CN105862873B - Deep basal pit narrow space underground waterproof and external wall structure construction method - Google Patents
Deep basal pit narrow space underground waterproof and external wall structure construction method Download PDFInfo
- Publication number
- CN105862873B CN105862873B CN201610226325.0A CN201610226325A CN105862873B CN 105862873 B CN105862873 B CN 105862873B CN 201610226325 A CN201610226325 A CN 201610226325A CN 105862873 B CN105862873 B CN 105862873B
- Authority
- CN
- China
- Prior art keywords
- waterproof
- construction
- external wall
- deep basal
- basal pit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Paleontology (AREA)
- Physics & Mathematics (AREA)
- Life Sciences & Earth Sciences (AREA)
- Electromagnetism (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
A kind of deep basal pit narrow space underground waterproof and external wall structure construction method, for the project under construction of downtown area narrow field deep basal pit, fertile groove concrete is poured using the outer single side formwork of slope protection pile first, form the waterproof construction scope of operation of outer anti-interior patch while also solve fertile groove backfill problem, then external wall structure construction is carried out using single side formwork again, solve at this in particular cases because insufficient space can not carry out waterproof outside exterior wall, fertile groove backfill, the problem of underground waterproof coiled material and outer wall of underground structure are constructed, it can effectively ensure that outer wall of basement waterproof construction smoothly deploys, prevent leakage scenarios.Sequence of construction of the present invention is clear, and construction waterproof works well.
Description
Technical field
The present invention relates to deep basal pit underground waterproof and external wall structure construction field, particularly a kind of depth under narrow space
Foundation ditch underground waterproof and external wall structure construction method.
Background technology
At present, the construction of small space deep basal pit underground waterproof mainly faces problems with specific condition:
(1), on the premise of the maximization of building area is pursued by construction unit, downtown area and building are intensive
Area has that foundation ditch area occupies scene and can use construction area more than 90%.Such situation is usually associated with ultra-deep foundation pit
In the presence of, the construction deviation of slope protection pile and design and construction face is narrow and small so that underground external wall waterproof construction becomes very difficult, slope protection pile
Traditionally the advanced behavior external wall structure construction of Waterproof Construction Technique carries out existing during the technique of waterproof paving again after the completion of construction:
Waterproof construction personnel are unable to reach operating surface and are constructed, can not set up waterproof operation shelf, waterproof construction quality and should not ensure
Etc. problems.
(2), the construction technology of between slope protection pile and outer wall of underground structure building solid wall by laying bricks or stones solves to a certain extent
Some problems, but the neither energy-conserving and environment-protective of this method(Solid brick has been stepped into superseded material register)People is wasted again
Work(Build by laying bricks or stones time consuming with plastering construction construction), a most important problem is masonry panel as the side form of underground external wall one
Certain risk be present in plate.
(3)Even if, another problem be exactly underground external wall waterproof and external wall structure construction after the completion of fertile slot part backfill
Work and a difficult point of later stage work, the selection of backfilling material first, according to traditional 2:8 dirt, backfill leakiness
It is unreliable to backfill quality, the waterproof effect for also in a disguised form reducing exterior wall is directly toppled over according to sand(2:8 dirt still belong to construct
One kind of waterproof), backfilled according to normal concrete, due to pouring excessive height, it is possible to fish tail and waterproof layer or masonry wall
Body damages, and then produces destruction to waterproof.
(4)If, be considered as concrete fertile groove backfilled in advance, be considered as fertile groove concrete one side formwork and install
Problem, how to ensure the flatness of fill concrete surface layer and perpendicularity be this construction emphasis.
Therefore, a kind of can solve in deep basal pit because insufficient space can not carry out asking for external wall waterproof construction is needed at present
Topic, will also solve the problems, such as structure outer formwork construction, the method for needing also exist for solving the problems, such as backfill in fertile groove.
The content of the invention
The present invention provides a kind of deep basal pit narrow space underground waterproof and external wall structure construction method, to solve small space
Constructing operation inconvenience existing for deep basal pit underground waterproof and external wall structure construction, waste of materials and it is artificial, waterproof quality is bad
Technical problem, and fertile groove concrete topping flatness and perpendicularity it is difficult to ensure that technical problem.
The technical solution adopted for the present invention to solve the technical problems is:
This deep basal pit narrow space underground waterproof and external wall structure construction method, construction procedure are as follows:
Step 1, one side mould is installed on the outside of the fertile groove first between slope protection pile and structure outer, from base in slope protection pile
Hole bottom surface is spaced punching upwards, is implanted into bar planting bolt in hole, horizontal elongated setting angle steel at bar planting between slope protection pile, angle steel and
It is welded to connect between bar planting bolt, interval welding through-wall bolt, the through-wall bolt other end pass through small punching block and fixation on angle steel;
Step 2, fertile groove concrete is poured in the one side mould inboard installed;
Step 3, when fertile groove concrete construction is completed highly to be higher than this Rotating fields exterior wall every time, suspend fertile groove coagulation soil application
Work, paving waterproof layer and fish tail and waterproof layer successively on fertile groove concrete;
Step 4, carrying out this Rotating fields exterior wall and structure roof construction, the construction of structure outer includes:Structure outer reinforcing bar
Colligation, structure outer one side formwork install and structure outer concreting;
Step 5, the outer concrete of last layer slope protection pile and waterproof construction are carried out, goes round and begins again and successively constructs.
The step 1, away from first hole is made a call at the 350mm of foundation ditch bottom surface in slope protection pile, it is spaced upwards by first hole
Second hole is made a call at 650mm~750mm.
The step 1, the bar planting bolt angle being implanted into slope protection pile is 30 degree, and bar planting depth is 200mm~300mm, is planted
Slope protection pile 200mm~400mm is stretched out on the outside of muscle bolt.
The step 1, the horizontal spacing between through-wall bolt are 700mm~800mm, through-wall bolt length be 600mm~
1000mm。
The step 1, the lap-joint between angle steel are not less than 100mm using welding and the lap of splice.
The step 2, the thickness of fertile groove concrete is 500mm~700mm, pours height every time and is no more than 1400mm.
The step 2, double operation shelf should be set up during fertile groove concreting at bed course or floor, operate shelf
Set up using steel pipe and fastener.
The step 3, waterproof layer are waterproof roll, and it is more moist such as to run into bank protection side slope, does not possess SBS waterproof rolls
During execution conditions, from polyethylene polypropylene fiber waterproof coiled material;The fish tail and waterproof layer is extruded sheet.
The step 4, structure outer one side formwork are unilateral steel joist plank sheathing band triangular form support of shaping.
The step 4, when agent structure intensity meets design requirement, remove the prestressed anchor in this layer of slope protection pile
And girder steel.
The features of the present invention and have the beneficial effect that:
The present invention is directed to the project under construction of downtown area narrow field deep basal pit, successively using the side of single side formwork twice
Formula.Single side formwork carries out fertile groove concrete construction first, while creates the outer water-proof sticking basic unit of underground external wall, solves waterproof and prevents
Water conservation layer is constructed no operatton space problem, then carries out the reinforcing bar colligation of vertical structure, single side formwork, concreting etc. again
The construction of outer wall of underground structure, at the same preferably solve deep basal pit small space underground external wall waterproof, structure construction process and
The problem of exterior wall fertilizer groove backfill construction.
The paving of waterproof layer and fish tail and waterproof layer of the present invention, it is in structure to be different from traditional external wall waterproof paving construction face
Waterproof layer and fish tail and waterproof layer are pasted onto on fertile groove concrete by the mode on the outside of exterior wall, the present invention, and fish tail and waterproof layer construction exists
Destroyed on the inside of waterproof roll, during for protecting waterproof roll not constructed by the colligation of exterior wall reinforcing bar.
Compared with prior art, this construction method it is a technical advantage that:
1st, the construction method can ensure the operability of deep basal pit small space waterproof construction simultaneously, solve this situation again
Lower fertile groove backfill problem, constructs applied to the waterproof construction in deep basal pit small space and external wall structure, can preferably protect
The construction quality of external wall waterproof coiled material is demonstrate,proved, further strengthens underground external wall integral waterproofing effect.
2nd, whole construction method construction orderliness understand, construction procedure clearly, wider, the relatively conventional settling mode of application surface
Can save it is artificial, improve efficiency of construction, reduce cost, while obtain good waterproof construction effect.
Brief description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Fig. 1 is the use condition schematic diagram of the present invention.
Fig. 2 is the top view of the fertile groove concrete support construction of the present invention.
Fig. 3 is the elevation of the fertile groove concrete support construction of the present invention.
Fig. 4 is the side view of the fertile groove concrete support construction of the present invention.
Fig. 5 is the schematic diagram that the present invention pastes waterproof layer and fish tail and waterproof layer on fertile groove concrete.
Fig. 6 is the schematic diagram of progress structure outer single side formwork after invention waterproof and protective layer construction.
Reference:1- slope protection piles, 2- prestressed anchors and girder steel, 3- structure outers, 4- structure roofs, 5- bases bottom
The small punching block of plate, 6-, 71- bar plantings bolt, 72- through-wall bolts, 8- angle steel, 9- waterproof layers and fish tail and waterproof layer, 11- fertilizer groove coagulations
Soil, 12- structure outer one side formworks.
Embodiment
Embodiment this deep basal pit narrow space underground waterproof and external wall structure construction method, is constructed referring to shown in Fig. 1-6
Step is as follows:
Referring to shown in Fig. 1-4, step 1, one side is installed on the outside of the fertile groove first between slope protection pile 1 and structure outer 3
Mould.Away from first hole is made a call at the 350mm of foundation ditch bottom surface in slope protection pile 1, being spaced 700mm upwards by first hole makes a call to second
Hole.Bar planting bolt 71 is implanted into hole, the angle of bar planting bolt 71 being implanted into slope protection pile 1 is 30 degree, and bar planting depth is 200mm,
Slope protection pile 200mm~400mm is stretched out in the outside of bar planting bolt 71.It is laterally elongated at bar planting between slope protection pile 1 that angle steel 8, angle steel 8 are set
It is welded to connect between bar planting bolt 71, the lap-joint between angle steel 8 is not less than 100mm using welding and the lap of splice.At angle
Welding through-wall bolt 72 in interval on steel 8, the other end of through-wall bolt 72 is through small punching block 6 and fixes.Horizontal stroke between through-wall bolt 72
It is 750mm to spacing, through-wall bolt length is 600mm~1000mm.
It is shown in Figure 5, step 2, fertile groove concrete 11 is poured in the one side mould inboard installed.Fertile groove concrete 11
C20 P8 concrete can be used, thickness 600mm, height is poured every time and is no more than 1400mm.Should when fertile groove concrete 11 pours
Double operation shelf is set up at bed course or floor, operation shelf is set up using steel pipe and fastener.
It is shown in Figure 5, step 3, when the fertile construction of groove concrete 11 is completed highly to be higher than this Rotating fields exterior wall 3 every time, temporarily
Stop fertile groove concrete construction, paving waterproof layer and fish tail and waterproof layer 9 successively on fertile groove concrete 11.The basic unit of waterproof layer should jail
, must not dusting, hollowing, loosening and decortication phenomenon Gu basal plane should be clean, smooth.Waterproof layer should be firmly bonded, it is tight to seal, take
Connect full size, surfacing, must not fold, alice and hollowing.Waterproof layer uses waterproof roll, and it is more damp such as to run into bank protection side slope
It is wet, when not possessing SBS waterproof coiled material construction conditions, from polyethylene polypropylene fiber waterproof coiled material.The fish tail and waterproof layer uses extrusion molding
Plate.
Shown in Figure 6, step 4, carries out this Rotating fields exterior wall 3 and structure roof 4 is constructed, the construction bag of structure outer 3
Include:The colligation of structure outer reinforcing bar, structure outer one side formwork 12 install and structure outer concreting.Structure outer one side mould
Plate 12 is unilateral steel joist plank sheathing band triangular form support of shaping.
It is shown in Figure 1, when agent structure intensity meets design requirement, remove the prestressed anchor in this layer of slope protection pile 1
Bar and girder steel 2.Must not once it remove two layers and above prestressed anchor and girder steel.
Referring to shown in Fig. 1-6, step 5, the outer concrete of last layer slope protection pile and waterproof construction are carried out, is gone round and begun again successively
Construction.
Claims (10)
1. a kind of deep basal pit narrow space underground waterproof and external wall structure construction method, it is characterised in that construction procedure is as follows:
Step 1, first in slope protection pile(1)And structure outer(3)Between fertile groove on the outside of install one side mould, in slope protection pile(1)On
Punching is spaced upwards from foundation ditch bottom surface, and bar planting bolt is implanted into hole(71), slope protection pile(1)Between laterally elongated setting at bar planting
Angle steel(8), angle steel(8)With bar planting bolt(71)Between be welded to connect, in angle steel(8)Upper interval welding through-wall bolt(72), wear
Wall screw(72)The other end passes through small punching block(6)It is and fixed;
Step 2, fertile groove concrete is poured in the one side mould inboard installed(11);
Step 3, each fertile groove concrete(11)Construction completes height and is higher than this Rotating fields exterior wall(3)When, suspend fertile groove concrete
Construction, in fertile groove concrete(11)On paving waterproof layer and fish tail and waterproof layer successively(9);
Step 4, carry out this Rotating fields exterior wall(3)And structure roof(4)Construction, structure outer(3)Construction include:Outside structure
The colligation of wall reinforcing bar, structure outer one side formwork(12)Install and structure outer concreting;
Step 5, the outer concrete of last layer slope protection pile and waterproof construction are carried out, goes round and begins again and successively constructs.
2. deep basal pit narrow space underground waterproof according to claim 1 and external wall structure construction method, it is characterised in that:
The step 1, in slope protection pile(1)On away from making a call to first hole at the 350mm of foundation ditch bottom surface, by first hole be spaced upwards 650mm~
Second hole is made a call at 750mm.
3. deep basal pit narrow space underground waterproof according to claim 1 and external wall structure construction method, it is characterised in that:
The step 1, it is implanted into slope protection pile(1)Interior bar planting bolt(71)Angle is 30 degree, and bar planting depth is 200~300mm, bar planting
Bolt(71)Slope protection pile 200mm~400mm is stretched out in outside.
4. deep basal pit narrow space underground waterproof according to claim 1 and external wall structure construction method, it is characterised in that:
The step 1, through-wall bolt(72)Between horizontal spacing be 700mm~800mm, through-wall bolt length be 600mm~
1000mm。
5. deep basal pit narrow space underground waterproof according to claim 1 and external wall structure construction method, it is characterised in that:
The step 1, angle steel(8)Between lap-joint using welding and the lap of splice be not less than 100mm.
6. deep basal pit narrow space underground waterproof according to claim 1 and external wall structure construction method, it is characterised in that:
The step 2, fertile groove concrete(11)Thickness be 500mm~700mm, pour every time height be no more than 1400mm.
7. deep basal pit narrow space underground waterproof according to claim 1 and external wall structure construction method, it is characterised in that:
The step 2, fertile groove concrete(11)Double operation shelf should be set up when pouring at bed course or floor, operation shelf uses
Steel pipe and fastener are set up.
8. deep basal pit narrow space underground waterproof according to claim 1 and external wall structure construction method, it is characterised in that:
The step 3, waterproof layer are waterproof roll, and it is more moist such as to run into bank protection side slope, does not possess SBS waterproof coiled material construction conditions
When, from polyethylene polypropylene fiber waterproof coiled material;The fish tail and waterproof layer is extruded sheet.
9. deep basal pit narrow space underground waterproof according to claim 1 and external wall structure construction method, it is characterised in that:
The step 4, structure outer one side formwork(12)For unilateral steel joist plank sheathing band triangular form support of shaping.
10. deep basal pit narrow space underground waterproof according to claim 1 and external wall structure construction method, its feature exist
In:The step 4, when agent structure intensity meets design requirement, remove this layer of slope protection pile(1)On prestressed anchor and
Girder steel(2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610226325.0A CN105862873B (en) | 2016-04-13 | 2016-04-13 | Deep basal pit narrow space underground waterproof and external wall structure construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610226325.0A CN105862873B (en) | 2016-04-13 | 2016-04-13 | Deep basal pit narrow space underground waterproof and external wall structure construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105862873A CN105862873A (en) | 2016-08-17 |
CN105862873B true CN105862873B (en) | 2017-11-10 |
Family
ID=56637212
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610226325.0A Active CN105862873B (en) | 2016-04-13 | 2016-04-13 | Deep basal pit narrow space underground waterproof and external wall structure construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105862873B (en) |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106759843A (en) * | 2016-12-27 | 2017-05-31 | 宁波二十冶建设有限公司 | A kind of outer wall of basement waterproof construction and its construction method |
CN106592754A (en) * | 2016-12-27 | 2017-04-26 | 中建四局第五建筑工程有限公司 | Method for guaranteeing waterproof construction quality of deep foundation pit basement |
CN107130631B (en) * | 2017-05-22 | 2019-03-29 | 中冶建工集团有限公司 | A kind of basement Retaining wall method based on concreting moulding wall |
CN107119695A (en) * | 2017-06-27 | 2017-09-01 | 中国建筑第二工程局有限公司 | Operation frame body for canceling basement exterior wall backfill and construction method |
CN108411950B (en) * | 2018-03-28 | 2020-11-10 | 中铁十一局集团第二工程有限公司 | Underground waterproof construction method |
CN109441099B (en) * | 2018-12-05 | 2024-01-23 | 中建一局集团建设发展有限公司 | Basement unilateral formwork supporting system and method for constructing basement outer wall by utilizing same |
CN111608185A (en) * | 2020-04-28 | 2020-09-01 | 中国二十冶集团有限公司 | Waterproof construction method for main body structure of narrow space of deep foundation pit |
CN112482555A (en) * | 2020-11-06 | 2021-03-12 | 云南建投第六建设有限公司 | Shear wall structure and construction method of shear wall |
CN112962663B (en) * | 2021-01-07 | 2022-08-12 | 司顺生 | Construction method for narrow outer enclosure space of deep foundation |
CN112982445B (en) * | 2021-02-24 | 2022-09-13 | 中建八局轨道交通建设有限公司 | Backfill method for common-structure fertilizer grooves of underground road with pipe gallery penetrating through underground |
CN113622431B (en) * | 2021-08-02 | 2023-07-21 | 江苏东合南岩土科技股份有限公司 | Underground structure with foam light soil partition wall and construction method thereof |
CN113802722B (en) * | 2021-09-23 | 2022-09-06 | 武汉建工集团股份有限公司 | Construction method for recyclable deep foundation pit and outer wall integrated structure |
CN113832986A (en) * | 2021-10-15 | 2021-12-24 | 中国二十二冶集团有限公司 | Waterproof construction method for underground outer wall in limited space in foundation pit supported by slope protection piles |
CN115059290A (en) * | 2022-07-04 | 2022-09-16 | 中国建筑第二工程局有限公司 | Reverse construction method for underground outer wall of narrow fertilizer groove |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11141126A (en) * | 1997-11-05 | 1999-05-25 | Fujita Corp | Processing method of driving joining part in reversely driving method |
CN103485365A (en) * | 2013-09-16 | 2014-01-01 | 中冶天工上海十三冶建设有限公司 | Installation method of underground concrete wall formwork of row pile supporting structure |
CN204000936U (en) * | 2014-08-28 | 2014-12-10 | 陕西建工第五建设集团有限公司 | Outer wall of basement single surface formwork system based on fastener type steel pipe earth anchor truss |
CN204357127U (en) * | 2014-12-10 | 2015-05-27 | 中建三局第一建设工程有限责任公司 | The monolateral formwork erecting structure of a kind of ultra-deep pre-buried Screw arbor with nut at both-ends of outer wall of basement narrow space |
CN204662499U (en) * | 2015-03-09 | 2015-09-23 | 江苏南通三建集团有限公司 | Concrete of basement exterior wall, waterproof, fertile groove integrated construction structure |
-
2016
- 2016-04-13 CN CN201610226325.0A patent/CN105862873B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN105862873A (en) | 2016-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105862873B (en) | Deep basal pit narrow space underground waterproof and external wall structure construction method | |
CN110607809B (en) | Waterproof construction method for basement of building engineering | |
CN107190844B (en) | The waterproof and water drainage system and construction method of a kind of basement bottom board and exterior wall | |
CN204000956U (en) | A kind of basement bottom plate rear pouring tape structure | |
CN206319910U (en) | Infiltration disposal system is reinforced in a kind of tunnel-liner | |
CN210104811U (en) | Basement pile-wall integrated waterproof structure system | |
CN207685961U (en) | Spliced drainage ditch based on corrugated pipe | |
CN209837281U (en) | Basement outer wall and bottom plate corner waterproof node | |
CN110593321B (en) | Construction method of basement outer wall post-cast strip advanced sealing prefabricated clamping groove formwork-free system | |
CN112112295A (en) | Reinforcing construction method for post-cast strip of post-sealed outer wall | |
CN207144012U (en) | A kind of post-cast strip prefabricated board barricade | |
CN212129250U (en) | Construction structure for additionally arranging collecting groove on post-cast strip of high-water-level foundation | |
CN109778916A (en) | A kind of poured band of outer wall of basement Antiseep method based on water resistant plate | |
CN205954707U (en) | Leading enclosed construction in basement outer wall post -cast strip | |
CN210766835U (en) | Foundation beam side vertical face waterproof structure | |
CN105756100A (en) | Basement post-pouring belt system and making method thereof | |
CN111608185A (en) | Waterproof construction method for main body structure of narrow space of deep foundation pit | |
CN208122041U (en) | A kind of IPS Cast-in-place concrete shear wall structure of self-heat preservation system system | |
CN103628506B (en) | Construction method for waterproof positions of foundation platform and pile head | |
CN114809000B (en) | Rapid construction method of prefabricated plate brick moulding bed | |
CN214614160U (en) | Pre-laying anti-sticking waterproof structure of ultra-deep independent foundation | |
CN206205166U (en) | It is a kind of can synchronous crossed construction outer wall of basement waterproofing protection structure | |
CN209891238U (en) | Tower crane foundation | |
CN206768879U (en) | A kind of poured band of outer wall of basement structure | |
CN209923989U (en) | Waterproof structure for basement without permanent wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |