TW418274B - A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall - Google Patents

A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall Download PDF

Info

Publication number
TW418274B
TW418274B TW86117641A TW86117641A TW418274B TW 418274 B TW418274 B TW 418274B TW 86117641 A TW86117641 A TW 86117641A TW 86117641 A TW86117641 A TW 86117641A TW 418274 B TW418274 B TW 418274B
Authority
TW
Taiwan
Prior art keywords
concrete
continuous wall
cast
wall
continuous
Prior art date
Application number
TW86117641A
Other languages
Chinese (zh)
Inventor
Yuan-Hua Jiang
Original Assignee
Jiang Yuan Hua
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiang Yuan Hua filed Critical Jiang Yuan Hua
Priority to TW86117641A priority Critical patent/TW418274B/en
Application granted granted Critical
Publication of TW418274B publication Critical patent/TW418274B/en

Links

Abstract

This is an invention of the construction method for the pre-cast and site-cast retaining and waterproof continuous wall. The main construction procedures are following steps. (1) Use conventional machinery to dredge the necessary guide trench around the building lot. Then hoist and position the pre-cast diaphragm wall units inside the guide trench to dig out for side wall, site-casting concrete followed to fill all gaps on earth pressure side to enhance its stiffness and waterproofing. (2) Dredge right-cross guide trenches on both X-axis and Y-axis at proper intervals. Then hoist and position the pre-cast concrete diaphragm wall units to temporarily support the retaining and waterproof continuous wall, of this pre-cast and site-cast combined construction, around the building lot to make basement earth dredging possible without conventional steel supporting. The pre-cast diaphragm wall units, assembled together with each other by lapping and screwing, can be adjusted into step shape to provide retaining bracing. Since no conventional steel supporting needed while dredging, the construction of this invention is superior to conventional ones on both time saving and cost saving.

