CN109138227A - Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology - Google Patents

Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology Download PDF

Info

Publication number
CN109138227A
CN109138227A CN201811223942.0A CN201811223942A CN109138227A CN 109138227 A CN109138227 A CN 109138227A CN 201811223942 A CN201811223942 A CN 201811223942A CN 109138227 A CN109138227 A CN 109138227A
Authority
CN
China
Prior art keywords
wall
exterior
construction
concrete
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811223942.0A
Other languages
Chinese (zh)
Inventor
王宝
王军良
高玉磊
方园
王婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao No 1 Construction Group Co Ltd
Original Assignee
Qingdao No 1 Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao No 1 Construction Group Co Ltd filed Critical Qingdao No 1 Construction Group Co Ltd
Priority to CN201811223942.0A priority Critical patent/CN109138227A/en
Publication of CN109138227A publication Critical patent/CN109138227A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • E04B2/8611Walls made by casting, pouring, or tamping in situ made in permanent forms with spacers being embedded in at least one form leaf
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • E04B2002/8682Mixed technique using permanent and reusable forms

Abstract

The present invention relates to technical field of building construction, especially without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology, including binding cushion block, composite insulation boards are installed, through-wall bolt is installed, installation template primary and secondary is stupefied, casting concrete and form removal, plate face cleaning, concrete curing and inspection, cast-in-place position and filled wall binding site are handled, partitioning slot construction, this engineering method uses two-sided inorganic composite heat-preserving plate, without using outer wall template, direct wooden flute is fixed, insulation board directly contacts curing concrete with concrete, improve concrete quality, there is the inorganic surface layer protection of 3mm in inside, it can be tightly combined with concrete, heat insulation core material can be protected again, cushion block encircles into insulation board when preventing from vibrating, this engineering method can shorten the high altitude operation time, outer wall template dosage is saved, both construction safety, guarantee that construction survives again Quality, and exterior wall is poured and is constructed simultaneously with insulating layer, can accelerate speed of application, reduces engineering cost.

Description

Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology
Technical field
The present invention relates to technical field of building construction, especially without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding Construction technology.
Background technique
Currently, traditional high-rise civil building exterior wall and the construction method of heat preservation are mostly to be carried out after cast-in-place concrete structure again The stickup of outer heat preservation system is installed, and common exterior wall heat-preserving system includes: to paste EPS sheet, XPS plate, rock wool board, and sprayed rigid foam is poly- Urethane heat preservation etc..Conventional construction method needs first casting concrete structure when pouring exterior wall, decoration stage is kept the temperature again after demoulding The stickup of plate, and fixed using outer wall template, concrete conjugation is poor, cannot protect to heat insulation core material, when vibrating Cushion block easily encircles into insulation board, constructs relatively complicated, time-consuming and laborious, the process for increasing sticking heat-preservation plate increases the entire duration The high and medium activity duration, a large amount of outer wall templates are needed, not only increased the security risk and construction cost of work progress, but also reduced and apply Work Survival Rate, slows down construction speed, reduces construction efficiency.
Summary of the invention
In view of the above shortcomings of the prior art, it provides no exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding is constructed Technique, insulation board directly can contact curing concrete with concrete, improve concrete quality, whether there is or not the protections of machine side layer for inside, both It can be tightly combined, and heat insulation core material can be protected with concrete, cushion block encircles into insulation board when preventing from vibrating, and shortens entire High and medium activity duration duration, outer wall template dosage is substantially saved, not only the safety of work progress, but also has been easily guaranteed that and is constructed into Bioplasm amount, effectively accelerates construction progress, easy to operate, work efficiency is high, and techno-economic effect is obvious.
In order to solve the above technical problems, the technical solution adopted by the present invention is that, no exterior sheathing exterior-wall heat insulation and structure one Body pouring molding construction technology, includes the following steps:
(1), after exterior wall steel corrosion quantity is qualified, cement mortar bedding block that binding is made by thickness of concrete cover requirements and often No less than 6 pieces in block insulation board.
(2), insulation board is cut: thermal insulating composite panel is cut in advance, is then pacified by the requirement provided according to engineering construction figure Fill thermal insulating composite panel, plate connect with plate opposite joint when installation, erection sequence: hung just vertically after by sequence assembly guarantor from left to right Warm production board, when construction section is larger can at two or at two more than construct simultaneously assembly, assembling method: monolith when assembled insulation board Insulation board splicing is firmly fitted together by two people up and down of plate simultaneously, and then installation is bored by predetermined position in finished product thermal insulation plate face Self-fastening anchoring piece is put at the position of hole anchoring piece, mounting hole spacing composite insulation boards should be not less than 50mm, and pass through The anchoring piece tail portion of insulation board is fixed it with wall steel bar with steel wire, and every square meter binding and fixing point is not less than 5, and adjusts Save the vertical flatness of plate face.
(3), through-wall bolt is installed: according to the spacing of thermal insulating composite panel through-wall bolt, drilling to thermal insulating composite panel, makes the lumps of wood It coincide with the hole of thermal insulating composite panel, through-wall bolt is passed through into hole.
(4), installation template primary and secondary is stupefied: vertical Outer Wall side is vertical secondary stupefied, is transversely mounted 2 48*3.5mm steel of horizontal direction Frame pipe is stupefied as master, and fixed inner and outer template, primary and secondary are stupefied, adjusts heat preservation Board position and verticality by construction requirement.
(5), casting concrete and form removal: after wall has found template, must be blocked in the upper end of composite insulation boards, Concreting in lifts, concrete discharging should be uniformly dispersed, be carried out continuously, and vibrating spear vibrates spacing and is not less than 0.5m, Mei Yizhen The perdurabgility of dynamic point is presented laitance with surface and does not sink now for degree.
(6), plate face cleaning, concrete curing and inspection: thermal insulating composite panel surface is cleared up, keeps the temperature plate surface such as after form removal There is cement slurry that should clear up in time, and examine the flatness of heat preservation plate surface, then carry out next process, by wall vibration compacting Uniformly, the bolt lore of through-wall bolt is smoothed out with polymerized in-situ object cement mortar, and complex heat-preservation plate cast-in-place concrete system is compound Insulation board construct it is cast-in-place after begin to carry out 25mm thickness leveling mortar construction.
(7), cast-in-place position and filled wall binding site are handled: when filled wall completion is no earlier than 14 days, using width The steel wire of 200mm, centered on bonding wire, then the levelling whole face wall of plastering mortar is used in the fixation of 100 millimeters of every side again Body, levelling thickness 20mm are intact by pinning steel wire all standing.
(8), partitioning slot is constructed: heat preservation plate heat preserving system presses the horizontal cracking resistance partitioning slot of storey setting before levelling construction, hangs down Straight cracking resistance partitioning slot is arranged by wall area, and area is not more than 36 ㎡, separates slit width 20mm, rejects insulation board until exposing wall Body, then insulating layer is filled up with A grades of glue powder polyphenyl particle slurries, finally filled and led up using plug sealant.
It is above-mentioned without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology, in the step (2), every layer Between composite insulation boards be higher by 20mm, then carry out upper layer construction.
It is above-mentioned without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology, for master ga(u)ge lattice can not be used to pacify The position of dress should be cut into satisfactory non-master specification with cast-cutting saw at the construction field (site) in advance, and non-master dimension board is most Small width is not less than 150mm.
It is above-mentioned without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology, it is secondary stupefied in the step (4) Specification is 40mm*70mm or 50mm*80mm.
It is above-mentioned without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology, in the step (6), plastering When levelling, wall overdrying is not easy to construct, then answers metope to spray water or carry out interfacial agents construction in advance, after plastering mortar completes 7 days, i.e., It can carry out the construction of 5mm thickness anticracking grout.
It is above-mentioned without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology, it is described in the step (7) Steel wire is galvanized steel wire netting, and specification is not less than 1.6*1.6*25, and plastering mortar requirement: M15 or 1:3 cement mortar adds 108 glue It uses.
It is above-mentioned without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology, in the step (8), sealing Glue should use polyurethane, silicone, acrylic ester type building sealant.
It is above-mentioned without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology, the thermal insulating composite panel be with XPS is core material, and 20mm glue powder polyphenyl particle slurry is wrapped up in side, and 3mm inorganic protective layer is wrapped up in the other side.
The present invention is the present invention without exterior sheathing exterior-wall heat insulation and the beneficial effect of structure-integrated pouring molding construction technology Suitable for industry and civil buildings exterior-wall heat insulation, it is particularly suitable for cast-in-place high residential building exterior wall heat-preserving system, using two-sided inorganic Composite insulation boards do not use outer wall template, and direct wooden flute is fixed, and insulation board directly contacts curing concrete with concrete, improve There are the inorganic surface layer protection of 3mm in concrete quality, inside, can be tightly combined with concrete and protect to heat insulation core material, Cushion block encircles into insulation board when preventing from vibrating, and can shorten the entire duration high and medium activity duration, substantially save outer wall template dosage, Not only the safety of work progress, but also be easily guaranteed that construction Survival Rate, effectively accelerates construction progress, and it is easy to operate, work efficiency is high, Techno-economic effect is obvious.
Insulation board is using XPS as core material, and 20mm glue powder polyphenyl particle slurry is wrapped up in side, and the inorganic guarantor of 3mm is wrapped up in the other side Sheath.This system is integrated it with concreting, and be reliably connected by connector based on double-sided composite insulating board And the cast-in-situ thermal-insulated system formed.In cast-in-place concrete construction, directly insulation board is reinforced as exterior wall outboard template, by steel The anchor bolt in reinforcing bar and composite insulation boards in reinforced concrete wall, after reinforcing bar binding and fixing, concreting in lifts.
The compound composition of layer in outside is mainly rubber powder granule, and is not burnt, and can be used as coat of plaster on the outside of insulation board, and play Template action also has fire-proof function, guarantees construction safety.External wall structure pours progress synchronous with exterior-wall heat insulation construction, to ensure Engineering, which is completed ahead of schedule, creates good condition, can shorten one month compared to the conventional construction method duration, while passing through this side Case application saves a large amount of formwork cost and insulation board pastes expense, largely reduces construction cost, has preferable Techno-economic effect and higher application value.
Detailed description of the invention
Fig. 1 for no exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology flow chart.
Specific embodiment
It elaborates combined with specific embodiments below to the present invention.
As shown in Figure 1, including the following steps: without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology
(1), after exterior wall steel corrosion quantity is qualified, cement mortar bedding block that binding is made by thickness of concrete cover requirements and often No less than 6 pieces in block insulation board, cushion block quantity is depending on plate is high, to ensure to have between reinforcing bar and insulation board enough outside cement Protective layer, and ensure outside insulation thickness uniformity.
(2), insulation board is cut: thermal insulating composite panel is cut in advance, is then pacified by the requirement provided according to engineering construction figure Thermal insulating composite panel is filled, plate is connect with plate opposite joint when installation, should in advance at the construction field (site) for that can not use the position of master ga(u)ge lattice installation It is cut into satisfactory non-master specification with cast-cutting saw, non-master dimension board minimum widith is not less than 150mm.
Erection sequence: hung it is just vertical after can be by sequence assembly heat preservation production board from left to right, when construction section is larger It constructs assembly simultaneously more than at two or at two, assembling method: two people up and down of entire plate will firmly protect simultaneously when assembled insulation board Warm plate splicing is fitted together, and is then put into self-tightening at position of the installation by predetermined position borehole anchorage part in finished product thermal insulation plate face Stationary anchoring piece, mounting hole spacing composite insulation boards should be not less than 50mm, and pass through the anchoring piece tail portion steel wire of insulation board It is fixed with wall steel bar, every square meter binding and fixing point is not less than 5, and adjust the vertical flatness of plate face, every layer it Between composite insulation boards be higher by 20mm, then carry out upper layer construction, flatness is more preferably.
(3), through-wall bolt is installed: according to the spacing of thermal insulating composite panel through-wall bolt, being drilled to thermal insulating composite panel, the side of making Wood coincide with the hole of thermal insulating composite panel, and hole should not be too big in order to avoid spillage, passes through hole, through-wall bolt fastening for through-wall bolt Correction, connect must it is tight, secured, prevent dislocation and spillage phenomenon.
(4), installation template primary and secondary is stupefied: vertical Outer Wall side is vertical secondary stupefied, and secondary stupefied specification is 40mm*70mm or 50mm* 80mm is transversely mounted 2 48*3.5mm steel frame pipes of horizontal direction and is used as master stupefied, and fixed inner and outer template, primary and secondary are stupefied, by construction requirement tune Whole heat preservation Board position and verticality.
Composite insulation boards install tolerance (mm)
Inspection item Tolerance Inspection method
Axial dimension 5 Steel tape inspection
Column, wall, beam section size 4, -5 Steel tape inspection
Layer high verticality 6 Theodolite or line pendant check
Surface smoothness 5 2 meters of guiding rulers and clearance gauge inspection
External corner verticality 3 2 meters of guiding rulers and clearance gauge inspection
Adjacent two surface difference of height 2 Steel tape inspection
(5), it casting concrete and form removal: after wall has found template, must be blocked in the upper end of composite insulation boards, coagulation Native placement layer by layer, concrete discharging should be uniformly dispersed, be carried out continuously, and vibrating spear vibrates spacing and is not less than 0.5m, each oscillation point Perdurabgility, with surface present laitance and do not sink now for spend.
(6), thermal insulating composite panel surface is cleared up, makes plate face cleaning without dirt, plate face cleaning, concrete curing and inspection: clear Thermal insulating composite panel surface is managed, heat preservation plate surface should clear up in time if any cement slurry after form removal, and examine heat preservation plate surface Flatness, then next process is carried out, wall vibration compacting is uniform, the bolt lore polymerized in-situ object cement bonded sand of through-wall bolt Slurry smoothes out, and it is levelling that complex heat-preservation plate cast-in-place concrete system begins to progress 25mm thickness after composite insulation boards construction is cast-in-place The construction of mortar, when plaster leveling, wall overdrying is not easy to construct, then answers metope to spray water or pre- carry out interfacial agents construction, plastering sand After slurry completion 7 days, the construction of 5mm thickness anticracking grout can be carried out.
(7), cast-in-place position and filled wall binding site are handled: when filled wall completion is no earlier than 14 days, using width The steel wire of 200mm, steel wire are galvanized steel wire netting, and specification is not less than 1.6*1.6*25, centered on bonding wire, every side 100 Millimeter fixation, then uses the levelling whole face wall of plastering mortar again, and levelling thickness 20mm is complete by pinning steel wire all standing It is good.Plastering mortar requirement: M15 or 1:3 cement mortar adds 108 glue to use.
(8), partitioning slot is constructed: heat preservation plate heat preserving system presses the horizontal cracking resistance partitioning slot of storey setting before levelling construction, hangs down Straight cracking resistance partitioning slot is arranged by wall area, and area is not more than 36 ㎡, separates slit width 20mm, rejects insulation board until exposing wall Body, then fill up insulating layer with A grades of glue powder polyphenyl particle slurries is finally filled and led up using plug sealant, sealant should using polyurethane, Silicone, acrylic ester type building sealant.
Thermal insulating composite panel be using XPS as core material, side wrap up 20mm glue powder polyphenyl particle slurry, the other side wrap up 3mm without Machine protective layer, insulation board directly contact curing concrete with concrete, improve concrete quality, and inside has the inorganic surface layer of 3mm to protect Shield, can be tightly combined with concrete and protect to heat insulation core material, cushion block encircles into insulation board when preventing from vibrating, this is System is based on double-sided composite insulating board to be integrated it with concreting, and be reliably connected to be formed by connector Cast-in-situ thermal-insulated system.In cast-in-place concrete construction, directly insulation board is reinforced as exterior wall outboard template, by reinforced concrete wall The anchor bolt in reinforcing bar and composite insulation boards in body, after reinforcing bar binding and fixing, concreting in lifts.
The compound composition of layer in outside is mainly rubber powder granule, and is not burnt, and can be used as coat of plaster on the outside of insulation board, and play Template action also has fire-proof function, guarantees construction safety.This engineering method is few using template number, and occupancy building-site space is small, only The step of needing one-time-concreting i.e. plastic, reducing sticking heat-preservation plate, from and also reduce construction time in decoration of exterior wall stage, Speed of application can effectively be accelerated.
Material
Composite insulation boards are marched into the arena, and quality of materials documentary evidence must be complete effective, and can come into operation after retrial is qualified.
Insulation board connecting material: 10 × 160 engineering plastics anchor bolt of φ.
Decorative mortar, anticracking grout, alkaline-resisting grid cloth.
Flexible waterproof putty and by design requirement use water-based elastic paint (or face brick).
Metal binding wire (zinc-plated).
Equipment
The main equipment that this engineering method is related to includes: operating platform, box ruler, ink fountain, electric saw, detection instrument (line cone, guiding ruler, longitude and latitude Instrument), reinforced steel bar binding tool, bench saw etc..
Quality control method
Before formal construction, preferably first makees template and lead the way.
Column, beam portion position preferably increase anchoring piece, reinforce connecting with main body.
Increase cement support at every screw rod through walls, insulation board is avoided to eat wall, column, beam phenomenon.
It checks whether anchoring piece has outer obscission when pouring concrete, such as finds the anchoring piece position of fastening adjustment in time, guarantee Exterior-wall heat insulation is effectively connect with shear wall.
It is covered after materials arrival with tarpaulin, prevents rainforest deformation of being exposed to the sun.
The positions such as composite insulation boards edge joint position, yin-yang angle intersection, smear pressure with finishing mucilage and squeegee, and are laid with Alkali-resisting fiberglass mesh, Reinforce Crack Resistance processing.
Certainly, above description is not limitation of the present invention, and the present invention is also not limited to the example above, the art The variations, modifications, additions or substitutions made within the essential scope of the present invention of those of ordinary skill, also should belong to the present invention Protection scope.

Claims (8)

1. without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology, which comprises the steps of:
(1), after exterior wall steel corrosion quantity is qualified, cement mortar bedding block that binding is made by thickness of concrete cover requirements and often No less than 6 pieces in block insulation board;
(2), insulation board is cut: the requirement provided according to engineering construction figure in advance cuts thermal insulating composite panel, and then installation is protected Warm composite plate, plate is connect with plate opposite joint when installation, erection sequence: hung it is just vertical after by sequence assembly heat preservation from left to right at Product plate, when construction section is larger can at two or at two more than construct simultaneously assembly, assembling method: entire plate when assembled insulation board Upper and lower two people simultaneously firmly by insulation board splicing is fitted together, then in finished product thermal insulation plate face installation by predetermined position drill anchor Self-fastening anchoring piece is put at the position of firmware, mounting hole spacing composite insulation boards should be not less than 50mm, and pass through heat preservation The anchoring piece tail portion of plate is fixed it with wall steel bar with steel wire, and every square meter binding and fixing point is not less than 5, and adjustable plate The vertical flatness in face;
(3), through-wall bolt is installed: according to the spacing of thermal insulating composite panel through-wall bolt, being drilled to thermal insulating composite panel, makes the lumps of wood and protects The hole of warm composite plate coincide, and through-wall bolt is passed through hole;
(4), installation template primary and secondary is stupefied: vertical Outer Wall side is vertical secondary stupefied, is transversely mounted 2 48*3.5mm steel frame pipes of horizontal direction Stupefied as master, fixed inner and outer template, primary and secondary are stupefied, adjust heat preservation Board position and verticality by construction requirement;
(5), it casting concrete and form removal: after wall has found template, must be blocked in the upper end of composite insulation boards, coagulation Native placement layer by layer, concrete discharging should be uniformly dispersed, be carried out continuously, and vibrating spear vibrates spacing and is not less than 0.5m, each oscillation point Perdurabgility, with surface present laitance and do not sink now for spend;
(6), plate face cleaning, concrete curing and inspection: thermal insulating composite panel surface is cleared up, heat preservation plate surface is if any water after form removal Material-mud should be cleared up in time, and examine the flatness of heat preservation plate surface, then carry out next process, and wall vibration compacting is equal Even, the bolt lore of through-wall bolt is smoothed out with polymerized in-situ object cement mortar, and complex heat-preservation plate cast-in-place concrete system is in compound guarantor Warm plate construct it is cast-in-place after begin to carry out 25mm thickness leveling mortar construction;
(7), cast-in-place position and filled wall binding site are handled: when filled wall completion is no earlier than 14 days, with width 200mm's Steel wire, centered on bonding wire, then the levelling whole face wall of plastering mortar, levelling thickness are used in the fixation of 100 millimeters of every side again 20mm is spent, pinning steel wire all standing is intact;
(8), partitioning slot is constructed: heat preservation plate heat preserving system presses the horizontal cracking resistance partitioning slot of storey setting before levelling construction, vertical anti- Partitioning slot is split to be arranged by wall area, area is not more than 36 ㎡, separates slit width 20mm, insulation board is rejected until exposing wall, then Insulating layer is filled up with A grades of glue powder polyphenyl particle slurries, is finally filled and led up using plug sealant.
2. no exterior sheathing exterior-wall heat insulation according to claim 1 and structure-integrated pouring molding construction technology, feature It is that in the step (2), composite insulation boards are higher by 20mm between every layer, then carry out upper layer construction.
3. no exterior sheathing exterior-wall heat insulation according to claim 1 and structure-integrated pouring molding construction technology, feature It is that, for the position that master ga(u)ge lattice can not be used to install, should be cut at the construction field (site) with cast-cutting saw in advance satisfactory non-master Specification, non-master dimension board minimum widith are not less than 150mm.
4. no exterior sheathing exterior-wall heat insulation according to claim 1 and structure-integrated pouring molding construction technology, feature It is that in the step (4), secondary stupefied specification is 40mm*70mm or 50mm*80mm.
5. no exterior sheathing exterior-wall heat insulation according to claim 1 and structure-integrated pouring molding construction technology, feature That in the step (6), when plaster leveling, wall overdrying is not easy to construct, then answer metope spray water or it is pre- carry out interfacial agents construction, After plastering mortar completes 7 days, the construction of 5mm thickness anticracking grout can be carried out.
6. no exterior sheathing exterior-wall heat insulation according to claim 1 and structure-integrated pouring molding construction technology, feature It is that in the step (7), the steel wire is galvanized steel wire netting, and specification is not less than 1.6*1.6*25, plastering mortar requirement: M15 or 1:3 cement mortar adds 108 glue to use.
7. no exterior sheathing exterior-wall heat insulation according to claim 1 and structure-integrated pouring molding construction technology, feature It is that in the step (8), sealant should use polyurethane, silicone, acrylic ester type building sealant.
8. no exterior sheathing exterior-wall heat insulation according to claim 1 and structure-integrated pouring molding construction technology, feature It is that the thermal insulating composite panel is using XPS as core material, and 20mm glue powder polyphenyl particle slurry is wrapped up in side, and it is inorganic that 3mm is wrapped up in the other side Protective layer.
CN201811223942.0A 2018-10-19 2018-10-19 Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology Pending CN109138227A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811223942.0A CN109138227A (en) 2018-10-19 2018-10-19 Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811223942.0A CN109138227A (en) 2018-10-19 2018-10-19 Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology

Publications (1)

Publication Number Publication Date
CN109138227A true CN109138227A (en) 2019-01-04

Family

ID=64809144

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811223942.0A Pending CN109138227A (en) 2018-10-19 2018-10-19 Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology

Country Status (1)

Country Link
CN (1) CN109138227A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853790A (en) * 2019-01-29 2019-06-07 哈尔滨鸿盛建筑材料制造股份有限公司 A kind of EPS module concrete frame filling wall construction technology
CN110866304A (en) * 2019-12-25 2020-03-06 中铁建设集团有限公司 Method for creating integrated straight wall component model based on steel bar formwork
CN111576681A (en) * 2020-05-15 2020-08-25 荣华建设集团有限公司 FS composite heat-preservation construction integrated technology construction process
CN115075545A (en) * 2022-06-20 2022-09-20 北京天润建设有限公司 Construction method of composite heat-insulation formwork

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103343617A (en) * 2013-07-17 2013-10-09 临沂铭泰建材科技有限公司 Thermal-insulation external form board and dismounting-free external form board insulating system
CN103835505A (en) * 2012-11-26 2014-06-04 中国建筑第七工程局有限公司 Outer wall compound heat preservation board construction method
CN106836567A (en) * 2017-01-24 2017-06-13 北京振利节能环保科技股份有限公司 A kind of rock wool cast-in-situ concrete heat-insulation wall with ribbing and its construction method
CN207499403U (en) * 2017-04-16 2018-06-15 山东博泰建设集团有限公司 A kind of FS composite thermal-insulating exterior formworks system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103835505A (en) * 2012-11-26 2014-06-04 中国建筑第七工程局有限公司 Outer wall compound heat preservation board construction method
CN103343617A (en) * 2013-07-17 2013-10-09 临沂铭泰建材科技有限公司 Thermal-insulation external form board and dismounting-free external form board insulating system
CN106836567A (en) * 2017-01-24 2017-06-13 北京振利节能环保科技股份有限公司 A kind of rock wool cast-in-situ concrete heat-insulation wall with ribbing and its construction method
CN207499403U (en) * 2017-04-16 2018-06-15 山东博泰建设集团有限公司 A kind of FS composite thermal-insulating exterior formworks system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
QQ14994638: "《FS复合外模板保温建筑节能专项施工方案》", 21 June 2017, HTTP://WWW.DOC88.COM/P-4092876309291.HTML *
车其杰等: "《安徽建筑》", 28 February 2017 *
钟汉华: "《建筑施工技术》", 28 February 2014, 中国电力出版社 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853790A (en) * 2019-01-29 2019-06-07 哈尔滨鸿盛建筑材料制造股份有限公司 A kind of EPS module concrete frame filling wall construction technology
CN110866304A (en) * 2019-12-25 2020-03-06 中铁建设集团有限公司 Method for creating integrated straight wall component model based on steel bar formwork
CN110866304B (en) * 2019-12-25 2024-02-02 中铁建设集团有限公司 Method for creating integrated straight wall component model based on reinforcing steel bar template
CN111576681A (en) * 2020-05-15 2020-08-25 荣华建设集团有限公司 FS composite heat-preservation construction integrated technology construction process
CN115075545A (en) * 2022-06-20 2022-09-20 北京天润建设有限公司 Construction method of composite heat-insulation formwork

Similar Documents

Publication Publication Date Title
CN104594387B (en) Improved post-cast strip advance water stop construction method
CN104358341B (en) Building brickwork and masonry construction method of building brickwork
CN109138227A (en) Without exterior sheathing exterior-wall heat insulation and structure-integrated pouring molding construction technology
CN101818527B (en) Assembled integral shear wall structure system and construction method thereof
CN109267677A (en) A kind of GAT external mold plate cast-in-place concrete compound insulation system and its construction technology
CN100572710C (en) The non-net polyphenyl plate cast-in-place concrete exterior wall heat-preserving job practices
CN103883026B (en) The construction method of the cast-in-situ thermal-insulated composite outer wall system of green energy conservation
CN103866885B (en) The construction method of the energy-saving heat preserving structure of light inlet window
CN101845857B (en) Metal mesh built-in insulating outer wall and construction method thereof
CN104314204A (en) Non-form stripping lightweight internal partition board and overall grouting construction method thereof
CN102644382B (en) Mounting technology of large-module wall
CN103835505A (en) Outer wall compound heat preservation board construction method
CN112459291A (en) Prefabricated heat insulation structure integrated wall structure and construction process thereof
CN109577639A (en) Exterior wall protects mould integrated board and aluminum alloy mould plate combined system construction method
CN108589975A (en) Assembling cladding and construction technology
CN111042392A (en) Construction method of SDHH type disassembly-free formwork foam concrete partition wall
CN103883022B (en) The construction method of space enclosing structure inner-outer wall antidetonation and sound insulation cracking resistance integrated structure
CN203856099U (en) Environment-friendly energy-saving cast-in-place heat-insulating windowed composite exterior wall system
CN106121102B (en) Precast concrete peripheral protective sandwich type wall panel mounts connection construction method
CN106639099B (en) Plant-fibre type heat preservation dismounting-free formwork formwork system surface smoothness control method
CN111379337B (en) Secondary structure anti-seepage and anti-leakage construction method
CN205502377U (en) Hanging wallboard is partly inlayed to unit -installment light
CN105937279B (en) The cast-in-place Integral Steel frame wall filled with masonry system and construction method of steel disc limit connection
CN211774518U (en) Node structure for fixedly connecting steel beam and aerated concrete block
CN105971155A (en) Installation joint for outer wallboards

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190104

RJ01 Rejection of invention patent application after publication