CN107781504A - 架空管道的集成化拆除方法 - Google Patents

架空管道的集成化拆除方法 Download PDF

Info

Publication number
CN107781504A
CN107781504A CN201610733559.4A CN201610733559A CN107781504A CN 107781504 A CN107781504 A CN 107781504A CN 201610733559 A CN201610733559 A CN 201610733559A CN 107781504 A CN107781504 A CN 107781504A
Authority
CN
China
Prior art keywords
pipeline
aerial
removable unit
boom hoisting
dismounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610733559.4A
Other languages
English (en)
Other versions
CN107781504B (zh
Inventor
孙剑
魏尚起
蔡联河
胡俊
王增堂
李宁
宁健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201610733559.4A priority Critical patent/CN107781504B/zh
Publication of CN107781504A publication Critical patent/CN107781504A/zh
Application granted granted Critical
Publication of CN107781504B publication Critical patent/CN107781504B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water

Abstract

本发明涉及建筑构件的运输或装配领域,具体为一种架空管道的集成化拆除方法。一种架空管道的集成化拆除方法,待拆除的架空管网(1)包括管道(11)和吊架(12),其特征是:按如下步骤依次实施:a 规划;b 设置;c 拆卸;d 转运。本发明操作方便,降低作业强度,减少成本,工作效率高,安全可靠。

Description

架空管道的集成化拆除方法
技术领域
[0001]本发明涉及建筑构件的运输或装配领域,具体为一种架空管道的集成化拆除方 法。
背景技术
[0002]随着冶金、化工业的发展,去产能已经陆续开始实施,随即面临着大量落后的生产 线需要拆除或者拆迀。架空管道素有生产线的“大动脉,,之称,拆除工程中架空管道拆除工 作一直是重中之重。现有的架空管道拆除多采用破坏性拆除或将管道支架及管道逐一拆除 的模式,不环保、不经济,拆除工作量大而且危险系数高,大大的增加了作业成本及工人的 劳动强度,也不利于工期进度控制。
发明内容
[00^3]为了克服现有技术的缺陷,提供一种操作方便、降低作业强度、减少成本、工作效 率高、安全可靠的管道拆除方法,本发明公开了一种架空管道的集成化拆除方法。
[0004] 本发明通过如下技术方案达到发明目的: 一种架空管道的集成化拆除方法,待拆除的架空管网包括管道和吊架,各条管道水平 地铺设在吊架内,吊架的顶端固定在顶支撑平台上,顶支撑平台选用厂房的天花板,或者在 地面固定立柱,在各根立柱上水平地固定横梁,以横梁作为顶支撑平台,其特征是:按如下 步骤依次实施: a规划:在拆卸地,根据架空管网确定分割面,分割面将架空管网分隔成一个个拆卸单 元,即相邻的两个分割面之间包含一个拆卸单元; b设置:在顶支撑平台上固定吊点,相邻的两个分割面之间包含至少一个吊点,每个吊 点上都设置一个起吊装置,使各个起吊装置都系住拆卸单元; c拆卸:沿分割面切割管道,使各个拆卸单元互相脱离; d转运:用起吊装置将各个拆卸单元逐个卸至搬运车上,装车运出拆卸地。
[0005] 所述的架空管道的集成化拆除方法,其特征是: 步骤a规划时,分割面按如下原则确定:i.分割面垂直于管道,ii •每个拆卸单元最多 包含两个吊架; 步骤b设置时,起吊装置选用差动滑轮或吊装钢丝绳,相邻两个起吊装置的起吊力之和 不小于拆卸单元重量的1.2倍; 步骤c拆卸时,选用气割或锯切切割管道。
[0006]本发明通过进行管道及其支架作集成化分段,并合理设置分割面和拼合面,将大 量的高空拆除及再装工作缩减至两个一次性工作,将管道及其支架整体拆除,大大降低了 高空作业的危险性及作业强度,提高了施工进度及降低了施工成本。本发明可适用于厂房 内及厂房外大型综合管网拆除工作。
[0007] 本发明的有益效果是:操作方便,降低作业强度,减少成本,工作效率高,安全可 — - o
附图说明
[0008]图1是本发明中待拆除的架空管网的剖面示意图; 图2是本发明中确定分割面的示意图; ’ 图3是本发明中分割下的拆卸单元的示意图。
具体实施方式
[0009]以下通过具体实施例进一步说明本发明。
[0010] 实施例1 待拆除的架空管网1如图1和图2所示:待拆除的架空管网1包括管道^和吊架12,各条 管道11水平地铺设在吊架12内,吊架12的顶端固定在顶支撑平台2上,顶支撑平台2可以g 用厂房的天花板,或者如本实施例所不,在地面固定立柱21,在各根立柱2i上水平地固定横 梁22,以横梁22作为顶支撑平台2, 架空管道的集成化拆除方法,按如下步骤依次实施: a规划:在拆卸地,根据架空管网1确定分割面3,分割面3将架空管网1分隔成一个个拆 卸单元I3,即相邻的两个分割面3之间包含一个拆卸单元13; 如图2所示:分割面3按如下原则确定:i.分割面3垂直于管道U,ii.每个拆卸单元13 最多包含两个吊架12; b设置:在顶支撑平台2上固定吊点4,相邻的两个分割面3之间包含至少一个吊点4,每 个吊点4上都设置一个起吊装置5,使各个起吊装置5都系住拆卸单元13;起吊装置5选用差 动滑轮或吊装钢丝绳,相邻两个起吊装置5的起吊力之和不小于拆卸单元13重量的1.2倍; c拆卸:沿分割面3用用气割或锯切切割管道11,使各个拆卸单元13互相脱离,分割后 的拆卸单元13如图3所示; d转运:用起吊装置5将各个拆卸单元13逐个卸至搬运车上,装车运出拆卸地。

Claims (2)

  1. 一种架空管道的集成化拆除方法,待拆除的架空管网(1)包括管道(11)和吊架(12), 巧,管道(11)水平地铺设在吊架(〇内,吊架(12)的顶端固定在顶支撑平台(2)上,顶支^ 干a (2)选用厂房的天花板,或者在地面固走立柱(21),在各根立柱(21)上水平地固定横梁 (22),以横梁(22)作为顶支撑平台(2),其特征是:按如下步骤依次实施: a规划:在拆卸地,根据架空管网(1)确定分割面(3),分割面⑶将架空管网(1)分隔成 一个个拆卸单元(1¾,即相邻的两个分割面(3)之间包含一个拆卸单元(13) ; T b设置:在顶支撑平台⑵上固定吊点⑷,相邻的两个分割面⑶之间包含至少一个吊 点⑷,母个吊点⑷上都设置一个起吊装置⑸,使各个起吊装置⑸都系住拆卸单元(13); c拆卸:沿分割面⑶切割管道(11),使各个拆卸单元(13)互相脱离; d转运:用起吊装置⑸将各个拆卸单元(13)逐个卸至搬运车上,装车运出拆卸地。
  2. 2.如权利要求1所述的架空管道的集成化拆除方法,其特征是: 步骤a规划时,分割面⑶按如下原则确定:i.分割面(3)垂直于管道(uhn.每个拆 卸单元(13)最多包含两个吊架(12); 步骤b设置时,起吊装置(5)选用差动滑轮或吊装钢丝绳,相邻两个起吊装置(5)的起吊 力之和不小于拆卸单元(13)重量的1.2倍; 步骤c拆卸时,选用气割或锯切切割管道(11)。
CN201610733559.4A 2016-08-27 2016-08-27 架空管道的集成化拆除方法 Active CN107781504B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610733559.4A CN107781504B (zh) 2016-08-27 2016-08-27 架空管道的集成化拆除方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610733559.4A CN107781504B (zh) 2016-08-27 2016-08-27 架空管道的集成化拆除方法

Publications (2)

Publication Number Publication Date
CN107781504A true CN107781504A (zh) 2018-03-09
CN107781504B CN107781504B (zh) 2020-11-03

Family

ID=61438391

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610733559.4A Active CN107781504B (zh) 2016-08-27 2016-08-27 架空管道的集成化拆除方法

Country Status (1)

Country Link
CN (1) CN107781504B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727148A (zh) * 2020-12-23 2021-04-30 上海建工集团股份有限公司 建筑结构外侧竖向排烟风管整体拆除方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437369A (zh) * 2013-08-30 2013-12-11 上海建工二建集团有限公司 一种深基坑支护及其拆除方法
US20150139734A1 (en) * 2012-04-12 2015-05-21 Enereco S.P.A. Method for removing from a terrain a buried pipe and a cutting machine used for actuating the method
CN104727192A (zh) * 2015-02-09 2015-06-24 安徽兴宇轨道装备有限公司 一种拆卸整体道床的施工方法
CN104806822A (zh) * 2015-04-16 2015-07-29 上海市安装工程集团有限公司 组合式立管及其模块化安装方法
CN105479098A (zh) * 2014-10-10 2016-04-13 五冶集团上海有限公司 一种大型煤气管道在线拆除方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150139734A1 (en) * 2012-04-12 2015-05-21 Enereco S.P.A. Method for removing from a terrain a buried pipe and a cutting machine used for actuating the method
CN103437369A (zh) * 2013-08-30 2013-12-11 上海建工二建集团有限公司 一种深基坑支护及其拆除方法
CN105479098A (zh) * 2014-10-10 2016-04-13 五冶集团上海有限公司 一种大型煤气管道在线拆除方法
CN104727192A (zh) * 2015-02-09 2015-06-24 安徽兴宇轨道装备有限公司 一种拆卸整体道床的施工方法
CN104806822A (zh) * 2015-04-16 2015-07-29 上海市安装工程集团有限公司 组合式立管及其模块化安装方法

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727148A (zh) * 2020-12-23 2021-04-30 上海建工集团股份有限公司 建筑结构外侧竖向排烟风管整体拆除方法

Also Published As

Publication number Publication date
CN107781504B (zh) 2020-11-03

Similar Documents

Publication Publication Date Title
CN104963301B (zh) 用于墩顶梁段与桥墩拆除的拖拉平移下放装置及方法
CN106758862B (zh) 格构式钢管塔架安、拆平台
CN105781590B (zh) Tbm用接收洞负环拆除工艺
CN108560560A (zh) 一种基坑围护结构的拆除方法
CN104818858B (zh) 室内重型电气柜吊装方法
CN107781504A (zh) 架空管道的集成化拆除方法
CN101818563B (zh) 自升式整体提升移动平台及使用方法
CN105133857A (zh) 干式曼型燃气柜拆除方法
CN110359729A (zh) 混凝土支撑梁无托架拆除方法
CN203437842U (zh) 管道焊接平台
CN107781505A (zh) 架空管道的集成化安装方法
CN105000153B (zh) 脚手马及脚手架搭设的方法
CN204035427U (zh) 移动式可变档调节的钢绞线穿束切割台车
CN106760558A (zh) 一种悬挂式锅炉汽包安装后空中找正方法
CN109629811A (zh) 用于钢管柱的拆卸式操作平台
CN203531352U (zh) 储罐维修专用挂式活动作业平台
CN105274976A (zh) 水中钢平台预制安装施工方法
CN101967903A (zh) 一种直升机组立输电线路铁塔塔腿段用基础导轨
CN202108435U (zh) 作业操作平台管具输送装置
CN204626927U (zh) 电梯井导轨滑升安全操作平台
CN108505539A (zh) 一种梁悬挑平台及其搭设方法
CN104355226B (zh) 一种用于更换液压剪机剪刃的装置
CN106121254A (zh) 一种逆作法拆卸后重型构件运输系统及施工方法
CN106150335B (zh) 一种用于转炉斜烟道补漏的人字梯及其使用方法
CN212270705U (zh) 一种装配式施工平台

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant