CN107288353A - 一种超高建筑楼层上设备吊装过渡支撑平台及其施工方法 - Google Patents

一种超高建筑楼层上设备吊装过渡支撑平台及其施工方法 Download PDF

Info

Publication number
CN107288353A
CN107288353A CN201710563457.7A CN201710563457A CN107288353A CN 107288353 A CN107288353 A CN 107288353A CN 201710563457 A CN201710563457 A CN 201710563457A CN 107288353 A CN107288353 A CN 107288353A
Authority
CN
China
Prior art keywords
equipment
floor
support frame
crossbeam
super
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710563457.7A
Other languages
English (en)
Inventor
孟庆礼
曹艳明
周大伟
任书华
赵艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Bureau Group Installation Engineering Co Ltd
Original Assignee
China Construction First Group Corp Ltd
China Construction First Bureau Group Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, China Construction First Bureau Group Installation Engineering Co Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201710563457.7A priority Critical patent/CN107288353A/zh
Publication of CN107288353A publication Critical patent/CN107288353A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Abstract

一种超高建筑楼层上设备吊装过渡支撑平台及其施工方法,其中施工方法包括:步骤一:悬挑钢梁的施工;步骤二:楼板的压型钢板的铺设;将压型钢板铺设在钢梁上;步骤三:支撑架的设计;步骤四:支撑架的制作;步骤五:支撑架的吊装及就位;步骤六:浇筑楼板的混凝土;步骤七:设备的吊装及一次就位;步骤八:设备的二次就位;至此设备就位完成,施工完毕。本发明解决了采取传统的预留洞或制作大型卸料平台等土建结构的吊装方式危险性较高,耗时耗成本以及会对主体结构产生影响的技术问题。

Description

一种超高建筑楼层上设备吊装过渡支撑平台及其施工方法
技术领域
[0001] 本发明涉及一种支撑平台及其施工方法,特别是一种超高建筑楼层上设备吊装过 渡支撑平台及其施工方法。
背景技术
[0002] 对于超高层建筑机电安装,其设备吊装具有工作量大、难度高、起吊能力受限制的 特点,尤其是部分大型机电设备安装在建筑楼层上,使得超高层建筑机电设备吊装难度增 大。超高层建筑设备吊装均采用塔吊进行,传统吊装方式主要包括塔吊结合卸料平台及预 留吊装孔洞两种形式。
[0003] 由于超高层建筑常在楼层内设置设备层,对于重量及尺寸均在卸料平台的承重范 围内的设备可直接采用塔吊结合卸料平台的吊装形式进行垂直运输;对于远远超过卸料平 台承重能力的设备,若采取预留吊装孔的方案,则需要采取多层预留,且吊装过程难度较 大,危险性较高,预留吊装孔一般尺寸较大,对结构安全性有一定影响,楼板需二次施工浇 筑,费时费力,一般不采取此方案;若采取增加卸料平台的承重能力的方案,则需增大卸料 平台型钢底座的型钢型号,卸料平台自重增大,吊装过程中加上设备的重量,这对结构的承 重要求较高,需对设备层结构进行加固处理,且卸料平台需通过专家评审才能施工,需要各 单位通力合作配合方可实现,过程中耗时耗成本,不经济。采用传统吊装方式,其危险性较 高,耗时耗本且对建筑结构有一定影响,传统吊装方式不宜采取!
发明内容
[0004] 本发明的目的是提供一种超高建筑楼层上设备吊装过渡支撑平台及其施工方法, 要解决采取传统的预留洞或制作大型卸料平台等土建结构的吊装方式危险性较高,耗时耗 成本以及会对主体结构产生影响的技术问题。
[0005] 为实现上述目的,本发明采用如下技术方案。
[0006] —种超高建筑楼层上设备吊装过渡支撑平台,包括有钢梁、铺设在钢梁上的楼板 以及安装在楼板上的支撑架;
[0007] 所述钢梁有一组,沿纵向、间隔垂直悬挑于主体结构的外侧面上;
[0008] 所述楼板为压型钢板与混凝土的组合楼板,其中压型钢板铺设在钢梁上,混凝土 浇筑在压型钢板的板面上;所述支撑架包括有横梁、纵梁和支腿;所述横梁有一组、沿纵向 平行间隔设置,相邻横梁之间的间距与相邻钢梁之间的间距相适应;所述纵梁有若干组,每 组纵梁沿横向、平行间隔连接在相邻两根横梁之间;其中横梁顶部与纵梁顶部平齐;所述支 腿有若干对,其中每对支腿焊接连接在横梁的两端底部;所述支撑架的支腿与钢梁对应设 置,且支腿的下端穿过楼板与钢梁对应焊接连接。
[0009] 优选的,所述横梁、纵梁和支腿均为型钢杆件制成;横梁和纵梁之间焊接连接。 [00Ί0]优选的,所述楼板中的压型钢板的厚度为60mm〜70mm,楼板的混凝土的厚度为 IlOmm 〜130mm〇
[0011] 优选的,所述纵梁与横梁之间设置有斜撑;所述斜撑为型钢制成,斜撑的下端焊接 连接在纵梁内侧,斜撑的上端焊接连接在横梁的底部、横梁与纵梁相交位置处。
[0012] 优选的,所述支腿的下端焊接连接有水平的连接板;所述支腿的下端通过连接板 与钢梁对应焊接连接。
[0013] —种超高建筑楼层上设备吊装过渡支撑平台的施工方法,包括步骤如下。
[0014] 步骤一:悬挑钢梁的施工;在主体结构的外侧面上沿纵向、间隔设置悬挑钢梁。
[0015] 步骤二:楼板的压型钢板的铺设;将压型钢板铺设在钢梁上。
[0016] 步骤三:支撑架的设计;根据支撑平台的特点及设备的性能参数,合理设计支撑架 的样式,并通过计算选择支撑架上各构件的型钢型号。
[0017] 步骤四:支撑架的制作;根据设计图纸进行支撑架的加工制作,其中相邻横梁之间 的间距与相邻钢梁之间的间距相适应。
[0018] 步骤五:支撑架的吊装及就位;将加工成型的支撑架吊装至预先设计好的位置处, 并使支撑架的支腿支撑在对应的横梁上;支腿下端的连接板穿过压型钢板,焊接连接在对 应的横梁上。
[0019] 步骤六:浇筑楼板的混凝土;在型钢压板上满浇筑混凝土,并且使支腿的下部埋设 在混凝土中。
[0020] 步骤七:设备的吊装及一次就位;将设备进行垂直运输并放置在支撑平台上,并对 设备与横梁进行临时连接。
[0021] 步骤八:设备的二次就位;其方法包括步骤如下。
[0022] 步骤A:待主体结构中的设备基础施工完成后,在设备下方布置水平运输装置和千 斤顶。
[0023] 步骤B:根据设备的尺寸对支撑架进行切割,切割点位于设备两侧,切割过程中用 千斤顶将设备顶住。
[0024] 步骤C:降低千斤顶的高度,使设备缓慢下落放置在水平运输装置上,并进行水平 运输。
[0025] 步骤D:将设备水平运输至设备基础上后,将设备提升,移走水平运输装置,调整好 设备的方向及位置,缓慢下降设备至设备基础上,至此设备就位完成。
[0026] 优选的,步骤七中设备的吊装及一次就位,其具体步骤包括。
[0027] 步骤a:进行设备吊装的受力计算,合理选用吊索及吊具。
[0028] 步骤b:将设备就位于支撑架上,设备的底座对应放置在支撑架的横梁上。
[0029] 步骤c:用固定件将设备的底座与横梁临时连接。
[0030] 优选的,所述固定件包括有U形卡槽;卡槽两条竖边的顶部均水平向外弯折形成连 接翻边;所述固定件的卡槽卡在底座的上方,卡槽两侧的连接翻边与横梁焊接连接。
[0031] 优选的,所述固定件的卡槽与底座之间垫有橡胶垫片;橡胶垫片的厚度为2mm〜 4mm 〇
[0032] 优选的,步骤八中的水平运输装置包括有运输小车水平牵引绳和电动萌芦,先用 运输小车、水平牵引绳和电动萌芦将设备水平运输至设备基础上后,在设备吊点上方设置 手动萌芦进行设备的提升,移走设备底部的运输小车,再将设备缓慢下降放置设备基础上。
[0033] 与现有技术相比本发明具有以下特点和有益效果。
[0034] 1、本发明的支撑平台设置在主体结构外侧面,并利用垂直悬挑于主体结构的外侧 面上的钢梁和楼板做为底部支撑,充分利用了原有的结构构件,对主体结构的安全性影响 较小,施工成本较小。
[0035] 2、本发明在钢梁和楼板上设置支撑架,楼板采用压型钢板和混凝土的混合楼板; 先将压型钢板铺设在钢梁上后,再将支撑架的支腿与钢梁对应设置,并将支腿的下端穿过 楼板与钢梁对应焊接连接,然后在浇筑混凝土,将支腿的下端浇筑在混凝土中,这种连接方 式,使得支撑架安装牢固;当设备吊装至支撑加上时吊装过程难度较小,危险性较低。
[0036] 3、本发明的设备放置在支撑架上采用固定件临时连接,并且在固定件的卡槽与底 座之间垫有橡胶垫片,在防止设备滑动的同时也防止底座了固定件之间的摩擦,避免损坏 底座表层。
[0037] 4、本发明设置在主体结构的外侧、靠近主体结构位置处,在进行垂直吊装的过程 中,快速高效的完成设备的垂直运输,节省了大量的人工费,材料费及机械费等费用。
[0038] 5、本发明在进行二次运输之前,通过切割支撑架,并利用千斤顶将设备从支架上 放置水平运输装置上,有效的避免了设备在吊装运输过程中出现碰撞,摩擦而导致设备出 现损坏,并且在保证吊装质量的同时,快速高效的完成设备的水平运输,节省了大量的人工 费,材料费及机械费等费用,本发明的垂直及水平运输过程均不会影响其他专业施工,无需 额外增加相关措施费用支出。
[0039] 6、本发明可广泛应用在各类超高层建筑楼层上大型设备吊装运输,在结构施工阶 段,利用塔吊将设备吊装固定于支撑平台上,避免多楼层吊装孔洞的预留,也避免重新制作 卸料平台及对结构进行加固。
附图说明
[0040] 下面结合附图对本发明做进一步详细的说明。
[0041] 图1是本发明支撑平台的正面结构示意图。
[0042] 图2是本发明的支撑平台上放置设备的正面结构示意图。
[0043] 图3是本发明的支撑平台上放置设备的侧面结构示意图。
[0044] 图4是图3中A点结构放大示意图。
[0045] 图5是本发明中的支撑架的立体结构示意图。
[0046] 图6是本发明中的支撑架的平面结构示意图。
[0047] 图7是图6中B-B的剖面结构示意图。
[0048] 图8是图6中A-A的剖面结构示意图。
[0049] 图9是本发明的方法步骤八中步骤A的过程图。
[0050] 图10是本发明的方法步骤八中步骤C的过程图。
[0051] 图11是本发明的方法步骤八中步骤D的过程图。
[0052] 附图标记:1 一钢梁、2 —楼板、2.1—混凝土、2.2—压型钢板、3—支撑架、3.1 —横 梁、3.2 —纵梁、3.3 —支腿、3.4 —斜撑、3.5 —连接板、4 一主体结构、5 —设备基础、6 —设备、 7 —底座、8—固定件、9 一千斤顶、10—运输小车、11 一电动萌芦、12 —水平牵引绳、13—切割 点。