Description

418274 五、發明說明α) : ' ~ 在建ΐ二地基擋土防水打造法,尤指-種 滿,達增強勁;與;處:場物土填 挖縱向與橫向正交母隔適當距離掘 父等溝槽,吊放臨時支撐建地四周外圍辟 合式擋土防水連續壁用的預鑄混凝土連續壁, 二!下i 土方開挖無需傳統之鋼支撐,此預鑄連續壁採預 =組叠接並於開挖中可調整成階梯狀, 支撐,挖時機具可直接進入建地内挖掘土方。俟開挖至 Ξ定ίίί陆再由下往上逐層施築樓版,上下層樓版完成 f其間時支撐建地四週外圍用的預鑄連續壁可鬆除Μ 鑄^組合螺針後拔除,亦可留作隔間牆用。對於道路面下 施築地下結構體之公共工程,可採傳統逆築法先行完 表層樓版,並預留足夠挖土機具進出之開口後,即可 道面供交通工具通行,對交通衝擊少。 現在的地基打造法,必須先挖完基地周爵的導 現場灌入混凝土形成連續壁體後,打入垂直支撐鋼柱 進行地下挖土,每挖一定深度,即須架設水平鋼支撐以 撐周圍的場鑄混凝土連續壁,如此返覆逐層挖土及架# 平鋼支撐,俟土方挖掘完成後再將水平鋼支撐以分層拆 回撐方式施築内牆及樓版,於各層樓版完成後雖可拆除 平鋼支撐,但垂直支撐鋼柱於地下層樓版整體完成前不能 拆除。因此’目前的地基打造法,有下述幾 b 1.目前場鑄連續璧的擋土行為須要水平鋼支稽;水平 418274 五、發明說明(2) 鋼支#又須要垂直支擒鋼柱扶持,其中只要有一環節變形 將立即造成開挖失敗’所造成之時間與金錢的損失無法估 計,鋼支撐因-變形而開挖失敗之例在國内外不勝枚舉,在 此不另贅述;另鋼支撐的架設為平面鋪設,每控一定深度 就須鋪設一層鋼支撐’該挖掘工程與鋼支揮是交互進行的 ’無法同時並進’且鋼支樓的層數與地下開挖深度非成等 比增加’為防連續壁因深開挖造成土壓不平衡需以間距較 密之水平鋼支撐來抵消,如此只有造成施工困難並增加工 期與成本(尤以鋼支撐費用極高)’其出土係採加長臂挖土 機或門形吊車配合小型推挖機出土,施工效率低且成本高 〇 2. 地基之外圍為場禱式混凝土連績壁,即在完成之導 溝槽内,於現場灌入混凝土;因導溝槽内的狀況無法預知 ’所灌入的混凝土在導溝槽内即無法成均質狀態,易產生 收龜點,品質不易控制,尤其當導溝槽内發生泥質壁體崩 %時’將導致混凝土與泥土混雜狀態,除所造成之連續壁 參漏問題更嚴重外亦有結構弱點之顧慮。結構弱點造成之 地下水滲流入結構體内將使設備受潮損壞外更不適居住, 一般為達成止水功能,勢必將花費大量金額止水,惟其最 終之效果僅於止漏’而陰滲問題仍需賴裝修處理之。 3. 參考地工技術雜誌第21期,有關場鑄連續壁單元接 缝形式計有*·平頭接縫、連所管接縫、鋼版聚乙烯纖維布 、特殊構造接缝、水密性連續〇 L形接縫等,其共同缺點 為場鑄混凝土單元施工先後之接縫易造成滲水;對於特殊418274 V. Description of the invention α): '~ Construction method for waterproofing of the foundation retaining soil in Jianou II, especially-full planting, strong and strong growth; and; Parents wait for the trench, and suspend the concrete concrete continuous wall used for the temporary support of the surrounding retaining ground and waterproof continuous wall around the construction site. Second, traditional earth support is not required for earth excavation. It can be overlapped and adjusted into a stepped shape during the excavation, and the support can be directly entered into the construction site to dig earth.俟 Excavation to Luding, and then build the floor version one by one from bottom to top. The upper and lower floor versions are completed. During this time, the continuous wall of concrete used to support the periphery of the construction site can be removed and the cast screw can be removed. , Can also be used as a partition wall. For the public works of constructing underground structures under the road surface, the traditional reverse construction method can be used to finish the surface floor version, and sufficient openings for the excavator can be reserved, and the road surface can be used for transportation, which has less impact on the traffic. . The current foundation building method must first be excavated at the base of Zhou Jue ’s site, poured into concrete to form a continuous wall, and driven into vertical support steel columns for underground excavation. For each certain depth, a horizontal steel support must be erected to support the surroundings. The continuous cast-in-place concrete wall of the site is repeated in this way. The flat steel support is used. The flat steel support is used. After the earthwork excavation is completed, the horizontal steel support is used to construct the internal wall and floor in layers. Although the flat steel support can be removed after completion, the vertical support steel column cannot be removed until the underground floor version is completely completed. Therefore, the current foundation building method has the following b 1. The current field casting continuous soil retaining behavior requires horizontal steel support; horizontal 418274 V. Description of the invention (2) Steel support # and vertical support by steel columns The loss of time and money caused by the failure of excavation will be incurred as long as one part of the deformation can't be estimated. The examples of failure of excavation due to -deformation of steel supports are numerous at home and abroad, so I won't repeat them here; The supporting frame is set to be laid on a plane, and a layer of steel support must be laid for each certain depth control. The excavation and steel support are interactive and cannot be performed simultaneously. The number of layers of the steel support is not proportional to the depth of the underground excavation. The increase of 'to prevent the imbalance of soil pressure caused by deep excavation of continuous walls needs to be offset by horizontal steel supports with a relatively close spacing, so that it only causes construction difficulties and increases the construction period and cost (especially the cost of steel support is very high)' Mining with a long-arm excavator or a portal crane coupled with a small pusher excavator, the construction efficiency is low and the cost is high. The periphery of the foundation is a field prayer concrete continuous wall, that is, within the completed guide trench, Concrete is poured into the site; it is impossible to predict because of the conditions in the channel. 'The poured concrete cannot be in a homogeneous state in the channel, which tends to cause turtle collecting points, and the quality is not easy to control, especially when mudiness occurs in the channel. When the wall collapses%, it will lead to a mixed state of concrete and soil. In addition to the serious problem of continuous wall leakage, there are also concerns about structural weakness. Groundwater leakage caused by structural weakness into the structure will make the equipment damp and damaged, making it more uncomfortable to live. Generally, in order to achieve the water-stopping function, it will inevitably spend a lot of money to stop the water, but its ultimate effect is only to stop leakage. Lai decoration dealt with it. 3. Refer to the 21st issue of Geotechnical Magazine. The types of joints for field-cast continuous wall units include: * flat joints, jointed joints, steel polyethylene fabric, special structural joints, and continuous watertightness. Joints, etc., their common disadvantage is that the joints in the construction of cast-in-situ concrete units are likely to cause water seepage;

418274 ~----; ^ ^— ______ ______ 五、發明說明(3) , 構造接縫止滲水理論雖較佳,然其施工複雜且常因璐凝土 壓力過大使特殊構造變形造成更嚴重之滲水問題。. 發明者鑑於上述之缺點,認為要使地下工程建造達到 省工時、省成本、施工方便及品質良好,必須改變時下的 _建造方法,麦是: 本發明之主要目的’在於藉由預鑄場鑄混合式擋土防 水連續壁代替現今場鑄混凝土連續壁;其預鑄式連續壁於 工麻統一製造’再採預鑄材組合螺釘疊接方法吊入導溝槽 ,既可控製預鑄成品之品質又可避免導溝槽深層泥土崩塌 ,另於導溝槽空隙處採場鑄混凝土填塞達完全止水功能。〇 本發明之次要目的’在於藉由建地内縱橫正交之導溝 槽内吊入預鑄混凝土連續壁代替垂直鋼柱及水平鋼表撐, 於挖土方刖已元成支稽·架設’於地下連續開挖中僅有調整 預鑄材組合螺釘工作’無開挖與支撐工作交替進行問題。 本發明之再一目的,在於土方開挖支撐無中間柱,挖 土機具可直接駛入地下進行開挖工作,尤以大地基之開挖 運土卡車可借由開挖斜坡面駛入地下運載棄土。 為使 貴審查委員瞭解本發明的目的及功效,兹借由 以下具體之實施例,並配合所附之圖式,對本發明作一詳 細說明,說明如后: :」 圖式說明: 第1圖係為本發明之平面圖。 第2圖係為本發明之支撐預鑄混凝土連續壁剖面圖。(a —A剖面)418274 ~ ----; ^ ^ — ______ ______ V. Description of the Invention (3) Although the theory of structural joints to prevent water seepage is better, its construction is complicated and often caused by Lu Ning's earth pressure over Ambassador's special structural deformation. Water seepage problem. In view of the above-mentioned shortcomings, the inventor believes that to make underground engineering construction to save man-hours, costs, convenient construction and good quality, the current _ construction method must be changed. Mai is: The main purpose of the present invention is to The cast-type cast mixed retaining water-repellent continuous wall replaces the present-day cast-concrete continuous wall; its concrete-type continuous wall is uniformly manufactured in industrial hemp. The quality of the cast product can avoid the deep soil collapse of the guide groove, and the cast concrete can be filled in the stope gap to achieve a complete water-stop function. 〇The secondary objective of the present invention is 'to replace the vertical steel columns and horizontal steel table braces by hanging concrete continuous walls in the vertical and horizontal guide trenches in the construction site, and the excavation has been completed and erected' In continuous underground excavation, there is only the problem of adjusting the bolts of the concrete material. There is no problem of alternate excavation and support work. A further object of the present invention is that the earth excavation support has no intermediate pillar, and the excavating equipment can directly drive into the ground for excavation work, especially the excavation and transportation truck for large foundations can drive into the ground by excavating the slope surface Spoil. In order for your reviewing committee to understand the purpose and effect of the present invention, the following specific examples are given in conjunction with the accompanying drawings to explain the present invention in detail, as follows: "" Schematic description: Figure 1 This is a plan view of the present invention. Figure 2 is a sectional view of the continuous concrete supporting wall of the present invention. (A —A section)

第6頁 4182 7 :, 418274 五、發明說明(4) 第3圖係為本發明之支撐預鑄混凝土連續壁剖面圖。(B —B剖面) 第4圖係為本發明之結構擋土防水壁體示意圖。 第5圖係為本發明之結構剖面圖。 圖號說明: 1 預鑄式連續壁 1 1建地周圍預鑄場鑄混合式連續壁導溝槽 1 2間隔版 1 3篩泥版 2 支撐用預鑄混凝土連續壁 2 1支撐用預鑄混凝土連續壁導溝槽 2 2預鑄混凝土樑 2 3誤差調整段 3 場鑄混凝土連續壁 3 1鋼筋 3 2預鑄材組合螺釘 3 3場鑄混凝土壓力版 3 4壓力版螺釘 3 5防水彈性材 3 Θ灌漿空隙 4 樓版 請參閱第1及第4圖,係為本發明之平面圖及結構擋 土防水壁體細部示意圖。如调所示:本發明之主要結構由 數條導溝槽1 1及2 1所構成;建地周圍預鑄場鑄混合式Page 6 4182 7:, 418274 V. Description of the invention (4) Figure 3 is a sectional view of the continuous concrete supporting wall of the present invention. (B-B section) Fig. 4 is a schematic diagram of a structural retaining wall of the present invention. Figure 5 is a sectional view of the structure of the present invention. Description of drawing number: 1 concrete continuous wall 1 1 mixed cast-in-place continuous groove guide groove around the construction site 1 2 partition plate 1 3 sieve mud plate 2 concrete concrete continuous wall for support 2 1 concrete concrete for support Continuous wall guide groove 2 2 Concrete beam 2 3 Error adjustment section 3 Field cast concrete continuous wall 3 1 Reinforcement 3 2 Composite material screw 3 Field cast concrete pressure plate 3 4 Pressure plate screw 3 5 Waterproof elastic material 3 The fourth floor version of Θ grouting gap, please refer to Figures 1 and 4, which are the plan view of the present invention and the detailed schematic diagram of the retaining wall. As shown in the note: the main structure of the present invention is composed of several guide grooves 1 1 and 21;

||

第7頁 418274 五、發明說明(5) 連續壁導溝槽1 1 防水或承載侧土壓 統場铸混凝土三分 場籍混凝土連續壁 預鑄混凝土連續壁 蘢)XI (單位厚 混凝土連續壁寬) 所以T =1· 25公尺 狀不完全密合,在 管或採既有技術施 第三道防水功能; 外側垂直或水平結 版3 3、壓力版螺 防水功能;建地周 外侧灌入場鑄混凝 周圍預鑄式連續壁 子形與預轉式連續 厚,具雙重功能: 定位準確性,而在 1 1轉角處吊入之 擇用預鑄混凝土連 最先吊入,用以控 支樓力乃借用於相 限制外侧場鑄混凝 吊入預鑄式連續 單一或雙重功能 之一厚度時,以 5公尺寬之鋼筋 寬為1. 2 5公尺, )X 20〇KG (鋼 X 1 / 3 (單位厚 ),該建地周圍 其灌漿空隙3 6 行灌漿,阻絕地 開挖面水平延伸 點採防水阻絕設 卸3 4及防水彈 圍預鑄場鑄混合 土連續3,此為 1於外侧連有間 壁1結合,總厚 第一功能為控制 建地周圍預鑄場 預鑄式連續壁1 續壁2,契形邊 制後續預鑄式連 臨鄰兩塊預鑄式 土連續壁3的注 壁1 (其設計可為具有 ’具雙重功能者若採傳 同規模吊裝機具,吊裝 籠’在相同深度下可吊 計算式為:5M (鋼筋 筋重/m3)=T (預鑄 )X 240 0KG (RC/m3 ) 預鑄式連續壁1採凹凸 處可預先設置灌漿用軟 下水滲入壁體内,此為 方向於預鑄式連續璧1 施如:場鑄混凝土壓力 性材,3 5 ,此為第二道 式連續壁導溝槽1 1的 第一道防水功能θ建地 隔版12 ,可呈T或I 相同於連續壁挖掘機具 預鑄式連續壁1吊入時 鑄混合式連續壁導溝槽 為契形為免除此處設支 長不宜過大’且契形應 續壁1吊入準確度’其 連續壁1 ;第二功能可 入流動範圍’不似傳統 ΛPage 7 418274 V. Description of the invention (5) Continuous wall guide groove 1 1 Waterproof or bearing side soil pressure field cast concrete three-point field concrete continuous niches concrete continuous niches) XI (unit thick concrete continuous wall width ) So T = 1.25 meters is not completely tight, and the existing technology can be used to apply the third waterproof function; vertical or horizontal knotting on the outside 3 3. Waterproof function of the pressure screw on the outside; Cast-concrete surrounding concrete continuous wall sub-shape and pre-rotation continuous thickness have dual functions: positioning accuracy, and the optional concrete concrete hanging at 11 corners is the first to be used to control the support. Floor force is used for phase-constrained external field cast concrete when hanging in one of the thicknesses of the continuous single or double function. The width of the steel bar with a width of 5 meters is 1.25 meters,) X 20〇KG (steel X 1/3 (unit thickness), the grouting gap around the construction site is 3 6 rows of grouting, the horizontal extension of the excavation surface of the cutoff site is waterproofed and blocked for installation 3 and 4 and the waterproof bomb enclosure is cast with continuous soil 3, this 1 is connected to the outer wall with a combination of 1 and the total thickness. The first function is to control the construction of the land. Wall-type continuous wall 1 continuous wall 2, continuation wall with tapered edge system next to two adjacent soil-shaped soil continuous wall 3 injection wall 1 (its design can be Using the same scale lifting equipment, the lifting cage 'can be hoisted at the same depth. The formula is: 5M (rebar weight / m3) = T (預鑄) X 240 0KG (RC / m3) It can be set in advance to soften the water into the wall for grouting. This is the direction of continuous continuous concrete. 1 Example: field cast concrete pressure material, 3 5 This is the second continuous wall guide groove 1 1 The first waterproof function θ built ground partition 12 can be T or I. It is the same as the continuous wall excavator 預鑄 type continuous wall 1 when cast in. The mixed continuous wall guide groove is tapered to avoid the need to set a support length here. It should not be too large, and the tapered shape should continue to the wall 1 for accuracy of its continuous wall 1; the second function can enter the flow range, unlike traditional Λ

第8頁 4 Ϊ8274 五、發明說明(6) 場鑄混凝土連續壁在灌入碎 合道 钂+ 時會導溝槽面積大,造成場 七4 /,1 易控制,本發明之場鑄混凝土連續壁3除 =f水功效外,尚有穩固建地周圍預鑄式連續壁丄凹凸狀 槽Η内於吊入預鑄:續壁導溝 ,Λ 埽'連續壁1後,於外侧灌入混凝土前 力筋31,使預鑄場鑄混合式連續壁…更強固其勁 二,$水。i地内支撑用預鑄混凝土連續壁導溝 、細人诚> 电人連續壁2,採凹凸狀結合並以預鑄材 ^ 且 ' 確保支撐成平直狀,為控制深開挖土 Ϊ平衡’支撐用預鑄混凝土連續壁2於開挖底面下相;應 處應施作成整體性。 .η 、表鐘ΐ參閱ί ^ :第3胃’係為本發明之支撐預鑄混凝土 j續壁剖面,(A- “Β — Β剖面)。如 内支樓用預鎮土連續壁2乃用U支禮四周連續壁建俜 於建地周圍預鑄式連、續壁i數單元接點處挖掘支 撑用預鎮混凝土連續壁導溝槽2 1 ;此支撑Page 8 4 Ϊ8274 V. Description of the invention (6) The field cast concrete continuous wall will lead to a large groove area when it is poured into the broken road 钂 +, resulting in field 7 4 /, 1 easy to control, the field cast concrete of the present invention is continuous In addition to the water effect of wall 3, there is still a continuous continuous wall 丄 concavo-convex groove around the stable ground to be suspended into the 預鑄: continuous wall guide channel, 埽 埽 ′, after the continuous wall 1, concrete is poured into the outside The front stiffener 31 makes Horiba cast a hybrid continuous wall ... more solid. Second, $ water. iConcrete continuous wall guide trench for in-situ support, slender person > Electric man continuous wall 2, combined with concave and convex shape and using concrete material ^ and 'to ensure that the support is straight, to control the balance of deep excavated soil 'The concrete concrete continuous wall 2 for support is under the excavation bottom surface; it should be integrated as a whole. .η, watch clock, see ^^: The third stomach is the supporting concrete j-continuous wall section of the present invention, (A- “B — Β section). For example, the pre-soiled continuous wall 2 of the inner branch building is Use U support to build a continuous wall around the slab, and dig the support at the joints of the continuous and continuous wall i.

連續壁2的採凹槽狀,待支樓用預鑄混ΐ土ί續 壁2申入完畢再挖方開挖中逐步將建 J 續壁i與建地2支;用預鎊混凝土連續壁2間採=: 合螺釘3 2結。,虽逐步挖深,側向土壓力將轉由預鑄材 組合螺釘3 2以剪力形式抵消,整體侧向土壓傾倒力及土 壓平衡力’將由支撐用預鑄混凝土連續壁2開挖底面下之 垂直反作用力及支撐用預鑄混凝土連續壁2相對應處整體 性之水平反作力抗衡。一般地下深開挖為防止開挖底部發 *The continuous wall 2 is in the shape of a groove, and the branch building will be filled with concrete. The continuation of wall 2 will be completed and then the excavation will be carried out. During the excavation, J will continue to build the wall and 2 land; two pre-pound concrete continuous walls will be used. Mining =: Closing screws 3 2 knots. Although it is gradually deepened, the lateral earth pressure will be offset by the concrete material screws 32 in the form of shear force, and the overall lateral earth pressure dumping force and earth pressure balance force will be excavated by the supporting concrete continuous wall 2 The vertical reaction force under the bottom surface and the horizontal reaction force corresponding to the integrity of the supporting concrete continuous wall 2 are counterbalanced. In general, deep underground excavation is used to prevent the bottom of the excavation *

第9頁 418274 五、發明說明(7) 生隆起或砂 言,可額外 力功能。建 預鑄混凝土 置加勁預鑄 結。因支撐 ,故於開挖 俟開挖至預 層樓版4完 暴除螺釘3 預鑄混凝土 預鑄混凝土 結合6如實 良好,其誤 鑄混凝土連 請參閱 :建地周圍 外侧設有間 泥版1 3, 續壁1吊入 ,可將懸浮 壁1外侧導 留於筛泥版 鑄混凝土連 湧’均採地 另增強支撐 地周圍預鑄 連續壁2水 混凝土樑2 用預鑄混凝 土方中僅有 定深度後, 成後,其間 2後予以抽 連續壁2與 連續壁2預 際施工,支 差調整段可 續壁2不拆 第5圖,係 預鑄式連續 隔版1 2, 該篩泥版1 建地周圍預 泥土沉澱於 溝槽内灌注 1 3之上方 續壁3品質 盤改良措施 用預鑄混凝 式連續壁1 平間距内, 2 ,並以預 土連續壁2 調整預鑄組 再由下往上 臨時支撐用 除,亦可留 樓版4間之 留孔槽,以 撐用預鑄混 不考慮,否 除時,可作 為本發明之 壁1.可直接 並於間隔版 3之_孔作 鑄場鑄混合 導溝槽底部 场禱混凝土 ’因浮泥經 較易確保》 ,此地盤改 土連續壁之 數單元接點 依開挖順序 轉組合螺釘 於土方開挖 合螺釘3 2 逐層施築樓 預鑄混凝土 作隔間用。 結合問題, 鋼筋與後施 凝土連續壁 則需予整修 為永久隔間 結構剖面圖 作為結構體 1 2底·設 適當設計, 式連續壁導 ’建地周圍 連續壁3之 由篩泥版1 良對本發明 垂直反作用 處之支撐用 由上而下設 3 2予以固 前先行放入 組合工作。 版4,上下 連續壁2可 對於支撐用 可於支撐用 築之樓版4 2高程控制 ’支撐用預 牆之用。 。如圖所示 内牆,於其 一至二層篩 於預鑄式連 溝槽1 1時 預鑄式連續 混凝土將停 3過慮,場Page 9 418274 V. Description of the invention (7) The uplift or sand words can provide extra force. Strengthen concrete when building concrete. Due to the support, excavation was carried out in the excavation to the pre-floor version. 4 The screws were completely removed. 3 The concrete was concretely bonded to 6. The concrete was miscast. 3, Continued wall 1 can be suspended, and the floating wall 1 can be guided to the outside of the sieve mud cast concrete, and the surrounding area is reinforced. The continuous wall 2 The water concrete beam 2 After setting the depth, after completion, the continuous wall 2 and continuous wall 2 will be pumped for preliminary construction. The balance adjustment section can be continued without the wall 2 (figure 5). Version 1 Pre-soil around the construction site is settled in the trench and poured above 1 3 Continued wall 3 Quality plate improvement measures Use concrete mixing continuous wall 1 within a flat space 2, and adjust the concrete group with pre-soil continuous wall 2 Then it can be used for temporary support from bottom to top. It can also be used to leave holes in the four floors of the floor version. It is not considered to support the concrete. If it is removed, it can be used as the wall of the present invention. 1. It can be directly used in the partition version 3. _ Kongzuo Casting Plant Casting Mixed Guide Groove Bottom Field Prayer Concrete Paul ", the number of the continuous wall of the contact unit has a site modified by soil excavation sequence to turn screw composition Excavation engagement screw 32 is applied layer by layer to build concrete floor 預鑄 compartment for use. Combining the problems, the continuous wall of reinforced concrete and post-concrete soil needs to be refurbished as a cross-section view of the structure of the permanent compartment as the structural body. 12 The bottom is designed with a proper design. Liang's support for the vertical reaction position of the present invention is fixed from top to bottom, and then put into the combined work before being fixed. Version 4, the upper and lower continuous wall 2 can be used for support. It can be used for support. The building version 4 2 is used for elevation control. . As shown in the figure, the inner wall will be screened on the first to second floor when the trench is connected to the trench. The continuous concrete will stop for 3 minutes.

第10頁 ,4182 74 五、發明說明(8)Page 10, 4182 74 V. Description of the invention (8)

承前所述,發明具有可使地基打造施工方便’支撐用 材料採用預鑄混凝土連續壁’不但品質穩定並可大量生產 降低成本外’對於拆除之支撐用預鑄混凝土連續壁亦可重 複使用,不會浪費資源;預鑄場鑄混合式擋土防水連續壁 因有三道防水功能,無需施築内牆止水’可節省結構造價 及止漏費,又因無中間垂鋼柱及水平鋼支撐,除可節省大 量鋼支樓費用及挖土費用外,亦因施工簡易可縮短工期所 產予之無形利益無法估算。符合發明專利申請之法定要件 管提出發明專利之申請,祈•局早日賜准專利, _According to the foregoing description, the invention has the advantage of making the foundation easy to construct and use. 'Concrete continuous wall for supporting materials' not only has stable quality and mass production and reduces costs. It can also be reused for dismantled concrete continuous walls for support. It will waste resources; due to the three waterproof functions of the cast-in-place hybrid retaining water-repellent continuous wall, there is no need to construct the inner wall to stop water ', which can save structural costs and leakage costs, and because there is no intermediate vertical steel column and horizontal steel support, In addition to saving a lot of steel branch costs and excavation costs, it is also impossible to estimate the intangible benefits that can be shortened due to the ease of construction. Comply with the statutory requirements of the invention patent application

第11頁Page 11

Claims (1)

418274418274 六、申請專利範圍 —種預鑄場鑄混合式擋土防水連續壁體構造之工法, 首先施挖建地四周外圍之導溝槽,在導溝槽内先吊放 入預鑄式連續壁,貼於開挖侧,並於預鑄式連續壁外 侧與土壓力侧間空隙,以現場灌注外圍場鑄混凝土連 續壁;於建地内先行完成開挖底部地盤改良,以增強 臨時支撐用預鑄混凝土連續壁底部垂直反作用能力, 再掘挖縱橫正交或交叉導 土連續壁,成為建地外圍 方開挖中之臨時支撐,於 式連續壁與建地内臨時支 預鑄材結合螺釘結合,以 ’同時支撐用預鑄混凝土 材組合螺釘結合方式調整 下與其相對應邊(處)之臨 形成整體性,以增強臨時 部水平反作用能力,用以 傾倒力及土壓平衡力;開 版,再逐層向上建造樓版 鬆開臨時支撐用預鑄混凝 ’抽出樓版間之支撐用預 離’再整修預留於樓版内 誤差調整段;臨時支撐用 於結構體内作為永久隔間 如申請專利範圍第1項所 溝槽並吊入支撐用預鑄混凝 預鑄場鑄混合式連續壁於土 開挖中逐步將建地外圍預铸 撐用預鱗混凝土連續壁間以 其抗剪能力抵消侧向土壓力 連續壁於開挖過程中以預鏵 成階梯狀’並於開挖完成面 時支撐用預鑄混凝土連續壁 支撐用預鑄混凝土連續壁底 抵抗深開挖之整體侧向土壓 挖至完成面即可施築底層樓 ’上下層樓版完成後可逐層 土連續壁之預鑄材組合螺釘 鑄混凝土連續壁,並逐層吊 支標用預鑄混凝土連續壁之 預鑄混凝土連續壁亦可留置 牆用。6. Scope of patent application—The construction method of the cast-in-place cast hybrid retaining water-repellent continuous wall structure is to first excavate the guide grooves around the construction site and hang the 預鑄 -type continuous wall in the guide groove first. Adhere to the excavation side and fill the gap between the outside of the concrete continuous wall and the earth pressure side to cast the concrete continuous wall in the peripheral field on site; complete the excavation at the bottom of the construction site to improve the temporary support concrete concrete The vertical reaction capacity at the bottom of the continuous wall, and then excavate the vertical or horizontal or cross-conducting continuous wall to become a temporary support during the excavation of the outer side of the construction site. The Yu-type continuous wall is combined with the temporary support materials in the construction site by screws. At the same time, it is supported by the combination of the concrete concrete screw combination method to form a whole with its corresponding edge (office) to enhance the horizontal reaction capacity of the temporary part for the dumping force and earth pressure balance force; open the plate, and then layer by layer Build the floor upwards, loosen the temporary support, use concrete coagulation, 'remove the support between floor versions, and use pre-removal' for refurbishment and reserve it for the error adjustment section in the floor. The structure body is used as a permanent compartment, such as the groove of the first patent application scope, and is suspended into the support. Concrete mixing cast-in-place continuous wall is used in the excavation of the soil. The continuous walls between the concrete continuous walls offset their lateral earth pressure with their shear resistance. The continuous walls were pre-concrete into a stepped shape during the excavation process, and the concrete continuous wall was used to support the concrete concrete wall at the end of the excavation. The overall lateral earth pressure resisting deep excavation can be built to the completion surface, and the ground floor can be built. After the completion of the upper and lower floors, the continuous wall of concrete and screw-cast concrete continuous wall can be constructed layer by layer, and the support is suspended layer by layer. Concrete concrete continuous wall with concrete concrete continuous wall can also be left as wall. 述之預鑄場鑄混合式擋土防Horiba cast hybrid soil retaining 第12頁Page 12 麵 六 3 4 5 4182 74 —— — 申請專利範園 水速續壁體構造之工法,該 其形狀如电 預鑄式連續壁為工廠統〜 製邊^狀如長、t、厚度依 。 •如f請專利範圍第i項所述之 j 水速續壁體構造之工法,1 从,鑄混。式擋土防 式連續壁,於開挖面垂直== 卜圍導溝槽内之預鱗 水乎狀態且不完全密合作為灌聚空Ϊ \:ΪΪί置灌漿用軟管或採既有技術施行灌聚 阻絕地下水滲入壁體内,此盏二 艰 式連續壁外側垂直或水平結點採功能,·預縳 ± - 丁知黏抹防水阻絕之設施如填 轉混凝土麗力版’堡力版螺釘及防切性材,此 二道防水功能;預鑄式連續壁的外側與土壓力侧 空隙場鑄混凝土連續壁,此為第—道防水功能., 預鑄連績壁視材料特性與厚(勁)度,可分為單具有防 水功能或兼具防水與抗侧向土壓力功能;每塊^地周 圍預鑄式連續壁於外侧皆連有間隔版,可呈τ或1 ^ 形與預鑄混凝土連續壁結合厚度相同於連續壁^掘機 具厚度’具有預鑄式連續壁吊入時之定位準確性及限 制場鑄連續壁流動範圍功能;間隔版底部可加設筛泥 版,篩除導溝槽之浮泥。 ' 士申請專利桃圍第1項所述之預禱場禱現合式撞土防 水連續壁體構造之工法,其建地四周外圍導溝槽之角 偶處填入之預鑄式連續壁可為契形。 如申請專利範圍第1項所述之預鑄場鑄混合式撞土防 水連續壁體構造之工法,其建地四周外圍導溝槽内在Surface 6 3 4 5 4182 74 ———— Applicable to the patent Fan Yuan The construction method of the water-speed continuous wall structure, the shape of which is the same as the electric-type continuous wall of the factory, and the edges are like long, t, and thickness. • As described in item f of the patent scope, please refer to the method for j water-speed continued wall structure construction, 1 from, casting and mixing. -Type retaining wall, vertical wall on the excavation surface == The pre-scale water in the guide channel is in a state of incomplete and incomplete close cooperation. It is used to fill the empty space. Irrigation and polymerization are used to prevent groundwater from seeping into the wall. The vertical or horizontal nodes on the outside of this distressed continuous wall adopt the function of pre-binding ±-Ding Zhi sticks waterproof barrier facilities such as filling concrete Lili version 'baoli version' Screws and cut-resistant materials, these two waterproof functions; the outer side of the concrete type continuous wall and the earth pressure side gap field cast concrete continuous wall, this is the first channel waterproof function. (Stiffness), can be divided into single with waterproof function or both waterproof and lateral earth pressure resistance function; each ^ ground around the 預鑄 -type continuous wall on the outside are connected to the partition plate, can be τ or 1 ^ shape and结合 The combined thickness of the concrete continuous wall is the same as the thickness of the continuous wall. ^ The thickness of the digging machine has the function of positioning accuracy when the continuous wall is hoisted and the function of limiting the flow range of the continuous wall of the field casting. Remove the floating mud from the guide groove. '' The patent application for the construction method of the prayer praying site and the continuous waterproof wall structure described in Taowei No. 1 in the patent application. The 连续 type continuous wall filled in at the corners of the outer guide grooves around the construction site may be Shaped. According to the construction method of the Horiba cast hybrid soil-impact continuous water wall structure described in item 1 of the scope of the patent application, the peripheral guide grooves around the construction site are internal 第13頁 4182 74 六、申請專利範圍 吊入預鑄式連續壁 與土遷力侧之間, 混合式連續壁之勁 6 ·如申請專利範圍第 水連續壁體構造之 釘結合後,可視勁 連續壁水平間距内 設加勁預鑄混凝土 7 ·如申請專利範圍第 水連續壁體構造之 連續壁之吊入法, 8 *如申請專利範圍第 水連續壁體構造之 包含鋼筋混凝土以 9 ·如申請專利範圍第 水連續壁體構造之 於任何掘挖施工機 續壁體厚度係與導 後,加設鋼 再灌注場鑄 度及防水功 1項所述之 工法,其連 度加強需要 與建地周圍 並以預鑄材 1項所述之 工法,其臨 可採凹槽階 1項所述之 工法,其預 外之材料。 1項所述之 工法,其所 具,而預鑄 溝槽掘挖施 筋於預鑄 混凝土, 能。 預鑄場鑄 續壁間以 ,於支撐 預鑄式連 組合螺釘 預鑄場鑄 時支撐用 梯狀態者 預鑄場鑄 鱗式連續 預鑄場鑄 需掘挖之 場鑄混合 工機具同 式連續 提高預 混合式 預鑄材 用預鑄 續壁單 結合。 混合式 的預鑄 〇 混合式 壁材質 混合式 導溝槽 式擋土 寬。 壁外側 鑄場鑄 擋土防 組合螺 混凝土 元間架 擋土防 混凝土 擋土防 之組合 撞土防 不受限 防水連Page 13 4182 74 6. The patent application range is suspended between the concrete continuous wall and the soil movement force side, and the strength of the hybrid continuous wall 6 · If the nails of the water continuous wall structure in the patent application range are combined, the strength can be seen Reinforced concrete is installed in the horizontal space of continuous wall. 7 · If the continuous wall of the continuous wall structure of the patent application is suspended, 8 * If the continuous wall structure of the patent application includes reinforced concrete, The scope of the patent application scope is the continuous wall thickness of any excavation and construction machine. The thickness of the continuous wall of any excavation and construction machine is the same as that of the guide. A steel reperfusion field casting degree and waterproof work are added. Around the ground, use the method described in item 1 of the wood material, which can be used in the method described in item 1 of the groove step, and the extra materials. The method described in item 1 has its own, and the trench concrete excavation can be reinforced with concrete. Horiba casting continuous wall, supporting the state of the ladder when supporting the cast iron with combination screws Improve the pre-mixed type of lintel continuous wall single joint. Hybrid 預鑄 〇 Hybrid Wall Material Hybrid Guide Groove Retaining Width. Outside the wall Foundry casting Retaining defense Combined screw concrete Element frame Retaining defense Concrete Retaining defense Combination Impact prevention Unrestricted Waterproof connection 第14頁Page 14
TW86117641A 1997-06-20 1997-06-20 A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall TW418274B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW86117641A TW418274B (en) 1997-06-20 1997-06-20 A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW86117641A TW418274B (en) 1997-06-20 1997-06-20 A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall

Publications (1)

Publication Number Publication Date
TW418274B true TW418274B (en) 2001-01-11

Family

ID=21627288

Family Applications (1)

Application Number Title Priority Date Filing Date
TW86117641A TW418274B (en) 1997-06-20 1997-06-20 A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall

Country Status (1)

Country Link
TW (1) TW418274B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI472668B (en) * 2012-06-15 2015-02-11

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI472668B (en) * 2012-06-15 2015-02-11

Similar Documents

Publication Publication Date Title
CN103741714B (en) Underground engineering full sheltered reverse excavation construction method
CN107542108B (en) A kind of reverse construction method of building basement structure
CN205742213U (en) Foundation pit supporting construction
KR20210148031A (en) tunnel shaft and Construction Method forstructures according to the excavation.
CN107012871B (en) A kind of suspension type goes along with sb. to guard him the deep reversed construction method for greatly enhancing foundation pit fabricated construction
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
CN108797637A (en) Prefabricated board combined cast-in-situ concrete considers the underground pipe gallery construction method of structure and ground
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
JP2000008394A (en) Construction method for underground structure such as underground pit for installation of parking lot
JP2000352296A (en) Method o constructing passage just under underground structure
CN105113513B (en) Anti-seepage foundation pit supporting structure and construction method
KR100376590B1 (en) Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts
TW418274B (en) A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall
CN205804366U (en) A kind of slag runner structure
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
CN114922195A (en) Construction method of soft soil deep and large foundation pit adjacent to protected object
CN110318419A (en) The construction method of the lining door opening supporting of underpass type piping lane one
JPS582294B2 (en) Continuous basement wall construction method
KR200291370Y1 (en) Concrete caisson structure for earth and sand guard of pier's basis
KR100981061B1 (en) Method for backfill gap of structure
CN217601446U (en) A concrete waist rail watertight fittings for facing combine underground structure forever
CN209907437U (en) Cover digging method is with trading propping to pass power area
JP2571426B2 (en) Construction method of retaining wall
CN210562118U (en) Novel combined steel sheet pile
CN206667229U (en) Diaphragm wall circular construction joint waterproof construction

Legal Events

Date Code Title Description
GD4A Issue of patent certificate for granted invention patent
MM4A Annulment or lapse of patent due to non-payment of fees