CN104404985A - Construction method for basement floor post-cast strip waterproofing structure - Google Patents
Construction method for basement floor post-cast strip waterproofing structure Download PDFInfo
- Publication number
- CN104404985A CN104404985A CN201410524254.3A CN201410524254A CN104404985A CN 104404985 A CN104404985 A CN 104404985A CN 201410524254 A CN201410524254 A CN 201410524254A CN 104404985 A CN104404985 A CN 104404985A
- Authority
- CN
- China
- Prior art keywords
- casting
- ater
- concrete
- cast strip
- post
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
Abstract
The invention discloses a construction method for a basement floor post-cast strip waterproofing structure and belongs to the technical field of waterproofing of buildings. The construction method comprises the following steps: laying a main drain pipe and a branch drain pipe in a water filtering tank to a floor sump, fully laying graded broken stone in the water filtering tank to form a broken stone water filtering layer, arranging mortar stop blocks on two sides at the lower part of a post-cast strip, and mounting floor reinforcing bars; mounting mortar stop blocks on two sides at the upper part of the post-cast strip after mounting a post-cast strip side form; and pouring post-cast strip concrete after pouring floor concrete on two sides of the post-cast strip, and curing concrete under a strip-film heat and moisture preservation condition for not less than 14 days. The construction method provided by the invention can reduce water pressure of a basement floor, realizes the waterproofing function of the basement floor post-cast strip and guarantees the pouring quality of concrete.
Description
Technical field
The invention belongs to building waterproofing technique field, be specifically related to a kind of construction method of basement bottom plate rear pouring tape waterproof construction.
Background technology
In big basement structure construction, need to establish ater-casting to solve differential settlement and to reduce the problem of shrinkage stress, the structure design of ater-casting and construction technology can affect the construction quality of rear whole basement structure, even affect normal usage function.Present stage basement bottom plate rear pouring tape waterproof construction mainly to adopt to block up be main construction method, the construction measure of waterproofing course is set at the bottom of pre-embedded steel slab waterstop and plate in the soleplate, but still there is leakage scenarios in various degree in basement bottom plate rear pouring tape.
Summary of the invention
The object of the invention is to the technical problem for existing in existing basement bottom plate rear pouring tape construction method, a kind of construction method of basement bottom plate rear pouring tape waterproof construction is provided.
The construction method concrete steps of a kind of basement bottom plate rear pouring tape waterproof construction provided by the present invention are as follows:
(1) after foundation pad 6 has been constructed, drain header 5 and branch drain 7 to base plate sump is buried underground in drainage trap, be paved with graded broken stone in drainage trap after installation below ater-casting 2 and form rubble drainage layer 4, then on rubble drainage layer 4, lay plastic sheeting separation layer 9 along direction, ater-casting 2.
(2) before base plate lower floor reinforcement installation, in ater-casting, 2 liang of side lower parts arrange mortar block 8, are placed on by reinforcing bar in the groove of described mortar block 8, prevent concrete in basement bottom board 1 casting process from flowing in ater-casting 2, then install other baseplate reinforcing bar.
(3) install ater-casting side form, ater-casting side form 3 adopts dense mesh and cage of reinforcement to install, and dense mesh is placed on the concrete side of basement bottom board 1, and firm with tied silk colligation; Cage of reinforcement and base plate top reinforcement and base plate lower floor reinforcement welding are fixed, and install mortar block 8 at top reinforcement mesh sheet ater-casting upper position.
(4) build both sides, ater-casting underplate concrete, build both sides, ater-casting concrete and vibration compacting by the requirement of underplate concrete job specfication, clear up the loose concrete in both sides, ater-casting in time and rinse well.
(5) until basement bottom board concrete shrinkage and building settlement basicly stable and carry out ater-casting concreting after reaching the designing requirement time, foreign material before building in cleaning ater-casting 2 and dismounting are positioned at the mortar block of ater-casting 2 upper position, inspection adjustment is carried out to reinforcing bar, water water-wet, adopt the concreting ater-casting of admixture micro-expanding agent, abundant vibration compacting, take curing concrete under band film heat and moisture preserving condition, curing time is no less than 14 days.
The present invention has following technical characterstic:
1, late poured band structure is simple, constructability operation and quality control;
2, reduce basement bottom board water pressure, realize basement bottom plate rear pouring tape water-proof function;
3, in ater-casting without ponding, concrete pouring quality is guaranteed;
4, adopt rubble drainage layer to substitute ater-casting bottom reinforcement bars concrete and strengthen structure, cancel coil waterproof layer, steel plate water stopper, saved cost, accelerating construction progress.
Accompanying drawing explanation
Fig. 1 is the ater-casting waterproof construction schematic diagram after the inventive method construction.
In figure: 1: basement bottom board; 2: ater-casting; 3: ater-casting side form; 4: rubble drainage layer; 5: drain header; 6: foundation pad; 7: branch drain; 8: mortar block; 9: plastic sheeting separation layer.
Detailed description of the invention
The construction sequence of basement bottom plate rear pouring tape waterproof construction provided by the present invention is specific as follows:
1, after foundation pad 6 has been constructed, drain header 5 and branch drain 7 to base plate sump is buried underground in drainage trap, drain header 5 first half is provided with the drain hole of φ 8-10mm, be paved with graded broken stone after installation in basement bottom plate rear pouring tape bottom and form rubble drainage layer 4, macadam gradating is preferably 10-31.5; Finally on rubble drainage layer, spread the wide 1.5m of one deck thick 0.5mm plastic sheeting separation layer 9 along direction, ater-casting 2 sky.
2, before base plate steel bar binding, mortar block 8 is placed at ater-casting, both sides lower position, bottom layer of the reinforcing steel mesh sheet lower floor reinforcing bar is placed in the groove of mortar block 8, prevents concrete in basement bottom board 1 casting process from flowing in ater-casting 2, then other baseplate reinforcing bars are installed.
3, ater-casting side form 3 adopts dense mesh and cage of reinforcement to install, dense mesh is placed on basement bottom board 1 concrete side, and it is firm with tied silk colligation, cage of reinforcement and base plate top reinforcement and base plate lower floor reinforcement welding are fixed, and install mortar block 8 at top reinforcement mesh sheet ater-casting upper position.
4, build both sides, ater-casting 2 basement bottom board 1 concrete and vibration compacting by underplate concrete constructure scheme and code requirement, clear up the loose concrete in both sides, ater-casting 2 in time and rinse well.
5, treat basement bottom board 1 concrete shrinkage and building settlement basicly stable, and can ater-casting 2 concreting be carried out after reaching the designing requirement time; Foreign material before building in cleaning ater-casting 2 and dismounting are positioned at the mortar block 8 on top, ater-casting 2, and watering, it is wetting to rinse, and carry out inspection adjustment to reinforcing bar; Adopt the concreting ater-casting 2 of admixture micro-expanding agent, abundant vibration compacting; Take curing concrete under band film heat and moisture preserving condition, curing time is no less than 14 days.
Claims (3)
1. a construction method for basement bottom plate rear pouring tape waterproof construction, is characterized in that these construction method concrete steps are as follows:
(1) after foundation pad has been constructed, drain header and branch drain is buried underground to base plate sump in drainage trap, be paved with graded broken stone in drainage trap after installation below ater-casting and form rubble drainage layer, then on rubble drainage layer, lay plastic sheeting separation layer along direction, ater-casting;
(2) before base plate lower floor reinforcement installation, in ater-casting two, side lower part arranges mortar block, is placed on by reinforcing bar in the groove of described mortar block, prevents concrete in basement bottom board casting process from flowing in ater-casting, then installs other baseplate reinforcing bar;
(3) install ater-casting side form, ater-casting side form adopts dense mesh and cage of reinforcement to install, and dense mesh is placed on the concrete side of basement bottom board, and firm with tied silk colligation; Cage of reinforcement and base plate top reinforcement and base plate lower floor reinforcement welding are fixed, and install mortar block at top reinforcement mesh sheet ater-casting upper position;
(4) build both sides, ater-casting underplate concrete, build both sides, ater-casting concrete and vibration compacting by the requirement of underplate concrete job specfication, clear up the loose concrete in both sides, ater-casting in time and rinse well;
(5) until basement bottom board concrete shrinkage and building settlement basicly stable and carry out ater-casting concreting after reaching the designing requirement time, foreign material before building in cleaning ater-casting and dismounting are positioned at the mortar block of ater-casting upper position, inspection adjustment is carried out to reinforcing bar, water water-wet, adopt the concreting ater-casting of admixture micro-expanding agent, abundant vibration compacting, take curing concrete under band film heat and moisture preserving condition, curing time is no less than 14 days.
