CN104404985A - Construction method for basement floor post-cast strip waterproofing structure - Google Patents
Construction method for basement floor post-cast strip waterproofing structure Download PDFInfo
- Publication number
- CN104404985A CN104404985A CN201410524254.3A CN201410524254A CN104404985A CN 104404985 A CN104404985 A CN 104404985A CN 201410524254 A CN201410524254 A CN 201410524254A CN 104404985 A CN104404985 A CN 104404985A
- Authority
- CN
- China
- Prior art keywords
- casting
- ater
- concrete
- post
- pouring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 26
- 238000004078 waterproofing Methods 0.000 title abstract description 3
- 239000004567 concrete Substances 0.000 claims abstract description 33
- 238000005266 casting Methods 0.000 claims abstract description 23
- 239000004570 mortar (masonry) Substances 0.000 claims abstract description 15
- 230000002787 reinforcement Effects 0.000 claims abstract description 11
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 10
- 238000009434 installation Methods 0.000 claims abstract 3
- 239000003795 chemical substances by application Substances 0.000 claims description 3
- 239000004575 stone Substances 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 2
- 230000003014 reinforcing effect Effects 0.000 claims 3
- 238000004140 cleaning Methods 0.000 claims 1
- 238000007689 inspection Methods 0.000 claims 1
- 238000000926 separation method Methods 0.000 claims 1
- 238000003466 welding Methods 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 5
- 230000014759 maintenance of location Effects 0.000 abstract description 3
- 238000009415 formwork Methods 0.000 abstract description 2
- 238000009413 insulation Methods 0.000 abstract description 2
- 229910000831 Steel Inorganic materials 0.000 description 18
- 239000010959 steel Substances 0.000 description 18
- 238000002955 isolation Methods 0.000 description 3
- 239000002985 plastic film Substances 0.000 description 3
- 229920006255 plastic film Polymers 0.000 description 3
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004321 preservation Methods 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000009736 wetting Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
本发明公开一种地下室底板后浇带防水结构的施工方法,属于建筑防水技术领域。该施工方法步骤如下:在滤水槽内埋设排水主管以及排水支管至底板集水坑,然后在滤水槽内铺满级配碎石形成碎石滤水层,然后在后浇带下部两侧设置砂浆挡块以及安装底板钢筋;安装后浇带侧模后在后浇带上部两侧安装砂浆挡块;浇筑后浇带两侧底板混凝土后进行后浇带混凝土浇筑,采取带膜保温保湿条件下养护混凝土,养护时间不少于14天。本发明方法能够降低地下室底板水压力,实现地下室底板后浇带防水功能,使混凝土浇筑质量得到保证。
The invention discloses a construction method for a post-cast waterproof structure of a basement bottom plate, which belongs to the technical field of building waterproofing. The steps of the construction method are as follows: bury the drainage main pipe and the drainage branch pipes in the filter tank to the sump of the bottom plate, then fill the filter tank with graded gravel to form a gravel filter layer, and then set mortar on both sides of the lower part of the post-casting belt Stoppers and installation of bottom slab reinforcement; after installing the post-pouring belt side formwork, install mortar blocks on both sides of the upper part of the post-pouring belt; after pouring the bottom slab concrete on both sides of the post-pouring belt, perform post-casting concrete pouring, and maintain under the condition of film insulation and moisture retention Concrete, the curing time is not less than 14 days. The method of the invention can reduce the water pressure of the bottom plate of the basement, realize the waterproof function of the post-cast belt of the bottom plate of the basement, and ensure the quality of concrete pouring.
Description
技术领域technical field
本发明属于建筑防水技术领域,具体涉及一种地下室底板后浇带防水结构的施工方法。The invention belongs to the technical field of building waterproofing, and in particular relates to a construction method for a post-cast waterproof structure of a basement bottom plate.
背景技术Background technique
在大型地下室结构施工中,需要设后浇带以解决沉降差以及减少收缩应力的问题,后浇带的结构设计和施工工艺会影响后整个地下室结构的施工质量,甚至影响正常使用功能。现阶段地下室底板后浇带防水施工主要采用以堵为主的施工方法,在底板中预埋钢板止水带和板底设置防水层的构造措施,但地下室底板后浇带仍然存在不同程度的渗漏情况。In the construction of large-scale basement structures, it is necessary to set up post-casting belts to solve the problems of poor settlement and reduce shrinkage stress. The structural design and construction technology of post-casting belts will affect the construction quality of the entire basement structure, and even affect the normal use function. At present, the waterproof construction of the basement bottom slab post-casting belt mainly adopts the construction method of plugging, and the structural measures of pre-embedding steel plate waterstops in the bottom slab and setting a waterproof layer at the bottom of the slab, but there are still different degrees of seepage in the basement bottom slab post-casting belt. leakage situation.
发明内容Contents of the invention
本发明的目的在于针对现有地下室底板后浇带施工方法中存在的技术问题,提供一种地下室底板后浇带防水结构的施工方法。The object of the present invention is to provide a construction method for the waterproof structure of the post-cast belt of the basement floor aiming at the technical problems existing in the existing construction method of the post-cast belt of the basement floor.
本发明所提供的一种地下室底板后浇带防水结构的施工方法具体步骤如下:The concrete steps of the construction method of a basement basement post-cast waterproof structure provided by the present invention are as follows:
(1)基础垫层6施工完成后,在滤水槽内埋设排水主管5以及排水支管7至底板集水坑,安装完成后在后浇带2下方的滤水槽内铺满级配碎石形成碎石滤水层4,然后在碎石滤水层4的上沿后浇带2方向铺设塑料薄膜隔离层9。(1) After the construction of the foundation cushion 6 is completed, the drainage main pipe 5 and the drainage branch pipe 7 are buried in the water filter tank to the bottom sump. Stone water filter layer 4, and then on the crushed stone water filter layer 4, a plastic film isolation layer 9 is laid along the post-casting belt 2 direction.
(2)底板下层钢筋安装前,在后浇带2两侧下部设置砂浆挡块8,将钢筋放置在所述砂浆挡块8的凹槽内,防止地下室底板1浇筑过程中混凝土流入后浇带2内,再安装其它底板钢筋。(2) Before installing the steel bars on the lower floor of the basement, set mortar stoppers 8 on the lower parts of both sides of the post-cast belt 2, and place the steel bars in the grooves of the mortar stoppers 8 to prevent concrete from flowing into the post-cast belt during the pouring process of the basement floor 1 2, and then install other bottom plate reinforcement.
(3)安装后浇带侧模,后浇带侧模3采用密目钢丝网和钢筋骨架支设,密目钢丝网放置在地下室底板1的混凝土侧,并用扎丝绑扎牢固;钢筋骨架与底板上层钢筋和底板下层钢筋焊接固定,在上层钢筋网片后浇带上部位置安装砂浆挡块8。(3) Install the post-cast belt side formwork, and the post-cast belt side form 3 is supported by a dense mesh steel wire mesh and a steel skeleton, and the dense mesh steel mesh is placed on the concrete side of the basement floor 1 and tied firmly with tie wires; the steel skeleton and the bottom floor The upper layer of steel bars and the lower layer of the bottom plate are welded and fixed, and a mortar stopper 8 is installed at the upper position of the upper layer of reinforcement mesh.
(4)浇筑后浇带两侧底板混凝土,按底板混凝土施工规范要求浇筑后浇带两侧混凝土并振捣密实,及时清理后浇带两侧松散混凝土并冲洗干净。(4) Concrete on both sides of the post-poured belt shall be poured and compacted according to the construction specifications of the bottom-slab concrete, and the loose concrete on both sides of the post-poured belt shall be cleaned and rinsed in time.
(5)待地下室底板混凝土收缩及建筑物沉降基本稳定并达到设计要求时间后进行后浇带混凝土浇筑,浇筑前清理后浇带2内的杂物以及拆除位于后浇带2上部位置的砂浆挡块,对钢筋进行检查调整,浇水润湿,采用掺加微膨胀剂的混凝土浇筑后浇带,充分振捣密实,采取带膜保温保湿条件下养护混凝土,养护时间不少于14天。(5) After the concrete shrinkage of the basement floor and the settlement of the building are basically stable and reach the design requirements, the post-pouring concrete is poured, and the sundries in the post-pouring 2 are cleaned before pouring and the mortar block located on the upper part of the post-pouring 2 is removed. block, check and adjust the steel bars, water and moisten them, use concrete mixed with micro-expansion agent to pour and then pour the belt, fully vibrate and compact, and use the film to maintain the concrete under the condition of heat preservation and moisture retention, and the curing time is not less than 14 days.
本发明具有以下技术特点:The present invention has the following technical characteristics:
1、后浇带结构简单,便于施工操作和质量控制;1. The post-pouring belt has a simple structure, which is convenient for construction operation and quality control;
2、降低地下室底板水压力,实现地下室底板后浇带防水功能;2. Reduce the water pressure of the basement floor and realize the waterproof function of the post-cast belt of the basement floor;
3、后浇带内无积水,混凝土浇筑质量有保证;3. There is no accumulated water in the post-pouring zone, and the quality of concrete pouring is guaranteed;
4、采用碎石滤水层替代后浇带底部钢筋混凝土加强结构,取消卷材防水层、钢板止水带,节约了成本,加快施工进度。4. The reinforced concrete reinforced structure at the bottom of the post-pouring belt is replaced by the gravel water filter layer, and the waterproof layer of the coiled material and the steel plate waterstop are canceled, which saves costs and speeds up the construction progress.
附图说明Description of drawings
图1为本发明方法施工后的后浇带防水结构示意图。Fig. 1 is a schematic diagram of the post-pouring tape waterproof structure after the construction of the method of the present invention.
图中:1:地下室底板;2:后浇带;3:后浇带侧模;4:碎石滤水层;5:排水主管;6:基础垫层;7:排水支管;8:砂浆挡块;9:塑料薄膜隔离层。In the figure: 1: Basement floor; 2: Post-pouring belt; 3: Post-pouring belt side form; 4: Gravel water filter layer; 5: Drainage main; 6: Foundation cushion; 7: Drainage branch pipe; 8: Mortar retaining Block; 9: plastic film isolation layer.
具体实施方式Detailed ways
本发明所提供的地下室底板后浇带防水结构的施工步骤具体如下:The construction steps of the post-cast waterproof structure of the basement floor provided by the present invention are as follows:
1、在基础垫层6施工完成后,在滤水槽内埋设排水主管5以及排水支管7至底板集水坑,排水主管5上半部设有φ8-10mm的排水孔,安装完成后在地下室底板后浇带下部铺满级配碎石形成碎石滤水层4,碎石级配宜为10-31.5;最后在碎石滤水层上沿后浇带2方向空铺一层宽1.5m厚0.5mm塑料薄膜隔离层9。1. After the construction of the foundation cushion 6 is completed, the drainage main pipe 5 and the drainage branch pipe 7 are buried in the filter tank to the bottom sump. The upper part of the drainage main pipe 5 is provided with a φ8-10mm drainage hole. The lower part of the post-pouring belt is covered with graded gravel to form a gravel filter layer 4, and the gradation of the gravel should be 10-31.5; finally, a layer 1.5m wide and 1.5m thick is laid on the gravel filter layer along the direction of the post-casting zone 2 0.5mm plastic film isolation layer9.
2、底板钢筋绑扎前,在两侧后浇带下部位置放置砂浆挡块8,将底层钢筋网片下层钢筋放置在砂浆挡块8的凹槽内,防止地下室底板1浇筑过程中混凝土流入后浇带2内,再安装其他底板钢筋。2. Before the reinforcement of the base plate is bound, place mortar stoppers 8 at the lower part of the post-pouring belts on both sides, and place the lower steel bars of the bottom reinforcement mesh in the grooves of the mortar stoppers 8 to prevent the concrete from flowing into the post-pouring during the pouring process of the basement floor 1. Inside the belt 2, install other bottom plate steel bars.
3、后浇带侧模3采用密目钢丝网和钢筋骨架支设,密目钢丝网放置在地下室底板1混凝土侧,并用扎丝绑扎牢固,钢筋骨架与底板上层钢筋和底板下层钢筋焊接固定,在上层钢筋网片后浇带上部位置安装砂浆挡块8。3. The post-cast side form 3 is supported by a dense mesh steel wire mesh and a steel skeleton. The dense mesh steel mesh is placed on the concrete side of the basement floor 1 and tied firmly with tie wires. The steel skeleton is welded to the upper and lower floors of the bottom floor. Mortar stopper 8 is installed at the upper position of the post-cast belt of the upper layer of steel mesh.
4、按底板混凝土施工方案和规范要求浇筑后浇带2两侧地下室底板1混凝土并振捣密实,及时清理后浇带2两侧松散混凝土并冲洗干净。4. According to the floor concrete construction plan and specification requirements, pour the concrete of the basement floor 1 on both sides of the post-pouring belt 2 and vibrate it compactly. Clean up the loose concrete on both sides of the post-pouring belt 2 and rinse it.
5、待地下室底板1混凝土收缩及建筑物沉降基本稳定,并达到设计要求时间后方可进行后浇带2混凝土浇筑;浇筑前清理后浇带2内的杂物以及拆除位于后浇带2上部的砂浆挡块8,浇水冲洗润湿,并对钢筋进行检查调整;采用掺加微膨胀剂的混凝土浇筑后浇带2,充分振捣密实;采取带膜保温保湿条件下养护混凝土,养护时间不少于14天。5. After the concrete shrinkage of the basement floor 1 and the settlement of the building are basically stable, and the time required by the design is reached, the concrete pouring of the post-pouring belt 2 can be carried out; Mortar stopper 8, watering, rinsing and wetting, and checking and adjustment of steel bars; pouring belt 2 after pouring concrete mixed with micro-expansion agent, fully vibrating and compacting; curing concrete under the condition of thermal insulation and moisture retention with film, the curing time is not Less than 14 days.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410524254.3A CN104404985B (en) | 2014-10-08 | 2014-10-08 | The construction method of basement bottom plate rear pouring tape waterproof construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410524254.3A CN104404985B (en) | 2014-10-08 | 2014-10-08 | The construction method of basement bottom plate rear pouring tape waterproof construction |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104404985A true CN104404985A (en) | 2015-03-11 |
CN104404985B CN104404985B (en) | 2016-10-05 |
Family
ID=52642645
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410524254.3A Active CN104404985B (en) | 2014-10-08 | 2014-10-08 | The construction method of basement bottom plate rear pouring tape waterproof construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104404985B (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105133644A (en) * | 2015-08-05 | 2015-12-09 | 中国十九冶集团有限公司 | Basement terrace structure of prevention of seepage water |
CN105155695A (en) * | 2015-08-06 | 2015-12-16 | 中国十七冶集团有限公司 | Outer wall post-pouring strip blocking method |
CN107012893A (en) * | 2017-05-04 | 2017-08-04 | 民族建设集团有限公司 | A kind of basement bottom wall board post poured band waterproof construction and its construction method |
CN110565774A (en) * | 2019-08-23 | 2019-12-13 | 中国十七冶集团有限公司 | Construction method of basement open drainage system with weak permeability soil |
CN110644538A (en) * | 2019-10-22 | 2020-01-03 | 中联建设集团股份有限公司 | Basement side wall extra front and back pouring belt periphery protection structure |
CN111576658A (en) * | 2020-05-21 | 2020-08-25 | 武汉博宏建设有限公司 | Construction method of post-cast strip protection wall of assembled basement outer wall |
CN112982459A (en) * | 2021-03-11 | 2021-06-18 | 中国二十二冶集团有限公司 | Large-area drainage construction method for strongly weathered rock substrate rich in low-pressure-bearing fracture water |
CN113006158A (en) * | 2021-02-07 | 2021-06-22 | 中铁十六局集团第一工程有限公司 | Basement bottom plate waterproof structure and construction process thereof |
CN115262558A (en) * | 2022-07-19 | 2022-11-01 | 中建八局科技建设有限公司 | Concrete interception structure for post-cast strip and construction method thereof |
CN115787747A (en) * | 2022-12-02 | 2023-03-14 | 中国二十冶集团有限公司 | Basement water-proof and drainage structure and construction method thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030029111A1 (en) * | 2001-08-07 | 2003-02-13 | Akio Yabuuchi | Joint structure of steel plate concrete structure |
KR20060005466A (en) * | 2004-07-13 | 2006-01-18 | 엄기형 | Basement floor drainage method |
CN202247961U (en) * | 2011-08-12 | 2012-05-30 | 武汉建工股份有限公司 | Basement post-cast strip assembled side form device |
CN202706064U (en) * | 2012-06-12 | 2013-01-30 | 浙江城建建设集团有限公司 | Basement and semi-basement waterproof structure |
CN103469828A (en) * | 2013-09-25 | 2013-12-25 | 浙江天力建设集团有限公司 | Construction method of hydrophobic structure of post-cast strip of bottom plate of basement |
CN103615053A (en) * | 2013-11-27 | 2014-03-05 | 温州宏源水电建设有限公司 | Construction method for post-cast belt of cast-in-place reinforced concrete structure |
CN103821181A (en) * | 2014-02-28 | 2014-05-28 | 中天建设集团有限公司 | Basement bottom plate water drainage layer construction method |
-
2014
- 2014-10-08 CN CN201410524254.3A patent/CN104404985B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030029111A1 (en) * | 2001-08-07 | 2003-02-13 | Akio Yabuuchi | Joint structure of steel plate concrete structure |
KR20060005466A (en) * | 2004-07-13 | 2006-01-18 | 엄기형 | Basement floor drainage method |
CN202247961U (en) * | 2011-08-12 | 2012-05-30 | 武汉建工股份有限公司 | Basement post-cast strip assembled side form device |
CN202706064U (en) * | 2012-06-12 | 2013-01-30 | 浙江城建建设集团有限公司 | Basement and semi-basement waterproof structure |
CN103469828A (en) * | 2013-09-25 | 2013-12-25 | 浙江天力建设集团有限公司 | Construction method of hydrophobic structure of post-cast strip of bottom plate of basement |
CN103615053A (en) * | 2013-11-27 | 2014-03-05 | 温州宏源水电建设有限公司 | Construction method for post-cast belt of cast-in-place reinforced concrete structure |
CN103821181A (en) * | 2014-02-28 | 2014-05-28 | 中天建设集团有限公司 | Basement bottom plate water drainage layer construction method |
Non-Patent Citations (2)
Title |
---|
朱日新: "地下室底板后浇带施工", 《中国科技信息》 * |
胡贵仓: "地下室底板后浇带施工技术措施", 《建筑技术》 * |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105133644A (en) * | 2015-08-05 | 2015-12-09 | 中国十九冶集团有限公司 | Basement terrace structure of prevention of seepage water |
CN105155695A (en) * | 2015-08-06 | 2015-12-16 | 中国十七冶集团有限公司 | Outer wall post-pouring strip blocking method |
CN107012893A (en) * | 2017-05-04 | 2017-08-04 | 民族建设集团有限公司 | A kind of basement bottom wall board post poured band waterproof construction and its construction method |
CN110565774A (en) * | 2019-08-23 | 2019-12-13 | 中国十七冶集团有限公司 | Construction method of basement open drainage system with weak permeability soil |
CN110644538A (en) * | 2019-10-22 | 2020-01-03 | 中联建设集团股份有限公司 | Basement side wall extra front and back pouring belt periphery protection structure |
CN111576658A (en) * | 2020-05-21 | 2020-08-25 | 武汉博宏建设有限公司 | Construction method of post-cast strip protection wall of assembled basement outer wall |
CN111576658B (en) * | 2020-05-21 | 2021-08-31 | 武汉博宏建设有限公司 | Construction method of post-cast strip protection wall of assembled basement outer wall |
CN113006158A (en) * | 2021-02-07 | 2021-06-22 | 中铁十六局集团第一工程有限公司 | Basement bottom plate waterproof structure and construction process thereof |
CN112982459A (en) * | 2021-03-11 | 2021-06-18 | 中国二十二冶集团有限公司 | Large-area drainage construction method for strongly weathered rock substrate rich in low-pressure-bearing fracture water |
CN115262558A (en) * | 2022-07-19 | 2022-11-01 | 中建八局科技建设有限公司 | Concrete interception structure for post-cast strip and construction method thereof |
CN115787747A (en) * | 2022-12-02 | 2023-03-14 | 中国二十冶集团有限公司 | Basement water-proof and drainage structure and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN104404985B (en) | 2016-10-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104404985B (en) | The construction method of basement bottom plate rear pouring tape waterproof construction | |
CN105178357B (en) | Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition | |
CN106284427B (en) | A kind of basement post-pouring zone temporary leaking water earth-retaining construction method | |
CN107326940B (en) | A kind of basement structure and construction method | |
CN105649113B (en) | The structure and construction method of a kind of basement post-pouring zone | |
CN102966114B (en) | Tower crane foundation structure and construction method thereof | |
CN110747899B (en) | Basement waterproof construction method | |
CN105401605B (en) | Deformation joint structure and its construction method | |
CN106499070B (en) | The construction method of connecting sewing between assembled architecture component and component | |
CN203531009U (en) | Basement bottom plate rubble layer hydrophobic structure | |
CN104805870A (en) | Construction method for first soil filling and then casting at settlement post-cast strip of top plate of basement | |
CN205776348U (en) | A kind of overlapping monoblock type pipe gallery prefabricated assembly structural | |
CN103410317A (en) | Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part | |
CN109736847A (en) | Primary concreting concrete inverted arch and its construction method | |
CN104631677A (en) | Construction technology for hollow super-thick concrete terrace | |
CN107574842A (en) | Basement post-pouring zone advance water stop construction method | |
CN106759354A (en) | A kind of stratified continuous pouring mode of ultra-long and ultra-thick volume of concrete foundation | |
CN104060781A (en) | Cast-in-situ cranked slab stair without seams at stair sections and construction method | |
CN103161176B (en) | Tower crane foundation construction method in main building disjunctor garage | |
CN107012893A (en) | A kind of basement bottom wall board post poured band waterproof construction and its construction method | |
CN108638322B (en) | Prefabricated post concreting method in a kind of assembled architecture | |
CN108240045A (en) | A kind of compound late poured band structure of outer wall precast slab and its construction method | |
CN212223971U (en) | Post-cast strip side-fixing inner-supporting steel plate combined template | |
CN206245730U (en) | A kind of cast-in-place pitched roof double template structure | |
CN106948502A (en) | A kind of water-proof top cover and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20150311 Assignee: Bengbu Jin'an Real Estate Co.,Ltd. Assignor: CHINA MCC17 GROUP Co.,Ltd. Contract record no.: X2024980045195 Denomination of invention: Construction method for waterproofing structure of basement floor with post pouring strip Granted publication date: 20161005 License type: Common License Record date: 20250102 |
|
EE01 | Entry into force of recordation of patent licensing contract |