CN104404985B - The construction method of basement bottom plate rear pouring tape waterproof construction - Google Patents
The construction method of basement bottom plate rear pouring tape waterproof construction Download PDFInfo
- Publication number
- CN104404985B CN104404985B CN201410524254.3A CN201410524254A CN104404985B CN 104404985 B CN104404985 B CN 104404985B CN 201410524254 A CN201410524254 A CN 201410524254A CN 104404985 B CN104404985 B CN 104404985B
- Authority
- CN
- China
- Prior art keywords
- post
- cast strip
- concrete
- basement bottom
- bottom plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
Abstract
The present invention discloses the construction method of a kind of basement bottom plate rear pouring tape waterproof construction, belongs to building waterproofing technique field.This construction method step is as follows: bury drain header and branch drain in drainage trap underground to base plate catch pit, is then paved with graded broken stone in drainage trap and forms rubble drainage layer, then arranges mortar block and mounting base reinforcing bar in both sides, bottom, post-cast strip;Mortar block is installed in both sides, top, post-cast strip after post-cast strip side form is installed;Carrying out post-cast strip concreting after pouring both sides, post-cast strip underplate concrete, take curing concrete under the conditions of band film heat and moisture preserving, curing time is no less than 14 days.The inventive method can reduce basement bottom board water pressure, it is achieved basement bottom plate rear pouring tape water-proof function, makes concrete pouring quality be guaranteed.
Description
Technical field
The invention belongs to building waterproofing technique field, be specifically related to a kind of basement bottom plate rear pouring tape waterproof construction
Construction method.
Background technology
In big basement structure construction, need to set post-cast strip to solve differential settlement and to reduce shrinkage stress
Problem, the structure design of post-cast strip and construction technology can affect after the construction quality of whole basement structure,
Even affect normal usage function.It is main that present stage basement bottom plate rear pouring tape waterproof construction mainly uses to block up
Construction method, the construction measure of waterproof layer is set at the bottom of pre-embedded steel slab waterstop and plate in the soleplate, but underground
Room bottom plate rear pouring tape yet suffers from leakage scenarios in various degree.
Summary of the invention
The technology present in existing basement bottom plate rear pouring tape construction method that present invention aims to is asked
Topic, it is provided that the construction method of a kind of basement bottom plate rear pouring tape waterproof construction.
The construction method concrete steps of a kind of basement bottom plate rear pouring tape waterproof construction provided by the present invention are such as
Under:
(1), after blinding layer 6 has been constructed, in drainage trap, drain header 5 and branch drain 7 are buried underground
To base plate catch pit, it is paved with graded broken stone in drainage trap below post-cast strip 2 after installation and forms rubble
Drainage layer 4, then lays plastic sheeting sealing coat 9 on rubble drainage layer 4 along direction, post-cast strip 2.
(2), before base plate lower floor reinforcement installation, 2 liang, post-cast strip, side lower part arranges mortar block 8, by reinforcing bar
It is placed in the groove of described mortar block 8, after preventing in basement bottom board 1 casting process concrete to flow into
Water in band 2, then other baseplate reinforcing bar is installed.
(3) installing post-cast strip side form, post-cast strip side form 3 uses dense mesh and framework of steel reinforcement to install, close
Mesh steel wire is placed on the concrete side of basement bottom board 1, and firm with tied silk colligation;Framework of steel reinforcement and the end
Plate top bars and base plate lower floor reinforcement welding are fixed, and install sand at top bars mesh sheet post-cast strip upper position
Slurry block 8.
(4) pour both sides, post-cast strip underplate concrete, pour post-cast strip by underplate concrete job specfication requirement
Both sides concrete vibration compacting, clear up the loose concrete in both sides, post-cast strip in time and rinse well.
(5) treat that basement bottom board concrete shrinkage and building settlement are basicly stable and reach design and want seeking time
After carry out post-cast strip concreting, pour before cleaning post-cast strip 2 in foreign material and dismounting be positioned at post-cast strip
The mortar block of 2 upper positions, carries out reinforcing bar checking adjustment, waters water-wet, uses admixture micro-expanding agent
Concreting post-cast strip, abundant vibration compacting, take curing concrete under the conditions of band film heat and moisture preserving,
Curing time is no less than 14 days.
The present invention has a techniques below feature:
1, late poured band structure is simple, it is simple to constructing operation and quality control;
2, basement bottom board water pressure is reduced, it is achieved basement bottom plate rear pouring tape water-proof function;
3, without hydrops in post-cast strip, concrete pouring quality is guaranteed;
4, employing rubble drainage layer replacement post-cast strip bottom reinforcement bars concrete reinforcement structure, cancellation coil waterproof layer,
Steel plate water stopper, has saved cost, accelerating construction progress.
Accompanying drawing explanation
Fig. 1 is the post-cast strip waterproof construction schematic diagram after the inventive method construction.
In figure: 1: basement bottom board;2: post-cast strip;3: post-cast strip side form;4: rubble drainage layer;5:
Drain header;6: blinding layer;7: branch drain;8: mortar block;9: plastic sheeting sealing coat.
Detailed description of the invention
The construction procedure of basement bottom plate rear pouring tape waterproof construction provided by the present invention is specific as follows:
1, after blinding layer 6 has been constructed, in drainage trap, drain header 5 and branch drain 7 are buried underground
To base plate catch pit, drain header 5 first half is provided with the osculum of φ 8-10mm, in underground after installation
Bottom plate rear pouring tape bottom, room is paved with graded broken stone and forms rubble drainage floor 4, and macadam gradating is preferably 10-31.5;?
After on rubble drainage layer, spread a slice width 1.5m thickness 0.5mm plastic sheeting sealing coat 9 along direction, post-cast strip 2 sky.
2, before base plate steel bar binding, mortar block 8 is placed at post-cast strip, both sides lower position, by bottom layer of the reinforcing steel
Mesh sheet lower floor reinforcing bar is placed in the groove of mortar block 8, prevents coagulation in basement bottom board 1 casting process
Soil flows in post-cast strip 2, then installs other baseplate reinforcing bars.
3, post-cast strip side form 3 uses dense mesh and framework of steel reinforcement to install, and dense mesh is placed on underground
Room base plate 1 concrete side, and firm with tied silk colligation, framework of steel reinforcement and base plate top bars and base plate lower floor
Reinforcement welding is fixed, and installs mortar block 8 at top bars mesh sheet post-cast strip upper position.
4, both sides, post-cast strip 2 basement bottom board 1 coagulation is poured by underplate concrete arrangement and method for construction and code requirement
Soil vibration compacting, clear up the loose concrete in both sides, post-cast strip 2 in time and rinse well.
5, treat that basement bottom board 1 concrete shrinkage and building settlement are basicly stable, and reach design when requiring
Post-cast strip 2 concreting can be carried out after between;Foreign material in cleaning post-cast strip 2 and dismounting position before pouring
In the mortar block 8 on top, post-cast strip 2, flushing moistening of watering, and carry out reinforcing bar checking adjustment;Use
The concreting post-cast strip 2 of admixture micro-expanding agent, abundant vibration compacting;Take band film heat and moisture preserving condition
Lower curing concrete, curing time is no less than 14 days.
Claims (3)
1.The construction method of a kind of basement bottom plate rear pouring tape waterproof construction, it is characterised in that this construction method specifically comprises the following steps that
(1) after blinding layer has been constructed, drain header and branch drain is buried underground to base plate catch pit in drainage trap, it is paved with graded broken stone after installation in drainage trap below post-cast strip and forms rubble drainage layer, on rubble drainage layer, then lay plastic sheeting sealing coat along direction, post-cast strip;
(2) before base plate lower floor reinforcement installation, in post-cast strip two, side lower part arranges mortar block, is placed on by reinforcing bar in the groove of described mortar block, prevents in basement bottom board casting process in concrete inflow post-cast strip, then installs other baseplate reinforcing bar;
(3) installing post-cast strip side form, post-cast strip side form uses dense mesh and framework of steel reinforcement to install, and dense mesh is placed on the concrete side of basement bottom board, and firm with tied silk colligation;Framework of steel reinforcement is fixed with base plate top bars and base plate lower floor reinforcement welding respectively, installs mortar block at top bars mesh sheet post-cast strip upper position;
(4) pour both sides, post-cast strip underplate concrete, pour both sides, post-cast strip concrete vibration compacting by underplate concrete job specfication requirement, clear up the loose concrete in both sides, post-cast strip in time and rinse well;
(5) treat that basement bottom board concrete shrinkage and building settlement are stablized and reached design and want seeking time laggard row post-cast strip concreting, before pouring, the foreign material in cleaning post-cast strip and dismounting are positioned at the mortar block of post-cast strip upper position, carry out reinforcing bar checking and adjust, water water-wet, use the concreting post-cast strip of admixture micro-expanding agent, fully vibration compacting, takes curing concrete under the conditions of band film heat and moisture preserving, and curing time is no less than 14 days.
2.The construction method of a kind of basement bottom plate rear pouring tape waterproof construction, it is characterised in that the macadam gradating of described rubble drainage layer is 10-31.5mm.
3.According to claim 2 Described a kind of basement bottom plate rear pouring tape waterproof construction, it is characterised in that the first half of described drain header is provided with some diameter phi 8-10 mm Osculum.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410524254.3A CN104404985B (en) | 2014-10-08 | 2014-10-08 | The construction method of basement bottom plate rear pouring tape waterproof construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410524254.3A CN104404985B (en) | 2014-10-08 | 2014-10-08 | The construction method of basement bottom plate rear pouring tape waterproof construction |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104404985A CN104404985A (en) | 2015-03-11 |
CN104404985B true CN104404985B (en) | 2016-10-05 |
Family
ID=52642645
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410524254.3A Active CN104404985B (en) | 2014-10-08 | 2014-10-08 | The construction method of basement bottom plate rear pouring tape waterproof construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104404985B (en) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105133644A (en) * | 2015-08-05 | 2015-12-09 | 中国十九冶集团有限公司 | Basement terrace structure preventing water seepage |
CN105155695A (en) * | 2015-08-06 | 2015-12-16 | 中国十七冶集团有限公司 | Outer wall post-pouring strip blocking method |
CN107012893A (en) * | 2017-05-04 | 2017-08-04 | 民族建设集团有限公司 | A kind of basement bottom wall board post poured band waterproof construction and its construction method |
CN110565774B (en) * | 2019-08-23 | 2021-03-19 | 中国十七冶集团有限公司 | Construction method of basement open drainage system with weak permeability soil |
CN110644538A (en) * | 2019-10-22 | 2020-01-03 | 中联建设集团股份有限公司 | Basement side wall extra front and back pouring belt periphery protection structure |
CN111576658B (en) * | 2020-05-21 | 2021-08-31 | 武汉博宏建设有限公司 | Construction method of post-cast strip protection wall of assembled basement outer wall |
CN113006158A (en) * | 2021-02-07 | 2021-06-22 | 中铁十六局集团第一工程有限公司 | Basement bottom plate waterproof structure and construction process thereof |
CN112982459A (en) * | 2021-03-11 | 2021-06-18 | 中国二十二冶集团有限公司 | Large-area drainage construction method for strongly weathered rock substrate rich in low-pressure-bearing fracture water |
CN115262558A (en) * | 2022-07-19 | 2022-11-01 | 中建八局科技建设有限公司 | Concrete interception structure for post-cast strip and construction method thereof |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3899866B2 (en) * | 2001-08-07 | 2007-03-28 | 鹿島建設株式会社 | Joint structure of steel plate concrete structure |
KR100655384B1 (en) * | 2004-07-13 | 2006-12-08 | 엄기형 | Method of drain construction for basement |
CN202247961U (en) * | 2011-08-12 | 2012-05-30 | 武汉建工股份有限公司 | Basement back strip assembled side mold device |
CN202706064U (en) * | 2012-06-12 | 2013-01-30 | 浙江城建建设集团有限公司 | Basement and semi-basement waterproof structure |
CN103469828A (en) * | 2013-09-25 | 2013-12-25 | 浙江天力建设集团有限公司 | Construction method of hydrophobic structure of post-cast strip of bottom plate of basement |
CN103615053B (en) * | 2013-11-27 | 2016-09-28 | 温州宏源水电建设有限公司 | Monolithic reinforced concrete structure post empiricism engineering method |
CN103821181A (en) * | 2014-02-28 | 2014-05-28 | 中天建设集团有限公司 | Basement bottom plate water drainage layer construction method |
-
2014
- 2014-10-08 CN CN201410524254.3A patent/CN104404985B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN104404985A (en) | 2015-03-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104404985B (en) | The construction method of basement bottom plate rear pouring tape waterproof construction | |
US10202737B2 (en) | Free-flowing waterproofing system | |
CN105178357B (en) | Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition | |
CN106284427B (en) | A kind of basement post-pouring zone temporary leaking water earth-retaining construction method | |
CN103821181A (en) | Basement bottom plate water drainage layer construction method | |
CN203531009U (en) | Macadam layer hydrophobic structure for basement base plate | |
CN103572808A (en) | Building toilet caisson waterproof device and construction method | |
US20130186035A1 (en) | Method of basement construction | |
CN106013471A (en) | Anti-seepage construction method for expansion joint | |
CN105863089A (en) | Post-cast strip water-proof structure and treatment method | |
CN108301466A (en) | Integral prefabricated caisson of toilet and caisson of toilet construction and its construction method | |
CN109372016A (en) | Basement bottom plate rear pouring tape structure and construction method under high artesian | |
CN108638322B (en) | Prefabricated post concreting method in a kind of assembled architecture | |
CN104652495A (en) | Waterproof construction process for joint of inner support upright post of foundation pit and bottom plate | |
CN207268004U (en) | Toilet leakage protective system | |
CN102619329B (en) | Expansion restraint construction method for post-pouring belt | |
CN113404170A (en) | Waterproof structure at joint of prefabricated outer wall and cast-in-place floor slab and construction method thereof | |
CN109518769A (en) | A kind of method and structure using PVC waterstop joint installation sewer pipe | |
CN110295630A (en) | The late poured band structure of multilayer constraint antiseep | |
KR20140139217A (en) | Concrete protection wall with linear drainage functions and construction method thereof | |
CN206539353U (en) | A kind of tunnel-liner infiltration punishment is reserved to check aperture apparatus | |
CN112281860B (en) | Inner lining wall structure and construction method thereof | |
CN104455757A (en) | Downcomer assembly and installation method thereof | |
CN110565774B (en) | Construction method of basement open drainage system with weak permeability soil | |
CN208088439U (en) | Integral prefabricated caisson of toilet and caisson of toilet construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |