CN107781504B - 架空管道的集成化拆除方法 - Google Patents
架空管道的集成化拆除方法 Download PDFInfo
- Publication number
- CN107781504B CN107781504B CN201610733559.4A CN201610733559A CN107781504B CN 107781504 B CN107781504 B CN 107781504B CN 201610733559 A CN201610733559 A CN 201610733559A CN 107781504 B CN107781504 B CN 107781504B
- Authority
- CN
- China
- Prior art keywords
- pipeline
- overhead
- hoisting
- supporting platform
- disassembly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
Abstract
本发明涉及建筑构件的运输或装配领域,具体为一种架空管道的集成化拆除方法。一种架空管道的集成化拆除方法,待拆除的架空管网(1)包括管道(11)和吊架(12),其特征是:按如下步骤依次实施:a.规划;b.设置;c.拆卸;d.转运。本发明操作方便,降低作业强度,减少成本,工作效率高,安全可靠。
Description
技术领域
本发明涉及建筑构件的运输或装配领域,具体为一种架空管道的集成化拆除方法。
背景技术
随着冶金、化工业的发展,去产能已经陆续开始实施,随即面临着大量落后的生产线需要拆除或者拆迁。架空管道素有生产线的“大动脉”之称,拆除工程中架空管道拆除工作一直是重中之重。现有的架空管道拆除多采用破坏性拆除或将管道支架及管道逐一拆除的模式,不环保、不经济,拆除工作量大而且危险系数高,大大的增加了作业成本及工人的劳动强度,也不利于工期进度控制。
发明内容
为了克服现有技术的缺陷,提供一种操作方便、降低作业强度、减少成本、工作效率高、安全可靠的管道拆除方法,本发明公开了一种架空管道的集成化拆除方法。
本发明通过如下技术方案达到发明目的:
一种架空管道的集成化拆除方法,待拆除的架空管网包括管道和吊架,各条管道水平地铺设在吊架内,吊架的顶端固定在顶支撑平台上,顶支撑平台选用厂房的天花板,或者在地面固定立柱,在各根立柱上水平地固定横梁,以横梁作为顶支撑平台,其特征是:按如下步骤依次实施:
a 规划:在拆卸地,根据架空管网确定分割面,分割面将架空管网分隔成一个个拆卸单元,即相邻的两个分割面之间包含一个拆卸单元;
b 设置:在顶支撑平台上固定吊点,相邻的两个分割面之间包含至少一个吊点,每个吊点上都设置一个起吊装置,使各个起吊装置都系住起吊装置各自所在吊点对应的拆卸单元;
c 拆卸:沿分割面切割管道,使各个拆卸单元互相脱离;
d 转运:用起吊装置将各个拆卸单元逐个卸至搬运车上,装车运出拆卸地。
所述的架空管道的集成化拆除方法,其特征是:
步骤a规划时,分割面按如下原则确定:i. 分割面垂直于管道,ii. 每个拆卸单元最多包含两个吊架;
步骤b设置时,起吊装置选用差动滑轮或吊装钢丝绳,相邻两个起吊装置的起吊力之和不小于拆卸单元重量的1.2倍;
步骤c拆卸时,选用气割或锯切切割管道。
本发明通过进行管道及其支架作集成化分段,并合理设置分割面和拼合面,将大量的高空拆除及再装工作缩减至两个一次性工作,将管道及其支架整体拆除,大大降低了高空作业的危险性及作业强度,提高了施工进度及降低了施工成本。本发明可适用于厂房内及厂房外大型综合管网拆除工作。
本发明的有益效果是:操作方便,降低作业强度,减少成本,工作效率高,安全可靠。
附图说明
图1是本发明中待拆除的架空管网的剖面示意图;
图2是本发明中确定分割面的示意图;
图3是本发明中分割下的拆卸单元的示意图。
具体实施方式
以下通过具体实施例进一步说明本发明。
实施例1
待拆除的架空管网1如图1和图2所示:待拆除的架空管网1包括管道11和吊架12,各条管道11水平地铺设在吊架12内,吊架12的顶端固定在顶支撑平台2上,顶支撑平台2可以选用厂房的天花板,或者如本实施例所示,在地面固定立柱21,在各根立柱21上水平地固定横梁22,以横梁22作为顶支撑平台2,
架空管道的集成化拆除方法,按如下步骤依次实施:
a 规划:在拆卸地,根据架空管网1确定分割面3,分割面3将架空管网1分隔成一个个拆卸单元13,即相邻的两个分割面3之间包含一个拆卸单元13;
如图2所示:分割面3按如下原则确定:i. 分割面3垂直于管道11,ii. 每个拆卸单元13最多包含两个吊架12;
b 设置:在顶支撑平台2上固定吊点4,相邻的两个分割面3之间包含至少一个吊点4,每个吊点4上都设置一个起吊装置5,使各个起吊装置5都系住起吊装置5各自所在吊点4对应的拆卸单元13;起吊装置5选用差动滑轮或吊装钢丝绳,相邻两个起吊装置5的起吊力之和不小于拆卸单元13重量的1.2倍;
c 拆卸:沿分割面3用用气割或锯切切割管道11,使各个拆卸单元13互相脱离,分割后的拆卸单元13如图3所示;
d 转运:用起吊装置5将各个拆卸单元13逐个卸至搬运车上,装车运出拆卸地。
Claims (2)
1.一种架空管道的集成化拆除方法,待拆除的架空管网(1)包括管道(11)和吊架(12),各条管道(11)水平地铺设在吊架(12)内,吊架(12)的顶端固定在顶支撑平台(2)上,顶支撑平台(2)选用厂房的天花板,或者在地面固定立柱(21),在各根立柱(21)上水平地固定横梁(22),以横梁(22)作为顶支撑平台(2),其特征是:按如下步骤依次实施:
a 规划:在拆卸地,根据架空管网(1)确定分割面(3),分割面(3)将架空管网(1)分隔成一个个拆卸单元(13),即相邻的两个分割面(3)之间包含一个拆卸单元(13);
b 设置:在顶支撑平台(2)上固定吊点(4),相邻的两个分割面(3)之间包含至少一个吊点(4),每个吊点(4)上都设置一个起吊装置(5),使各个起吊装置(5)都系住起吊装置(5)各自所在吊点(4)对应的拆卸单元(13);
c 拆卸:沿分割面(3)切割管道(11),使各个拆卸单元(13)互相脱离;
d 转运:用起吊装置(5)将各个拆卸单元(13)逐个卸至搬运车上,装车运出拆卸地。
2.如权利要求1所述的架空管道的集成化拆除方法,其特征是:
步骤a规划时,分割面(3)按如下原则确定:i. 分割面(3)垂直于管道(11),ii. 每个拆卸单元(13)最多包含两个吊架(12);
步骤b设置时,起吊装置(5)选用差动滑轮或吊装钢丝绳,相邻两个起吊装置(5)的起吊力之和不小于拆卸单元(13)重量的1.2倍;
步骤c拆卸时,选用气割或锯切切割管道(11)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610733559.4A CN107781504B (zh) | 2016-08-27 | 2016-08-27 | 架空管道的集成化拆除方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610733559.4A CN107781504B (zh) | 2016-08-27 | 2016-08-27 | 架空管道的集成化拆除方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107781504A CN107781504A (zh) | 2018-03-09 |
CN107781504B true CN107781504B (zh) | 2020-11-03 |
Family
ID=61438391
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610733559.4A Active CN107781504B (zh) | 2016-08-27 | 2016-08-27 | 架空管道的集成化拆除方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107781504B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112727148B (zh) * | 2020-12-23 | 2022-09-27 | 上海建工集团股份有限公司 | 建筑结构外侧竖向排烟风管整体拆除方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103437369A (zh) * | 2013-08-30 | 2013-12-11 | 上海建工二建集团有限公司 | 一种深基坑支护及其拆除方法 |
US20150139734A1 (en) * | 2012-04-12 | 2015-05-21 | Enereco S.P.A. | Method for removing from a terrain a buried pipe and a cutting machine used for actuating the method |
CN104727192A (zh) * | 2015-02-09 | 2015-06-24 | 安徽兴宇轨道装备有限公司 | 一种拆卸整体道床的施工方法 |
CN104806822A (zh) * | 2015-04-16 | 2015-07-29 | 上海市安装工程集团有限公司 | 组合式立管及其模块化安装方法 |
CN105479098A (zh) * | 2014-10-10 | 2016-04-13 | 五冶集团上海有限公司 | 一种大型煤气管道在线拆除方法 |
-
2016
- 2016-08-27 CN CN201610733559.4A patent/CN107781504B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150139734A1 (en) * | 2012-04-12 | 2015-05-21 | Enereco S.P.A. | Method for removing from a terrain a buried pipe and a cutting machine used for actuating the method |
CN103437369A (zh) * | 2013-08-30 | 2013-12-11 | 上海建工二建集团有限公司 | 一种深基坑支护及其拆除方法 |
CN105479098A (zh) * | 2014-10-10 | 2016-04-13 | 五冶集团上海有限公司 | 一种大型煤气管道在线拆除方法 |
CN104727192A (zh) * | 2015-02-09 | 2015-06-24 | 安徽兴宇轨道装备有限公司 | 一种拆卸整体道床的施工方法 |
CN104806822A (zh) * | 2015-04-16 | 2015-07-29 | 上海市安装工程集团有限公司 | 组合式立管及其模块化安装方法 |
Also Published As
Publication number | Publication date |
---|---|
CN107781504A (zh) | 2018-03-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100557168C (zh) | 一种大跨度钢桁架高空安装方法 | |
CN103061506B (zh) | 一种钢结构穹顶的施工方法 | |
CN111042540A (zh) | 超大跨度预应力管桁架地面挂索空中对接的施工方法 | |
CN102409838A (zh) | 移动操作平台及利用移动操作平台的屋面吊顶施工方法 | |
CN107781504B (zh) | 架空管道的集成化拆除方法 | |
CN104018659A (zh) | 一种球罐内部定检辅助载人器具 | |
CN111779229B (zh) | 一种大型通风管道的施工安装方法 | |
CN110040646B (zh) | 用于厂房屋面固定电动葫芦的方法 | |
CN202220435U (zh) | 逆作地下混凝土结构降模设备 | |
CN105040592B (zh) | 一种平拉索桥及其架设方法 | |
WO2023193403A1 (zh) | 一种成排管束吊装工装及其施工方法 | |
CN107487423B (zh) | 一种船用悬挂式脚手架及其建造方法 | |
CN103791156A (zh) | 大直径玻璃钢管道超高空快速安装方法 | |
CN110700573A (zh) | 一种采用钢梁的模板支撑体系施工方法、装置及应用 | |
CN215060111U (zh) | 一种大口径立管安装固定结构 | |
CN103486330B (zh) | 车间内部高空管道安装施工方法 | |
CN115507222A (zh) | 一种风管安装装置及安装方法 | |
US11390497B2 (en) | Construction system | |
CN211971497U (zh) | 一种热力站管道简易吊装装置 | |
CN210884873U (zh) | 一种管道的安装吊梁及吊装设备 | |
CN204001751U (zh) | 超高层钢结构施工悬挑卸料平台 | |
CN202481941U (zh) | 一种用于悬吊汽轮机轴瓦的平衡装置 | |
CN102635732A (zh) | 较长管线的安装工艺 | |
CN208735013U (zh) | 一种小尺寸管线活动式吊架 | |
CN112342330A (zh) | 用于高炉冷却壁的安装方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |