CN205954707U - Leading enclosed construction in basement outer wall post -cast strip - Google Patents

Leading enclosed construction in basement outer wall post -cast strip Download PDF

Info

Publication number
CN205954707U
CN205954707U CN201620877127.6U CN201620877127U CN205954707U CN 205954707 U CN205954707 U CN 205954707U CN 201620877127 U CN201620877127 U CN 201620877127U CN 205954707 U CN205954707 U CN 205954707U
Authority
CN
China
Prior art keywords
wall
basement
steel plate
cast strip
post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620877127.6U
Other languages
Chinese (zh)
Inventor
钱永军
陈添鹤
杨再岗
路远
钱兵成
李月彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiashi (group) Co Ltd
Original Assignee
Shanghai Jiashi (group) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiashi (group) Co Ltd filed Critical Shanghai Jiashi (group) Co Ltd
Priority to CN201620877127.6U priority Critical patent/CN205954707U/en
Application granted granted Critical
Publication of CN205954707U publication Critical patent/CN205954707U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model relates to an its characterized in that of leading enclosed construction in basement outer wall post -cast strip, including shut (4), brick setting inoxidizing coating (5), waterproof layer (6), mortar levelling layer (7), connector plates (8), stagnant water steel sheet (9), connection cant chisei (10) etc, assemble shut (4) in mortar levelling layer (7) the outside, it is nested through splice bar (45) in the vertical direction even for whole each other with the protruding strip (43) and recess (44) of lower extreme on it, connector plates (8) one end card is equipped with the reinforcing bar through hole, penetrates horizontal muscle and welding in going into draw -in groove (48) on shut (4) on it, the other end is equipped with post -cast strip template fixed connection screw rod (15). The utility model belongs to basement outer wall and post -cast strip construction field in industry and the civilian building subject structure have leading stagnant water, to keep off soil effectual, and characteristics that construction speed is fast have better technological economic benefits.

Description

The advanced enclosed construction of poured band of outer wall of basement
Technical field
This utility model is related to the advanced enclosed construction of poured band of outer wall of basement, belongs to industry and civil buildings agent structure Middle outer wall of basement and post empiricism field, are mainly used in the advanced protection of poured band of outer wall of basement and pour after the later stage In band concrete pouring construction.
Background technology
In the construction of outer wall of basement, due to single construct body of wall length restriction and construction in Deformation control will Ask, outer wall of basement needs arrange post-cast strip.The construction operation being carried out before poured band of outer wall of basement closing is not only There is potential safety hazard, and debris, rainwater and construction water are easily accessible underground interior before the closing of post-cast strip, affect post-cast strip Pouring quality and normal construction.Poured band of outer wall of basement concreting time interval is longer, generally requires underground body junction Structure construction just carries out the pouring construction of post-cast strip after finishing, therefore if do not carried out the advanced closing of post-cast strip, can make outdoor backfill Operation can not be carried out, and also can not install to agent structure and equipment provides necessary place.
The at present advanced closing of poured band of outer wall of basement is constructed using concrete prefabricated closed plate, its enclosed construction and Construction method is in document " card slot type formwork construction technology outside poured band of outer wall of basement(《Construction technology》, 2015,44 (23):85-87)" disclosed in, which solve the gear soil antiseepage problem of the advanced enclosed construction in post-cast strip, but still there are the following problems: (1)Enclosed construction is assembled by polylith precoated plate, easily tilts, shifts, close when leading to later stage post-cast strip to pour in construction Structure is serious under malformation to become position influence construction;(2)Enclosed construction itself does not have barrier properties, in outside because construction becomes When shape is larger, waterproof layer tears and destroys, the waterproof of enclosed construction can not work;(3)Outer wall of basement and post-cast strip coagulation It is complicated that soil pours formwork.
Content of the invention
The purpose of this utility model is that the technology existing for the advanced enclosed construction of existing poured band of outer wall of basement is asked A kind of topic, there is provided the advanced enclosed construction in post-cast strip, using the closed plate on-site consolidation with draw-in groove and watertight rubber bar and pass through Dowel is linked as entirety, simultaneously setting steel plate for sealing water and accessory structure in closed plate, reaches the technology such as sealing, gear soil, formwork Effect.
In order to realize above-mentioned technical purpose, this utility model employs technical scheme below:
A kind of advanced enclosed construction of poured band of outer wall of basement it is characterised in that include closed plate, brick setting overcoat, Waterproof layer, mortar levelling layer, junction steel plate, steel plate for sealing water, connection peg, described brick setting overcoat is built by laying bricks or stones in campshed within the walls Outside side, outer wall of basement, described waterproof layer is arranged on brick setting overcoat, arranges mortar levelling layer, described company outside it Connect steel plate and be provided with reinforcing bar through hole, the horizontal bar of framework of steel reinforcement passes through reinforcing bar through hole and is welded on junction steel plate, described The raised item of the upper and lower side of closed plate and groove are nested with one another and be linked as entirety by dowel in vertical direction, described connection steel Plate one end snaps in the draw-in groove in closed plate, and filling flexible sealing material.
Described closed plate is made up of supported on both sides plate and panel;One layer of isolating membrane is arranged on gripper shoe;Closed plate upper and lower side It is respectively provided with groove and raised item, groove surfaces are embedded with rubber strip, rubber strip upper surface exceeds groove surfaces 2mm;Gripper shoe and It is provided with draw-in groove between panel;Pre-buried pvc pipe in gripper shoe vertical direction, upper end is provided with cavity.
Described junction steel plate is L-shaped, and on its long side, the steel plate for sealing water of welding and connection peg are respectively protruding into first to pour and apply In the post-cast strip of the outer wall of basement of work and after-pouring construction, its minor face is provided with the through hole of screw rod.
The method carrying out poured band of outer wall of basement construction using the advanced enclosed construction of above-mentioned poured band of outer wall of basement, applies Work step is suddenly as follows:
Step one, brick setting overcoat building construction:Along outer wall of basement build by laying bricks or stones with the outside of post-cast strip together with brick setting Overcoat;
Step 2, construction of waterproof layer:Brick setting protection layer surface base cleaning is clean, smooth, uniform application in basic unit Adhesive bitument primer, pastes waterproof roll to form waterproof layer;
Step 3, the construction of mortar levelling layer:One layer of mortar levelling layer of construction on waterproof layer;
Step 4, closed plate are installed:Prefabricated closed plate lifting is put in place, dowel is reserved through in closed plate Every layer of closed plate is fastened by pvc pipe by bolt, and the bolt after fastening is placed in cavity, and gripper shoe is pasted one layer of isolating membrane;
Step 5, tie with reinforcing bar and junction steel plate are fixed:The framework of steel reinforcement of colligation outer wall of basement, outdoor in underground Wall and the intersection of post-cast strip, horizontal full-length cage bar passes through the reserving hole on junction steel plate, and junction steel plate is welded with water-stopping steel Plate and connection peg, junction steel plate one end snaps in groove, and filling flexible sealing material, and screw rod passes through on junction steel plate minor face Reserving hole be welded on framework of steel reinforcement;
Step 6, outer wall of basement inner side template are installed and casting concrete:Outer wall of basement inner side template is using unilateral Formwork method is installed, and adopts and is bolted on screw rod, and casting concrete;
Step 7, backfill layer construction:After outer wall of basement concrete strength reaches requirement, in brick setting overcoat and campshed Fill backfill layer between wall, and remove outer wall of basement inner side template;
Step 8, post-cast strip inner side template are installed:Main structure construction finish and stabilization after, carry out post-cast strip and apply Work, removes the framework of steel reinforcement surface rusty stain of post-cast strip, installs post-cast strip inner side template;
Step 9, post-cast strip concreting:Pour the concrete of post-cast strip, and vibration compacting;
Step 10, post-cast strip concrete curing form removal:After the concrete curing of post-cast strip, intensity reaches strength of mould stripping, removes Post-cast strip inner side template.
Further, in step 8, inner side template is made by plywood, using level stupefied and perpendicular stupefied as shuttering supporting bone Frame, will erect stupefied being anchored on junction steel plate minor face by fastening bolt and screw rod.
