JPH11141126A - Processing method of driving joining part in reversely driving method - Google Patents
Processing method of driving joining part in reversely driving methodInfo
- Publication number
- JPH11141126A JPH11141126A JP9320445A JP32044597A JPH11141126A JP H11141126 A JPH11141126 A JP H11141126A JP 9320445 A JP9320445 A JP 9320445A JP 32044597 A JP32044597 A JP 32044597A JP H11141126 A JPH11141126 A JP H11141126A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- floor
- concrete wall
- wall
- gap
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は床を構築した後、こ
の床を支保工として地下の根切りを行なって地下の躯体
を構築していく逆打ち工法における打ち継ぎ部の処理方
法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of treating a spliced portion in a reverse construction method in which a floor is constructed, and then the underground root is cut off using the floor as a support to construct an underground frame.
【0002】[0002]
【従来の技術】一階床を構築した後、この床を支保工と
して地下の根切りを行なって地下階の躯体を構築してい
く逆打ち工法では、床の下方で地下の根切りの後に形成
される立上りコンクリート壁は、型枠内においてその上
方からコンクリートを打設するので、先打ちコンクリー
ト壁(床の構築と共に床の周囲に形成されるコンクリー
ト壁)の下端と、立上りコンクリート壁の上端との間に
は10cm〜20cm程度の隙間が生じる。一方、建物
が完成された後は、コンクリート壁は地上階の重量を受
け、また、地下階及び地上階の建物を支える基本的な躯
体要素の一つとして機能する。そのため、先打ちコンク
リート壁の下端と、立上りコンクリート壁の上端との打
ち継ぎ部は、双方が確実に連結され一体化されている必
要があり、逆打ち工法においてコンクリート壁の打ち継
ぎ部の処理は極めて重要となる。2. Description of the Related Art In a reverse striking method in which a first-floor floor is constructed and then this floor is used as a support to perform underground excavation to construct a basement floor frame, the underground excavation is performed below the floor. The rising concrete wall to be formed casts concrete from above in the formwork, so the lower end of the pre-cast concrete wall (the concrete wall formed around the floor together with the construction of the floor) and the upper end of the rising concrete wall And a gap of about 10 cm to 20 cm is generated between them. On the other hand, after the building is completed, the concrete wall receives the weight of the ground floor and functions as one of the basic building elements supporting the building on the basement floor and the ground floor. Therefore, the joint between the lower end of the precast concrete wall and the upper end of the rising concrete wall needs to be securely connected and integrated with each other. It is extremely important.
【0003】このコンクリート壁の打ち継ぎ部の処理
は、従来、次のように行われている。まず、先打ちコン
クリート壁の下端の表面と、立上りコンクリート壁の上
端の表面との間にわたり型枠板を取り付け、先打ちコン
クリート壁の下端と立上りコンクリート壁の上端との隙
間を塞ぐ。なお、この型枠板の下端には注入口が設けら
れ、上端には空気抜き孔が設けられている。次に、前記
空気抜き孔から空気を排出しつつ注入口から前記隙間に
無収縮モルタルを注入し、所定の充填圧力をかけて無収
縮モルタルで隙間を充填する。[0003] Conventionally, the processing of the spliced portion of the concrete wall is performed as follows. First, a formwork plate is attached between the lower end surface of the pre-cast concrete wall and the upper end surface of the rising concrete wall to close a gap between the lower end of the pre-cast concrete wall and the upper end of the rising concrete wall. An injection port is provided at the lower end of the form plate, and an air vent hole is provided at the upper end. Next, non-shrinkable mortar is injected into the gap from the inlet while discharging air from the air vent hole, and a predetermined filling pressure is applied to fill the gap with the non-shrinkable mortar.
【0004】[0004]
【発明が解決しようとする課題】しかしながら上記のよ
うな従来の処理方法では、隙間に無収縮モルタルを充填
するために、型枠板の取り付け、取り外し作業を要し、
それらの作業が面倒であるという不具合があった。ま
た、無収縮モルタルの充填時の圧力管理が難しいという
不具合があった。すなわち、充填圧力が大きすぎると、
型枠が変形する(はらむ)。また、充填圧力が小さいと
無収縮モルタルが十分にいきわたらず、無収縮モルタル
と先打ちコンクリート壁との間に隙間が生じる。更に、
従来の処理方法では、無収縮モルタルの充填時に空気を
巻き込み、無収縮モルタルと先打ちコンクリ−ト壁との
間に気泡が生じるという不具合もあった。本発明は前記
事情に鑑み案出されたものであって、本発明の目的は、
先打ちコンクリート壁の下端と立上りコンクリート壁の
上端との打ち継ぎ部の処理を簡略化でき、しかも、双方
のコンクリート壁を確実に一体化できる逆打ち工法にお
ける打ち継ぎ部の処理方法を提供することにある。However, in the conventional processing method as described above, in order to fill the gap with the non-shrinkable mortar, it is necessary to mount and remove the form plate.
There was a problem that those operations were troublesome. Further, there is a problem that it is difficult to control the pressure when filling the non-shrink mortar. That is, if the filling pressure is too high,
The formwork is deformed. On the other hand, if the filling pressure is low, the non-shrink mortar does not spread sufficiently, and a gap is formed between the non-shrink mortar and the pre-cast concrete wall. Furthermore,
In the conventional processing method, there is also a problem that air is entrapped at the time of filling the non-shrink mortar and air bubbles are generated between the non-shrink mortar and the pre-cast concrete wall. The present invention has been devised in view of the above circumstances, the object of the present invention,
Disclosed is a method of treating a spliced portion in a reverse striking method, which can simplify the processing of a spliced portion between a lower end of a pre-cast concrete wall and an upper end of a rising concrete wall, and can surely integrate both concrete walls. It is in.
【0005】[0005]
【課題を解決するための手段】前記目的を達成するため
本発明は、床を構築した後、この床を支保工として地下
の根切りを行ない地下の躯体を構築していく逆打ち工法
において、床の構築と共に床の周囲に形成される先打ち
コンクリート壁の下端と、床の下方で地下の根切りの後
に形成される立上がりコンクリート壁の上端との間の隙
間に、含水率の小さいコンクリートを吹き付けて充填
し、この吹き付けられたコンクリートの表面をコテで仕
上げるようにしたことを特徴とする。また、本発明は、
前記吹き付けるコンクリートの骨材として粒径が1〜2
mm程度のものが用いられることを特徴とする。In order to achieve the above-mentioned object, the present invention relates to a reverse striking method for constructing a floor, constructing an underground skeleton by cutting the underground using the floor as a support, In the gap between the lower end of the pre-cast concrete wall formed around the floor with the construction of the floor and the upper end of the rising concrete wall formed after the underground root cutting below the floor, put concrete with a small moisture content in the gap. It is characterized by being sprayed and filled, and the surface of the sprayed concrete is finished with an iron. Also, the present invention
Particle size is 1-2 as the aggregate of the concrete to be sprayed
It is characterized in that a diameter of about mm is used.
【0006】本発明によれば、先打ちコンクリート壁の
下端と、立上りコンクリート壁の上端との間の隙間に含
水率の小さいコンクリートを吹き付けるという簡単な作
業で、双方のコンクリート壁を効率良く連結し一体化す
ることができる。また、含水率の小さいコンクリートを
隙間に充填するので、表面だれや、ブリージング、コン
クリートの沈降も生じない。また、含水率の小さいコン
クリートは気泡を巻き込むこともなく、コンクリート壁
の強度上も有利となる。According to the present invention, both concrete walls are efficiently connected by a simple operation of spraying concrete having a low water content into a gap between the lower end of the precast concrete wall and the upper end of the rising concrete wall. Can be integrated. In addition, since the gaps are filled with concrete having a low water content, there is no occurrence of surface dripping, breathing, or concrete settling. Further, concrete having a small water content does not involve air bubbles, which is advantageous in the strength of the concrete wall.
【0007】[0007]
【発明の実施の形態】以下、本発明の実施の形態を図面
を参照して説明する。図1は先打ちコンクリート壁の下
端と立上がりコンクリート壁の上端との間の隙間にコン
クリートを吹き付ける状態の説明図、図2は隙間がコン
クリートにより充填されコテにより表面が仕上げられた
状態の説明図を示す。2は地中、4はH形鋼からなる山
留め壁であり、逆打ち工法では、まず、山留め壁4の内
側で1階の床6とその周囲から下方へ突出する壁8を施
工する。1階の壁8、すなわち先打ちコンクリート壁8
を施工するに際しては、山留め壁4に対向しセパレータ
ー16を介して型枠が配置され、山留め壁4と型枠の間
の空間に鉄筋18を配筋した後、コンクリートが打設さ
れることで形成される。Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is an explanatory view of a state in which concrete is sprayed into a gap between a lower end of a pre-cast concrete wall and an upper end of a rising concrete wall, and FIG. 2 is an explanatory view of a state in which the gap is filled with concrete and the surface is finished with an iron. Show. Reference numeral 2 denotes underground, and 4 denotes a retaining wall made of H-shaped steel. In the reverse striking method, first, a floor 6 on the first floor and a wall 8 projecting downward from the periphery thereof are constructed inside the retaining wall 4. First floor wall 8, ie, pre-cast concrete wall 8
At the time of constructing, the formwork is arranged via the separator 16 in opposition to the retaining wall 4, and after reinforcing bars 18 are arranged in the space between the retaining wall 4 and the formwork, concrete is poured. It is formed.
【0008】1階の床6と先打ちコンクリート壁8が構
築されたならば、床6を支保工として床6の下方の根切
りが行われ、次に、地下1階の床と壁12が作られる。
壁12、すなわち立上がりコンクリート壁12は、山留
め壁4に対向しセパレーター16を介して型枠20が配
置され、山留め壁4と型枠20の間の空間に鉄筋18を
配筋した後、この空間に上方からコンクリートが打設さ
れることで形成される。これにより先打ちコンクリート
壁8の下端と、立上りコンクリート壁12の上端との間
には10cm〜20cm程度の隙間Sが生じる。When the floor 6 on the first floor and the pre-cast concrete wall 8 are constructed, the floor 6 is used as a support to cut off the lower part of the floor 6, and then the floor and the wall 12 on the first basement are connected. Made.
The wall 12, that is, the rising concrete wall 12 is opposed to the retaining wall 4, and the formwork 20 is disposed via the separator 16. After the reinforcing bar 18 is arranged in the space between the retaining wall 4 and the formwork 20, this space is formed. Is formed by casting concrete from above. Thereby, a gap S of about 10 cm to 20 cm is generated between the lower end of the pre-cast concrete wall 8 and the upper end of the rising concrete wall 12.
【0009】そして、本実施の形態では、まず前記隙間
Sを清掃し、次に、前記隙間Sに吹き付け機22を用い
てそのノズル2202からコンクリートを吹き付け、隙
間Sを充填する。隙間Sをコンクリートで充填したなら
ば、コンクリートの表面を定規で均し、コテで押え仕上
げを行ない、コンクリートが硬化した後、図2に示すよ
うに、先打ちコンクリート壁8の下端と、立上りコンク
リート壁12の上端との間の隙間Sは吹き付けコンクリ
ートにより連結され一体化される。なお、図2において
符号24は、隙間Sに充填されその表面が仕上げられた
コンクリートを示す。In the present embodiment, first, the gap S is cleaned, and then concrete is sprayed from the nozzle 2202 to the gap S using a spraying machine 22 to fill the gap S. When the gap S is filled with concrete, the surface of the concrete is leveled with a ruler, pressed down with a trowel, and after the concrete is hardened, as shown in FIG. The gap S between the upper end of the wall 12 and the wall S is connected and integrated by sprayed concrete. In FIG. 2, reference numeral 24 denotes concrete filled in the gap S and having a finished surface.
【0010】この場合、使用するコンクリートとしては
含水率の小さいものを用い、表面だれや、ブリージン
グ、コンクリートの沈降が発生しないようにする。ま
た、使用する骨材は、コンクリート壁の強度、コンクリ
ート硬化時の収縮、隙間Sへの充填性を考慮した場合、
約1mm程度のふるいを通過できず、約5mm程度のふ
るいを通過できる大きさのものが好ましく、本実施の形
態では、粒径が1〜2mm程度の骨材が用いられてい
る。In this case, a concrete having a low water content is used as the concrete to be used so as to prevent surface drooling, breathing and sedimentation of the concrete. In addition, the aggregate to be used, when considering the strength of the concrete wall, shrinkage during hardening of the concrete, and the filling property of the gap S,
It is preferable that the material has a size that cannot pass through a sieve of about 1 mm but can pass through a sieve of about 5 mm. In the present embodiment, an aggregate having a particle size of about 1 to 2 mm is used.
【0011】このような本実施の形態によれば、先打ち
コンクリート壁8の下端と、立上りコンクリート壁12
の上端との間の隙間Sにコンクリートを吹き付けるとい
う簡単な作業で双方のコンクリート壁8,12を効率良
く連結し一体化することができ、隙間Sに無収縮モルタ
ルを充填するために従来行われていた型枠板の取り付
け、取り外し作業を省略し、作業を簡略化して施工コス
トを低減する上で有利となる。また、含水率の小さいコ
ンクリートを隙間Sに吹き付けて充填するので、表面だ
れや、ブリージング、コンクリートの沈降も生ぜず、従
って、従来のように隙間Sに充填したモルタルの圧力管
理も要せず、施工コストを削減する上でより一層有利と
なる。また、含水率の小さいコンクリートは流動体と固
体の中間の半流動体であり、この半流動体を吹き付ける
ため気泡を巻き込むこともなく、従来のように流動体を
充填する工法とは異なって先打ちコンクリート8の下部
に気泡が生ぜす、コンクリート壁の強度上も有利とな
る。According to the present embodiment, the lower end of the pre-cast concrete wall 8 and the rising concrete wall 12
The concrete walls 8 and 12 can be efficiently connected and integrated by a simple operation of spraying concrete into the gap S between the upper end of the concrete wall and the concrete wall. This is advantageous in simplifying the work and reducing the construction cost by eliminating the work of attaching and removing the formwork plate. In addition, since the concrete having a small water content is sprayed and filled into the gap S, no surface drooping, breathing, and sedimentation of the concrete occurs, and therefore, pressure control of the mortar filled in the gap S as in the related art is not required, It is even more advantageous in reducing construction costs. In addition, concrete with a low water content is a semi-fluid intermediate between a fluid and a solid, and this semi-fluid is sprayed without air bubbles, and unlike the conventional method of filling the fluid with a conventional method. Bubbles are generated in the lower part of the cast concrete 8, which is advantageous in the strength of the concrete wall.
【0012】[0012]
【発明の効果】以上の説明で明らかなように本発明は、
床を構築した後、この床を支保工として地下の根切りを
行ない地下の躯体を構築していく逆打ち工法において、
床の構築と共に床の周囲に形成される先打ちコンクリー
ト壁の下端と、床の下方で地下の根切りの後に形成され
る立上がりコンクリート壁の上端との間の隙間に、含水
率の小さいコンクリートを吹き付けて充填し、この吹き
付けられたコンクリートの表面をコテで仕上げるように
した。そのため先打ちコンクリート壁の下端と、立上り
コンクリート壁の上端との間の隙間に含水率の小さいコ
ンクリートを吹き付けるという簡単な作業で双方のコン
クリート壁を効率良く連結し一体化することができ、ま
た、含水率の小さいコンクリートを隙間に充填するの
で、表面だれや、ブリージング、コンクリートの沈降も
生ぜず、気泡を巻き込むこともない。従って、逆打ち工
法における打ち継ぎ部の処理を簡略化でき、しかも、双
方のコンクリート壁を確実に一体化することが可能とな
る。As is clear from the above description, the present invention
After constructing the floor, in the reverse striking method to construct the underground skeleton by cutting the underground with this floor as a support,
In the gap between the lower end of the pre-cast concrete wall formed around the floor with the construction of the floor and the upper end of the rising concrete wall formed after the underground root cutting below the floor, put concrete with a small moisture content in the gap. The sprayed concrete was filled, and the surface of the sprayed concrete was finished with a trowel. Therefore, both concrete walls can be efficiently connected and integrated by a simple operation of spraying concrete having a low water content into the gap between the lower end of the pre-cast concrete wall and the upper end of the rising concrete wall, Since the gaps are filled with concrete having a low water content, there is no surface drooping, breathing, sedimentation of concrete, and no air bubbles. Therefore, it is possible to simplify the processing of the spliced portion in the reverse driving method, and it is possible to reliably integrate both concrete walls.
【図1】先打ちコンクリート壁の下端と立上がりコンク
リート壁の上端との間の隙間にコンクリートを吹き付け
る状態の説明図である。FIG. 1 is an explanatory view showing a state in which concrete is blown into a gap between a lower end of a pre-cast concrete wall and an upper end of a rising concrete wall.
【図2】隙間がコンクリートにより充填されコテにより
表面が仕上げられた状態の説明図である。FIG. 2 is an explanatory view showing a state in which a gap is filled with concrete and a surface is finished with an iron;
2 地中 4 山留め壁 6 床 8 先打ちコンクリート壁 12 立上がりコンクリート壁 S 隙間 2 Underground 4 Mountain retaining wall 6 Floor 8 Precast concrete wall 12 Upstanding concrete wall S Gap
Claims (2)
地下の根切りを行ない地下の躯体を構築していく逆打ち
工法において、 床の構築と共に床の周囲に形成される先打ちコンクリー
ト壁の下端と、床の下方で地下の根切りの後に形成され
る立上がりコンクリート壁の上端との間の隙間に、含水
率の小さいコンクリートを吹き付けて充填し、この吹き
付けられたコンクリートの表面をコテで仕上げるように
した、 ことを特徴とする逆打ち工法における打ち継ぎ部の処理
方法。Claims: 1. A reverse-casting method in which a floor is constructed, and then the floor is used as a support to cut an underground and construct an underground frame. The gap between the lower edge of the wall and the upper edge of the rising concrete wall below the floor, which is formed after the underground excavation, is filled with low-moisture content concrete by spraying, and the surface of the sprayed concrete is A method of processing a spliced part in a reverse-casting method, characterized in that the joint is finished with:
て粒径が1〜2mm程度のものが用いられる請求項1記
載の逆打ち工法における打ち継ぎ部の処理方法。2. The method for treating a spliced portion in a reverse-casting method according to claim 1, wherein the aggregate of the sprayed concrete has a particle size of about 1 to 2 mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9320445A JPH11141126A (en) | 1997-11-05 | 1997-11-05 | Processing method of driving joining part in reversely driving method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9320445A JPH11141126A (en) | 1997-11-05 | 1997-11-05 | Processing method of driving joining part in reversely driving method |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH11141126A true JPH11141126A (en) | 1999-05-25 |
Family
ID=18121538
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9320445A Pending JPH11141126A (en) | 1997-11-05 | 1997-11-05 | Processing method of driving joining part in reversely driving method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH11141126A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014224457A (en) * | 2014-09-11 | 2014-12-04 | 大成建設株式会社 | Underground structure and construction method for the same |
CN105862873A (en) * | 2016-04-13 | 2016-08-17 | 北京建工四建工程建设有限公司 | Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit |
-
1997
- 1997-11-05 JP JP9320445A patent/JPH11141126A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014224457A (en) * | 2014-09-11 | 2014-12-04 | 大成建設株式会社 | Underground structure and construction method for the same |
CN105862873A (en) * | 2016-04-13 | 2016-08-17 | 北京建工四建工程建设有限公司 | Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8959862B1 (en) | Thixotropic concrete forming system | |
CN205857530U (en) | Joint bar positioner | |
CN110145124A (en) | A kind of control shear wall level connects the reinforcement tools and its construction method of batch quality | |
JP2008127873A (en) | Block out flask, and recess forming method using the same | |
JPH08296243A (en) | Construction method for underground structure by precast concrete central pillar | |
JPH11141126A (en) | Processing method of driving joining part in reversely driving method | |
JPH0579049A (en) | Constructing method for beam and slab in underground body construction work | |
GB1400277A (en) | Process for the erection of concrete constructions | |
JP3214809B2 (en) | Ground treatment method in slope construction | |
JP2581209B2 (en) | Concrete casting method | |
JP2699819B2 (en) | Construction method of precast reinforced concrete foundation block | |
JP2002356854A (en) | Method for building concrete wall using floor slab of building | |
JP2980792B2 (en) | Column and concrete slab joining method | |
KR100298629B1 (en) | Method for constructing the stairway of a building and precasting finishing materials | |
JPH07331871A (en) | Method for constructing concrete foundation | |
JPS62253821A (en) | Construction of concrete floor slab | |
JP2903937B2 (en) | Concrete splicing method | |
JP4045623B2 (en) | Construction method of reinforced concrete underground floor and underground structure constructed by this method | |
JPH0651979B2 (en) | Reverse winding concrete method | |
JP4059413B2 (en) | Formwork mounting apparatus for building a frame and method for building a frame using the same | |
JPS6245370B2 (en) | ||
JPS6062328A (en) | Treatment of head of cast-in-place pile | |
JPH1072838A (en) | Charging method of void of concrete joint in inverted construction method | |
JP2003041576A (en) | Composite underground continuous wall and construction method of the wall | |
JPS5927024A (en) | Construction of continuous underground wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20041014 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050811 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050823 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20051228 |