具体实施方式
[0053] 本发明涉及一种支撑平台及其施工方法,特别是一种超高建筑楼层上设备吊装过 渡支撑平台及其施工方法;过渡支撑平台是利用超高层建筑结构施工的特点,在结构施工 阶段预制支撑架,预先安装在结构钢梁上,利用塔吊吊装设备,先将设备就位于支撑平台 上,待主体结构中的设备基础施工完成后,切除支撑架并进行设备的二次运输,最后就位至 设备基础上;从而解决在超高层建筑大型设备垂直运输过程中卸料平台载荷不能满足要 求,多层结构需预留吊装预留孔、更改结构设计等技术问题;同时也达到节约成本,节省工 期的目标。
[0054] 如图1 -3、11所示,这种超高建筑楼层上设备吊装过渡支撑平台,包括有钢梁1、铺 设在钢梁1上的楼板2以及安装在楼板2上的支撑架3;所述钢梁1有一组,沿纵向、间隔垂直 悬挑于主体结构4的外侧面上;所述楼板2为压型钢板2.2与混凝土 2.1的组合楼板,其中压 型钢板2.2铺设在钢梁1上,混凝土2.1浇筑在压型钢板2.2的板面上;所述支撑架3包括有 横梁3.1、纵梁3.2和支腿3.3;所述横梁3.1有一组、沿纵向平行间隔设置,相邻横梁3.1之间 的间距与相邻钢梁1之间的间距相适应;所述纵梁3.2有若干组,每组纵梁3.2沿横向、平行 间隔连接在相邻两根横梁3.1之间;其中横梁3.1顶部与纵梁3.2顶部平齐;所述支腿3.3有 若干对,其中每对支腿3.3焊接连接在横梁3.1的两端底部;所述支撑架3的支腿3.3与钢梁1 对应设置,且支腿3.3的下端穿过楼板2与钢梁1对应焊接连接。
[0055] 如图5-8所示本实施例中,所述横梁3.1、纵梁3.2和支腿3.3均为型钢杆件制成;横 梁3.1和纵梁3.2之间焊接连接。
[0056] 本实施例中,所述楼板2中的压型钢板2.2的厚度为65mm,楼板2的混凝土2.1的厚 度为120mm。
[0057] 当然在其他实施例中,所述楼板2中的压型钢板2.2的厚度还可以在60mm〜70mm 中选取,楼板2的混凝土 2.1的厚度还可以在IlOmm〜130mm中任意选取。
[0058] 本实施例中,所述主体结构4为超高层建筑钢结构,其总建筑高度438m,设备6实 际就位高度325.65m。
[0059] 当然在其他实施例中,本发明还可以用于建筑高度大于100米或者建筑层数大于 40层的超高层饶筑中。
[0060] 本实施例中,所述纵梁3.2与横梁3.1之间设置有斜撑3.4;所述斜撑3.4为型钢制 成,斜撑3.4的下端焊接连接在纵梁3.2内侧,斜撑3.4的上端焊接连接在横梁3.1的底部、 横梁3.1与纵梁3.2相交位置处。
[0061] 本实施例中,所述支腿3.3的下端焊接连接有水平的连接板3.5;所述支腿3.3的 下端通过连接板3.5与钢梁1对应焊接连接。
[0062] 这种超高建筑楼层上设备吊装过渡支撑平台的施工方法,包括步骤如下。
[0063] 步骤一:悬挑钢梁1的施工;在主体结构4的外侧面上沿纵向、间隔设置悬挑钢梁1。
[0064] 步骤二:楼板2的压型钢板2.2的铺设;将压型钢板2.2铺设在钢梁1上。
[0065] 步骤三:支撑架3的设计;根据支撑平台的特点及设备6的性能参数,合理设计支撑 架3的样式,并通过计算选择支撑架3上各构件的型钢型号;支撑架3的设计需满足超高层建 筑钢结构的结构特点,满足设备6的承载力,满足设备6固定并确保建筑完工后可以切割。
[0066] 2、型钢的型号计算校核
[0067] 横梁3.1的形式为简支梁,载荷受力形式为简支梁中间受集中载荷,其设计计算载 荷:
[0068] F = p* γ *g
[0069] 其中F一设计计算载荷,KN
[0070] P—集中载荷,kg;
[0071] γ=1·2,安全系数;
[0072] G = 10N/kg,重力加速度。
[0073] 计算简支梁的最大弯矩:
Figure CN107288353AD00081
[0075] 其中Mmax—最大弯矩,KN/m;
[0076] L 一简支梁长度,m。
[0077] 强度及刚度验算:
[0078] ①、弯曲正应丈
Figure CN107288353AD00082
:抗弯设计值f;f = 205N/mm2;
[0079] ②、支点最大剪应力
Figure CN107288353AD00083
抗剪设计值t;fv=125N/mm2;
[0080] ③、最大烧度
Figure CN107288353AD00084
Figure CN107288353AD00085
[0081] ④、跨中挠度相对值
Figure CN107288353AD00086
挠度控制值
[0082] 其中Omax—弯曲正应力,N/mm2;
[0083] Tmax—支点最大剪应力,N/mm2;
[0084] Wx、Sx、tw—型钢截面特性参数,型钢表中可查的;
[0085] Yx—X轴塑性发展系数,取1.05;
[0086] fmax一最大烧度,mm;
[0087] V—跨中挠度相对值;
[0088] f—抗弯设计值,N/mm2;
[0089] fv—抗剪设计值,N/mm2;
[0090] E—钢的弹性模量,E = 2100000N/mm2;
[0091] I—钢的截面惯性矩,可在型钢表中查的,mm4。
[0092] 步骤四:支撑架3的制作;根据设计图纸进行支撑架3的加工制作,其中相邻横梁 3.1之间的间距与相邻钢梁1之间的间距相适应;型钢的品种、规格、性能应符合设计要求和 国家现行有关产品标准的规定,严格按照图纸尺寸进行切割,型钢直段不允许有焊接点;焊 接制作过程中必须由通过考试的专业焊工进行施焊,连接点全部满焊连接。
[0093] 步骤五:支撑架3的吊装及就位;将加工成型的支撑架3吊装至预先设计好的位置 处,并使支撑架3的支腿3.3支撑在对应的横梁3.1上;支腿3.3下端的连接板3.5穿过压型 钢板2.2,焊接连接在对应的横梁3.1上;本实施例中超高层建筑结构形式为框架剪力墙结 构,外框楼板2为压型钢板2.2和混凝土2.1组合楼板,此步骤需在压型钢板2.2施工完成后, 混凝土2.1浇筑前进行,设备6所在楼层结构的钢梁1及压型钢板2.2施工完成后,将加工成 型的支撑架3通过塔吊吊装至预先设计好的位置;支撑架3的支腿3.3的根部必须完全落在 钢梁1上面,并焊接在结构的钢梁1上,满焊处理。
[0094] 步骤六:浇筑楼板2的混凝土2.1;在型钢压板上满浇筑混凝土2.1,并且使支腿3.3 的下部埋设在混凝土 2.1中。
[0095] 步骤七:设备6的吊装及一次就位;将设备6进行垂直运输并放置在支撑平台上,并 对设备6与横梁3.1进行临时连接;其具体步骤包括。
[0096] 步骤a:进行设备6吊装的受力计算,合理选用吊索及吊具。
[0097] 步骤b:将设备6就位于支撑架3上,设备6的底座7对应放置在支撑架3的横梁3.1 上。
[0098] 步骤c:用固定件8将设备6的底座7与横梁3.1临时连接。
[0099] 如图3和图4所示,所述固定件8包括有U形卡槽;U形卡槽由40*6mm的扁钢制成;卡 槽两条竖边的顶部均水平向外弯折形成连接翻边8.1;所述固定件8的卡槽卡在底座7的上 方,卡槽两侧的连接翻边8.1与横梁3.1满焊连接,使设备6稳固不易滑动;在固定件8的卡槽 与底座7之间垫有橡胶垫片;橡胶垫片的厚度为2mm〜4mm,防止摩擦及避免损坏底座7表 层。
[0100] 步骤八:设备6的二次就位;其方法包括步骤如下。
[0101] 步骤A:待主体结构4中的设备基础5施工完成后,在设备6下方布置水平运输装置 和千斤顶9,如图9所示。
[0102] 步骤B:根据设备6的尺寸对支撑架3进行切割,切割点13位于设备6两侧,切割过程 中用千斤顶9将设备6顶住。
[0103] 步骤C:降低千斤顶9的高度,使设备6缓慢下落放置在水平运输装置上,并进行水 平运输,如图10所示。
[0104] 步骤D:将设备6水平运输至设备基础5上后,将设备6提升,移走水平运输装置,调 整好设备6的方向及位置,缓慢下降设备6至设备基础5上,至此设备6就位完成,如图11所 不。
[0105] 本实施例中,所述水平运输装置包括有运输小车10水平牵引绳12和电动萌芦11, 先用运输小车10、水平牵引绳12和电动萌芦11将设备6水平运输至设备基础5上后,在设备 6吊点上方设置手动萌芦进行设备6的提升,移走设备6底部的运输小车10,再将设备6缓慢 下降放置设备基础5上。
[0106] 上述实施例并非具体实施方式的穷举,还可有其它的实施例,上述实施例目的在 于说明本发明,而非限制本发明的保护范围,所有由本发明简单变化而来的应用均落在本 发明的保护范围内。

Claims (10)

1. 一种超高建筑楼层上设备吊装过渡支撑平台,包括有钢梁(I)、铺设在钢梁(1)上的 楼板⑵以及安装在楼板⑵上的支撑架(3);其特征在于:所述钢梁⑴有一组,沿纵向、间 隔垂直悬挑于主体结构⑷的外侧面上;所述楼板(2)为压型钢板(2.2)与混凝土 (2.1)的组 合楼板,其中压型钢板(2.2)铺设在钢梁(1)上,混凝土 (2.1)浇筑在压型钢板(2.2)的板面 上;所述支撑架⑶包括有横梁(3.1)、纵梁(3.2)和支腿(3.3);所述横梁(3.1)有一组、沿纵 向平行间隔设置,相邻横梁(3.1)之间的间距与相邻钢梁(1)之间的间距相适应;所述纵梁 (3.2) 有若干组,每组纵梁(3.2)沿横向、平行间隔连接在相邻两根横梁(3.1)之间;其中横 梁(3.1)顶部与纵梁(3.2)顶部平齐;所述支腿(3.3)有若干对,其中每对支腿(3.3)焊接连 接在横梁(3.1)的两端底部;所述支撑架⑶的支腿(3.3)与钢梁⑴对应设置,且支腿(3.3) 的下端穿过楼板(2)与钢梁(1)对应焊接连接。
2. 根据权利要求1所述的一种超高建筑楼层上设备吊装过渡支撑平台,其特征在于:所 述横梁(3.1)、纵梁(3.2)和支腿(3.3)均为型钢杆件制成;横梁(3.1)和纵梁(3.2)之间焊接 连接。
3. 根据权利要求1所述的一种超高建筑楼层上设备吊装过渡支撑平台,其特征在于:所 述楼板(2)中的压型钢板(2.2)的厚度为60mm〜70mm,楼板(2)的混凝土(2.1)的厚度为 IlOmm 〜130mm〇
4. 根据权利要求1所述的一种超高建筑楼层上设备吊装过渡支撑平台,其特征在于:所 述纵梁(3.2)与横梁(3.1)之间设置有斜撑(3.4);所述斜撑(3.4)为型钢制成,斜撑(3.4)的 下端焊接连接在纵梁(3.2)内侧,斜撑(3.4)的上端焊接连接在横梁(3.1)的底部、横梁 (3.1) 与纵梁(3.2)相交位置处。
5. 根据权利要求1所述的一种超高建筑楼层上设备吊装过渡支撑平台,其特征在于:所 述支腿(3.3)的下端焊接连接有水平的连接板(3.5);所述支腿(3.3)的下端通过连接板 (3.5)与钢梁(1)对应焊接连接。
6. —种权利要求1-5中任意一项所述的超高建筑楼层上设备吊装过渡支撑平台的施工 方法,其特征在于,包括步骤如下: 步骤一:悬挑钢梁(1)的施工;在主体结构(4)的外侧面上沿纵向、间隔设置悬挑钢梁 (1); 步骤二:楼板⑵的压型钢板(2.2)的铺设;将压型钢板(2.2)铺设在钢梁⑴上; 步骤三:支撑架(3)的设计;根据支撑平台的特点及设备(6)的性能参数,合理设计支撑 架(3)的样式,并通过计算选择支撑架(3)上各构件的型钢型号; 步骤四:支撑架(3)的制作;根据设计图纸进行支撑架(3)的加工制作,其中相邻横梁 (3.1) 之间的间距与相邻钢梁(1)之间的间距相适应; 步骤五:支撑架(3)的吊装及就位;将加工成型的支撑架(3)吊装至预先设计好的位置 处,并使支撑架⑶的支腿(3.3)支撑在对应的横梁(3.1)上;支腿(3.3)下端的连接板(3.5) 穿过压型钢板(2.2),焊接连接在对应的横梁(3.1)上; 步骤六:浇筑楼板(2)的混凝土(2.1);在型钢压板上满浇筑混凝土(2.1),并且使支腿 (3.3) 的下部埋设在混凝土 (2.1)中; 步骤七:设备(6)的吊装及一次就位;将设备(6)进行垂直运输并放置在支撑平台上,并 对设备(6)与横梁(3.1)进行临时连接; 步骤八:设备(6)的二次就位;其方法包括步骤如下: 步骤A:待主体结构(4)中的设备基础(5)施工完成后,在设备(6)下方布置水平运输装 置和千斤顶(9); 步骤B:根据设备(6)的尺寸对支撑架⑶进行切割,切割点(13)位于设备(6)两侧,切割 过程中用千斤顶(9)将设备(6)顶住;步骤C:降低千斤顶(9)的高度,使设备(6)缓慢下落放 置在水平运输装置上,并进行水平运输; 步骤D:将设备(6)水平运输至设备基础(5)上后,将设备(6)提升,移走水平运输装置, 调整好设备(6)的方向及位置,缓慢下降设备(6)至设备基础(5)上,至此设备(6)就位完成。
7. 根据权利要求6所述的超高建筑楼层上设备吊装过渡支撑平台的施工方法,其特征 在于:步骤七中设备(6)的吊装及一次就位,其具体步骤包括: 步骤a:进行设备(6)吊装的受力计算,合理选用吊索及吊具; 步骤b:将设备(6)就位于支撑架(3)上,设备(6)的底座(7)对应放置在支撑架(3)的横 梁(3.1)上; 步骤c:用固定件⑶将设备(6)的底座⑵与横梁(3.1)临时连接。
8. 根据权利要求7所述的超高建筑楼层上设备吊装过渡支撑平台的施工方法,其特征 在于:所述固定件(8)包括有U形卡槽;卡槽两条竖边的顶部均水平向外弯折形成连接翻边 (8.1);所述固定件⑶的卡槽卡在底座⑵的上方,卡槽两侧的连接翻边(8.1)与横梁(3.1) 焊接连接。
9. 根据权利要求8所述的超高建筑楼层上设备吊装过渡支撑平台的施工方法,其特征 在于:所述固定件⑶的卡槽与底座⑵之间垫有橡胶垫片;橡胶垫片的厚度为2mm〜4_。
10. 根据权利要求6所述的超高建筑楼层上设备吊装过渡支撑平台的施工方法,其特征 在于:步骤八中的水平运输装置包括有运输小车(10)水平牵引绳(12)和电动萌芦(11),先 用运输小车(10)、水平牵引绳(12)和电动萌芦(11)将设备(6)水平运输至设备基础(5)上 后,在设备(6)吊点上方设置手动萌芦进行设备(6)的提升,移走设备(6)底部的运输小车 (10),再将设备(6)缓慢下降放置设备基础⑶上。
CN201710563457.7A 2017-07-11 2017-07-11 一种超高建筑楼层上设备吊装过渡支撑平台及其施工方法 Pending CN107288353A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710563457.7A CN107288353A (zh) 2017-07-11 2017-07-11 一种超高建筑楼层上设备吊装过渡支撑平台及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710563457.7A CN107288353A (zh) 2017-07-11 2017-07-11 一种超高建筑楼层上设备吊装过渡支撑平台及其施工方法

Publications (1)

Publication Number Publication Date
CN107288353A true CN107288353A (zh) 2017-10-24

Family

ID=60101116

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710563457.7A Pending CN107288353A (zh) 2017-07-11 2017-07-11 一种超高建筑楼层上设备吊装过渡支撑平台及其施工方法

Country Status (1)

Country Link
CN (1) CN107288353A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108166626A (zh) * 2017-12-27 2018-06-15 中国核工业二四建设有限公司 一种高支模多组合式大荷载楼板支撑体系施工方法
CN111894136A (zh) * 2020-08-10 2020-11-06 中冶建工集团有限公司 一种大跨度型钢混凝土梁的施工方法
CN113565222A (zh) * 2021-07-22 2021-10-29 中建二局第一建筑工程有限公司 建筑避难层与结构梁的简易结构及施工工法
CN113979299A (zh) * 2021-11-24 2022-01-28 北京市第三建筑工程有限公司 一种吊装系统的安装方法和吊装方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102493666A (zh) * 2011-12-22 2012-06-13 北京首钢建设集团有限公司 一种超大超重构件高空平移安装施工方法
CN102635225A (zh) * 2012-04-05 2012-08-15 广东省工业设备安装公司 超高层建筑上用于设备吊装的吊装平台及吊装方法
CN204876630U (zh) * 2015-06-15 2015-12-16 中建一局集团安装工程有限公司 一种超高层建筑设备临时支撑平台

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102493666A (zh) * 2011-12-22 2012-06-13 北京首钢建设集团有限公司 一种超大超重构件高空平移安装施工方法
CN102635225A (zh) * 2012-04-05 2012-08-15 广东省工业设备安装公司 超高层建筑上用于设备吊装的吊装平台及吊装方法
CN204876630U (zh) * 2015-06-15 2015-12-16 中建一局集团安装工程有限公司 一种超高层建筑设备临时支撑平台

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
卢凯: "超高层建筑大型机电设备吊装技术", 《安装》 *
张伟等: "超高层建筑楼层上大型设备钢托架垂直运输施工技术", 《安装》 *
钱屹: "超高层建筑楼盖选型研究", 《建筑结构》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108166626A (zh) * 2017-12-27 2018-06-15 中国核工业二四建设有限公司 一种高支模多组合式大荷载楼板支撑体系施工方法
CN111894136A (zh) * 2020-08-10 2020-11-06 中冶建工集团有限公司 一种大跨度型钢混凝土梁的施工方法
CN113565222A (zh) * 2021-07-22 2021-10-29 中建二局第一建筑工程有限公司 建筑避难层与结构梁的简易结构及施工工法
CN113979299A (zh) * 2021-11-24 2022-01-28 北京市第三建筑工程有限公司 一种吊装系统的安装方法和吊装方法
CN113979299B (zh) * 2021-11-24 2022-07-29 北京市第三建筑工程有限公司 一种吊装系统的安装方法和吊装方法

Similar Documents

Publication Publication Date Title
CN107288353A (zh) 一种超高建筑楼层上设备吊装过渡支撑平台及其施工方法
CN103161126A (zh) 路桥变截面空心高墩滑模施工方法
CN103590602B (zh) 现浇混凝土空心楼盖的施工方法
CN105971276B (zh) 整体式铝模板楼梯一次连续浇筑成型结构及施工方法
CN211646905U (zh) 一种钢筋桁架预应力混凝土叠合板
CN101408021B (zh) 移动式托架、模板整体系统及其施工连续梁的方法
CN105756252A (zh) 一种预应力混凝土桁架叠合板及其制作方法
CN210562056U (zh) 用于溢流面曲面混凝土施工的可调连续四杆自适应拉模
CN103276894A (zh) 空心楼盖大截面梁式转换层的支撑体系及施工工艺
CN106592962A (zh) 一种大高差、大跨度劲性骨架外包混凝土模板施工方法及施工设备
CN104213728B (zh) 体育馆看台斜梁及其施工工艺
CN203795311U (zh) 多肢高墩同滑施工装置
CN108004932A (zh) 利用梁下运梁方式施工钢混组合梁的方法
CN108582466A (zh) 一种预制箱梁钢筋笼胎具
CN105971287B (zh) 反力墙竖向预应力施工方法
CN106049858A (zh) 一种爬模平台的布料机支撑平台
CN104018607B (zh) 一种拼接空间桁架隔层楼板
CN207293909U (zh) 一种预制梁钢筋骨架吊装装置
CN207551767U (zh) 利用预制主梁作为受力构件的桥梁施工用吊装设备
CN202064281U (zh) 一种滑模模架
CN109877940A (zh) 预制板的制作、吊装和二次浇筑一体化装置及施工方法
CN110387824A (zh) 一种索塔爬模空中变轨施工方法
CN109281425A (zh) 一种装配式混凝土楼板及其施工方法
CN105821750B (zh) 一种预制预应力双t板及其使用方法
CN206205434U (zh) 整体式铝模板楼梯一次连续浇筑成型结构

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171024

RJ01 Rejection of invention patent application after publication