This utility model has the characteristics that and beneficial effect:
(1)Using the closed plate with draw-in groove and watertight rubber bar and by the fastening of dowel it is ensured that enclosed construction is formed Gear soil supports entirety, and has sealing barrier properties in itself, is prevented effectively from the outer muddy water of wall and infiltrates the impact to construction;
(2)The gripper shoe at closed plate two ends and outside brick setting overcoat(Including waterproof layer and mortar levelling layer)In underground Use as outboard template during the exterior wall concreting of room, after the completion of construction, by the soil pressure of the soil that fillered after closed plate and water Pressure passes on outer wall of basement, and the presence of isolating membrane simultaneously ensures between enclosed construction and outer wall of basement in vertical direction energy Enough deformation that freely misplaces;
(3)Junction steel plate is provided with steel plate for sealing water and connects peg it is ensured that while outer wall of basement barrier properties intentinonally Bonding strength between lower room exterior wall and post-cast strip, junction steel plate snaps in the draw-in groove of enclosed construction and filling flexible sealing material, Improve the impermeability of post-cast strip further;
(4)What the minor face of junction steel plate was provided with alter-pouring strips mould plate is fixedly connected bolt hole and screw rod, facilitates alter-pouring strips mould plate Install.
Brief description
Fig. 1 is poured band of outer wall of basement advanced enclosed construction plane graph;
Fig. 2 is the advanced closed plate in post-cast strip and connects schematic three dimensional views;
Fig. 3 is node 1 detail;
Fig. 4 is node 2 thin portion three-dimensional detail drawing.
In figure:1- outer wall of basement, 2- post-cast strip, 3- framework of steel reinforcement, 4- closed plate, 5- brick setting overcoat, 6- waterproof Layer, 7- mortar levelling layer, 8- junction steel plate, 9- steel plate for sealing water, 10- connects peg, 11- inner side template, and 12- level is stupefied, and 13- erects Stupefied, 14- fastening bolt, 15- screw rod, 16- flexibility sealing material, 17- backfill layer, 18- campshed wall, 19- water-stop curtain, 20- every From film, 41- gripper shoe, 42- panel, 43- raised item, 44- groove, 45- dowel, 46- cavity, 47- rubber strip, 48- draw-in groove, 49-PVC manages.
Specific embodiment
Below in conjunction with the accompanying drawings and by embodiment this utility model is described in further detail, following examples are to this The explanation of utility model is not limited to following examples.
Fig. 1 is poured band of outer wall of basement advanced enclosed construction plane graph, and Fig. 2 is the advanced closed plate in post-cast strip and connects three Dimension schematic diagram, Fig. 3 is node 1 detail, and Fig. 3 is node 2 thin portion three-dimensional detail drawing.
Shown in reference Fig. 1 ~ 3, this post-cast strip width 800mm, outer wall of basement thickness 300mm, advanced enclosed construction includes Closed plate 4, brick setting overcoat 5, waterproof layer 6, mortar levelling layer 7, junction steel plate 8, steel plate for sealing water 9, connection peg 10 etc.
Closed plate 4 outer profile size is length 1200mm, height 500mm, thickness 200mm, by supported on both sides plate 41 dough-making powder Plate 42 is constituted;Closed plate 4 upper and lower side is respectively provided with groove 44 and raised item 43, and groove 44 surface is embedded with rubber strip 47, rubber strip 47 upper surfaces exceed groove 44 surface 2mm;It is provided with draw-in groove 48 between gripper shoe 41 and panel 42;Pre- in gripper shoe 41 vertical direction Bury pvc pipe 49, upper end is provided with cavity 46.
Brick setting overcoat 5 thickness 120mm, builds by laying bricks or stones outside campshed wall 18 inner side, outer wall of basement 1, brick setting protects The waterproof layer 6 of layer 5 inner side setting a layer thickness 3mm, waterproof layer 6 arranges the mortar levelling layer 7 of 10mm.
Junction steel plate 8 thickness 6mm, which is provided with reinforcing bar through hole, and the horizontal bar of framework of steel reinforcement 3 passes through reinforcing bar through hole simultaneously It is welded on junction steel plate 8.
The raised item 43 of the upper and lower side of closed plate 4 and groove 44 are nested with one another and be linked as in vertical direction by dowel 45 Overall, described junction steel plate 8 one end snaps in the draw-in groove 48 in closed plate 4, and filling flexible sealing material 16.
Junction steel plate 8 is L-shaped, and the steel plate for sealing water 9 of welding on its long side and connection peg 10 are respectively protruding into first to pour and apply In the post-cast strip 2 of the outer wall of basement 1 of work and after-pouring construction, its minor face is provided with the through hole of screw rod 15.
The construction procedure carrying out poured band of outer wall of basement 2 using this advanced enclosed construction is as follows:
Step one, brick setting overcoat 5 building construction:Along outer wall of basement 1 build by laying bricks or stones with the outside of post-cast strip 2 together with brick Body overcoat 5;
Step 2, waterproof layer 6 are constructed:Brick setting overcoat 5 surface base cleaning is clean, smooth, uniformly applies in basic unit Smear adhesive bitument primer, paste waterproof roll to form waterproof layer 6;
Step 3, mortar levelling layer 7 are constructed:One layer of mortar levelling layer 7 of construction on waterproof layer 6;
Step 4, closed plate 4 are installed:Prefabricated closed plate 4 lifting is put in place, dowel 45 passes through pre- in closed plate 4 Every layer of closed plate 4 is fastened by the pvc pipe 49 staying by bolt, and the bolt after fastening is placed in cavity 46, and gripper shoe 41 pastes One layer of isolating membrane 20;
Step 5, framework of steel reinforcement 3 colligation and junction steel plate 8 are fixing:The framework of steel reinforcement 3 of colligation outer wall of basement 1, in underground Room exterior wall 1 and the intersection of post-cast strip 2, horizontal full-length cage bar passes through the reserving hole on junction steel plate 8, and junction steel plate 8 welds There is steel plate for sealing water 9 and connect peg 10, junction steel plate 8 one end snaps in groove 44, and filling flexible sealing material 16, screw rod 15 It is welded on framework of steel reinforcement 3 through the reserving hole on the minor face of junction steel plate 8;
Step 6, outer wall of basement 1 inner side template are installed and casting concrete:Outer wall of basement 1 inner side template is using single Collateral modulus method is installed, and adopts and is bolted on screw rod 15, and casting concrete;
Step 7, backfill layer 17 are constructed:After outer wall of basement 1 concrete strength reaches requirement, in brick setting overcoat 5 He Fill backfill layer 17 between campshed wall 18, and remove outer wall of basement 1 inner side template;
Step 8, post-cast strip 2 inner side template 11 are installed:Main structure construction finish and stabilization after, carry out post-cast strip 2 Construction, removes the framework of steel reinforcement 3 surface rusty stain of post-cast strip 2, installs post-cast strip 2 inner side template 11;
Step 9, post-cast strip 2 concreting:Pour the concrete of post-cast strip 2, and vibration compacting;
Step 10, post-cast strip 2 concrete curing form removal:After the concrete curing of post-cast strip 2, intensity reaches strength of mould stripping, tears open Except post-cast strip 2 inner side template 11.

Claims (3)

1. a kind of advanced enclosed construction of poured band of outer wall of basement is it is characterised in that include closed plate(4), brick setting overcoat (5), waterproof layer(6), mortar levelling layer(7), junction steel plate(8), steel plate for sealing water(9), connect peg(10), described brick setting prevent Sheath(5)Build by laying bricks or stones in campshed wall(18)Inner side, outer wall of basement(1)Outside, described waterproof layer(6)It is arranged at brick setting overcoat (5)On, mortar levelling layer is set outside it(7), described junction steel plate(8)It is provided with reinforcing bar through hole, framework of steel reinforcement(3)Water Flat muscle passes through reinforcing bar through hole and is welded in junction steel plate(8)On, described closed plate(4)Upper and lower side raised item(43)With recessed Groove(44)Nested with one another and pass through dowel(45)It is linked as entirety in vertical direction, described junction steel plate(8)One end snaps in closing Plate(4)On draw-in groove(48)Interior, and filling flexible sealing material(16).
2. the advanced enclosed construction of poured band of outer wall of basement according to claim 1 is it is characterised in that described closed plate (4)By supported on both sides plate(41)And panel(42)Constitute;Gripper shoe(41)One layer of isolating membrane of upper setting(20);Closed plate(4)On Lower end is respectively provided with groove(44)And raised item(43), groove(44)Surface is embedded with rubber strip(47), rubber strip(47)Upper surface Beyond groove(44)Surface 2mm;Gripper shoe(41)And panel(42)Between be provided with draw-in groove(48);Gripper shoe(41)In vertical direction Pre-buried pvc pipe(49), upper end is provided with cavity(46).
3. the advanced enclosed construction of poured band of outer wall of basement according to claim 1 is it is characterised in that described junction steel plate (8)L-shaped, the steel plate for sealing water of welding on its long side(9)With connection peg(10)It is respectively protruding into the basement of first pouring construction Exterior wall(1)Post-cast strip with after-pouring construction(2)In, its minor face is provided with screw rod(15)Through hole.
CN201620877127.6U 2016-08-12 2016-08-12 Leading enclosed construction in basement outer wall post -cast strip Expired - Fee Related CN205954707U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620877127.6U CN205954707U (en) 2016-08-12 2016-08-12 Leading enclosed construction in basement outer wall post -cast strip

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620877127.6U CN205954707U (en) 2016-08-12 2016-08-12 Leading enclosed construction in basement outer wall post -cast strip

Publications (1)

Publication Number Publication Date
CN205954707U true CN205954707U (en) 2017-02-15

Family

ID=57974926

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620877127.6U Expired - Fee Related CN205954707U (en) 2016-08-12 2016-08-12 Leading enclosed construction in basement outer wall post -cast strip

Country Status (1)

Country Link
CN (1) CN205954707U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120870A (en) * 2016-08-12 2016-11-16 上海嘉实(集团)有限公司 The advanced enclosed construction of poured band of outer wall of basement and construction method
CN106869304A (en) * 2017-02-24 2017-06-20 中国十七冶集团有限公司 Outer wall of basement waterproof construction and construction method in a kind of confined space
CN109137989A (en) * 2018-10-23 2019-01-04 北京市城远市政工程有限责任公司 Well room builds device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120870A (en) * 2016-08-12 2016-11-16 上海嘉实(集团)有限公司 The advanced enclosed construction of poured band of outer wall of basement and construction method
CN106869304A (en) * 2017-02-24 2017-06-20 中国十七冶集团有限公司 Outer wall of basement waterproof construction and construction method in a kind of confined space
CN109137989A (en) * 2018-10-23 2019-01-04 北京市城远市政工程有限责任公司 Well room builds device
CN109137989B (en) * 2018-10-23 2023-09-22 北京市城远市政工程有限责任公司 Well chamber masonry device

Similar Documents

Publication Publication Date Title
CN106120870B (en) The advanced enclosed construction of poured band of outer wall of basement and construction method
CN103233520B (en) Self-waterproof construction method of building external wall structure
CN105862873B (en) Deep basal pit narrow space underground waterproof and external wall structure construction method
CN101403218B (en) Processing method for basement water-proof concrete construction joint
CN105484391A (en) Construction method for manufacturing heat-preservation waterproof wall through light heat-preservation GRC disassembling-free formworks
US20020059763A1 (en) Pre-fabricated bathroom
CN101818527A (en) Assembled integral shear wall structure system and construction method thereof
CN208167956U (en) A kind of basement inwall using reverse construction
CN113186985B (en) Anti-seepage treatment method for basement bottom plate construction joint
CN102644382B (en) Mounting technology of large-module wall
CN205954707U (en) Leading enclosed construction in basement outer wall post -cast strip
CN109577639A (en) Exterior wall protects mould integrated board and aluminum alloy mould plate combined system construction method
CN209837281U (en) Basement outer wall and bottom plate corner waterproof node
CN111173198A (en) Construction method of wall-attached constructional column for constructional engineering
CN109235702B (en) Assembled double-steel-plate combined shear wall structure with ribs and construction method thereof
CN111997232A (en) Construction method of concrete steel wire net rack disassembly-free template heat preservation system
CN109138227A (en) Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
CN108951840A (en) Based on setting bracket single side formwork basement arc external wall construction method
CN114164977A (en) Method for combining construction of aluminum template and laminated slab
CN109778916A (en) A kind of poured band of outer wall of basement Antiseep method based on water resistant plate
CN105937279B (en) The cast-in-place Integral Steel frame wall filled with masonry system and construction method of steel disc limit connection
CN210117716U (en) Trapezoidal foundation ditch lateral wall concrete typical forms of elevartor shaft
CN112411627A (en) Construction method for eliminating construction joint stubbles on inner side of outer wall of underground structure
CN217353538U (en) Disposable integral molding construction structure for sunken well and reversed ridge

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170215

CF01 Termination of patent right due to non-payment of annual fee