CN109518769A - A kind of method and structure using PVC waterstop joint installation sewer pipe - Google Patents
A kind of method and structure using PVC waterstop joint installation sewer pipe Download PDFInfo
- Publication number
- CN109518769A CN109518769A CN201811549815.XA CN201811549815A CN109518769A CN 109518769 A CN109518769 A CN 109518769A CN 201811549815 A CN201811549815 A CN 201811549815A CN 109518769 A CN109518769 A CN 109518769A
- Authority
- CN
- China
- Prior art keywords
- pvc
- floor
- waterstop joint
- pipeline
- sewer pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009434 installation Methods 0.000 title claims abstract description 22
- 238000000034 method Methods 0.000 title claims abstract description 18
- 238000010276 construction Methods 0.000 claims abstract description 10
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 8
- 239000010959 steel Substances 0.000 claims abstract description 8
- 238000005266 casting Methods 0.000 claims abstract description 6
- 238000007789 sealing Methods 0.000 claims abstract description 6
- 239000002390 adhesive tape Substances 0.000 claims abstract description 5
- 238000007596 consolidation process Methods 0.000 claims abstract description 4
- 238000005034 decoration Methods 0.000 claims description 8
- 239000000463 material Substances 0.000 abstract description 4
- 238000009435 building construction Methods 0.000 description 4
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 230000000903 blocking effect Effects 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000008447 perception Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03C—DOMESTIC PLUMBING INSTALLATIONS FOR FRESH WATER OR WASTE WATER; SINKS
- E03C1/00—Domestic plumbing installations for fresh water or waste water; Sinks
- E03C1/12—Plumbing installations for waste water; Basins or fountains connected thereto; Sinks
- E03C1/122—Pipe-line systems for waste water in building
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/48—Special adaptations of floors for incorporating ducts, e.g. for heating or ventilating
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Environmental & Geological Engineering (AREA)
- Civil Engineering (AREA)
- Electromagnetism (AREA)
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Sewage (AREA)
Abstract
The invention discloses a kind of method and structure using PVC waterstop joint installation sewer pipe, the present invention constructs according to the following steps: the nozzle of PVC waterstop joint being sealed with adhesive tape, and is fixed on the steel mesh of floor and positions;Carry out floor concrete casting;The sealing tape that PVC waterstop joint will be removed after the concrete of floor consolidation, installs PVC pipeline.The present invention not only solves the problems, such as that the prior art takes a lot of work, takes material and the quality purpose that is difficult to ensure, while also achieving energy-saving material-saving, reducing cost.It is applicable in the installation of civic building architecture indoor plastic drainage pipeline, can be accelerated construction progress.
Description
Technical field
The present invention relates to a kind of method and structure using PVC waterstop joint installation sewer pipe, belong to pipe installation technology
Field.
Background technique
At present in building construction electromechanical installation, after drainage system still uses reserving hole using plastic drainage pipeline
The conventional mounting mode for adding steel sleeve will increase the project amount of structure box out mouth, then carry out secondary pour.The construction method is not only
Undesirable element is leaked in the presence of taking a lot of work, taking material, long construction period and the secondary cannula structure plate that pours, the perception matter of engineering but will be influenced
Amount.Drainage pipeline in present most of building constructions is installed using plastic drainage pipeline, and the drainpipe of toilet uses steel
The mounting means of conduit crossing floor carries out the installation of drainage pipeline, there are biggish hidden leakage defect, while later period pipeline damage
Maintenance needs are destroyed after floor takes out steel sleeve and rearrange drainpipe and casing afterwards, and process is many and diverse.
Summary of the invention
The object of the present invention is to provide a kind of method and structure using PVC waterstop joint installation sewer pipe, to solve
The installation leakage problems of a large amount of plastic drainage pipeline passing through floors in building construction, thus overcome the deficiencies in the prior art.
To achieve the above object, the present invention adopts the following technical scheme:
A kind of method using PVC waterstop joint installation sewer pipe of the invention is that this method is constructed according to the following steps: by PVC
The nozzle of waterstop joint is sealed with adhesive tape, and is fixed on the steel mesh of floor and is positioned;Carry out floor concrete casting;To floor
The sealing tape that PVC waterstop joint will be removed after concrete consolidation, installs PVC pipeline.
In preceding method, after the PVC pipeline is installed, concrete building plate top surface carry out screed-coat, waterproof layer and
Facing decoration construction.
A kind of structure using PVC waterstop joint installation sewer pipe of the invention constituted according to the above method, including pour
Build the PVC waterstop joint in floor;The PVC pipeline through floor is equipped in PVC waterstop joint, floor top surface is successively set from the bottom to top
There are screed-coat, waterproof layer and facing decoration.
By adopting the above-described technical solution, the present invention is compared with prior art: the present invention is for traditional reserving hole
Afterwards plus the installation of steel sleeve, secondary hole of hanging optimize, and utilize the formed by integrally casting of pre-buried PVC finished product waterstop joint and structural slab
The innovation and application of globality.It not only solves the problems, such as to take a lot of work, take material and guarantee both quality and quantity, while also achieving energy-saving material-saving, low
Cost installation.It is applicable in the installation of civic building architecture indoor plastic drainage pipeline, can accelerate construction progress, reach cost efficiency
Purpose.
Detailed description of the invention
Fig. 1 is application example schematic diagram of the invention.
In the figure, it is marked as 1- floor, 2-PVC waterstop joint, 3-PVC pipeline, 4- screed-coat, 5- waterproof layer, 6- facing decoration,
7- toilet interface, 8- platform basin interface, 9- floor drain interface, 10- furred ceiling.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.
A kind of method using PVC waterstop joint installation sewer pipe of the invention, as shown in Figure 1, this method presses following step
Rapid construction: the nozzle of PVC waterstop joint is sealed with adhesive tape, and is fixed on the steel mesh of floor and positions;Carry out floorslab concrete
It pours;The sealing tape that PVC waterstop joint will be removed after the concrete of floor consolidation, installs PVC pipeline.PVC pipeline installs
Cheng Hou carries out screed-coat, waterproof layer and facing decoration construction in concrete building plate top surface.
A kind of structure using PVC waterstop joint installation sewer pipe of the invention constituted according to the above method, such as Fig. 1 institute
Show, including the PVC waterstop joint 2 being cast in floor 1;The PVC pipeline 3 through floor 1 is equipped in PVC waterstop joint 2, floor 1 pushes up
Face is successively arranged screed-coat 4, waterproof layer 5 and facing decoration 6 from the bottom to top.
Embodiment
PVC waterstop joint is carried out sealing protection using adhesive tape by this example, can prevent from blocking PVC sealing in concreting
Section;PVC waterstop joint can be prevented from being displaced when casting concrete by iron wire with the reinforcing bar binding and fixing in concrete, it is fixed
Reliably;Selection is poured with PVC waterstop joint when carrying out floor concrete casting and is integrated, leak risk can be reduced;PVC pipeline
Matched PVC waterstop joint is poured when installing PVC pipeline without carrying out second coagulation soil;After PVC pipeline is installed, in floor
Top surface carries out construction of leveling blanket, and carries out preventing layer from constructing at the top of screed-coat, then applies preventing layer top surface from carrying out facing decoration
Work.The mounting means of the present invention and jacketed pipe after traditional plastic drainage stack reserving hole.Not only solve take a lot of work, take material and
It guarantees both quality and quantity, the secondary leakage problem poured in floor slab pipeline root, while also achieving the high efficiency, low of PVC pipeline installation
Cost installation.It suitable for the installation of plastic drainage pipeline passing through floors in building construction room, can accelerate construction progress, reach drop originally
The purpose of synergy.
Claims (3)
1. a kind of method using PVC waterstop joint installation sewer pipe, it is characterised in that: this method is constructed according to the following steps: 1.
The nozzle of PVC waterstop joint is sealed with adhesive tape, and is fixed on the steel mesh of floor and positions;2. carrying out floor concrete casting;
3. the sealing tape of PVC waterstop joint will be removed after the concrete of floor consolidation, PVC pipeline is installed.
2. method according to claim 1, it is characterised in that: after the PVC pipeline is installed, in concrete building plate top surface
Carry out screed-coat, waterproof layer and facing decoration construction.
3. the structure using PVC waterstop joint installation sewer pipe that a kind of method according to claim 1 or claim 2 is constituted, including
The PVC waterstop joint (2) being cast in floor (1);It is characterized by: being equipped with the PVC through floor (1) in PVC waterstop joint (2)
Pipeline (3), floor (1) top surface are successively arranged screed-coat (4), waterproof layer (5) and facing decoration (6) from the bottom to top.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811549815.XA CN109518769A (en) | 2018-12-18 | 2018-12-18 | A kind of method and structure using PVC waterstop joint installation sewer pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811549815.XA CN109518769A (en) | 2018-12-18 | 2018-12-18 | A kind of method and structure using PVC waterstop joint installation sewer pipe |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109518769A true CN109518769A (en) | 2019-03-26 |
Family
ID=65796632
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811549815.XA Pending CN109518769A (en) | 2018-12-18 | 2018-12-18 | A kind of method and structure using PVC waterstop joint installation sewer pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109518769A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112252658A (en) * | 2020-11-27 | 2021-01-22 | 梁雪芽 | Wet floor heating structure and construction method thereof |
CN112982623A (en) * | 2021-03-19 | 2021-06-18 | 中国二十二冶集团有限公司 | Assembly type construction method for drainage pipeline of high-rise building |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204647576U (en) * | 2015-02-12 | 2015-09-16 | 中天建设集团有限公司 | Concrete floor pre-arranged hole mouth water sealing structure |
CN106284694A (en) * | 2016-08-30 | 2017-01-04 | 中建八局第四建设有限公司 | A kind of floor waterstop joint construction method |
JP6212606B1 (en) * | 2016-07-20 | 2017-10-11 | ヤマグチ株式会社 | Construction method of water stop structure with joint of concrete and water stop plate fixture used therefor |
-
2018
- 2018-12-18 CN CN201811549815.XA patent/CN109518769A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204647576U (en) * | 2015-02-12 | 2015-09-16 | 中天建设集团有限公司 | Concrete floor pre-arranged hole mouth water sealing structure |
JP6212606B1 (en) * | 2016-07-20 | 2017-10-11 | ヤマグチ株式会社 | Construction method of water stop structure with joint of concrete and water stop plate fixture used therefor |
CN106284694A (en) * | 2016-08-30 | 2017-01-04 | 中建八局第四建设有限公司 | A kind of floor waterstop joint construction method |
Non-Patent Citations (1)
Title |
---|
孙泽明: "PVC排水管止水节在住宅卫生间中的应用" * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112252658A (en) * | 2020-11-27 | 2021-01-22 | 梁雪芽 | Wet floor heating structure and construction method thereof |
CN112982623A (en) * | 2021-03-19 | 2021-06-18 | 中国二十二冶集团有限公司 | Assembly type construction method for drainage pipeline of high-rise building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104404985B (en) | The construction method of basement bottom plate rear pouring tape waterproof construction | |
CN113186985B (en) | Anti-seepage treatment method for basement bottom plate construction joint | |
CN205841994U (en) | A kind of new indoor drainage system combined water proof pipe collar | |
CN103015721B (en) | Leakage prevention construction method of reserved holes in kitchen and toilet | |
CN106013471B (en) | A kind of construction method of expansion joint antiseep | |
CN108301466A (en) | Integral prefabricated caisson of toilet and caisson of toilet construction and its construction method | |
CN109518769A (en) | A kind of method and structure using PVC waterstop joint installation sewer pipe | |
CN111733988A (en) | Full-penetration construction floor water interception system | |
CN103410318B (en) | Washroom pipe well water-leakage construction method | |
CN207919780U (en) | The plugging system of toilet bath room floor sewer pipe preformed hole | |
CN113404170A (en) | Waterproof structure at joint of prefabricated outer wall and cast-in-place floor slab and construction method thereof | |
CN104455757A (en) | Downcomer assembly and installation method thereof | |
CN209585309U (en) | Subsided rest room waterproof construction | |
CN204551694U (en) | A kind of pre-buried type balcony floor drain | |
CN209397671U (en) | A kind of structure using PVC waterstop joint installation sewer pipe | |
CN103835421B (en) | Leakage-proof floor and anti-seepage construction method | |
CN102900144A (en) | Undermining floor drain automatic drainage structure capable of preventing leakage of toilet | |
CN208792690U (en) | Structure of antiseep of finished product exhaust passage installation root | |
CN108589793A (en) | A kind of poured band of outer wall of basement postposition assembled advance water stop construction method | |
CN107989205A (en) | The plugging system of toilet bath room floor sewer pipe preformed hole | |
CN211923600U (en) | High-rise residential building outer wall interlude construction system of intercepting water | |
JP2001254414A (en) | Remodeling method for drain pipe penetrating concrete building frame | |
CN104775484A (en) | Water supply and drainage system of water supply and drainage integrated module and building | |
CN207685959U (en) | A kind of floor when construction for Super High intercepts water drainage arrangement | |
CN114197866A (en) | Construction method for reserved hole of drainage vertical pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190326 |