CN104404985A - Construction method for basement floor post-cast strip waterproofing structure - Google Patents

Construction method for basement floor post-cast strip waterproofing structure Download PDF

Info

Publication number
CN104404985A
CN104404985A CN201410524254.3A CN201410524254A CN104404985A CN 104404985 A CN104404985 A CN 104404985A CN 201410524254 A CN201410524254 A CN 201410524254A CN 104404985 A CN104404985 A CN 104404985A
Authority
CN
China
Prior art keywords
casting
ater
concrete
cast strip
post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410524254.3A
Other languages
Chinese (zh)
Other versions
CN104404985B (en
Inventor
江国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201410524254.3A priority Critical patent/CN104404985B/en
Publication of CN104404985A publication Critical patent/CN104404985A/en
Application granted granted Critical
Publication of CN104404985B publication Critical patent/CN104404985B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Abstract

The invention discloses a construction method for a basement floor post-cast strip waterproofing structure and belongs to the technical field of waterproofing of buildings. The construction method comprises the following steps: laying a main drain pipe and a branch drain pipe in a water filtering tank to a floor sump, fully laying graded broken stone in the water filtering tank to form a broken stone water filtering layer, arranging mortar stop blocks on two sides at the lower part of a post-cast strip, and mounting floor reinforcing bars; mounting mortar stop blocks on two sides at the upper part of the post-cast strip after mounting a post-cast strip side form; and pouring post-cast strip concrete after pouring floor concrete on two sides of the post-cast strip, and curing concrete under a strip-film heat and moisture preservation condition for not less than 14 days. The construction method provided by the invention can reduce water pressure of a basement floor, realizes the waterproofing function of the basement floor post-cast strip and guarantees the pouring quality of concrete.

Description

The construction method of basement bottom plate rear pouring tape waterproof construction
Technical field
The invention belongs to building waterproofing technique field, be specifically related to a kind of construction method of basement bottom plate rear pouring tape waterproof construction.
Background technology
In big basement structure construction, need to establish ater-casting to solve differential settlement and to reduce the problem of shrinkage stress, the structure design of ater-casting and construction technology can affect the construction quality of rear whole basement structure, even affect normal usage function.Present stage basement bottom plate rear pouring tape waterproof construction mainly to adopt to block up be main construction method, the construction measure of waterproofing course is set at the bottom of pre-embedded steel slab waterstop and plate in the soleplate, but still there is leakage scenarios in various degree in basement bottom plate rear pouring tape.
Summary of the invention
The object of the invention is to the technical problem for existing in existing basement bottom plate rear pouring tape construction method, a kind of construction method of basement bottom plate rear pouring tape waterproof construction is provided.
The construction method concrete steps of a kind of basement bottom plate rear pouring tape waterproof construction provided by the present invention are as follows:
(1) after foundation pad 6 has been constructed, drain header 5 and branch drain 7 to base plate sump is buried underground in drainage trap, be paved with graded broken stone in drainage trap after installation below ater-casting 2 and form rubble drainage layer 4, then on rubble drainage layer 4, lay plastic sheeting separation layer 9 along direction, ater-casting 2.
(2) before base plate lower floor reinforcement installation, in ater-casting, 2 liang of side lower parts arrange mortar block 8, are placed on by reinforcing bar in the groove of described mortar block 8, prevent concrete in basement bottom board 1 casting process from flowing in ater-casting 2, then install other baseplate reinforcing bar.
(3) install ater-casting side form, ater-casting side form 3 adopts dense mesh and cage of reinforcement to install, and dense mesh is placed on the concrete side of basement bottom board 1, and firm with tied silk colligation; Cage of reinforcement and base plate top reinforcement and base plate lower floor reinforcement welding are fixed, and install mortar block 8 at top reinforcement mesh sheet ater-casting upper position.
(4) build both sides, ater-casting underplate concrete, build both sides, ater-casting concrete and vibration compacting by the requirement of underplate concrete job specfication, clear up the loose concrete in both sides, ater-casting in time and rinse well.
(5) until basement bottom board concrete shrinkage and building settlement basicly stable and carry out ater-casting concreting after reaching the designing requirement time, foreign material before building in cleaning ater-casting 2 and dismounting are positioned at the mortar block of ater-casting 2 upper position, inspection adjustment is carried out to reinforcing bar, water water-wet, adopt the concreting ater-casting of admixture micro-expanding agent, abundant vibration compacting, take curing concrete under band film heat and moisture preserving condition, curing time is no less than 14 days.
The present invention has following technical characterstic:
1, late poured band structure is simple, constructability operation and quality control;
2, reduce basement bottom board water pressure, realize basement bottom plate rear pouring tape water-proof function;
3, in ater-casting without ponding, concrete pouring quality is guaranteed;
4, adopt rubble drainage layer to substitute ater-casting bottom reinforcement bars concrete and strengthen structure, cancel coil waterproof layer, steel plate water stopper, saved cost, accelerating construction progress.
Accompanying drawing explanation
Fig. 1 is the ater-casting waterproof construction schematic diagram after the inventive method construction.
In figure: 1: basement bottom board; 2: ater-casting; 3: ater-casting side form; 4: rubble drainage layer; 5: drain header; 6: foundation pad; 7: branch drain; 8: mortar block; 9: plastic sheeting separation layer.
Detailed description of the invention
The construction sequence of basement bottom plate rear pouring tape waterproof construction provided by the present invention is specific as follows:
1, after foundation pad 6 has been constructed, drain header 5 and branch drain 7 to base plate sump is buried underground in drainage trap, drain header 5 first half is provided with the drain hole of φ 8-10mm, be paved with graded broken stone after installation in basement bottom plate rear pouring tape bottom and form rubble drainage layer 4, macadam gradating is preferably 10-31.5; Finally on rubble drainage layer, spread the wide 1.5m of one deck thick 0.5mm plastic sheeting separation layer 9 along direction, ater-casting 2 sky.
2, before base plate steel bar binding, mortar block 8 is placed at ater-casting, both sides lower position, bottom layer of the reinforcing steel mesh sheet lower floor reinforcing bar is placed in the groove of mortar block 8, prevents concrete in basement bottom board 1 casting process from flowing in ater-casting 2, then other baseplate reinforcing bars are installed.
3, ater-casting side form 3 adopts dense mesh and cage of reinforcement to install, dense mesh is placed on basement bottom board 1 concrete side, and it is firm with tied silk colligation, cage of reinforcement and base plate top reinforcement and base plate lower floor reinforcement welding are fixed, and install mortar block 8 at top reinforcement mesh sheet ater-casting upper position.
4, build both sides, ater-casting 2 basement bottom board 1 concrete and vibration compacting by underplate concrete constructure scheme and code requirement, clear up the loose concrete in both sides, ater-casting 2 in time and rinse well.
5, treat basement bottom board 1 concrete shrinkage and building settlement basicly stable, and can ater-casting 2 concreting be carried out after reaching the designing requirement time; Foreign material before building in cleaning ater-casting 2 and dismounting are positioned at the mortar block 8 on top, ater-casting 2, and watering, it is wetting to rinse, and carry out inspection adjustment to reinforcing bar; Adopt the concreting ater-casting 2 of admixture micro-expanding agent, abundant vibration compacting; Take curing concrete under band film heat and moisture preserving condition, curing time is no less than 14 days.

Claims (3)

1. a construction method for basement bottom plate rear pouring tape waterproof construction, is characterized in that these construction method concrete steps are as follows:
(1) after foundation pad has been constructed, drain header and branch drain is buried underground to base plate sump in drainage trap, be paved with graded broken stone in drainage trap after installation below ater-casting and form rubble drainage layer, then on rubble drainage layer, lay plastic sheeting separation layer along direction, ater-casting;
(2) before base plate lower floor reinforcement installation, in ater-casting two, side lower part arranges mortar block, is placed on by reinforcing bar in the groove of described mortar block, prevents concrete in basement bottom board casting process from flowing in ater-casting, then installs other baseplate reinforcing bar;
(3) install ater-casting side form, ater-casting side form adopts dense mesh and cage of reinforcement to install, and dense mesh is placed on the concrete side of basement bottom board, and firm with tied silk colligation; Cage of reinforcement and base plate top reinforcement and base plate lower floor reinforcement welding are fixed, and install mortar block at top reinforcement mesh sheet ater-casting upper position;
(4) build both sides, ater-casting underplate concrete, build both sides, ater-casting concrete and vibration compacting by the requirement of underplate concrete job specfication, clear up the loose concrete in both sides, ater-casting in time and rinse well;
(5) until basement bottom board concrete shrinkage and building settlement basicly stable and carry out ater-casting concreting after reaching the designing requirement time, foreign material before building in cleaning ater-casting and dismounting are positioned at the mortar block of ater-casting upper position, inspection adjustment is carried out to reinforcing bar, water water-wet, adopt the concreting ater-casting of admixture micro-expanding agent, abundant vibration compacting, take curing concrete under band film heat and moisture preserving condition, curing time is no less than 14 days.
2. the construction method of a kind of basement bottom plate rear pouring tape waterproof construction according to claim 1, is characterized in that the macadam gradating of described rubble drainage layer is 10-31.5mm.
3. a kind of basement bottom plate rear pouring tape waterproof construction according to claim 2, is characterized in that the first half of described drain header is provided with the drain hole of some φ 8-10mm.
CN201410524254.3A 2014-10-08 2014-10-08 The construction method of basement bottom plate rear pouring tape waterproof construction Active CN104404985B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410524254.3A CN104404985B (en) 2014-10-08 2014-10-08 The construction method of basement bottom plate rear pouring tape waterproof construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410524254.3A CN104404985B (en) 2014-10-08 2014-10-08 The construction method of basement bottom plate rear pouring tape waterproof construction

Publications (2)

Publication Number Publication Date
CN104404985A true CN104404985A (en) 2015-03-11
CN104404985B CN104404985B (en) 2016-10-05

Family

ID=52642645

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410524254.3A Active CN104404985B (en) 2014-10-08 2014-10-08 The construction method of basement bottom plate rear pouring tape waterproof construction

Country Status (1)

Country Link
CN (1) CN104404985B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105133644A (en) * 2015-08-05 2015-12-09 中国十九冶集团有限公司 Basement terrace structure preventing water seepage
CN105155695A (en) * 2015-08-06 2015-12-16 中国十七冶集团有限公司 Outer wall post-pouring strip blocking method
CN107012893A (en) * 2017-05-04 2017-08-04 民族建设集团有限公司 A kind of basement bottom wall board post poured band waterproof construction and its construction method
CN110565774A (en) * 2019-08-23 2019-12-13 中国十七冶集团有限公司 Construction method of basement open drainage system with weak permeability soil
CN111576658A (en) * 2020-05-21 2020-08-25 武汉博宏建设有限公司 Construction method of post-cast strip protection wall of assembled basement outer wall
CN112982459A (en) * 2021-03-11 2021-06-18 中国二十二冶集团有限公司 Large-area drainage construction method for strongly weathered rock substrate rich in low-pressure-bearing fracture water
CN113006158A (en) * 2021-02-07 2021-06-22 中铁十六局集团第一工程有限公司 Basement bottom plate waterproof structure and construction process thereof
CN115262558A (en) * 2022-07-19 2022-11-01 中建八局科技建设有限公司 Concrete interception structure for post-cast strip and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030029111A1 (en) * 2001-08-07 2003-02-13 Akio Yabuuchi Joint structure of steel plate concrete structure
KR20060005466A (en) * 2004-07-13 2006-01-18 엄기형 Method of drain construction for basement
CN202247961U (en) * 2011-08-12 2012-05-30 武汉建工股份有限公司 Basement back strip assembled side mold device
CN202706064U (en) * 2012-06-12 2013-01-30 浙江城建建设集团有限公司 Basement and semi-basement waterproof structure
CN103469828A (en) * 2013-09-25 2013-12-25 浙江天力建设集团有限公司 Construction method of hydrophobic structure of post-cast strip of bottom plate of basement
CN103615053A (en) * 2013-11-27 2014-03-05 温州宏源水电建设有限公司 Construction method for post-cast belt of cast-in-place reinforced concrete structure
CN103821181A (en) * 2014-02-28 2014-05-28 中天建设集团有限公司 Basement bottom plate water drainage layer construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030029111A1 (en) * 2001-08-07 2003-02-13 Akio Yabuuchi Joint structure of steel plate concrete structure
KR20060005466A (en) * 2004-07-13 2006-01-18 엄기형 Method of drain construction for basement
CN202247961U (en) * 2011-08-12 2012-05-30 武汉建工股份有限公司 Basement back strip assembled side mold device
CN202706064U (en) * 2012-06-12 2013-01-30 浙江城建建设集团有限公司 Basement and semi-basement waterproof structure
CN103469828A (en) * 2013-09-25 2013-12-25 浙江天力建设集团有限公司 Construction method of hydrophobic structure of post-cast strip of bottom plate of basement
CN103615053A (en) * 2013-11-27 2014-03-05 温州宏源水电建设有限公司 Construction method for post-cast belt of cast-in-place reinforced concrete structure
CN103821181A (en) * 2014-02-28 2014-05-28 中天建设集团有限公司 Basement bottom plate water drainage layer construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
朱日新: "地下室底板后浇带施工", 《中国科技信息》 *
胡贵仓: "地下室底板后浇带施工技术措施", 《建筑技术》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105133644A (en) * 2015-08-05 2015-12-09 中国十九冶集团有限公司 Basement terrace structure preventing water seepage
CN105155695A (en) * 2015-08-06 2015-12-16 中国十七冶集团有限公司 Outer wall post-pouring strip blocking method
CN107012893A (en) * 2017-05-04 2017-08-04 民族建设集团有限公司 A kind of basement bottom wall board post poured band waterproof construction and its construction method
CN110565774A (en) * 2019-08-23 2019-12-13 中国十七冶集团有限公司 Construction method of basement open drainage system with weak permeability soil
CN111576658A (en) * 2020-05-21 2020-08-25 武汉博宏建设有限公司 Construction method of post-cast strip protection wall of assembled basement outer wall
CN111576658B (en) * 2020-05-21 2021-08-31 武汉博宏建设有限公司 Construction method of post-cast strip protection wall of assembled basement outer wall
CN113006158A (en) * 2021-02-07 2021-06-22 中铁十六局集团第一工程有限公司 Basement bottom plate waterproof structure and construction process thereof
CN112982459A (en) * 2021-03-11 2021-06-18 中国二十二冶集团有限公司 Large-area drainage construction method for strongly weathered rock substrate rich in low-pressure-bearing fracture water
CN115262558A (en) * 2022-07-19 2022-11-01 中建八局科技建设有限公司 Concrete interception structure for post-cast strip and construction method thereof

Also Published As

Publication number Publication date
CN104404985B (en) 2016-10-05

Similar Documents

Publication Publication Date Title
CN104404985A (en) Construction method for basement floor post-cast strip waterproofing structure
CN105178357B (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN106013228B (en) A kind of overlapping monoblock type pipe gallery prefabricated assembly structural and its construction method
CN106284427B (en) A kind of basement post-pouring zone temporary leaking water earth-retaining construction method
CN105401605B (en) Deformation joint structure and its construction method
CN205776348U (en) A kind of overlapping monoblock type pipe gallery prefabricated assembly structural
CN204343339U (en) A kind of temporary support columns waterproof base plate
CN203531009U (en) Macadam layer hydrophobic structure for basement base plate
CN107574842A (en) Basement post-pouring zone advance water stop construction method
CN104805870A (en) Construction method for first soil filling and then casting at settlement post-cast strip of top plate of basement
CN202830989U (en) Semi-general formula of induced joint system for underground structure reinforced concrete wall
CN208280185U (en) A kind of post-cast strip advanced water-stopping construction
CN106284412A (en) A kind of prefabricated pipe gallery and construction method
CN110219458A (en) A kind of waterproof integrated equipment room floor construction method of sound insulation and noise reducing
CN103161176B (en) Tower crane foundation construction method in main building disjunctor garage
US20140250803A1 (en) Apparatus and method of basement construction
CN110318543A (en) The building construction method that integration pours
CN108560586A (en) Half prefabricated assembled pipe gallery and its construction method
CN107299678B (en) A kind of fabricated structure
CN108301466A (en) Integral prefabricated caisson of toilet and caisson of toilet construction and its construction method
CN108560588A (en) Assembled pipe gallery and its construction method
CN108638322B (en) Prefabricated post concreting method in a kind of assembled architecture
CN106948502A (en) A kind of water-proof top cover and its construction method
CN104652495A (en) Waterproof construction process for joint of inner support upright post of foundation pit and bottom plate
CN108240045A (en) A kind of compound late poured band structure of outer wall precast slab and its construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant