JPH09242091A - Construction method for underground structure - Google Patents
Construction method for underground structureInfo
- Publication number
- JPH09242091A JPH09242091A JP8089856A JP8985696A JPH09242091A JP H09242091 A JPH09242091 A JP H09242091A JP 8089856 A JP8089856 A JP 8089856A JP 8985696 A JP8985696 A JP 8985696A JP H09242091 A JPH09242091 A JP H09242091A
- Authority
- JP
- Japan
- Prior art keywords
- reinforced concrete
- wall
- concrete
- waterproof layer
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】この発明は、地下室などの地
下構造物の施工方法に関し、詳しくは、工期短縮および
有効床面積の増大と共に、軟弱地盤や狭隘な土地に好適
な地下構造物の施工方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground structure such as a basement, and more specifically, a method for constructing an underground structure suitable for soft ground and narrow land as well as shortening the construction period and increasing the effective floor area. Regarding
【0002】[0002]
【従来の技術】在来工法により地下室などを施工する場
合、まず、周囲にH型鋼などを打込んで土留め工事を行
い、その内側の地盤を掘削する。そして、割栗石および
捨てコンクリートを打設した地盤上に型枠を組み立てて
鉄筋を配筋した後コンクリートを打設する。その後、コ
ンクリートの固化後型枠を取り外してコンクリート底版
およびコンクリート外壁を築造する。コンクリート底版
およびコンクリート外壁には防水処理を施し、コンクリ
ート外壁の外側に掘削した土砂を埋め戻す。このように
して、地下室が施工される。また、近年PC板ユニット
を使用した地下室の施工方法が提案されている。この方
法は、掘削して行きながらPC板をセットして行き、そ
れを土留めにして随時埋め戻しを行い、土の搬出、搬入
をできるだけ減らしたものである。この工法ではPC板
を外型枠として利用する。2. Description of the Related Art When constructing a basement or the like by a conventional method, first, an H-shaped steel or the like is driven into the surrounding area for earth retaining work, and the ground inside is excavated. Then, a mold is assembled on the ground on which the split stone and the discarded concrete have been placed, the reinforcing bars have been arranged, and then the concrete is placed. After that, after the concrete is solidified, the formwork is removed to build a concrete bottom slab and a concrete outer wall. The concrete slab and the concrete outer wall will be waterproofed, and the earth and sand excavated outside the concrete outer wall will be backfilled. In this way, the basement is constructed. Further, in recent years, a method of constructing a basement using a PC board unit has been proposed. In this method, a PC plate is set while excavating, and it is used as earth retaining material and backfilling is performed at any time to reduce the carry-out and carry-in of soil as much as possible. In this method, a PC board is used as an outer mold.
【0003】[0003]
【発明が解決しようとする課題】ところで、前述した在
来工法は、H型鋼などの打込みによる土留め工事が不可
欠であって、重機搬入の困難な場所には適用が難しい。
しかも、土留め工事や掘削した土砂の埋め戻し作業の分
だけ工期も長くかかる。また、土留めの内側に型枠の設
置スペースを確保しなければならず、その分、地下室な
どの有効床面積が減少する。しかも、築造したコンクリ
ート外壁の外方に十分な作業スペースを確保し難いの
で、外側防水処理等の工事に手間がかかるという問題も
あった。By the way, the conventional construction method described above is indispensable for earth retaining work by driving in H-shaped steel or the like, and it is difficult to apply it to a place where it is difficult to carry in heavy equipment.
Moreover, the construction period will be extended by the amount of earth retaining work and backfilling of excavated earth and sand. In addition, it is necessary to secure a space for installing the formwork inside the earth retaining wall, which reduces the effective floor area such as the basement. In addition, it is difficult to secure a sufficient working space outside the built concrete outer wall, so that there is a problem that it takes a lot of time for construction such as outer waterproofing.
【0004】もっとも、土留め部材と外型枠とを兼用す
るPC板を使用した工法によれば、地下室などの有効床
面積は幾分増大する。しかし、この工法においても、土
砂の埋め戻し作業は不可欠であってそれに伴う工期は短
縮できない。また、従来公知の工法では、狭隘な土地に
は工事用重機の搬入が困難であり、地下室等の築造がで
きないという問題があった。さらに、コンクリート外壁
の外側には掘削した土が埋め戻されるので、従来の地盤
と比較すると軟弱な地盤となっている。このために、隣
地際まで掘削して埋め戻した場合には、月日が経つにつ
れて埋め戻した部分は外周からの土圧によって圧縮され
るから、隣地に建物がある場合には沈下によってその建
物が傾くという問題があった。However, according to the construction method using the PC board which also serves as the earth retaining member and the outer form, the effective floor area of the basement or the like increases somewhat. However, even in this construction method, backfilling of earth and sand is indispensable, and the construction period associated therewith cannot be shortened. Further, in the conventionally known construction method, there is a problem that it is difficult to carry heavy construction equipment into a narrow land, and it is impossible to construct a basement or the like. Furthermore, since the excavated soil is backfilled on the outside of the concrete outer wall, the soil is softer than the conventional soil. For this reason, when excavating to the adjacent land and backfilling, the backfilled part will be compressed by the earth pressure from the outer circumference as the time passes, so if there is a building on the adjacent land, the building will be subsided due to subsidence. There was a problem of tilting.
【0005】そこで、この発明は重機搬入の困難な場所
にも適用できて工期も短縮でき、また、有効床面積も増
大することができ、外側防水処理を容易に行なうことが
でるばかりでなく、しかも軟弱地盤や狭隘な土地に好適
な地下構造物の施工方法を提供することを目的とする。Therefore, the present invention can be applied to a place where it is difficult to carry in heavy equipment, the construction period can be shortened, the effective floor area can be increased, and not only the outer waterproof treatment can be easily performed, but also Moreover, it is an object of the present invention to provide a method for constructing an underground structure suitable for soft ground and narrow land.
【0006】[0006]
【課題を解決するための手段】前記目的を達成する手段
として、この発明は、地上にて鉄筋コンクリート外壁を
築造し、その内側および下方の地盤を掘削しつつ鉄筋コ
ンクリート外壁を沈降させ、その後、鉄筋コンクリート
外壁から引き出した配筋とコンクリート底版用配筋とを
接続し、コンクリートを打設して鉄筋コンクリート底版
を成形し、さらに前記配筋の接続部分にコンクリートを
打設して突出した連結部を設け、前記外壁及びコンクリ
ート底版に連続した防水層を設けることを特徴とする。
また、前記鉄筋コンクリート外壁には予め地上にて防水
層を形成しておき、鉄筋コンクリート外壁の沈降後、そ
の内側の鉄筋コンクリート底版には、鉄筋コンクリート
外壁に形成された防水層に連続して防水層を形成するこ
とを特徴とする。As a means for achieving the above object, the present invention is to construct a reinforced concrete outer wall on the ground, to settle the reinforced concrete outer wall while excavating the ground inside and below, and then to the reinforced concrete outer wall. Connecting the reinforcing bar drawn out from and the concrete bottom slab rebar, casting concrete to form a reinforced concrete bottom slab, and further providing a projecting connecting portion by casting concrete into the connecting part of the rebar, The feature is that a continuous waterproof layer is provided on the outer wall and the concrete bottom slab.
In addition, a waterproof layer is previously formed on the reinforced concrete outer wall on the ground, and after the reinforced concrete outer wall is settled, a waterproof layer is continuously formed on the inner reinforced concrete bottom plate to the waterproof layer formed on the reinforced concrete outer wall. It is characterized by
【0007】そして、前記鉄筋コンクリート外壁の外面
及び下面に地上にて予め防水層を形成しておき、その内
側に打設した捨てコンクリートの上面に防水層を形成し
た後、鉄筋コンクリート底版を打設して鉄筋コンクリー
ト外壁の外面から鉄筋コンクリート底版の下面に連続し
た防水層を設けることが好ましい。また、鉄筋コンクリ
ート外壁の下端部は、予め地上にて保護板で覆ってお
き、鉄筋コンクリート外壁を沈降させた後、前記保護板
の内側辺を捨てコンクリート面に倒して鉄筋コンクリー
ト底版を形成することが好ましい。Then, a waterproof layer is previously formed on the outer surface and the lower surface of the outer wall of the reinforced concrete on the ground, and after forming a waterproof layer on the upper surface of the discarded concrete placed inside thereof, a bottom plate of the reinforced concrete is placed. It is preferable to provide a continuous waterproof layer from the outer surface of the reinforced concrete outer wall to the lower surface of the reinforced concrete bottom slab. Further, it is preferable that the lower end portion of the outer wall of the reinforced concrete is covered with a protective plate on the ground in advance, the outer wall of the reinforced concrete is allowed to settle, and then the inner side of the protective plate is discarded and the reinforced concrete bottom slab is formed by laying it down on the concrete surface.
【0008】そして、連続した防水層を設けるには、鉄
筋コンクリート外壁を形成する型枠内に溝状に折り曲げ
底部内面に防水層を設けた保護板を設置し、外型枠と内
型枠とを撤去した後、保護板の外側辺を倒して鉄筋コン
クリート外壁面に防水層を施して再度前記保護板の外側
辺を起立させ、前記鉄筋コンクリート外壁の沈降後捨て
コンクリートを打設し、前記保護板の内側辺を倒して捨
てコンクリート面に鉄筋コンクリート外壁から連続した
防水層を設け、その上に鉄筋コンクリート底版を形成す
ることが好ましい。さらに、前記保護板ぼの使用に当た
っては、前記鉄筋コンクリート外壁の下端部を覆う保護
板の角部にスペーサブロックを設置しておき、コンクリ
ート打設後外側角部のスペーサブロックは地上にて撤去
して防水剤を充填し、内側角部のスペーサブロックは沈
降後に撤去して防水剤を充填し、前記防水剤を介して防
水層を連続させることが好ましい。In order to provide a continuous waterproof layer, a protective plate having a waterproof layer provided on the inner surface of the bottom bent in a groove is installed in the formwork forming the outer wall of the reinforced concrete, and the outer formwork and the inner formwork are connected to each other. After removal, the outer side of the protective plate is laid down to give a waterproof layer to the outer wall of the reinforced concrete and the outer side of the protective plate is erected again. It is preferable that a waterproof layer continuous from the outer wall of the reinforced concrete is provided on the concrete surface by laying down the side and the reinforced concrete bottom slab is formed thereon. Furthermore, in using the protection plate, a spacer block is installed at a corner portion of the protection plate that covers the lower end portion of the outer wall of the reinforced concrete, and after placing concrete, the spacer block at the outer corner portion is removed on the ground. It is preferable that the waterproof layer is filled, the spacer block at the inner corner is removed after settling, the waterproof layer is filled, and the waterproof layer is continuous with the waterproof layer.
【0009】[0009]
【発明の実施の形態】以下、この発明の実施の形態を添
付の図面を参照して具体的に説明する。住宅等の地下室
を対象とした一実施形態の地下構造物の施工方法では、
まず、図1(a),(b),(c)に示すように、地上
にて鉄筋コンクリート外壁1を築造し、その外面に防水
層2を形成する。また、防水層2に重ねて滑性塗膜層3
も形成する。そして、鉄筋コンクリート外壁1の内側に
は補剛用の間仕切り4,4を架設しておく。前記鉄筋コ
ンクリート外壁1を築造する際には、コンクリート底版
と接続するための鉄筋を内型枠に折り曲げて当接させて
おき、内型枠を取り外したときに露出するように配筋し
ておく。あるいはコンクリート打設の際にケミカルアン
カを埋設しておく。BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be specifically described below with reference to the accompanying drawings. In the method of constructing an underground structure of an embodiment for a basement such as a house,
First, as shown in FIGS. 1A, 1B, and 1C, a reinforced concrete outer wall 1 is built on the ground, and a waterproof layer 2 is formed on the outer surface thereof. In addition, it is laminated on the waterproof layer 2 to form a slippery coating layer 3
Also forms. Then, partitions 4 and 4 for stiffening are installed inside the outer wall 1 of the reinforced concrete. When constructing the reinforced concrete outer wall 1, a reinforcing bar for connecting to the concrete bottom slab is bent and brought into contact with the inner mold, and arranged so that it is exposed when the inner mold is removed. Alternatively, a chemical anchor should be buried when pouring concrete.
【0010】図2(a)ないし(e)、及び図3(a)
ないし(e)は、鉄筋コンクリート外壁1の下端部の打
設工程を示している。まず、図2(a)に示すように、
地盤面に受け板5を敷き、その上にブロック6を介して
底型枠7を内側上がりの傾斜状態に設置すると共に、外
型枠8を立設する。そして、溝状に折曲げ加工した保護
板9を底型枠7上に設置し、その外側9aを外型枠8の
内側に添わせて起立させ、内側辺9bも後述する内型枠
の内面に添うように起立させる。前記保護板9は、鉄
板、ブリキ板あるいは樹脂板等によって形成することが
できる。2 (a) to 2 (e) and FIG. 3 (a)
8A to 8E show a step of placing the lower end portion of the reinforced concrete outer wall 1. First, as shown in FIG.
The receiving plate 5 is laid on the ground surface, the bottom formwork 7 is installed on the base plate via a block 6 in an upwardly inclined state, and the outer formwork 8 is erected. Then, the protective plate 9 bent in a groove shape is installed on the bottom mold 7, the outer side 9a thereof is erected along the inner side of the outer mold 8, and the inner side 9b is also the inner surface of the inner mold described later. Stand up to follow. The protection plate 9 can be formed of an iron plate, a tin plate, a resin plate, or the like.
【0011】続いて、図2(b)に示すように、保護板
9の底部内面に防水層2aを形成し、図2(c)のよう
に、保護板9の内側の両角部にスペーサブロック10,
11を設置する。また、図2(d)に示すように、受け
板5上に内型枠12を立設して保護板9の内側辺9bに
添わせる。そして、外型枠8と内型枠12との間にコン
クリートを打設した後、外型枠8と内型枠12とを撤去
することにより、図2(e)に示すような、下端部が保
護板9で覆われ、かつ下面に防水層2aが形成された鉄
筋コンクリート外壁1を得る。Subsequently, as shown in FIG. 2 (b), a waterproof layer 2a is formed on the inner surface of the bottom of the protective plate 9, and spacer blocks are formed on both inner corners of the protective plate 9 as shown in FIG. 2 (c). 10,
Install 11. Further, as shown in FIG. 2D, the inner formwork 12 is erected on the receiving plate 5 so as to be attached to the inner side 9 b of the protective plate 9. Then, after placing concrete between the outer mold 8 and the inner mold 12, by removing the outer mold 8 and the inner mold 12, the lower end portion as shown in FIG. 2 (e) To obtain a reinforced concrete outer wall 1 covered with a protective plate 9 and having a waterproof layer 2a formed on its lower surface.
【0012】次に、図3(a)に示すように、鉄筋コン
クリート外壁1の外面に添う保護板9の外側辺9aを倒
してスペーサブロック11を撤去する。続いて、図3
(b)に示すように、スペーサブロック11を撤去して
できた隙間に防水剤12を充填し、鉄筋コンクリート外
壁1の外面に防水層2bを形成することにより、鉄筋コ
ンクリート外壁1の外面から下面にわたって連続する防
水層2b、2aを形成する。尚、鉄筋コンクリート外壁
1の外面の防水層2の上には、滑性塗膜層3を重ねて形
成しておく(図3(c)参照)。前記防水層2は、アス
ファルト防水、シート防水、塗布防水等任意の防水手段
によって形成することができる。そして、図3(d)の
ように保護板9の外側辺9aを鉄筋コンクリート外壁1
の外面に添うよう起立させ、保護板9の下方の地盤を掘
削して受け板5、ブロック6、底型枠7を撤去する。Next, as shown in FIG. 3 (a), the outer side 9a of the protective plate 9 along the outer surface of the reinforced concrete outer wall 1 is tilted down to remove the spacer block 11. Subsequently, FIG.
As shown in (b), the gap formed by removing the spacer block 11 is filled with the waterproofing agent 12, and the waterproof layer 2b is formed on the outer surface of the reinforced concrete outer wall 1 to continuously connect the outer surface of the reinforced concrete outer wall 1 to the lower surface. The waterproof layers 2b and 2a are formed. A slippery coating layer 3 is formed on the waterproof layer 2 on the outer surface of the reinforced concrete outer wall 1 (see FIG. 3 (c)). The waterproof layer 2 can be formed by any waterproofing means such as asphalt waterproofing, sheet waterproofing and coating waterproofing. Then, as shown in FIG. 3D, the outer side 9a of the protection plate 9 is attached to the reinforced concrete outer wall 1
It stands up so as to follow the outer surface of the base plate, excavates the ground below the protective plate 9, and removes the receiving plate 5, the block 6, and the bottom formwork 7.
【0013】以上の工程によりアンカ配筋を有する鉄筋
コンクリート外壁1を地上にて築造したら、図4(a)
ないし(c)に示すように、その内側および下方の地盤
を掘削して鉄筋コンクリート外壁1を自重により所定の
深さまで沈降させる。その際、防水層2a、2bと共に
鉄筋コンクリート外壁1の下端部は予め保護板9により
覆われているので、防水層2a、2bが剥がれたり鉄筋
コンクリート外壁1の下端部が破損することはない。そ
して、この保護板9がクサビ形の断面形状をなして地盤
を掘削し得ること、及び鉄筋コンクリート外壁1の外面
に滑性塗膜層3が形成されていることにより、鉄筋コン
クリート外壁1は円滑に沈降する。When the reinforced concrete outer wall 1 having anchor reinforcement is built on the ground by the above steps, FIG.
As shown in (c) to (c), the ground inside and below the ground is excavated and the outer wall 1 of the reinforced concrete is settled down to a predetermined depth by its own weight. At this time, since the lower end portion of the reinforced concrete outer wall 1 together with the waterproof layers 2a and 2b is previously covered with the protective plate 9, the waterproof layers 2a and 2b are not peeled off or the lower end portion of the reinforced concrete outer wall 1 is not damaged. The protective plate 9 has a wedge-shaped cross-sectional shape so that the ground can be excavated, and the slippery coating layer 3 is formed on the outer surface of the reinforced concrete outer wall 1, so that the reinforced concrete outer wall 1 is smoothly settled. To do.
【0014】鉄筋コンクリート外壁1が所定の深さまで
沈降したら、図5(a)ないし(c)に示すように、鉄
筋コンクリート外壁1の内側の地盤面に割栗石13を敷
き詰め、その上に捨てコンクリート14を施した後、ア
ンカ配筋を有する鉄筋コンクリート底版15を打設す
る。その際、図6(a)ないし(c)に示す工程によ
り、捨てコンクリート14と鉄筋コンクリート底版15
との間に防水層2cを形成する。即ち、図6(a)に示
すように、鉄筋コンクリート底版15の打設の前に捨て
コンクリート14上に保護板9の内側辺9bを倒してス
ペーサブロック10を撤去する。続いて、図6(b)に
示すように、スペーサブロック10を撤去してできた隙
間に防水剤12を充填し、これに連続して保護板9の内
側辺9b上から捨てコンクリート14の上面に防水層2
cを形成する。これにより、鉄筋コンクリート外壁1の
外面から下面を介して捨てコンクリート14上に連続す
る防水層2が形成され、地下室の外側防水処理が完了す
る。When the outer wall 1 of the reinforced concrete has settled to a predetermined depth, as shown in FIGS. 5 (a) to 5 (c), the crushed stone 13 is laid on the ground surface inside the outer wall 1 of the reinforced concrete, and the discarded concrete 14 is placed on it. After the application, a reinforced concrete bottom plate 15 having anchor rebars is placed. At that time, by the steps shown in FIGS. 6A to 6C, the discarded concrete 14 and the reinforced concrete bottom slab 15 are disposed.
A waterproof layer 2c is formed between the and. That is, as shown in FIG. 6A, the inner side 9b of the protection plate 9 is laid down on the discarded concrete 14 before the reinforced concrete bottom slab 15 is placed, and the spacer block 10 is removed. Subsequently, as shown in FIG. 6B, the gap formed by removing the spacer block 10 is filled with the waterproofing agent 12, and continuously from this, from the inner side 9b of the protection plate 9 to the upper surface of the discarded concrete 14. Waterproof layer 2
Form c. As a result, a continuous waterproof layer 2 is formed on the discarded concrete 14 from the outer surface of the reinforced concrete outer wall 1 through the lower surface, and the outer waterproof treatment of the basement is completed.
【0015】その後、図6(c)に示すように鉄筋コン
クリート底版15を打設し、図7(a)ないし(c)に
示すように、鉄筋コンクリート底版15の周辺の鉄筋コ
ンクリート外壁1との接合部分にコンクリートを打設し
て鉄筋連結部16を設ける。即ち、図8に示すように、
予め鉄筋コンクリート外壁1の内面側に突出できるよう
に予め設けられたアンカ配筋1aと、鉄筋コンクリート
底版15の上面に突設されたアンカ配筋15aとを接続
し、コンクリートを打設することによって鉄筋連結部1
6を設ける。尚、図9に示すように、鉄筋コンクリート
外壁1に予め埋設されたケミカルアンカ1bを利用して
鉄筋連結部16を設けてもよい。Thereafter, a reinforced concrete bottom slab 15 is placed as shown in FIG. 6 (c), and as shown in FIGS. 7 (a) to 7 (c), at the joint portion with the reinforced concrete outer wall 1 around the reinforced concrete bottom slab 15. Concrete is poured to provide the reinforcing bar connecting portion 16. That is, as shown in FIG.
Anchored bars 1a provided beforehand so as to project to the inner surface side of the reinforced concrete outer wall 1 and anchor bars 15a protruding from the upper surface of the reinforced concrete bottom slab 15 are connected to each other to connect the reinforcing bars by placing concrete. Part 1
6 is provided. As shown in FIG. 9, the reinforcing bar connecting portion 16 may be provided by utilizing the chemical anchor 1b embedded in the reinforced concrete outer wall 1 in advance.
【0016】鉄筋連結部16の構成については上記のよ
うにアンカ配筋1aとアンカ配筋15aとを接続して設
ける場合と、ケミカルアンカ1bを利用して設ける場合
と、さらに、コンクリート外壁1の埋設後にコンクリー
トにケミカルアンカ用穴を明け、この穴にケミカルアン
カを取り付けてアンカ配筋15aと接続することにより
鉄筋連結部16を設けるようにしてもよい。さらに、上
記実施形態における保護板9の外側辺9a及び内側辺9
bは起倒可能としたが、外側辺9aについては予め防水
層2a、2bを設け、防水剤12を充填しておくことに
より起倒しない構成としてもよい。Regarding the structure of the reinforcing bar connecting portion 16, as described above, the case where the anchor reinforcement 1a and the anchor reinforcement 15a are connected, the case where the reinforcement reinforcement connection is provided by using the chemical anchor 1b, and the concrete outer wall 1 The reinforcing bar connecting portion 16 may be provided by making a hole for a chemical anchor in the concrete after the burying, and attaching a chemical anchor to this hole to connect with the anchor bar 15a. Further, the outer side 9a and the inner side 9 of the protection plate 9 in the above-described embodiment.
Although b can be turned upside down, the outer side 9a may be provided with the waterproof layers 2a and 2b in advance and filled with the waterproofing agent 12 so as not to be turned down.
【0017】鉄筋連結部16の形成により、鉄筋コンク
リート外壁1と鉄筋コンクリート底版15とは強固に接
続され、剛接合となるとともに外側防水処理は完全なも
のとなる(図10参照)。尚、上記実施形態では鉄筋コ
ンクリート外壁1の外面に防水処理を施す場合について
説明したが、図11に示すように、鉄筋コンクリート外
壁1の内面から鉄筋連結部16の上面および側面を経て
鉄筋コンクリート底版15の上面に連続する他の防水層
17を形成して内側防水処理を施せば、さらに完全な防
水処理が達成される。また、外側防水を省略して前記内
側防水17のみとしてもよい。また、鉄筋コンクリート
外壁1の下端面は傾斜面としたが、これに限定されるも
のではなく、湾曲面、V字形面あるいは水平面等任意の
形状とすることができる。By forming the reinforced concrete connecting portion 16, the reinforced concrete outer wall 1 and the reinforced concrete bottom slab 15 are firmly connected to form a rigid joint and complete outer waterproofing treatment (see FIG. 10). In addition, although the case where the outer surface of the reinforced concrete outer wall 1 is waterproofed has been described in the above embodiment, as shown in FIG. 11, the upper surface of the reinforced concrete bottom slab 15 is passed from the inner surface of the reinforced concrete outer wall 1 through the upper surface and the side surface of the reinforcing bar connecting portion 16. Further complete waterproofing can be achieved by forming another waterproofing layer 17 continuous with and performing inner waterproofing. The outer waterproof may be omitted and only the inner waterproof 17 may be provided. Further, although the lower end surface of the reinforced concrete outer wall 1 is an inclined surface, it is not limited to this and may be any shape such as a curved surface, a V-shaped surface or a horizontal surface.
【0018】このように防水処理が施された地下室に
は、内面に断熱材等を設け床を張り、建築すればよい。
即ち、鉄筋コンクリート外壁1の上端を基礎とし(図1
2参照)、または鉄筋連結部16を基礎とし(図13参
照)、あるいは鉄筋コンクリート外壁1に連続した鉄筋
コンクリートスラブ18の天井を基礎として(図14参
照)、木造住宅や、鉄骨造、鉄筋コンクリート造などの
適宜の家屋が建築される。この場合、地下室の施工にあ
たっては、土留め工事が不要であり、大型重機の搬入が
必要ないから、軟弱地盤や狭隘な土地にも適用できる。
また、掘削した地盤の土砂を埋め戻す必要がないから、
その分、工期も短縮する。特に、コンクリート外壁1は
地上にて隣地際まで打設することができるので、土留め
部材と外型枠とを兼用するPC板を使用した工法に較べ
ても、地下室の有効床面積を増大することができる。さ
らに、埋め戻しが不要で地質に変更を加えるものではな
いから、隣地の建造物を傾けさせる等の悪影響を与える
ことがない。In the basement room thus waterproofed, a heat insulating material or the like may be provided on the inner surface of the basement to build a floor.
That is, based on the upper end of the reinforced concrete outer wall 1 (Fig. 1
2) or based on the reinforced connecting portion 16 (see FIG. 13) or the ceiling of the reinforced concrete slab 18 continuous to the reinforced concrete outer wall 1 (see FIG. 14), such as a wooden house, a steel frame structure, a reinforced concrete structure. Appropriate houses are built. In this case, when constructing the basement, earth retaining work is not required and large heavy equipment is not required to be carried in, so it can be applied to soft ground and narrow land.
In addition, because it is not necessary to backfill the soil of the excavated ground,
The construction period is shortened accordingly. In particular, since the concrete outer wall 1 can be cast on the ground to the adjacent ground, the effective floor area of the basement is increased even when compared with the construction method using a PC board that also serves as an earth retaining member and an outer formwork. be able to. Furthermore, since backfilling is not necessary and the geology is not changed, there is no adverse effect such as tilting the building on the adjacent land.
【0019】尚、この発明は、前述した建造物の地下室
に限らず、プールや水槽などにも適用できる。また、天
井として鉄筋コンクリートスラブを設けることにより、
ガソリンスタンドの地下タンク等や、各種のシェルタに
も適用することができる。The present invention can be applied not only to the above-mentioned basement of a building but also to a pool or a water tank. Also, by providing a reinforced concrete slab as the ceiling,
It can also be applied to underground tanks of gas stations and various shelters.
【0020】[0020]
【発明の効果】以上説明したとおりこの発明によれば、
地下構造物の施工にあたり、土留め工事が不要であるか
ら狭隘な土地で重機搬入の困難な場所にも適用できる。
また、土留め工事に加えて土砂の埋め戻し作業も不要で
あるから、その分、工期も短縮することができるばかり
でなく、地質に変更を加えることもない。さらに、コン
クリート外壁は地上にて打設するので、隣地際に打設す
ることも可能である。従って、土留め部材と外型枠とを
兼用するPC板を使用した工法に較べても、有効床面積
を増大することができる。As described above, according to the present invention,
Since earth retaining work is not required when constructing an underground structure, it can be applied to a place where it is difficult to carry heavy equipment on a narrow land.
In addition, since soil backfilling work is not required in addition to earth retaining work, not only the construction period can be shortened, but also the geology is not changed. Furthermore, since the concrete outer wall is cast on the ground, it is also possible to cast it on the adjacent land. Therefore, the effective floor area can be increased as compared with the construction method using the PC plate that also serves as the earth retaining member and the outer form.
【0021】特に、コンクリート外壁の外面および下面
には予め地上にて防水層を形成しておき、コンクリート
外壁の沈降後、その内側のコンクリート底版の打設面に
は防水層を形成してコンクリート外壁に形成された防水
層に連続させるので、外側防水処理を容易かつ完全に行
なうことができる。しかも、コンクリート外壁の沈降作
業は、防水層の存在により円滑に行なうことができる。In particular, a waterproof layer is formed on the outer surface and the lower surface of the concrete outer wall in advance on the ground, and after the concrete outer wall is settled, a waterproof layer is formed on the driving surface of the concrete bottom slab inside the concrete outer wall. Since it is continuous with the waterproof layer formed on, the outer waterproofing process can be performed easily and completely. Moreover, the settling operation of the concrete outer wall can be smoothly performed due to the presence of the waterproof layer.
【0022】また、コンクリート外壁およびコンクリー
ト底版には、それぞれアンカ配筋手段を設けておき、コ
ンクリート底版の打設後、その周辺のコンクリート外壁
との接合部分にコンクリートを打設して鉄筋連結部を設
けるので、剛接合とした強固な地下構造物を得ることが
でき、外側防水処理もより完全なものとすることができ
る。An anchor reinforcing means is provided on each of the concrete outer wall and the concrete bottom slab, and after placing the concrete bottom slab, concrete is struck at the joint portion with the concrete outer wall around the concrete bottom slab to form the reinforcing bar connecting portion. Since it is provided, it is possible to obtain a rigid underground structure that is rigidly joined, and the outer waterproof treatment can be more complete.
【0023】さらに、防水層と共にコンクリート外壁の
下端部を予め地上にて保護板で覆っておくので、コンク
リート外壁の沈降作業に際して下端部の破損が防止さ
れ、コンクリート外壁を円滑に沈降させることができ
る。Furthermore, since the lower end of the concrete outer wall is covered with a protective plate in advance on the ground together with the waterproof layer, the lower end of the concrete outer wall is prevented from being damaged when the concrete outer wall is settled, and the concrete outer wall can be smoothly settled. .
【図1】この発明の一実施形態における地上にて築造さ
れた鉄筋コンクリート外壁を示し、(a)は平面図、
(b)は(a)のA−A線断面図、(c)は(a)のB
−B線断面図である。FIG. 1 shows a reinforced concrete outer wall built on the ground in an embodiment of the present invention, (a) is a plan view,
(B) is a sectional view taken along the line AA of (a), and (c) is a sectional view of B of (a).
FIG. 4 is a cross-sectional view taken along line B.
【図2】(a)〜(e)は、一実施形態における鉄筋コ
ンクリート外壁の下端部の打設作業の工程図である。2 (a) to 2 (e) are process drawings of a work for placing a lower end portion of a reinforced concrete outer wall in one embodiment.
【図3】(a)〜(e)は、一実施形態における鉄筋コ
ンクリート外壁の下端部の防水層形成作業の工程図であ
る。3A to 3E are process diagrams of a waterproof layer forming operation on a lower end portion of a reinforced concrete outer wall according to an embodiment.
【図4】一実施形態における鉄筋コンクリート外壁の沈
降状態を示し、(a)は平面図、(b)は(a)のA−
A線断面図、(c)は(a)のB−B線断面図である。FIG. 4 shows a settling state of a reinforced concrete outer wall in one embodiment, (a) is a plan view, and (b) is A- of (a).
A line sectional view, (c) is a BB line sectional view of (a).
【図5】一実施形態における鉄筋コンクリート底版の打
設状態を示し、(a)は平面図、(b)は(a)のA−
A線断面図、(c)は(a)のB−B線断面図である。FIG. 5 shows a reinforced concrete bottom slab in one embodiment, in which (a) is a plan view and (b) is A- in (a).
A line sectional view, (c) is a BB line sectional view of (a).
【図6】(a)ないし(c)は、一実施形態における捨
てコンクリート上の防水層形成作業を示す工程図であ
る。6A to 6C are process diagrams showing a waterproof layer forming operation on abandoned concrete in one embodiment.
【図7】一実施形態における鉄筋連結部の状態を示し、
(a)は平面図、(b)は(a)のA−A線断面図、
(c)は(a)のB−B線断面図である。FIG. 7 shows a state of a reinforcing bar connecting portion in one embodiment,
(A) is a plan view, (b) is a sectional view taken along line AA of (a),
(C) is a BB line sectional view of (a).
【図8】一実施形態における鉄筋連結部の配筋状態を示
す断面図である。FIG. 8 is a cross-sectional view showing a reinforcing bar connecting portion according to an embodiment.
【図9】一実施形態における鉄筋連結部の他の配筋状態
を示す断面図である。FIG. 9 is a cross-sectional view showing another reinforcing bar arrangement state of the reinforcing bar connecting portion in the embodiment.
【図10】一実施形態における外側防水処理の状態を示
す部分断面図である。FIG. 10 is a partial cross-sectional view showing a state of outer waterproofing processing in one embodiment.
【図11】一実施形態における外側防水処理および内側
防水処理の状態を示す部分断面図である。FIG. 11 is a partial cross-sectional view showing the states of the outer waterproof treatment and the inner waterproof treatment in the embodiment.
【図12】一実施形態における鉄筋コンクリート外壁の
上端を基礎とした家屋の建築状態を示す部分断面図であ
る。FIG. 12 is a partial cross-sectional view showing a building state of a house based on an upper end of a reinforced concrete outer wall in one embodiment.
【図13】一実施形態における鉄筋連結部を基礎とした
家屋の建築状態を示す部分断面図である。FIG. 13 is a partial cross-sectional view showing a building state of a house based on a reinforcing bar connecting portion in one embodiment.
【図14】一実施形態における鉄筋コンクリートスラブ
を基礎とした家屋の建築状態を示す部分断面図である。FIG. 14 is a partial cross-sectional view showing a building state of a house based on a reinforced concrete slab according to an embodiment.
1 鉄筋コンクリート外壁 1a アンカ配筋 1b ケミカルアンカ 2 防水層 3 滑性塗膜 4 間仕切り 5 受け板 6 ブロック 7 底型枠 8 外型枠 9 保護板 9a 外側辺 9b 内側辺 10 スペーサブロック 11 スペーサブロック 12 防水剤 13 割栗石 14 捨てコンクリート 15 鉄筋コンクリート底版 16 鉄筋連結部 17 他の防水層 18 鉄筋コンクリートスラブ 1 Reinforced concrete outer wall 1a Anchor reinforcement 1b Chemical anchor 2 Waterproof layer 3 Sliding coating film 4 Partition 5 Receiving plate 6 Block 7 Bottom formwork 8 Outer formwork 9 Protective plate 9a Outer side 9b Inner side 10 Spacer block 11 Spacer block 12 Waterproof Agent 13 Cracked stone 14 Discarded concrete 15 Reinforced concrete bottom slab 16 Reinforcing bar joint 17 Other waterproof layer 18 Reinforced concrete slab
───────────────────────────────────────────────────── フロントページの続き (72)発明者 石井 康隆 埼玉県東松山市箭弓町3−1−3−405 (72)発明者 吉田 雅光 東京都江戸川区本一色1−3−9 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Yasutaka Ishii 3-1-3-405 Yasumicho, Higashimatsuyama City, Saitama Prefecture (72) Inventor Masamitsu Yoshida 1-3-9 Honichiki, Edogawa-ku, Tokyo
Claims (6)
し、その内側および下方の地盤を掘削しつつ鉄筋コンク
リート外壁を沈降させ、その後、鉄筋コンクリート外壁
から引き出した配筋と鉄筋コンクリート底版用配筋とを
接続し、コンクリートを打設して鉄筋コンクリート底版
を成形し、さらに前記配筋の接続部分にコンクリートを
打設して突出した連結部を設け、前記外壁及びコンクリ
ート底版に連続した防水層を設けることを特徴とする地
下構造物の施工方法。1. A reinforced concrete outer wall is constructed on the ground, the inner and lower grounds of the reinforced concrete outer wall are settled while excavating the ground, and after that, the reinforcing bar drawn out from the reinforced concrete outer wall and the reinforcing bar for reinforced concrete bottom plate are connected, Characterized in that concrete is cast to form a reinforced concrete bottom slab, and further concrete is placed at a connecting portion of the reinforcing bar to provide a protruding connecting portion, and a continuous waterproof layer is provided to the outer wall and the concrete bottom slab. Construction method of underground structure.
にて防水層を形成しておき、鉄筋コンクリート外壁の沈
降後、その内側の鉄筋コンクリート底版には鉄筋コンク
リート外壁に形成された防水層に連続して防水層を形成
することを特徴とする請求項1記載の地下構造物の施工
方法。2. A waterproof layer is previously formed on the reinforced concrete outer wall on the ground, and after the reinforced concrete outer wall is settled, a waterproof layer is continuously formed on the reinforced concrete bottom slab to the waterproof layer formed on the reinforced concrete outer wall. It forms, The construction method of the underground structure of Claim 1 characterized by the above-mentioned.
面に地上にて予め防水層を形成しておき、その内側に打
設した捨てコンクリートの上面に防水層を形成した後、
コンクリート底版を形成して鉄筋コンクリート外壁の外
面から鉄筋コンクリート底版の下面に連続した防水層を
設けることを特徴とする請求項1記載の地下構造物の施
工方法。3. A waterproof layer is preliminarily formed on the outer surface and the lower surface of the reinforced concrete outer wall on the ground, and a waterproof layer is formed on the upper surface of the discarded concrete cast therein,
2. The method for constructing an underground structure according to claim 1, wherein a concrete bottom slab is formed and a continuous waterproof layer is provided from the outer surface of the reinforced concrete outer wall to the lower surface of the reinforced concrete bottom slab.
地上にて保護板で覆っておき、鉄筋コンクリート外壁を
沈降させた後、前記保護板の内側辺を捨てコンクリート
面に倒して鉄筋コンクリート底版を形成することを特徴
とする請求項1ないし請求項3のいずれか1項に記載の
地下構造物の施工方法。4. The lower end of the reinforced concrete outer wall is previously covered with a protective plate on the ground, the reinforced concrete outer wall is allowed to settle, and then the inner side of the protective plate is discarded to form a reinforced concrete bottom slab. The method for constructing an underground structure according to any one of claims 1 to 3, wherein:
に溝状に折り曲げ底部内面に防水層を設けた保護板を設
置し、外型枠と内型枠とを撤去した後、保護板の外側辺
を倒して鉄筋コンクリート外壁面に防水層を施して再度
前記保護板の外側辺を起立させ、前記鉄筋コンクリート
外壁の沈降後捨てコンクリートを打設し、前記保護板の
内側辺を倒して捨てコンクリート面に鉄筋コンクリート
外壁から連続した防水層を設け、その上に鉄筋コンクリ
ート底版を形成することを特徴とする請求項1または請
求項2記載の地下構造物の施工方法。5. A protective plate having a waterproof layer provided on the inner surface of the bottom bent in a groove in a form forming a reinforced concrete outer wall, and after removing the outer form and the inner form, the outer side of the protect plate. And erected the outer side of the protective plate again by applying a waterproof layer to the outer wall of reinforced concrete, and after setting down the outer wall of the reinforced concrete, cast abandoned concrete, and overturn the inner side of the protective plate to abandon the concrete surface The method for constructing an underground structure according to claim 1 or 2, wherein a continuous waterproof layer is provided from the outer wall, and a reinforced concrete bottom slab is formed thereon.
う保護板の角部にスペーサブロックを設置しておき、コ
ンクリート打設後外側角部のスペーサブロックは地上に
て撤去して防水剤を充填し、内側角部のスペーサブロッ
クは沈降後に撤去して防水剤を充填し、前記防水剤を介
して防水層を連続させるようにしたことを特徴とする請
求項5記載の地下構造物の施工方法。6. A spacer block is installed at a corner portion of a protective plate covering a lower end portion of the reinforced concrete outer wall, and after the concrete is placed, the spacer block at the outer corner portion is removed on the ground and filled with a waterproofing agent, The method for constructing an underground structure according to claim 5, wherein the spacer block at the inner corner portion is removed after settling, filled with a waterproofing agent, and the waterproofing layer is made continuous through the waterproofing agent.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8089856A JP2927727B2 (en) | 1996-03-07 | 1996-03-07 | Construction method of underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8089856A JP2927727B2 (en) | 1996-03-07 | 1996-03-07 | Construction method of underground structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH09242091A true JPH09242091A (en) | 1997-09-16 |
JP2927727B2 JP2927727B2 (en) | 1999-07-28 |
Family
ID=13982439
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP8089856A Expired - Lifetime JP2927727B2 (en) | 1996-03-07 | 1996-03-07 | Construction method of underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2927727B2 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102535520A (en) * | 2010-12-13 | 2012-07-04 | 五冶集团上海有限公司 | Waterproof construction method of large-area civil air defense basement |
CN106193119A (en) * | 2016-08-01 | 2016-12-07 | 福州市第三建筑工程公司 | A kind of circular underground structure and layer and section thereof are against operation construction method |
CN110258651A (en) * | 2019-07-16 | 2019-09-20 | 中城投集团第六工程局有限公司 | Basement roof post-cast strip shifts to an earlier date enclosed construction and construction method |
CN113802724A (en) * | 2021-09-27 | 2021-12-17 | 中国建筑第二工程局有限公司 | Anti-seepage construction structure and construction method for outer wall tongue-and-groove joint |
CN114575388A (en) * | 2020-11-30 | 2022-06-03 | 中铁十四局集团大盾构工程有限公司 | Method for improving quality of horizontal construction joint |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0211847U (en) * | 1989-04-26 | 1990-01-25 |
-
1996
- 1996-03-07 JP JP8089856A patent/JP2927727B2/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0211847U (en) * | 1989-04-26 | 1990-01-25 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102535520A (en) * | 2010-12-13 | 2012-07-04 | 五冶集团上海有限公司 | Waterproof construction method of large-area civil air defense basement |
CN106193119A (en) * | 2016-08-01 | 2016-12-07 | 福州市第三建筑工程公司 | A kind of circular underground structure and layer and section thereof are against operation construction method |
CN106193119B (en) * | 2016-08-01 | 2018-04-03 | 福州市第三建筑工程公司 | A kind of circular underground structure and its layer and section are against operation construction method |
CN110258651A (en) * | 2019-07-16 | 2019-09-20 | 中城投集团第六工程局有限公司 | Basement roof post-cast strip shifts to an earlier date enclosed construction and construction method |
CN114575388A (en) * | 2020-11-30 | 2022-06-03 | 中铁十四局集团大盾构工程有限公司 | Method for improving quality of horizontal construction joint |
CN113802724A (en) * | 2021-09-27 | 2021-12-17 | 中国建筑第二工程局有限公司 | Anti-seepage construction structure and construction method for outer wall tongue-and-groove joint |
Also Published As
Publication number | Publication date |
---|---|
JP2927727B2 (en) | 1999-07-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4021056B2 (en) | Underground structure construction method such as underground pit for parking lot installation | |
JP2927727B2 (en) | Construction method of underground structure | |
JP4083334B2 (en) | Underground structure having arch roof and method for constructing the same | |
JPH08269984A (en) | Construction of basement in outside waterproofing construction method | |
JPH09324431A (en) | Construction method of basement | |
JP2813807B2 (en) | How to build an underground tunnel | |
JPH09111776A (en) | Basement and construction method thereof | |
JPS601458B2 (en) | Precast concrete basement construction method | |
JPH0721196B2 (en) | Reverse construction method of underground structure | |
JPH0995955A (en) | External wall construction method of underground structure, external wall construction, waterproof panel for external wall of underground structure, and manufacture thereof | |
JPS6335923A (en) | Basement and its construction | |
JPS621930A (en) | Foundation structure of underground structure | |
JPH0726569A (en) | Pile foundation construction method for structure exposed to partial earth pressure | |
JP2001348886A (en) | Building foundation construction method in weak ground | |
JP3530128B2 (en) | Composite waterproofing method for underground structures | |
JP7362447B2 (en) | How to build buildings | |
JPH10280434A (en) | Construction method for basement under application of outside waterproofing | |
JPH11323966A (en) | Footing block for retaining wall | |
CN107653905B (en) | Full-package waterproof structure for reverse construction method building and construction method thereof | |
JP3401282B2 (en) | Construction method of soil between unit type buildings | |
JPH05230842A (en) | Construction method of underground structure | |
JPS6024249B2 (en) | How to build a basement | |
JPH0711630A (en) | Method of underground continuous wall used for precast prestressed concrete slab wall | |
JPH11166242A (en) | Underground space constructing method and supporting structure in underground space construction | |
JP2796591B2 (en) | Water tank bottom plate mounting structure |