2. the construction method of a kind of basement bottom plate rear pouring tape waterproof construction according to claim 1, is characterized in that the macadam gradating of described rubble drainage layer is 10-31.5mm.
3. a kind of basement bottom plate rear pouring tape waterproof construction according to claim 2, is characterized in that the first half of described drain header is provided with the drain hole of some φ 8-10mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410524254.3A CN104404985B (en) | 2014-10-08 | 2014-10-08 | The construction method of basement bottom plate rear pouring tape waterproof construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410524254.3A CN104404985B (en) | 2014-10-08 | 2014-10-08 | The construction method of basement bottom plate rear pouring tape waterproof construction |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104404985A true CN104404985A (en) | 2015-03-11 |
CN104404985B CN104404985B (en) | 2016-10-05 |
Family
ID=52642645
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410524254.3A Active CN104404985B (en) | 2014-10-08 | 2014-10-08 | The construction method of basement bottom plate rear pouring tape waterproof construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104404985B (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105133644A (en) * | 2015-08-05 | 2015-12-09 | 中国十九冶集团有限公司 | Basement terrace structure preventing water seepage |
CN105155695A (en) * | 2015-08-06 | 2015-12-16 | 中国十七冶集团有限公司 | Outer wall post-pouring strip blocking method |
CN107012893A (en) * | 2017-05-04 | 2017-08-04 | 民族建设集团有限公司 | A kind of basement bottom wall board post poured band waterproof construction and its construction method |
CN110565774A (en) * | 2019-08-23 | 2019-12-13 | 中国十七冶集团有限公司 | Construction method of basement open drainage system with weak permeability soil |
CN111576658A (en) * | 2020-05-21 | 2020-08-25 | 武汉博宏建设有限公司 | Construction method of post-cast strip protection wall of assembled basement outer wall |
CN112982459A (en) * | 2021-03-11 | 2021-06-18 | 中国二十二冶集团有限公司 | Large-area drainage construction method for strongly weathered rock substrate rich in low-pressure-bearing fracture water |
CN113006158A (en) * | 2021-02-07 | 2021-06-22 | 中铁十六局集团第一工程有限公司 | Basement bottom plate waterproof structure and construction process thereof |
CN115262558A (en) * | 2022-07-19 | 2022-11-01 | 中建八局科技建设有限公司 | Concrete interception structure for post-cast strip and construction method thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030029111A1 (en) * | 2001-08-07 | 2003-02-13 | Akio Yabuuchi | Joint structure of steel plate concrete structure |
KR20060005466A (en) * | 2004-07-13 | 2006-01-18 | 엄기형 | Method of drain construction for basement |
CN202247961U (en) * | 2011-08-12 | 2012-05-30 | 武汉建工股份有限公司 | Basement back strip assembled side mold device |
CN202706064U (en) * | 2012-06-12 | 2013-01-30 | 浙江城建建设集团有限公司 | Basement and semi-basement waterproof structure |
CN103469828A (en) * | 2013-09-25 | 2013-12-25 | 浙江天力建设集团有限公司 | Construction method of hydrophobic structure of post-cast strip of bottom plate of basement |
CN103615053A (en) * | 2013-11-27 | 2014-03-05 | 温州宏源水电建设有限公司 | Construction method for post-cast belt of cast-in-place reinforced concrete structure |
CN103821181A (en) * | 2014-02-28 | 2014-05-28 | 中天建设集团有限公司 | Basement bottom plate water drainage layer construction method |
-
2014
- 2014-10-08 CN CN201410524254.3A patent/CN104404985B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030029111A1 (en) * | 2001-08-07 | 2003-02-13 | Akio Yabuuchi | Joint structure of steel plate concrete structure |
KR20060005466A (en) * | 2004-07-13 | 2006-01-18 | 엄기형 | Method of drain construction for basement |
CN202247961U (en) * | 2011-08-12 | 2012-05-30 | 武汉建工股份有限公司 | Basement back strip assembled side mold device |
CN202706064U (en) * | 2012-06-12 | 2013-01-30 | 浙江城建建设集团有限公司 | Basement and semi-basement waterproof structure |
CN103469828A (en) * | 2013-09-25 | 2013-12-25 | 浙江天力建设集团有限公司 | Construction method of hydrophobic structure of post-cast strip of bottom plate of basement |
CN103615053A (en) * | 2013-11-27 | 2014-03-05 | 温州宏源水电建设有限公司 | Construction method for post-cast belt of cast-in-place reinforced concrete structure |
CN103821181A (en) * | 2014-02-28 | 2014-05-28 | 中天建设集团有限公司 | Basement bottom plate water drainage layer construction method |
Non-Patent Citations (2)
Title |
---|
朱日新: "地下室底板后浇带施工", 《中国科技信息》 * |
胡贵仓: "地下室底板后浇带施工技术措施", 《建筑技术》 * |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105133644A (en) * | 2015-08-05 | 2015-12-09 | 中国十九冶集团有限公司 | Basement terrace structure preventing water seepage |
CN105155695A (en) * | 2015-08-06 | 2015-12-16 | 中国十七冶集团有限公司 | Outer wall post-pouring strip blocking method |
CN107012893A (en) * | 2017-05-04 | 2017-08-04 | 民族建设集团有限公司 | A kind of basement bottom wall board post poured band waterproof construction and its construction method |
CN110565774A (en) * | 2019-08-23 | 2019-12-13 | 中国十七冶集团有限公司 | Construction method of basement open drainage system with weak permeability soil |
CN111576658A (en) * | 2020-05-21 | 2020-08-25 | 武汉博宏建设有限公司 | Construction method of post-cast strip protection wall of assembled basement outer wall |
CN111576658B (en) * | 2020-05-21 | 2021-08-31 | 武汉博宏建设有限公司 | Construction method of post-cast strip protection wall of assembled basement outer wall |
CN113006158A (en) * | 2021-02-07 | 2021-06-22 | 中铁十六局集团第一工程有限公司 | Basement bottom plate waterproof structure and construction process thereof |
CN112982459A (en) * | 2021-03-11 | 2021-06-18 | 中国二十二冶集团有限公司 | Large-area drainage construction method for strongly weathered rock substrate rich in low-pressure-bearing fracture water |
CN115262558A (en) * | 2022-07-19 | 2022-11-01 | 中建八局科技建设有限公司 | Concrete interception structure for post-cast strip and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN104404985B (en) | 2016-10-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104404985A (en) | Construction method for basement floor post-cast strip waterproofing structure | |
CN105178357B (en) | Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition | |
CN106013228B (en) | A kind of overlapping monoblock type pipe gallery prefabricated assembly structural and its construction method | |
CN106284427B (en) | A kind of basement post-pouring zone temporary leaking water earth-retaining construction method | |
CN105401605B (en) | Deformation joint structure and its construction method | |
CN205776348U (en) | A kind of overlapping monoblock type pipe gallery prefabricated assembly structural | |
CN204343339U (en) | A kind of temporary support columns waterproof base plate | |
CN203531009U (en) | Macadam layer hydrophobic structure for basement base plate | |
CN107574842A (en) | Basement post-pouring zone advance water stop construction method | |
CN104805870A (en) | Construction method for first soil filling and then casting at settlement post-cast strip of top plate of basement | |
CN202830989U (en) | Semi-general formula of induced joint system for underground structure reinforced concrete wall | |
CN208280185U (en) | A kind of post-cast strip advanced water-stopping construction | |
CN106284412A (en) | A kind of prefabricated pipe gallery and construction method | |
CN110219458A (en) | A kind of waterproof integrated equipment room floor construction method of sound insulation and noise reducing | |
CN103161176B (en) | Tower crane foundation construction method in main building disjunctor garage | |
US20140250803A1 (en) | Apparatus and method of basement construction | |
CN110318543A (en) | The building construction method that integration pours | |
CN108560586A (en) | Half prefabricated assembled pipe gallery and its construction method | |
CN107299678B (en) | A kind of fabricated structure | |
CN108301466A (en) | Integral prefabricated caisson of toilet and caisson of toilet construction and its construction method | |
CN108560588A (en) | Assembled pipe gallery and its construction method | |
CN108638322B (en) | Prefabricated post concreting method in a kind of assembled architecture | |
CN106948502A (en) | A kind of water-proof top cover and its construction method | |
CN104652495A (en) | Waterproof construction process for joint of inner support upright post of foundation pit and bottom plate | |
CN108240045A (en) | A kind of compound late poured band structure of outer wall precast slab and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |