JPS5927024A - Construction of continuous underground wall - Google Patents

Construction of continuous underground wall

Info

Publication number
JPS5927024A
JPS5927024A JP13594682A JP13594682A JPS5927024A JP S5927024 A JPS5927024 A JP S5927024A JP 13594682 A JP13594682 A JP 13594682A JP 13594682 A JP13594682 A JP 13594682A JP S5927024 A JPS5927024 A JP S5927024A
Authority
JP
Japan
Prior art keywords
wall
underground wall
iron bar
construction
trench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13594682A
Other languages
Japanese (ja)
Inventor
Masamitsu Kikuchi
菊池 正光
Shinichi Nagao
真一 長尾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP13594682A priority Critical patent/JPS5927024A/en
Publication of JPS5927024A publication Critical patent/JPS5927024A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To smoothly finish up the wall of an on-site RC continuous underground wall by a method in which an iron bar cage whose inside is attached with a precast concrete slab for set iron bar reinforcement is inserted into a trench and then concrete is placed into the cage. CONSTITUTION:A 5-6cm thick precast concrete slab 9 for set iron bar reinforcement is integrally attached to the inside face of an iron bar cage 8 inserted. The iron bar cage 8 is inserted into the trench, and concrete 1 is placed between the precast concrete slab 9 and the trench wall 5, whereupon an RC continuous underground wall having a given smooth face is constructed. Since the surface of the underground wall is smooth, the underground wall can be utilized as it is as formwork material having improved function and also as base material for outside water-proofing work.

Description

【発明の詳細な説明】 この発明は連続地下壁の構築工法に係わる。[Detailed description of the invention] This invention relates to a construction method for continuous underground walls.

場所打RO連続地下壁の壁面は土層より表面に土砂の付
着、溝壁のくずれ等による凹凸が発生する。
The wall surface of a continuous underground wall of cast-in-place RO is uneven due to the adhesion of earth and sand to the surface from the soil layer and the collapse of the trench wall.

その為、躯体施工時や防水下地工事の際、壁面のケレン
、折りの必要となる。
For this reason, it is necessary to clean and fold the walls when constructing the frame or waterproofing the groundwork.

又、防水工事の時は2モルタル下地塗等の作業をも要し
ているのが現状である。
In addition, the current situation is that waterproofing work requires work such as applying a second mortar base coat.

すなわち、電1図イ図に示す如く、場所打RO連続地下
壁1の壁面は2表面に土砂の付着、溝壁のくずれ等によ
る凹凸2が通常発生する。
That is, as shown in Figure 1A, the wall surface of the cast-in-place RO continuous underground wall 1 usually has unevenness 2 due to the adhesion of earth and sand, collapse of the trench wall, etc.

このままでは、地下階の外壁躯体施工工事や外防水下地
工事に差し支えるので2足場3を組み。
If things continue as they are, it will interfere with the construction of the exterior wall structure on the basement floor and the exterior waterproofing groundwork, so two and three scaffolds will be erected.

作業者4が壁面のケレン、祈りをとり行って、四面に示
す如く平滑化せねばならない。
Worker 4 must clean and clean the wall surface and smooth it as shown on the four sides.

尚2図中5は背面土砂層を示す。Note that 5 in Figure 2 indicates the back soil layer.

壁面に防水工事を施こす場合には、へ図に示す如くモル
タル下地塗6を要し、この上に外防水層7が施こされる
としているのが現状である。
When carrying out waterproofing work on a wall surface, the current situation is that a mortar base coat 6 is required as shown in Figure 1, and an outer waterproof layer 7 is applied on top of this.

この為、仮設足場架払し等の作業負担が増加し。As a result, the burden of work such as removing temporary scaffolding increased.

工期が延び、又、コストも過大なものとなる。The construction period will be extended and the cost will be excessive.

そこで、値上の如き面倒な平滑化修正作業を省略り得る
手段として、溝壁自体であるプレキャストコンクリート
版を連続壁溝内に挿入する施工技術もあるが2重量物と
なって深さが10?FL程度までの対応技術にすぎず、
その水以深には適応できないという難点を有する。
Therefore, as a means to omit the troublesome smoothing correction work that would increase the price, there is a construction technique that inserts a precast concrete slab, which is the trench wall itself, into the continuous wall trench, but it is a 2-heavy object and has a depth of 10 mm. ? It is only a technology that supports FL level,
It has the disadvantage that it cannot be adapted to depths beyond that level.

本発明は、値上の事情に雌みなされたもので。This invention was considered a failure due to price reasons.

溝深さによって制約されることもなく、かつ、壁面修正
工事の必要なくして場所打RO連続壁の壁面を平滑に仕
上げ、そのまま型枠材としての機能の向上、外防水工事
の下地として活用し得るようにしたもので、その特徴は
、鉄筋篭の内側面に薄肉の組立鉄筋補強のプレキャスト
コンクリート版を取利けて、溝内に挿入したところにあ
る。
It is not limited by the groove depth, and without the need for wall surface modification work, it can finish the wall surface of cast-in-place RO continuous walls smoothly, improve its function as a formwork material, and use it as a base for external waterproofing work. Its feature is that a precast concrete plate reinforced with prefabricated thin walls is taken from the inner surface of the rebar cage and inserted into the groove.

以下、これの詳細を図にもとづいて説明する。Details of this will be explained below based on the drawings.

すなわち、第2図イ図は2本発明に於ける溝内挿入鉄筋
篭8を示し、これには根切側の内側面に。
That is, FIG. 2A shows the reinforcing bar cage 8 inserted into the groove according to the present invention, and there are two holes on the inner surface of the root cutting side.

例えば5〜6crn程度の薄肉の組立鉄筋補強のプレキ
ャストコンクリート版9が一体的に取付けられるが重量
的には、BA述の溝壁自体であるプレギヤストコンクリ
ート版の如く2重量的にさほどかさむことにはならない
For example, a precast concrete slab 9 with a thin wall of about 5 to 6 crn reinforced with prefabricated reinforcing steel is installed integrally, but in terms of weight, it is not very bulky, like the precast concrete slab that is the trench wall itself described in BA. It won't be.

この特殊な鉄筋篭8を溝内に挿入してコンクリートを打
設して完成したものは2口図に示す如くなり、根切りで
、プレキャストコンクリート版9の平滑面が露呈する。
This special reinforcing bar cage 8 is inserted into the groove, concrete is poured, and the completed product is shown in the two-piece drawing, and the smooth surface of the precast concrete slab 9 is exposed when the roots are cut.

しかして、付着上の洗い流し程度の簡易な手刈のみで、
そのまま地下階の外壁躯体工事に利用出来、かつ、防水
工事を施こす場合にはへ図に示す如く直ちに外防水層7
を施こせばよい。
However, with only simple manual cutting such as washing off the adhesion,
It can be used as it is for the construction of the exterior wall of the basement floor, and if waterproofing work is to be carried out, the outer waterproofing layer 7 can be used immediately as shown in the figure.
All you have to do is

値上の如く本発明によるならば、十分に吊り込み可能な
重量に挿入鉄筋篭を栴成し得ると共にコンクリートを打
設すれば、所定の平滑面をもったRO連続地下壁が構築
し得ることとなるもので。
As mentioned above, according to the present invention, an RO continuous underground wall with a predetermined smooth surface can be constructed by constructing an inserted reinforcing bar cage with a weight sufficient to allow it to be lifted and by pouring concrete. That's what it is.

極めて好適である。Very suitable.

尚2本発明工法を従来工法と比較して利点を示すと次記
の如くである。
2 The advantages of the construction method of the present invention compared to the conventional construction method are as follows.

品 質   壁面精度の向上による躯体精度の向上壁面
精度の向上による防水下地の完全化大深度連続壁にも対
応した施工が可能 コスト  従来工法比30%DOWIJ工 期   従
来の方法に比べ20〜30%の短縮
Quality: Improved frame accuracy due to improved wall surface accuracy.Complete waterproof foundation due to improved wall surface accuracy.Construction compatible with deep continuous walls.Cost: 30% compared to conventional methods.DOWIJ Construction period: 20-30% compared to conventional methods. shortening of

【図面の簡単な説明】[Brief explanation of drawings]

第1図イ、四、ハは従来工法の施工手順図。 第2図イ2口、ハは本発明工法の施工手順図である。 8・・・挿入鉄筋篭 9・・・組立鉄筋補強のプレキャストフシ′り°リート
版ズツIAI) =108
Figure 1 A, 4, and C are construction procedure diagrams using conventional construction methods. Figures 2A and 2C are construction procedure diagrams of the construction method of the present invention. 8... Inserted reinforcing bar basket 9... Precast frame for reinforcing assembled reinforcing bars (REIT version Zutsu IAI) = 108

Claims (1)

【特許請求の範囲】[Claims] 挿入鉄筋惰の内側面に薄肉の組立鉄筋補強のプレキャス
トコンクリート版を取付けて溝内に挿入し、コンクリー
トを打設してなることを特徴とする連続地下壁の構築工
法。
A continuous underground wall construction method characterized by attaching a precast concrete plate reinforced with thin prefabricated reinforcing bars to the inner surface of inserted reinforcing bars, inserting them into a groove, and pouring concrete.
JP13594682A 1982-08-04 1982-08-04 Construction of continuous underground wall Pending JPS5927024A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13594682A JPS5927024A (en) 1982-08-04 1982-08-04 Construction of continuous underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13594682A JPS5927024A (en) 1982-08-04 1982-08-04 Construction of continuous underground wall

Publications (1)

Publication Number Publication Date
JPS5927024A true JPS5927024A (en) 1984-02-13

Family

ID=15163534

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13594682A Pending JPS5927024A (en) 1982-08-04 1982-08-04 Construction of continuous underground wall

Country Status (1)

Country Link
JP (1) JPS5927024A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06193083A (en) * 1992-12-24 1994-07-12 Kajima Corp Construction method for underground structure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS544416A (en) * 1977-06-13 1979-01-13 Kingo Asayama Method of constructing underground wall and its structure
JPS5450119A (en) * 1977-09-29 1979-04-19 Obayashi Gumi Kk Method of constructing underground continuous wall

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS544416A (en) * 1977-06-13 1979-01-13 Kingo Asayama Method of constructing underground wall and its structure
JPS5450119A (en) * 1977-09-29 1979-04-19 Obayashi Gumi Kk Method of constructing underground continuous wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06193083A (en) * 1992-12-24 1994-07-12 Kajima Corp Construction method for underground structure

Similar Documents

Publication Publication Date Title
CN102430277B (en) Coarse grid sunk well for physically processing waste water and construction method thereof
CN105332386B (en) Structure construction method for tower crane foundation serving as basement bottom plate
JPH08269984A (en) Construction of basement in outside waterproofing construction method
JPH0579049A (en) Constructing method for beam and slab in underground body construction work
JPS5927024A (en) Construction of continuous underground wall
US3200548A (en) Precast shell coping and method of construction for swimming pools
JPH09242091A (en) Construction method for underground structure
JPH0128172B2 (en)
JPH10299003A (en) Foundation work using precast concrete member
JPS62253821A (en) Construction of concrete floor slab
RU173169U1 (en) Reinforced concrete pile column
TW418274B (en) A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall
JPH10280434A (en) Construction method for basement under application of outside waterproofing
JPH0467533B2 (en)
JPS59154229A (en) Construction of foundation structure of housing and formwork therefor
JPH0324676Y2 (en)
JP2004360266A (en) Structure and construction method for floor post base part
ES2245841B1 (en) BUILDING CONSTRUCTION SYSTEM.
JPS598846A (en) Construction of balcony
JPH06146308A (en) Construction method of underground skeleton
JPH11141126A (en) Processing method of driving joining part in reversely driving method
JPH07113220B2 (en) Beam construction method
JP2770604B2 (en) Underground outer wall waterproofing method
JP2004150150A (en) Reuse type separator with driving section and its manufacturing method
JPH0786230B2 (en) How to build a synthetic basement wall