, uniform, bubble-free recessed Shape groove.
Presently preferred embodiments of the present invention is the foregoing is only, not to limit the present invention, all essences in the present invention Within god and principle, any modification, equivalent substitution and improvements made etc. should be included within the scope of the present invention.

Claims (2)

1. extension system, including body of wall, connecting corner yard, support suspension member, at least one block insulation material are put in a kind of wall thermal insulating integration And at least one piece ceramic wafer, it is characterised in that the insulation material is sealed between the ceramic wafer and the body of wall, described Heat insulation material surface is enclosed with alkali-resistant glass fiber net, and is coated with polymers anti-cracking sand in the alkali-resistant glass fiber net Slurry;The gap filling existed between the adjacent insulation material of the adjacent ceramic wafer of each two and/or each two has epoxy Resin glue, per ceramic wafer described in block on be bonded with four support suspension members, the support suspension member bonding location is apart from the ceramic wafer Edge 100-300mm, the end face towards the ceramic wafer and/or the body of wall of the support suspension member is integrally formed with some convex Rise, dovetail grooved gap is formed between adjacent protrusion, epoxy structural rubber is filled with the dovetail grooved gap, and the support is hung Part is fixedly connected by bolt away from the other end of the ceramic wafer and/or the body of wall with the connecting corner yard, the connection Corner brace is fixed on the body of wall;And the plate face of the ceramic wafer is parallel with the surface of wall.
2. a kind of wall thermal insulating according to claim 1 integration point hangs system installation method, it is characterised in that include with Lower step:
1) base treatment:Basal plane need to be cleaned out, and surface must not have dust, greasy dirt, releasing agent etc. to affect adhesive and basal plane viscous The material of knot, it is again levelling with cement mortar again after being rooted out, it is finally with broom that dust and garbage-cleaning is clean;Before construction Washing moistening is carried out to basal plane, can be constructed after basal plane is without open fire;
2) lattice unwrapping wire, drilling are played:Backing is installed or ceramic wafer is appropriate to the occasion using carrying out from lower to upper, according to guarantor at side wall, top board Warm decorative panel hang vertically, set side, play THICKNESS CONTROL line, and on metope play heat insulating decorative board install control line, subsequently in body of wall Get out the installation preformed hole of fixed corner code;
3) connecting corner yard is installed:Installed with bolt on the support suspension member being fixed on by epoxy structural rubber on ceramic wafer and fixed Connecting corner yard;
4) coating adhesive and the insulation material that bonds:Insulation material is bonded on ceramic wafer by epoxide-resin glue, meanwhile, in wall Face applies and has scraped cement base rubber, and then ceramic wafer is bonded on body of wall, if cement-based adhesive surface is dried up after should wiping off again Painting is scraped;
5) expansion bolt is installed:After bonding ceramic wafer, expansion bolt should be in time installed and connecting corner yard is fixed on body of wall, joint angle Code should with wall connecting firmly, non-loosening, must not excessively move during installation, loosen the ceramic wafer for having bondd, in order to avoid impact glue The adhesion strength of stick;
6) fluid sealant jointing:Install and should use in time after ceramic wafer fluid sealant jointing, first (usually steeped with insulation material during jointing Foam bar) joint filling, then with weather proofing sealant joint filling is built, jointing should be full, closely knit, continuous, uniform, bubble-free spill ditch Groove.
CN201410710824.8A 2014-11-27 2014-11-27 Wall heat-preservation integration point hanging system and mounting method thereof Active CN104499614B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410710824.8A CN104499614B (en) 2014-11-27 2014-11-27 Wall heat-preservation integration point hanging system and mounting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410710824.8A CN104499614B (en) 2014-11-27 2014-11-27 Wall heat-preservation integration point hanging system and mounting method thereof

Publications (2)

Publication Number Publication Date
CN104499614A CN104499614A (en) 2015-04-08
CN104499614B true CN104499614B (en) 2017-05-10

Family

ID=52941055

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410710824.8A Active CN104499614B (en) 2014-11-27 2014-11-27 Wall heat-preservation integration point hanging system and mounting method thereof

Country Status (1)

Country Link
CN (1) CN104499614B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155697A (en) * 2015-06-24 2015-12-16 江苏省建筑科学研究院有限公司 Exterior wall composite insulation structure and construction method thereof
CN108868045A (en) * 2018-07-04 2018-11-23 广东绿屋建筑科技工程有限公司 A kind of ceramic integrated wall plate mounting structure for smooth metope
CN109958253A (en) * 2019-03-29 2019-07-02 广东绿屋建筑科技工程有限公司 A kind of frame structure of integrated wall plate
CN110439312A (en) * 2019-08-12 2019-11-12 贵州建工集团第六建筑工程有限责任公司 The construction method of the hanging integrated plate for heat insulation external wall reconstruction of point
CN110565844A (en) * 2019-09-10 2019-12-13 广东绿屋建筑科技工程有限公司 can absorb assembled partition wall system of construction error
CN111734024A (en) * 2020-06-24 2020-10-02 南京市第八建筑安装工程有限公司 Lightweight concrete ceramic thick plate curtain wall and mounting method thereof

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007170002A (en) * 2005-12-21 2007-07-05 Emaajii:Kk External heat insulation structure of building, and heat insulation panel mounting bracket for use therein
CN101538922A (en) * 2009-04-10 2009-09-23 沈英 Hanging attached installation structure of composite pottery plate
CN201649498U (en) * 2010-01-12 2010-11-24 王云飞 Hanging fastener component for stone ceramic plates
CN103174275B (en) * 2011-12-21 2015-08-05 王云飞 Heat insulating decorative board hanging fastener component and mounting method thereof
CN203412117U (en) * 2013-06-26 2014-01-29 天津中怡建筑规划设计有限公司 Internal and external composite outer-wall external thermal insulation system for phase change energy storage building thermal insulation mortar
CN203514711U (en) * 2013-10-24 2014-04-02 广东蒙娜丽莎新型材料集团有限公司 Curtain wall dry cladding structure with lightweight ceramic thin plate
CN204225324U (en) * 2014-11-27 2015-03-25 广东绿屋建筑科技工程有限公司 Wall thermal insulating integration point extension system

Also Published As

Publication number Publication date
CN104499614A (en) 2015-04-08

Similar Documents

Publication Publication Date Title
CN104499614B (en) Wall heat-preservation integration point hanging system and mounting method thereof
US9957722B2 (en) Insulated wall panel
CN104018598B (en) A kind of exterior wall structure and construction installation method
CN201190380Y (en) Thick plastering system of heated board for face brick wall
CN104612261A (en) Method for external insulation construction of polystyrene board thin plastered surface in cold and windy area
CN109267671A (en) A kind of decoration method of indoor wall system
CN106284706A (en) The construction method of external wall outer insulation rock cotton board
CN106193499A (en) A kind of combined heat-insulating integral plate anchoring torr hanging hang structure and process
CN105625589B (en) Exterior wall insulated structure and preparation method thereof
CN204225324U (en) Wall thermal insulating integration point extension system
CN117661844A (en) A kind of lightweight energy-saving wall partition installation and construction method
CN201660981U (en) An external thermal insulation wall with mechanically anchored metal mesh reinforced polystyrene board
CN102383507A (en) Light steel keel and plasterboard vitrified tile decoration wall and method for constructing same
CN100462515C (en) External wall ceramic tile wall surface with heat insulation function and constructing method thereof
CN209179240U (en) The integrated mounting structure of wall thermal insulating
CN103015656B (en) Component type exterior wall heat insulating decorative board and preparation method thereof and exterior wall mounting method
CN101570990A (en) Cast-in-situ concrete heat-insulation wall
CN204401809U (en) Surface has the skin insulation layer of simulated decorative effect
CN204326275U (en) Polyurethane composite thermal insulation template
CN202248387U (en) Light steel keel gypsum board vitrified tile decorative wall
CN208884889U (en) A kind of superthin stone and its mounting structure
CN114182848A (en) A kind of construction technology of steel mesh frame sandwich panel wall thick plastering project
CN106567465A (en) External thermal insulation system with supported and hanged anchored thermal insulating boards
CN208347208U (en) A kind of new indoor walling system
CN110835962A (en) Construction method of building heat-insulation outer wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 528000 Foshan City, Nanhai District, Xiqiao, Taiping Industrial Zone (office building), layer 6, No. third, No.

Patentee after: GUANGDONG GREEN BUILDING TECHNOLOGY ENGINEERING Co.,Ltd.

Address before: 528000 No. 16, Jiangwan Road, Chancheng District, Guangdong, Foshan

Patentee before: GUANGDONG GREEN BUILDING TECHNOLOGY ENGINEERING Co.,Ltd.

CP02 Change in the address of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20221228

Address after: 528211 Xiqiao Textile City Industrial Park, Nanhai District, Foshan City, Guangdong Province

Patentee after: Monalisa Group Co.,Ltd.

Patentee after: GUANGDONG GREEN BUILDING TECHNOLOGY ENGINEERING Co.,Ltd.

Address before: 528000 No.6, 3rd floor, Taiping Industrial Zone (office complex), Xiqiao Town, Nanhai District, Foshan City, Guangdong Province

Patentee before: GUANGDONG GREEN BUILDING TECHNOLOGY ENGINEERING Co.,Ltd.

TR01 Transfer of patent right