CN107932010A - 地铁列车转向架更换设备 - Google Patents
地铁列车转向架更换设备 Download PDFInfo
- Publication number
- CN107932010A CN107932010A CN201610891696.0A CN201610891696A CN107932010A CN 107932010 A CN107932010 A CN 107932010A CN 201610891696 A CN201610891696 A CN 201610891696A CN 107932010 A CN107932010 A CN 107932010A
- Authority
- CN
- China
- Prior art keywords
- electric flat
- subway train
- flat carriage
- assembling
- subway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000008878 coupling Effects 0.000 claims description 8
- 238000010168 coupling process Methods 0.000 claims description 8
- 238000005859 coupling reaction Methods 0.000 claims description 8
- 239000000203 mixture Substances 0.000 claims description 7
- 230000003014 reinforcing effect Effects 0.000 claims description 4
- 238000012423 maintenance Methods 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000011017 operating method Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23P—METAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
- B23P19/00—Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
- B66F3/00—Devices, e.g. jacks, adapted for uninterrupted lifting of loads
- B66F3/08—Devices, e.g. jacks, adapted for uninterrupted lifting of loads screw operated
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Structural Engineering (AREA)
- Types And Forms Of Lifts (AREA)
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
本发明涉及地铁列车检修设备,更换地铁列车上、出现问题的转向架。它的特征是:支撑装置1安装在与地铁列车地面轨道24等高的地面基础上、处于地铁车体22两侧的下方,电动平车2设置在地坑内,在电动平车2的下面设置螺杆升降机装配3,可根据需要,升高或落下电动平车2,当电动平车2处于升起状态时,作为地铁列车的轨道使用,当电动平车2处于落下状态时,可沿运行轨道21横向运行,移出地铁列车,更换转向架。
Description
技术领域
本发明涉及地铁列车检修设备,能方便快捷的更换地铁列车上、出现问题的转向架。
技术背景:
地铁列车转向架是地铁列车的重要部件,转向架的运行安全性影响到地铁列车的运行品质和乘客运输安全性。地铁列车转向架是列车牵引动力、车辆载荷的直接承受者。因此,在地铁列车运行过程中,特别关注转向架的运行安全性。
地铁列车转向架由受流器装配、驱动装置、基础制动装置、牵引装置、一系弹簧、二系悬挂装置、轮对轴箱装置、构架等部件组成,每个部件都是许多个零件的有机组合体,比如轮对轴箱装置是由车轮、车轴、轴箱、轴承等许多零件组成。任何一个零部件的故障,都会影响到转向架的运行安全性。
为了提高地铁列车的运用率,减少地铁列车的停放维护时间,地铁列车从结构上考虑了转向架的互换性。拆除转向架与其上部车辆之间连接,就可更换出现问题的转向架。
现有地铁列车转向架检修更换时,采用地坑式架车机将整个的地铁列车举升到一定的高度,然后将需要更换的转向架回落到地面上,进行转向架的更换。其优点是:不用拆除车厢之间的连接(电源电缆、通信信号电缆、机械车钩等),可以直接更换出现问题的转向架,在更换转向架的过程中,不会产生其他的故障隐患。但也有弊病:一是地坑式架车机是将整个地铁列车举升起来,投资费用比较高,占地面积比较大。二是用地坑式架车机更换转向架时,需要把整个列车架起一定的高度,架车单元比较多,设备比较复杂,其中的任何一个架车单元出现问题,都可能影响更换作业的正常进行,故障率比较高。
发明内容
针对现有地铁列车转向架更换设备所存在的问题,本发明提出地铁列车转向架更换设备,保留了用地坑式架车机更换转向架的优点,同时也克服了所存在的弊病:降低设备造价、降低设备的故障率。本地铁列车转向架更换设备的是通过如下措施来实现的:
地铁列车转向架更换设备包括支撑装置1、电动平车2、螺杆升降机装配3、运行轨道21。支撑装置1安装在与地铁列车地面轨道24等高的地面基础上、处于地铁车体22两侧的下方,电动平车2设置在地坑内,在电动平车2上设置有钢轨13,作为地铁列车地面轨道24的一部分,在电动平车2的下面设置螺杆升降机装配3,可根据需要,升高或落下电动平车2,当电动平车2处于升起状态时,作为地铁列车的轨道使用,当电动平车2处于落下状态时,作为横向运行的平车使用。
支撑装置1由调节螺杆4、支撑杆组件5、连接板6、转轴7、安装座8、加强筋9、预埋件10组成。支撑杆组件5能绕转轴7转动,当需要电动平车2落下时,支撑杆组件5直立,调节螺杆4处于支撑杆组件5的上端,通过旋转调节螺杆4,支承地铁车体22。
电动平车2由从动车轮装配11、车架12、钢轨13、主动车轮装配14组成,在车架12上安装了与地铁列车相同规格的钢轨13,供地铁列车通过。主动车轮装配14、从动车轮装配11安装在车架12的下面。在电动平车2处于落下状态时,可沿运行轨道21横向运行。在电动平车2处于升起状态时,作为地铁列车的轨道,允许地铁列车通过。
螺杆升降机装配3由螺杆升降机15、长轴联轴器装配16、短轴联轴器装配17、高速段联轴器装配18、电动机装配19、螺旋锥转向箱20组成。电动机装配19往两端出轴,通过两侧的螺旋锥转向箱20,驱动螺杆升降机15做升降运动,实现电动平车2的功能转换。
本发明所涉及的地铁列车转向架更换设备,与采用地坑式架车机,更换转向架相比,具有如下优点:1、结构简单。不需将整个列车架起,仅需按操作步骤,针对有问题的转向架进行直接更换即可。2、操作简单。对设备的同步控制要求低。3、因为仅仅针对有问题的转向架进行直接更换,设备投入少,因此投资费用低,占地面积小。4、安全可靠。转向架的更换工作仅需在地面高度上进行,不需将整个地铁列车抬起,不存在安全隐患。5、同时具有地坑式架车机更换转向架的优点:不用拆除车厢之间的连接(电源电缆、通信信号电缆、机械车钩等),可以直接更换出现问题的转向架,在更换转向架的过程中,不会产生其他的故障隐患。
附图说明
图1----地铁列车转向架更换设备主视图(转向架移出列车)
图2----地铁列车转向架更换设备主视图(转向架在列车下面)
图3----地铁列车转向架更换设备俯视图
图4----地铁列车转向架更换设备左视图
图5----支撑装置1的主视图
图6----支撑装置1的左视图
图7----电动平车2的主视图
图8----电动平车2的俯视图
图9----螺杆升降机装配3的平面布置图
支撑装置1、电动平车2、螺杆升降机装配3、调节螺杆4、支撑杆组件5、连接板6、转轴7、安装座8、加强筋9、预埋件10、从动车轮装配11、车架12、钢轨13、主动车轮装配14、螺杆升降机15、长轴联轴器装配16、短轴联轴器装配17、高速段联轴器装配18、电动机装配19、螺旋锥转向箱20、运行轨道21、地铁车体22、转向架23、地面轨道24。
具体实施方式
下面结合附图1、图2、附图3、附图4、附图5、附图6、附图7、附图8、附图9对实施方式进行说明。
地铁列车转向架更换设备由支撑装置1、电动平车2、螺杆升降机装配3、运行轨道21组成。支撑装置1安装在与地铁列车地面轨道24等高的地面基础上、处于地铁车体22两侧的下方,电动平车2设置在地坑内,在电动平车2上设置有钢轨13,作为地铁列车地面轨道24的一部分,在电动平车2的下面设置螺杆升降机装配3,可根据需要,升高或落下电动平车2,当电动平车2处于升起状态时,作为地铁列车的轨道使用,当电动平车2处于落下状态时,作为横向运行的平车使用。
支撑装置1(如图5、图6所示)由调节螺杆4、支撑杆组件5、连接板6、转轴7、安装座8、加强筋9、预埋件10组成。支撑杆组件5能绕转轴7转动,当需要电动平车2落下时,支撑杆组件5直立,调节螺杆4处于支撑杆组件5的上端,通过旋转调节螺杆4,支承地铁车体22。
电动平车2(如图7、图8所示)由从动车轮装配11、车架12、钢轨13、主动车轮装配14组成,在车架12上安装了与地铁列车相同规格的钢轨13,供地铁列车通过。主动车轮装配14、从动车轮装配11安装在车架12的下面。在电动平车2处于落下状态时,可沿运行轨道21横向运行。在电动平车2处于升起状态时,作为地铁列车的轨道,允许地铁列车通过。
螺杆升降机装配3(如图9所示)由螺杆升降机15、长轴联轴器装配16、短轴联轴器装配17、高速段联轴器装配18、电动机装配19、螺旋锥转向箱20组成。电动机装配19往两端出轴,通过两侧的螺旋锥转向箱20,驱动螺杆升降机15做升降运动,实现电动平车2的功能转换。
地铁列车转向架更换设备的工作过程:1)启动地铁列车,将需要更换的转向架23置于地铁列车转向架更换设备的电动平车2的上方。2)将支撑装置1回转到直立状态,并旋转调节螺杆4,直至调节螺杆4接触到地铁车体22两侧的下侧面上。3)解除转向架23与地铁车体22之间的连接。4)启动螺杆升降机装配3,将电动平车2降下到运行轨道21上,转向架23也随着电动平车2下降。5)启动电动平车2,横向运行到地铁列车的外侧适当位置(图1所示的位置上)。用合格的转向架更换出现问题的转向架。6)启动电动平车2,横向运行到地铁列车的下方(图2所示的位置上)。7)启动螺杆升降机装配3,将电动平车2升起,恢复转向架23与地铁车体22之间的连接。8)将支撑装置1落下,完成一个转向架的更换工作。
Claims (4)
1.一种地铁列车转向架更换设备,包括支撑装置(1)、电动平车(2)、螺杆升降机装配(3)、运行轨道(21),其特征是支撑装置(1)安装在与地铁列车地面轨道(24)等高的地面基础上、处于地铁车体(22)两侧的下方,电动平车(2)设置在地坑内,在电动平车(2)上设置有钢轨(13),作为地铁列车地面轨道(24)的一部分,在电动平车(2)的下面设置螺杆升降机装配(3),可根据需要,升高或落下电动平车(2),当电动平车(2)处于升起状态时,作为地铁列车的轨道使用,当电动平车(2)处于落下状态时,作为横向运行的平车使用。
2.根据权利要求1所述的地铁列车转向架更换设备,其特征是支撑装置(1)由调节螺杆(4)、支撑杆组件(5)、连接板(6)、转轴(7)、安装座(8)、加强筋(9)、预埋件(10)组成,支撑杆组件(5)能绕转轴(7)转动,当需要电动平车(2)落下时,支撑杆组件(5)直立,调节螺杆(4)处于支撑杆组件(5)的上端,通过旋转调节螺杆(4),支承地铁车体(22)。
3.根据权利要求1所述的地铁列车转向架更换设备,其特征是电动平车(2)由从动车轮装配(11)、车架(12)、钢轨(13)、主动车轮装配(14)组成,在车架(12)上安装了与地铁列车相同规格的钢轨(13),供地铁列车通过,主动车轮装配(14)、从动车轮装配(11)安装在车架(12)的下面,在电动平车(2)处于落下状态时,可沿运行轨道(21)横向运行,在电动平车(2)处于升起状态时,作为地铁列车的轨道,允许地铁列车通过。
4.根据权利要求1所述的地铁列车转向架更换设备,其特征是螺杆升降机装配(3)由螺杆升降机(15)、长轴联轴器装配(16)、短轴联轴器装配(17)、高速段联轴器装配(18)、电动机装配(19)、螺旋锥转向箱(20)组成,电动机装配(19)往两端出轴,通过两侧的螺旋锥转向箱(20),驱动螺杆升降机(15)做升降运动,实现电动平车(2)的功能转换。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610891696.0A CN107932010A (zh) | 2016-10-13 | 2016-10-13 | 地铁列车转向架更换设备 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610891696.0A CN107932010A (zh) | 2016-10-13 | 2016-10-13 | 地铁列车转向架更换设备 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107932010A true CN107932010A (zh) | 2018-04-20 |
Family
ID=61928823
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610891696.0A Pending CN107932010A (zh) | 2016-10-13 | 2016-10-13 | 地铁列车转向架更换设备 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107932010A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113146508A (zh) * | 2021-04-16 | 2021-07-23 | 中铁第一勘察设计院集团有限公司 | 车体落成转向架移动对位装置 |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2454225A (en) * | 1947-07-31 | 1948-11-16 | Whiting Corp | Apparatus for supporting bodies of railway vehicles in connection with removal and replacement of the trucks thereof |
CN87215916U (zh) * | 1987-11-30 | 1988-08-17 | 班学智 | 建筑用可调支撑 |
RO106230B1 (ro) * | 1989-07-19 | 1993-03-31 | Judeteana De Transport Local | Instalație pentru schimbat boghiuri la tramvai |
RU2099222C1 (ru) * | 1995-10-27 | 1997-12-20 | Научно-внедренческий центр "Путевые машины" Дальневосточной государственной академии путей сообщения | Устройство для замены тележек транспортного средства |
KR980008949A (ko) * | 1996-07-19 | 1998-04-30 | 열차대차의 교체작업장치 | |
CN2858202Y (zh) * | 2005-12-22 | 2007-01-17 | 北京聚龙科技发展有限公司 | 机车车辆转向架更换装置 |
CN201132555Y (zh) * | 2007-09-28 | 2008-10-15 | 中铁工程设计院有限公司 | 转向架更换设备 |
CN201371349Y (zh) * | 2009-04-02 | 2009-12-30 | 北京铁科合力科技有限责任公司 | 动车组转向架更换设备 |
CN201620615U (zh) * | 2010-01-30 | 2010-11-03 | 盛明春 | 建筑工程模板支撑可调节立柱 |
CN201913565U (zh) * | 2011-01-25 | 2011-08-03 | 徐工集团工程机械股份有限公司科技分公司 | 一种新型可调浮动支撑机构 |
CN202559772U (zh) * | 2012-04-17 | 2012-11-28 | 中国十七冶集团有限公司 | 可调节式预制板、墙临时支撑杆 |
CN104071173A (zh) * | 2014-07-22 | 2014-10-01 | 北京控股磁悬浮技术发展有限公司 | 一种磁悬浮车辆的转向架更换系统及更换方法 |
CN204800252U (zh) * | 2015-05-14 | 2015-11-25 | 北京聚龙科技发展有限公司 | 机车车辆转向架更换装置 |
CN105460831A (zh) * | 2014-09-26 | 2016-04-06 | 梅尔乔加比隆多有限公司 | 千斤顶 |
CN206216199U (zh) * | 2016-10-13 | 2017-06-06 | 中铁华铁工程设计集团有限公司 | 地铁列车转向架更换设备 |
-
2016
- 2016-10-13 CN CN201610891696.0A patent/CN107932010A/zh active Pending
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2454225A (en) * | 1947-07-31 | 1948-11-16 | Whiting Corp | Apparatus for supporting bodies of railway vehicles in connection with removal and replacement of the trucks thereof |
CN87215916U (zh) * | 1987-11-30 | 1988-08-17 | 班学智 | 建筑用可调支撑 |
RO106230B1 (ro) * | 1989-07-19 | 1993-03-31 | Judeteana De Transport Local | Instalație pentru schimbat boghiuri la tramvai |
RU2099222C1 (ru) * | 1995-10-27 | 1997-12-20 | Научно-внедренческий центр "Путевые машины" Дальневосточной государственной академии путей сообщения | Устройство для замены тележек транспортного средства |
KR980008949A (ko) * | 1996-07-19 | 1998-04-30 | 열차대차의 교체작업장치 | |
CN2858202Y (zh) * | 2005-12-22 | 2007-01-17 | 北京聚龙科技发展有限公司 | 机车车辆转向架更换装置 |
CN201132555Y (zh) * | 2007-09-28 | 2008-10-15 | 中铁工程设计院有限公司 | 转向架更换设备 |
CN201371349Y (zh) * | 2009-04-02 | 2009-12-30 | 北京铁科合力科技有限责任公司 | 动车组转向架更换设备 |
CN201620615U (zh) * | 2010-01-30 | 2010-11-03 | 盛明春 | 建筑工程模板支撑可调节立柱 |
CN201913565U (zh) * | 2011-01-25 | 2011-08-03 | 徐工集团工程机械股份有限公司科技分公司 | 一种新型可调浮动支撑机构 |
CN202559772U (zh) * | 2012-04-17 | 2012-11-28 | 中国十七冶集团有限公司 | 可调节式预制板、墙临时支撑杆 |
CN104071173A (zh) * | 2014-07-22 | 2014-10-01 | 北京控股磁悬浮技术发展有限公司 | 一种磁悬浮车辆的转向架更换系统及更换方法 |
CN105460831A (zh) * | 2014-09-26 | 2016-04-06 | 梅尔乔加比隆多有限公司 | 千斤顶 |
CN204800252U (zh) * | 2015-05-14 | 2015-11-25 | 北京聚龙科技发展有限公司 | 机车车辆转向架更换装置 |
CN206216199U (zh) * | 2016-10-13 | 2017-06-06 | 中铁华铁工程设计集团有限公司 | 地铁列车转向架更换设备 |
Non-Patent Citations (1)
Title |
---|
李龙根,第70-71页,上海交通大学出版社,2014年8月: "《机械制造技术》", 31 August 2014, 上海交通大学出版社, pages: 70 - 71 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113146508A (zh) * | 2021-04-16 | 2021-07-23 | 中铁第一勘察设计院集团有限公司 | 车体落成转向架移动对位装置 |
CN113146508B (zh) * | 2021-04-16 | 2023-09-19 | 中铁第一勘察设计院集团有限公司 | 车体落成转向架移动对位装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206216199U (zh) | 地铁列车转向架更换设备 | |
CN206255822U (zh) | 一种转向架拆装移动设备 | |
CN102718172A (zh) | 兼容型地坑式架车机车体举升单元 | |
CN102701111A (zh) | 地坑式架车机分段式翻转盖板装置 | |
CN202245932U (zh) | 轨道交通车辆转向架举升装置 | |
CN107932010A (zh) | 地铁列车转向架更换设备 | |
CN202626775U (zh) | 多轮支承转盘道岔 | |
CN207211884U (zh) | 一种二层立体停车设备 | |
CN204978655U (zh) | 一种低地板铰接动车组转向架驱动及制动装置 | |
CN203334742U (zh) | 无齿条式无避让立体停车设备 | |
CN105417431A (zh) | 一种架车机组同步升降方法 | |
CN202687722U (zh) | 锁罐摇台 | |
CN108891437B (zh) | 一种动力工艺转向架 | |
CN208774784U (zh) | 一种工艺转向架驱动结构以及工艺转向架 | |
CN204454420U (zh) | 一种结构简单的列车同步架车机 | |
CN101704488A (zh) | 一种移动式轨道车辆举升机 | |
CN201580369U (zh) | 气袋升降气垫移动落车机 | |
CN210529388U (zh) | 公铁两用铣磨车体 | |
CN205257901U (zh) | 一种用于锁定托头的卡销结构 | |
CN205257899U (zh) | 一种架车机用丝杠的安装结构 | |
CN210002981U (zh) | 一种立体停车库用升降机构 | |
CN202609867U (zh) | 兼容型地坑式架车机车体举升单元 | |
CN206842958U (zh) | 一种用于辅助拆装机车驱动单元的系统 | |
CN101890875B (zh) | 一种重型车轮拆装装置 | |
CN217376955U (zh) | 一种家用电梯对重装置结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |