CN113186985B - Anti-seepage treatment method for basement bottom plate construction joint - Google Patents
Anti-seepage treatment method for basement bottom plate construction joint Download PDFInfo
- Publication number
- CN113186985B CN113186985B CN202110452872.1A CN202110452872A CN113186985B CN 113186985 B CN113186985 B CN 113186985B CN 202110452872 A CN202110452872 A CN 202110452872A CN 113186985 B CN113186985 B CN 113186985B
- Authority
- CN
- China
- Prior art keywords
- construction joint
- concrete
- construction
- bottom plate
- seepage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/003—Injection of material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The application relates to an anti-seepage treatment method for a basement bottom plate construction joint, and belongs to the technical field of constructional engineering. In order to solve the problems that the water seepage is easy to occur to the bottom plate of the basement of the building due to construction joints, but the construction joints or the construction cold joints of water stop steel plates cannot be arranged due to the limitation of construction conditions are not arranged or limited, the conventional method is to treat the surface by simply cleaning and coating cement paste, and the problems of internal water seepage, single waterproof measure and poor construction effect are solved by a pressure grouting mode. According to the processing method provided by the application, the filler is arranged at the boundary of the concrete area poured firstly to form the step-shaped groove to play a role similar to a water stop steel plate; arranging a pressure grouting pipe between the groove and the surface layer of the bottom plate for grouting and waterproofing; waterproof coating tape setting and surface seepage centralized collection and drainage measures are carried out on the surface layer of the construction joint, and multi-azimuth seepage-proof treatment can be carried out on the construction joint from the inside to the outside. The method is simple to operate, and the hidden danger of water seepage at the construction joint of the basement bottom plate is eliminated.
Description
Technical Field
The application belongs to the technical field of constructional engineering, and particularly relates to an anti-seepage treatment method for a basement bottom plate construction joint.
Background
The construction joint refers to a joint formed between the concrete which is poured in advance and then due to the design requirement or the requirement of segmental pouring in the concrete pouring process. The construction joint is not a real existing joint, and only because the initial setting time of the first poured concrete is longer than the initial setting time or the type of the first poured concrete is different from that of the later poured concrete, a joint surface exists between the first poured concrete and the later poured concrete, and the joint surface is called as the construction joint.
According to relevant regulations of basement construction of buildings in China, construction joints are not allowed to be left in the construction of basement floors, and corresponding measures must be taken during construction to ensure that concrete of the basement floors of the buildings is continuously poured. However, in actual construction, due to construction power failure, failure of a concrete delivery pump and the like, a construction joint is formed because continuous pouring cannot be performed during concrete pouring. And the horizontal member and the vertical member in the basement can not be poured at one time due to the construction requirements of the basement of some buildings. Therefore, construction joints inevitably occur when the basement bottom plate is actually constructed.
The basement of the building is affected by self reasons and external environment, and the basement terrace is easy to damp due to the existence of the bottom plate construction joint, so that the water seepage condition is caused. The seepage problem is handled to construction joint present tradition adoption stagnant water steel sheet, increases behind the stagnant water steel sheet, meets during the gap infiltration of stagnant water steel sheet and can't ooze inwards again when water connects the gap at stubble position along new and old concrete, and the stagnant water steel sheet has played the effect of cutting off water infiltration route. Meanwhile, when water permeates along the gap between the water stop steel plate and the concrete, the water stop steel plate has a certain length, so that the permeation path of the water is also prolonged, and the waterproof effect can be achieved. However, for a construction joint or a construction cold joint in which a water-stop steel plate cannot be set due to the limitation of construction conditions or not, the conventional method is to simply clean the leakage surface and coat cement paste for treatment, and the method cannot fundamentally solve the problem of internal water seepage.
Application number in the prior art: CN 201811487810.9A foundation slab anti-leakage construction method and a building construction platform perform internal anti-leakage treatment through a pressure grouting method, and the construction platform cannot perform multi-directional protection substantially, and needs to perform grouting waterproof treatment repeatedly according to leakage conditions. Application No.: CN201721574296.3 is a basement floor water seepage treatment device, which is also used for grouting and waterproofing cracks cracked on the basement floor, and cannot be completely and effectively protected.
Disclosure of Invention
To the problems and the defects in the prior art, the application provides the anti-seepage treatment method for the basement bottom plate construction joint, and the step-shaped groove is formed by arranging the filler on the boundary of the concrete pouring area to play a role similar to a water stop steel plate; arranging a pressure grouting pipe between the groove and the surface layer of the bottom plate for grouting and waterproofing; waterproof coating tape setting and surface layer seepage water centralized collection and drainage measures are carried out on the surface layer of the construction joint, and multidirectional seepage prevention treatment can be carried out on the construction joint from the inside to the outside. The method is simple to operate, and the hidden danger of water seepage at the construction joint of the basement bottom plate is eliminated.
In order to achieve the technical effect, the following technical scheme is adopted in the application:
the utility model provides a antiseep processing method for basement bottom plate construction joint, divide into earlier concreting area and later concreting area according to basement bottom plate concreting's precedence order, and the crossing region of both is the construction joint, carries out antiseep to the construction joint after handling, carries out superstructure terrace construction to the basement bottom plate again, carries out antiseep to the construction joint and handles including following step:
s1, before a concrete pouring process of a concrete pouring area, laying a non-dismantling template net on a template boundary of the concrete pouring area in advance; embedding fillers between the non-dismantling template net and the bottom layer and the surface layer of the steel bars in the thickness direction, wherein the non-dismantling template net forms a step shape above and below the fillers;
s2, carrying out a concrete pouring procedure on the firstly poured concrete area; after the concrete is solidified, cleaning the boundary of the concrete pouring area until a non-dismantling template net laid in advance in S1 is cleaned; simultaneously taking out the pre-buried filler; firstly, pouring the boundary of a concrete area to form a step-shaped groove; the non-dismantling formwork mesh is arranged at the boundary so that when concrete is poured behind the formwork, the leftover pieces on the mesh are embedded in the concrete to form a mechanical wedge connected with the adjacent pouring blocks. The working procedures of punching, galling and the like can be omitted during subsequent pouring, the construction period can be shortened, and the strength of the poured body is increased. The step-shaped groove is formed after pouring is finished so as to play a role of a water stop steel plate, and a water stop strip is adhered to the bottom of the groove so as to play a role of blocking water from permeating along a construction joint; the upper step and the lower step of the step-shaped structure have certain length, which is equivalent to the length of the water stop steel plate, can prolong the permeation path of water and can play a certain waterproof role.
S3, sticking a water-swelling water stop strip to the bottom of the step-shaped groove formed in the step S2; the water-swelling water stop strip is arranged to make use of the characteristic that the water stop strip swells when meeting water, so that the gap of the construction joint is completely sealed after the water stop strip swells to play a role in stopping water.
S4, installing pressure grouting pipes at intervals along the construction joint direction on the upper side of the boundary of the concrete area poured in advance; when the pressure grouting pipe is installed, the pressure grouting pipe is a hollow structure with an opening at the upper part and a closed bottom, and a plurality of guniting through holes are formed along the outer pipe wall of the pressure grouting pipe; the installation depth of the pressure grouting pipe is at least greater than the depth of the upper step of the stepped groove. The arrangement is that a pressure grouting plugging layer is formed between the groove and the surface layer of the bottom plate of the construction joint, and a further waterproof effect is achieved.
S5, performing a concrete pouring process on the post-pouring concrete area, wherein a micro-expanding agent needs to be added into the poured concrete; firstly, pouring a concrete area and then pouring an intersection area of the concrete area to form a substantial construction joint; the micro-expansive concrete is poured in the post-pouring concrete area, so that the impermeability of the post-pouring concrete area is improved, water permeates along the construction joint, and the permeation of water from the pouring area is reduced.
S6, performing a base layer cleaning procedure on the construction joint position formed in the S5, and smearing permeable crystallization type waterproof paint on the surface of the structural layer along the construction joint position;
s7, carrying out leakage inspection on the construction joints of the bottom plate, and if leakage exists at the construction joints, carrying out pressure grouting treatment through the pressure grouting pipes pre-embedded in the S4;
s8, installing a closed drain pipe on the construction joint of the bottom plate along the direction of the construction joint; all the drainage pipes are communicated with the trench, and if the later construction joints leak, the seepage water can be guided into the trench and drained;
and S9, after the construction joints of the bottom plate are checked to be free of leakage, carrying out upper-layer building terrace construction.
Specifically, when the boundary of the concrete pouring area is cleaned in step S2, the concrete which is not well adhered to the net of the non-dismantling formwork is mainly cleaned, and after the filler is taken out, a chiseling process is required to be performed on the bottom of the stepped groove, and impurities generated during chiseling are cleaned. The operation is to chisel burrs at the bottom of the groove before the water-swelling water stop strip is adhered, so that the adhering effect is improved.
Specifically, when the water-swelling water stop strip is pasted in the S3 process, the water-swelling water stop strip is firmly pasted along the groove bottom direction by using a rolling tool, and a cement steel nail is additionally nailed at a certain distance along the groove bottom direction to assist in fixing. The arrangement is to effectively improve the fixing effect of the water stop strip.
Specifically, when the concrete pouring process is performed in the concrete pouring area after S5, the release paper of the water-swelling water stop strip in S3 needs to be removed before the concrete is poured; adding a micro-expanding agent into the poured concrete according to the addition amount of 8-10%; and after the pouring is finished, vibrating the concrete to ensure that the vibration is compact.
Specifically, when the waterproof coating is applied in S6, the waterproof coating is applied at equal intervals along both sides of the construction joint with the construction joint as the center, thereby forming a waterproof coating tape. The waterproof coating tape is arranged in order to take waterproof measures for the surface layer construction joints of the bottom plate.
Specifically, when the drain pipe is installed in S8, grooves are formed in the two sides of the waterproof coating tape along the construction joint direction; the water discharge pipe is of a semicircular structure, and the two semicircular ends of the water discharge pipe are respectively arranged in the slotted openings at the two sides of the waterproof coating tape. The arrangement is that the seepage water on the surface layer of the bottom plate is collected in a centralized way and drained to a trench for discharge.
Compared with the prior art, the beneficial effect of this application lies in:
this application sets up the filler through earlier concreting border and forms step form recess, plays the effect of stagnant water steel sheet, can effectively stop the inside especially bottom of construction joint to the effectual infiltration between the recess. On the basis, a pressure grouting pipe is arranged between the surface layer of the bottom plate and the groove to perform a pressure grouting process, so that effective waterproof treatment can be effectively performed on the construction joint at the section. On the basis, the treatment of arranging the waterproof coating tape, installing the drain pipe and draining to the trench for discharging is carried out on the construction joint on the surface layer of the bottom plate, so that the waterproof treatment can be effectively carried out on the construction joint on the surface layer. This application carries out diversified water-proof measurements through the analysis to the construction joint infiltration principle, can effectually eliminate the infiltration hidden danger of basement bottom plate construction joint department.
Drawings
FIG. 1 is a schematic view of anti-seepage treatment of a construction joint of a basement floor according to an embodiment;
FIG. 2 is a cross-sectional view of an embodiment of anti-seepage treatment for a basement floor construction joint;
FIG. 3 is a construction flow chart of the anti-seepage treatment method for the basement floor construction joint according to the embodiment.
In the figure: 1. firstly, pouring a concrete area; 2. then pouring a concrete area; 3. a cushion layer; 4. wood block; 4a, dense steel wire meshes; 5. reinforcing steel bars; 6. constructing a joint; 7. a water-swelling sealing strip when meeting water; 8. a waterproof paint tape; 9. a drain pipe; 10. grooving; 11. building a terrace; 12. a pressure grouting pipe; 13. and (4) a trench.
Detailed Description
In order that the objects and advantages of the present application will become more apparent, the present application will be described in detail with reference to the following examples. It is to be understood that the following text is merely illustrative of one or more specific embodiments of the application, and does not strictly limit the scope of the claims which specifically recite herein. In the embodiment, the basement bottom plate lower-layer cushion layer 3 is constructed, the flitch 4 is selected as a filler in the anti-leakage treatment construction, and the dense steel wire mesh 4a is selected as a disassembly-free template mesh.
Please refer to fig. 1-3, the application provides an anti-seepage processing method for a basement floor construction joint, which comprises a first concrete pouring area 1 and a second concrete pouring area 2 according to the sequence of the concrete pouring of the basement floor, wherein the crossed area of the first concrete pouring area and the second concrete pouring area is a construction joint 6, after the anti-seepage processing is carried out on the construction joint 6, the basement floor is constructed on an upper building terrace 11, and the anti-seepage processing on the construction joint 6 comprises the following steps:
s1, before the concrete pouring process of the first concrete pouring area 1, paving dense steel wire meshes 4a on the template boundary of the first concrete pouring area 1 in advance; the dense steel wire mesh 4a is embedded with the battens 4 in the thickness direction, namely between the bottom layer and the surface layer steel bars 5, and the dense steel wire mesh 4a forms a step shape above and below the battens 4;
s2, carrying out a concrete pouring procedure on the first concrete pouring area 1; after the concrete is solidified, cleaning the boundary of the concrete pouring area 1 until the dense steel wire meshes 4a laid in advance in the S1 are cleaned; simultaneously taking out the pre-buried battens 4; firstly, pouring the boundary of a concrete area 1 to form a step-shaped groove;
s3, sticking a water-swelling water stop bar 7 to the bottom of the step-shaped groove formed in the step S2;
s4, installing pressure grouting pipes 12 at intervals along the direction of the construction joint 6 on the upper side of the boundary of the first concrete pouring area 1;
s5, performing a concrete pouring process on the post-pouring concrete area 2, wherein an expanding agent needs to be slightly added into the poured concrete; firstly, pouring a concrete area 1 and then pouring a concrete area 2 to form a virtual construction joint 6;
s6, performing a base layer cleaning procedure on the position 6 of the construction joint formed in the S5, and smearing permeable crystallization type waterproof paint on the surface of the structural layer along the position of the construction joint;
s7, carrying out leakage inspection on the construction joint 6 of the bottom plate, and if leakage exists at the construction joint, carrying out pressure grouting treatment through a pressure grouting pipe 12 pre-embedded in the S4;
s8, installing a closed drain pipe 9 on the bottom plate construction joint 6 along the construction joint direction; all the drainage pipes 9 are communicated with the trench 13, and if the later construction joints 6 leak, seepage water can be guided into the trench 13 and drained; see fig. 2.
And S9, after the bottom plate construction joint 6 is checked to be free of leakage, constructing the upper building terrace 11. See section b6 of figure 3.
Further, when the boundary of the concrete pouring area 1 is cleaned in the step S2, the concrete which is not well adhered to the dense steel wire mesh 4a is mainly cleaned, after the batten 4 is taken out, a chiseling process needs to be carried out on the bottom of the step-shaped groove, and sundries generated during chiseling are cleaned. See section b1-b2 in figure 3.
Furthermore, when the procedure of sticking the water-swelling water stop bar 7 in the S3 is performed, the water-swelling water stop bar 7 is firmly stuck along the bottom direction of the groove by using a rolling tool, and a cement steel nail is additionally nailed at a certain distance in the bottom direction of the groove to assist in fixing.
Further, when the pressure grouting pipe 12 is installed in S4, the pressure grouting pipe 12 is a hollow structure with an open upper part and a closed bottom, and is provided with a plurality of guniting through holes along the outer pipe wall; the installation depth of the pressure grouting pipe 12 is at least greater than the depth of the upper step of the stepped groove. See section b2 of figure 3.
Further, when the concrete pouring process is performed in the concrete pouring area 2 after the step S5, before the concrete is poured, the release paper of the water-swelling water stop strip 7 in the step S3 needs to be removed; adding a micro-expanding agent into the poured concrete according to the addition amount of 8-10%; and after the pouring is finished, vibrating the concrete to ensure that the vibration is compact. See section b3 of figure 3.
Further, when the waterproof coating is applied in S6, the waterproof coating is applied at equal intervals along both sides of the construction joint 6 with the construction joint 6 as the center, to form a waterproof coating tape 8. See section b4 of figure 3.
Further, when the drain pipe 9 is installed in S8, grooves are formed on both sides of the waterproof coating tape 8 along the direction of the construction joint 6; the water discharge pipe 9 is of a semicircular structure, and two semicircular ends of the water discharge pipe are respectively arranged in the notches 10 at two sides of the waterproof coating tape. See section b5 of figure 3.
The working principle is as follows: through the antiseep processing method for basement bottom plate construction joint that this application provided, groundwater begins from lower floor's bed course and follows construction joint 6 when upwards permeating, when permeating to step form recess, the lower step and the upper step of recess have certain length, have prolonged the infiltration route, and reducible water continues upwards to permeate. Meanwhile, the water-swelling water stop strip 7 at the bottom of the groove plays a main water stopping role. If water can continue to permeate upwards along the construction joint 6 through the groove, a grouting anti-seepage layer for performing a pressure grouting process through the pressure grouting pipe 12 can be encountered, and the layer can further reduce the continuous upward permeation of water. Even if water can continuously permeate to the surface layer of the bottom plate, the water-proof coating strip 8 can be met, and finally the water seepage formed in the water discharge pipe 9 can be drained to a trench to be discharged, so that the seepage cannot be caused to the upper building terrace 11. The water seepage problem of the basement of the building is effectively guaranteed. The method is simple to operate and has a high-efficiency waterproof effect.
The embodiments of the present application have been described in detail with reference to the examples, but the present application is not limited to the embodiments, and those skilled in the art can make various equivalent changes and substitutions without departing from the principle of the present application after learning the content of the present application, and these equivalent changes and substitutions should be considered as belonging to the protection scope of the present application.
Claims (6)
1. The utility model provides a antiseep processing method for basement bottom plate construction joint, divide into according to basement bottom plate concreting's precedence order and pour concrete area earlier and back, the crossing region between them is the construction joint promptly, right the construction joint carries out antiseep processing back, carries out superstructure terrace construction, its characterized in that to the basement bottom plate again: the anti-leakage treatment of the construction joint comprises the following steps:
s1, before a concrete pouring process of a concrete pouring area, laying a non-dismantling template net on a template boundary of the concrete pouring area in advance; the non-dismantling template net is pre-buried with fillers in the thickness direction, namely between the bottom layer and the surface layer steel bars, and forms a step shape up and down on the fillers;
s2, performing a concrete pouring procedure on the concrete pouring area; after the concrete is solidified, cleaning the boundary of the concrete pouring area until the non-dismantling template net laid in advance in the S1 is cleaned; simultaneously taking out the pre-buried filler; the boundary of the concrete area is poured firstly to form a step-shaped groove;
s3, sticking a water-swelling water stop strip to the bottom of the step-shaped groove formed in the step S2;
s4, installing pressure grouting pipes at intervals along the direction of the construction joint on the upper side of the boundary of the first concrete pouring area; when the pressure grouting pipe is installed, the pressure grouting pipe is a hollow structure with an opening at the upper part and a closed bottom, and a plurality of guniting through holes are formed along the outer pipe wall of the pressure grouting pipe; the mounting depth of the pressure grouting pipe is at least greater than the depth of the upper step of the step-shaped groove;
s5, carrying out a concrete pouring process on the post-poured concrete area, wherein a micro-expanding agent needs to be added into the poured concrete; the intersection area of the first concrete pouring area and the second concrete pouring area forms the substantial construction joint;
s6, performing a base layer cleaning procedure on the construction joint position formed in the S5, and smearing permeable crystallization type waterproof paint on the surface of the structural layer along the construction joint position;
s7, carrying out leakage inspection on the construction joint of the bottom plate, and if leakage exists at the construction joint, carrying out pressure grouting treatment through a pressure grouting pipe pre-embedded in the S4;
s8, installing a closed drain pipe on the bottom plate construction joint along the construction joint direction; all the drainage pipes are communicated with the trench, and if the later construction joints leak, seepage water can be guided into the trench and drained;
and S9, after the construction joints of the bottom plate are checked to be free of leakage, carrying out upper-layer building terrace construction.
2. The anti-seepage treatment method for the basement floor construction joint as claimed in claim 1, wherein the anti-seepage treatment method comprises the following steps: when the boundary of the concrete pouring area is cleaned in the S2, the concrete which is not well adhered to the net of the non-dismantling formwork is mainly cleaned, and after the filler is taken out, a chiseling process is required to be carried out on the bottom of the step-shaped groove, and sundries generated during chiseling are cleaned.
3. The anti-seepage treatment method for the basement floor construction joint as claimed in claim 1, wherein the anti-seepage treatment method comprises the following steps: when the procedure of sticking the water-swelling water stop strip in S3 is performed, the water-swelling water stop strip is firmly stuck along the bottom direction of the groove by using a rolling tool, and a cement steel nail is additionally nailed at a certain distance along the bottom direction of the groove to assist in fixing.
4. The anti-seepage treatment method for the basement floor construction joint as claimed in claim 1, wherein the anti-seepage treatment method comprises the following steps: when the concrete pouring process is carried out in the concrete pouring area after S5, before the concrete is poured, the isolation paper of the water-swelling water stop strip in S3 needs to be removed; adding a micro-expanding agent into the poured concrete according to the addition amount of 8-10%; and after the pouring is finished, vibrating the concrete to ensure that the vibration is compact.
5. The anti-seepage treatment method for the basement floor construction joint as claimed in claim 1, wherein the anti-seepage treatment method comprises the following steps: and when the waterproof coating is coated in the step S6, the waterproof coating is coated at equal intervals along two sides of the construction joint by taking the construction joint as the center to form a waterproof coating belt.
6. The anti-seepage treatment method for the basement floor construction joint as claimed in claim 5, wherein the anti-seepage treatment method comprises the following steps: when a drain pipe is installed in S8, grooves are formed in two sides of the waterproof coating tape along the direction of a construction joint; the water discharge pipe is of a semicircular structure, and the semicircular two ends of the water discharge pipe are respectively arranged in the slotted openings at the two sides of the waterproof coating tape.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110452872.1A CN113186985B (en) | 2021-04-26 | 2021-04-26 | Anti-seepage treatment method for basement bottom plate construction joint |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110452872.1A CN113186985B (en) | 2021-04-26 | 2021-04-26 | Anti-seepage treatment method for basement bottom plate construction joint |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113186985A CN113186985A (en) | 2021-07-30 |
CN113186985B true CN113186985B (en) | 2022-10-14 |
Family
ID=76979386
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110452872.1A Active CN113186985B (en) | 2021-04-26 | 2021-04-26 | Anti-seepage treatment method for basement bottom plate construction joint |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113186985B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114232693B (en) * | 2021-12-09 | 2023-10-24 | 中国一冶集团有限公司 | Waterproof outer wall and construction method |
CN114718122A (en) * | 2022-03-16 | 2022-07-08 | 中国五冶集团有限公司 | Method for anti-seepage treatment of new and old structure underground corridor foundation connection construction joint |
CN115217156A (en) * | 2022-08-25 | 2022-10-21 | 苏州建设(集团)规划建筑设计院有限责任公司 | Waterproof structure at joint of new concrete and old concrete and construction method thereof |
CN115233720A (en) * | 2022-08-28 | 2022-10-25 | 中建八局第一建设有限公司 | Super-thick radiation-proof raft plate L-shaped construction joint structure and construction method |
CN115419293A (en) * | 2022-09-19 | 2022-12-02 | 四川正大未来建筑科技有限公司 | Structure and process for repairing leakage gap between kitchen and toilet in minimally invasive manner |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU2003903547A0 (en) * | 2003-07-10 | 2003-07-24 | Neoferma Australia Pty Ltd | Structures and methods of waterproofing same |
CN203160283U (en) * | 2013-02-22 | 2013-08-28 | 中国建筑材料科学研究总院 | Construction of horizontal construction joints of underground building waterproof outer walls |
CN109440951B (en) * | 2018-11-28 | 2024-03-01 | 山东汇通建设集团有限公司 | Waterproof structure for joint of new and old concrete structures and construction process |
CN110439035B (en) * | 2019-07-19 | 2021-05-11 | 中国十七冶集团有限公司 | Seepage-proofing construction method for post-cast strip of underground chamber floor |
CN112376620A (en) * | 2020-11-16 | 2021-02-19 | 中铁隧道局集团有限公司 | Waterproof treatment method for side wall of underground building structure by reverse construction joint |
-
2021
- 2021-04-26 CN CN202110452872.1A patent/CN113186985B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN113186985A (en) | 2021-07-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113186985B (en) | Anti-seepage treatment method for basement bottom plate construction joint | |
CN101403218B (en) | Processing method for basement water-proof concrete construction joint | |
CN107326940B (en) | basement advanced water stop post-cast strip structure and construction method thereof | |
CN106988440B (en) | Waterproof structure for main body and auxiliary interface of subway station and construction method of waterproof structure | |
CN105862873A (en) | Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit | |
CN104947719A (en) | Basement roof post-cast strip hanging support formwork structure and post-cast strip construction method thereof | |
CN102912945B (en) | Roof compound seepage-proofing steam exhausting hole detail treatment technology | |
CN113585351A (en) | Soil covering plane settlement post-cast strip prefabrication advanced reverse order closed construction method | |
CN210713552U (en) | Roof structure with inverted concrete slab protection layer | |
CN112609746B (en) | New and old basement joint concrete waterproof component and construction method thereof | |
CN214460602U (en) | Waterproof structure for existing building basement bottom plate construction joint | |
CN205954707U (en) | Leading enclosed construction in basement outer wall post -cast strip | |
CN212427842U (en) | Roof high-low span deformation joint cast-in-place cover plate sealing structure | |
CN112459115A (en) | Construction method for rebuilding basement exterior wall of existing building | |
CN110439035A (en) | A kind of basement bottom plate rear pouring tape Seepage method | |
CN109518769A (en) | A kind of method and structure using PVC waterstop joint installation sewer pipe | |
CN112610022B (en) | Old building translation construction method near deep foundation pit | |
CN103510547A (en) | Basement concrete horizontal construction joint waterproof structure and construction method | |
TW451019B (en) | Water-proof and damp-proof method for basement side wall | |
CN217379011U (en) | Basement bottom plate post-cast strip structure of prevention of seepage water | |
CN112302045A (en) | Construction method of foundation beam side vertical face waterproof structure | |
CN104818835A (en) | Toilet threshold stone waterproof structure and construction method | |
CN220704790U (en) | Super early closed construction structure of basement roof post-cast strip | |
CN203546760U (en) | Waterproof structure of horizontal construction joint of concrete of basement | |
CN204609233U (en) | Washroom threshold stone waterproof construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |