CN107268630A - A kind of side slope protection construction material transport system and method - Google Patents
A kind of side slope protection construction material transport system and method Download PDFInfo
- Publication number
- CN107268630A CN107268630A CN201710548740.2A CN201710548740A CN107268630A CN 107268630 A CN107268630 A CN 107268630A CN 201710548740 A CN201710548740 A CN 201710548740A CN 107268630 A CN107268630 A CN 107268630A
- Authority
- CN
- China
- Prior art keywords
- slope
- guide rail
- side slope
- supporting leg
- conveyor bucket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Forklifts And Lifting Vehicles (AREA)
Abstract
The present invention provides a kind of side slope protection construction material transport system and method, and system includes two parallel guide rails, conveyor bucket vehicle and hoist engine;The guide rail pushes up laying along side slope longitudinal direction by bottom of slope to slope, and every guide rail bottom is supported on domatic on provided with a plurality of supporting leg and by supporting leg, and the supporting leg is adjustable length structure, and hoist engine is pushed up positioned at slope, and the pull rope of hoist engine is connected with the front end of the conveyor bucket vehicle.During transported material, material is loaded on conveyor bucket vehicle in bottom of slope, the bottom of slope that conveyor bucket vehicle returns again to after being unloaded from elevator machine travel to slope top continues to feed transports to slope top, after the completion of a construction point, guide rail is dismantled, is transported to after being installed in the side slope of next construction point and continues to construct.
Description
Technical field
The present invention relates to road slope construction of prevention work field, and in particular to a kind of side slope protection construction material transport system
And material transportation method.
Background technology
During road slope construction of prevention work, construction material generally using it is artificial from bottom of slope to slope on carry, or use
Crane handling.Artificial to carry, efficiency is low, time-consuming, labour's consumption is big, often causes the work holdup to indulge in because material is supplied not as good as
Delay work the phase, in area of heavy rainfull, construction speed also results in side slope protection and destroyed not in time by rain drop erosion slowly;Hung using crane
Fortune, because construction point is more dispersed, and crane suffers from landform and the limitation of construction surface and can not flexibly moved, it is necessary to using many
Platform crane multiple spot construct, cause construction cost to increase, in the higher section of the gradient, crane can also not enough cause because of brachium use by
Limit.
The content of the invention
The problem of it is an object of the invention to be run into for material transportation link in current slope construction, there is provided a kind of side slope
Construction of prevention work material transport system and method, to reduce manpower consumption, save construction cost, and improve efficiency of construction.
To achieve the above object, the present invention provides a kind of side slope protection construction material transport system, it is characterised in that:
Including two parallel guide rails, conveyor bucket vehicle and hoist engine;The guide rail pushes up paving along side slope longitudinal direction by bottom of slope to slope
If every guide rail is formed using many Bolted angle connections, and two angle steel joints set screw is set on connecting plate, connecting plate respectively, two jiaos
Steel is connected by screw bolts by the screw on connecting plate;Every guide rail bottom is longitudinally provided with a plurality of supporting leg along guide rail, and passes through branch
Leg is supported on domatic, and the supporting leg is adjustable length structure, and every supporting leg is made up of two sleeve pipes being mutually socketed, a set
Inside pipe wall sets internal thread, and another sleeve outer wall sets external screw thread, and two sleeve pipes are spirally connected by internal and external threads;The conveyor bucket vehicle bottom two
Side is respectively equipped with roller, and two side wheels are respectively placed on the guide rail, the hoist engine positioned at slope push up, the pull rope of hoist engine with
The front end connection of the conveyor bucket vehicle.
The present invention also provides a kind of side slope protection construction material transportation method, utilizes above-mentioned side slope protection construction material
Transportation system's transported material, it is characterised in that:
(1) two parallel guide rails of laying are pushed up by bottom of slope to slope along side slope longitudinal direction, guide rail is supported on domatic by supporting leg,
The height of supporting leg is adjusted by adjusting the threadably engaged portion length between every sleeve pipe of supporting leg two, to adapt to the slope that side slope height rises and falls
Face, makes guide rail integrally keep straight;
(2) hoist engine is pushed up installed in slope, conveyor bucket vehicle is placed on guide rail positioned at bottom of slope, the pull rope and fortune of hoist engine
The front end connection of boxcar;
(3) construction material is loaded on conveyor bucket vehicle, starts elevator machine travel conveyor bucket vehicle and slide into Po Ding along guide rail
At construction point, after material is unloaded, hoist engine control conveyor bucket vehicle, which returns to bottom of slope, reloads and draws again after material to slope top, instead
Multiple transport completion until the construction point is constructed;After the completion of one construction point, guide rail is dismantled, in the side slope for being transported to next construction point
Continue to construct after installation.
The present invention is directed to the problem of slope construction material transportation, is overlapped with the small four-wheel boxcar of elevator machine travel in angle steel
Walking is basic structure on track, improves side slope protection engineering construction material transportation efficiency., will in side slope protection engineering construction
The track skeleton steady rest of angle steel overlap joint is stood on corresponding slope construction face, and power is provided by the hoist engine for being fixed on slope top,
Small four-wheel boxcar is drawn to be constructed from bottom of slope transported material to the side slope of corresponding series.Completing can be with after a construction point
Easily dismantle, shift, to the installation of next construction point, transported material, so circulation construction.The present invention solves traditional crane
Hoisting cost is high, the problem that hand haulage's labor intensity is big, efficiency is low, and efficiency of construction is also improved while cost is reduced.
Brief description of the drawings
Fig. 1 is the material transport system side structure schematic view of the present invention;
Fig. 2 is the attachment structure of enlarged drawing at A in Fig. 1, main display guide rail bottom and supporting leg, constitutes the angle steel of guide rail
Between attachment structure, and otic placode structure;
Fig. 3 is the material transport system overlooking the structure diagram of the present invention;
Fig. 4 is the material transport system backsight structural representation of the present invention.
Embodiment
As shown in Figure 1, Figure 2, Figure 3, Figure 4, a kind of side slope protection construction material transport system that the present invention is provided, including
Two parallel guide rails 1, conveyor bucket vehicle 2 and hoist engine 3, the guide rail 1 push up laying, every along the longitudinal direction of side slope 4 by bottom of slope to slope
The bottom of guide rail 1 is longitudinally provided with a plurality of supporting leg 5 along guide rail, and is supported on by supporting leg 5 on domatic;The bottom two of conveyor bucket vehicle 2
Side is respectively equipped with roller 6, and two side wheels 6 are respectively placed on two guide rails 1, pull rope 7 and the conveyor bucket vehicle of the hoist engine 3
2 front end connection.
The guide rail 1 is formed using many Bolted angle connections, and two angle steel joints set set spiral shell on connecting plate 8, connecting plate respectively
Hole, two angle steel are connected by the screw on connecting plate using bolt 9.
Because side slope surface generally height is uneven, to ensure that guide rail is straight, supporting leg 5 is set to length by the present invention can
Structure is adjusted, every supporting leg 5 is made up of two sleeve pipes being mutually socketed, and an internal surface of sleeve pipe sets internal thread, and another sleeve outer wall is set
External screw thread, and rotation handle 16 is set, two sleeve pipes are spirally connected by internal and external threads, long by adjusting the threadably engaged portion between two supporting leg sleeves
Degree, realizes that leg length is adjustable.
The upper end of supporting leg 5 is connected with the bottom of guide rail 1 by bearing pin 10, easy for removal and installation;To ensure domatic soft
Under rock geological conditions, guide rail structure is stable to ensure that bearing capacity meets requirement simultaneously, and point convex 11 is set in supporting leg lower end, side is facilitated insertion into
In slope;The top of point convex 11 sets pallet 12, and the area of plane of the pallet 12 is more than the cross-sectional area of supporting leg 5.Convex 11 insertion of point
After side slope, pallet 12 is supported on domatic, can provide guide rail stable support.
To be further ensured that guide rail is stable, it can also at spacing intervals set on an otic placode 13, otic placode 13 and set in the bottom of guide rail 1
Through hole, by otic placode through hole through an anchoring rope 14, the two ends of the anchoring rope 14 are anchored in side slope respectively;Anchor in side slope
Solid point uses concrete hardening, it is ensured that rail system monolithic stability.
As shown in figure 4, to prevent conveyor bucket vehicle from operationally derailing, one can be set respectively in the two bottom sides of conveyor bucket vehicle 2
Derailing device 15, derailing device 15 is L-shaped, and its upper end is welded with the bottom of conveyor bucket vehicle 2, and lower end forms one 90 ° of knuckle, two
The knuckle of derailing device 15 is respectively facing and close to the inner side of two guide rails, limits the transverse shifting of conveyor bucket vehicle, can prevent fortune
Boxcar occurs traversing and derailed when running.
During using above-mentioned side slope protection construction with material transport system transported material, method is as follows:
(1) two parallel guide rails of laying are pushed up by bottom of slope to slope along side slope longitudinal direction, guide rail is supported on domatic by supporting leg,
The height of supporting leg is adjusted by adjusting the threadably engaged portion length between every sleeve pipe of supporting leg two, to adapt to the slope that side slope height rises and falls
Face, makes guide rail integrally keep straight;
(2) hoist engine is pushed up installed in slope, conveyor bucket vehicle is placed on guide rail positioned at bottom of slope, the pull rope and fortune of hoist engine
The front end connection of boxcar;
(3) construction material is loaded on conveyor bucket vehicle, starts elevator machine travel conveyor bucket vehicle and slide into Po Ding along guide rail
At construction point, after material is unloaded, hoist engine control conveyor bucket vehicle, which returns to bottom of slope, reloads and draws again after material to slope top, instead
Multiple transport completion until the construction point is constructed;After the completion of one construction point, guide rail is dismantled, in the side slope for being transported to next construction point
Continue to construct after installation.
Claims (8)
1. a kind of side slope protection construction material transport system, it is characterised in that:Including two parallel guide rails, conveyor bucket vehicle and
Hoist engine;The guide rail pushes up laying along side slope longitudinal direction by bottom of slope to slope, and every guide rail is formed using many Bolted angle connections, two angle steel
Joint is set screw is set on connecting plate, connecting plate respectively, and two angle steel are connected by screw bolts by the screw on connecting plate;Every is led
Flange of rail portion is longitudinally provided with a plurality of supporting leg along guide rail, and is supported on by supporting leg on domatic, and the supporting leg is adjustable length structure, often
Root supporting leg is made up of two sleeve pipes being mutually socketed, and an internal surface of sleeve pipe sets internal thread, and another sleeve outer wall sets external screw thread, two sets
Pipe is spirally connected by internal and external threads;The conveyor bucket vehicle two bottom sides are respectively equipped with roller, and two side wheels are respectively placed in the guide rail
On, the hoist engine is pushed up positioned at slope, and the pull rope of hoist engine is connected with the front end of the conveyor bucket vehicle.
2. side slope protection construction material transport system according to claim 1, it is characterised in that:The supporting leg upper end with
Guide rail bottom is connected by bearing pin, and lower end sets sharp convex, and the convex top of point sets pallet, and the area of plane of the pallet is more than supporting leg
Cross-sectional area.
3. side slope protection construction material transport system according to claim 1, it is characterised in that:The guide rail bottom is every
Set across a certain distance and set through hole on an otic placode, otic placode, restricted by otic placode through hole through an anchoring, the two ends difference of the anchoring rope
It is anchored in side slope.
4. side slope protection construction material transport system according to claim 1, it is characterised in that:The conveyor bucket vehicle
Two bottom sides also set a derailing device respectively, and the derailing device is L-shaped, and its upper end is welded with conveyor bucket vehicle bottom, lower end shape
Into one 90 ° of knuckle, the knuckle of two derailing devices is respectively facing and close to the inner side of two guide rails.
5. a kind of side slope protection construction method of material transport system transported material described in use claim 1, its feature
It is:
(1) two parallel guide rails of laying are pushed up by bottom of slope to slope along side slope longitudinal direction, guide rail is supported on domatic by supporting leg, passed through
The threadably engaged portion length between every sleeve pipe of supporting leg two is adjusted to adjust the height of supporting leg, to adapt to the domatic of side slope height fluctuating,
Guide rail is set integrally to keep straight;
(2) hoist engine is pushed up installed in slope, conveyor bucket vehicle is placed on guide rail positioned at bottom of slope, the pull rope and conveyer bucket of hoist engine
The front end connection of car;
(3) construction material is loaded on conveyor bucket vehicle, starts elevator machine travel conveyor bucket vehicle and slide into the construction of slope top along guide rail
Point place, after material is unloaded, hoist engine control conveyor bucket vehicle, which returns to bottom of slope, reloads to draw again after material to slope and pushes up, and transports repeatedly
The defeated completion until the construction point is constructed;After the completion of one construction point, guide rail is dismantled, is transported in the side slope of next construction point and installs
Continue to construct afterwards.
6. material transportation method is used in side slope protection construction according to claim 5, it is characterised in that:The supporting leg upper end with
Guide rail bottom is connected by bearing pin, and lower end sets sharp convex, and the convex top of point sets pallet, and the area of plane of the pallet is more than supporting leg
Cross-sectional area;In sharp convex portion insertion side slope body, tray support is on side slope surface.
7. material transportation method is used in side slope protection construction according to claim 5, it is characterised in that:To keep guide rail steady
It is fixed, set at spacing intervals in the guide rail bottom and set through hole on an otic placode, otic placode, restricted by otic placode through hole through an anchoring,
The two ends of the anchoring rope are anchored in side slope respectively, concrete hardening is used at anchoring.
8. material transportation method is used in side slope protection construction according to claim 5, it is characterised in that:To prevent conveyor bucket vehicle
Derailing, sets a derailing device, the derailing device is L-shaped, its upper end and haul respectively in the two bottom sides of the conveyor bucket vehicle
Trolley bottom is welded, and lower end forms one 90 ° of knuckle, and the knuckle of two derailing devices is respectively facing and close to the interior of two guide rails
Side.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710548740.2A CN107268630A (en) | 2017-07-06 | 2017-07-06 | A kind of side slope protection construction material transport system and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710548740.2A CN107268630A (en) | 2017-07-06 | 2017-07-06 | A kind of side slope protection construction material transport system and method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107268630A true CN107268630A (en) | 2017-10-20 |
Family
ID=60073105
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710548740.2A Pending CN107268630A (en) | 2017-07-06 | 2017-07-06 | A kind of side slope protection construction material transport system and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107268630A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107986176A (en) * | 2017-11-13 | 2018-05-04 | 新疆兵团水利水电工程集团有限公司 | High slope masonry building stones transporter |
CN108487267A (en) * | 2018-06-04 | 2018-09-04 | 山东交通学院 | A kind of roadbed side slope laying device |
CN109322308A (en) * | 2018-10-22 | 2019-02-12 | 昆明理工大学 | A kind of assembly type side slope climbing feed device |
CN109335980A (en) * | 2018-09-29 | 2019-02-15 | 中铁十六局集团铁运工程有限公司 | A kind of high slope building stones transport device and method |
CN110004952A (en) * | 2019-05-10 | 2019-07-12 | 中冶建工集团有限公司 | Auxiliary operation rack and its installation method for high gradient slope supporting |
CN112376938A (en) * | 2020-12-08 | 2021-02-19 | 中国二十冶集团有限公司 | Mountain material conveying device and method |
CN113235621A (en) * | 2021-04-29 | 2021-08-10 | 通号工程局集团有限公司 | Cross sliding type side slope paving machine |
CN114180279A (en) * | 2021-11-22 | 2022-03-15 | 中国一冶集团有限公司 | Mobile operating device |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1161839A (en) * | 1997-08-26 | 1999-03-05 | Raito Kogyo Co Ltd | Slope face spraying device and slope face spraying construction method |
CN102060199A (en) * | 2010-12-16 | 2011-05-18 | 山西太行建设开发有限公司 | Transportation method for constructing high mountain building |
CN103508173A (en) * | 2013-09-13 | 2014-01-15 | 芜湖汉光立体停车设备有限公司 | Lifting transmission rail |
CN104261084A (en) * | 2014-08-07 | 2015-01-07 | 芜湖环球汽车配件有限公司 | Novel lifting antiskid transmission rail |
CN204173511U (en) * | 2014-09-27 | 2015-02-25 | 无锡明珠钢球有限公司 | A kind of steel ball is with accepting slide rail |
CN104790399A (en) * | 2015-03-23 | 2015-07-22 | 贵阳艺美观景观工程有限公司 | Construction material feeding and conveying method for slope construction |
CN205636741U (en) * | 2016-05-20 | 2016-10-12 | 中交一公局第五工程有限公司 | Slope construction's building materials loading attachment |
CN205676903U (en) * | 2016-05-26 | 2016-11-09 | 中国电建集团铁路建设有限公司 | A kind of high slope rockmass material slide rail transportation system |
-
2017
- 2017-07-06 CN CN201710548740.2A patent/CN107268630A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1161839A (en) * | 1997-08-26 | 1999-03-05 | Raito Kogyo Co Ltd | Slope face spraying device and slope face spraying construction method |
CN102060199A (en) * | 2010-12-16 | 2011-05-18 | 山西太行建设开发有限公司 | Transportation method for constructing high mountain building |
CN103508173A (en) * | 2013-09-13 | 2014-01-15 | 芜湖汉光立体停车设备有限公司 | Lifting transmission rail |
CN104261084A (en) * | 2014-08-07 | 2015-01-07 | 芜湖环球汽车配件有限公司 | Novel lifting antiskid transmission rail |
CN204173511U (en) * | 2014-09-27 | 2015-02-25 | 无锡明珠钢球有限公司 | A kind of steel ball is with accepting slide rail |
CN104790399A (en) * | 2015-03-23 | 2015-07-22 | 贵阳艺美观景观工程有限公司 | Construction material feeding and conveying method for slope construction |
CN205636741U (en) * | 2016-05-20 | 2016-10-12 | 中交一公局第五工程有限公司 | Slope construction's building materials loading attachment |
CN205676903U (en) * | 2016-05-26 | 2016-11-09 | 中国电建集团铁路建设有限公司 | A kind of high slope rockmass material slide rail transportation system |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107986176A (en) * | 2017-11-13 | 2018-05-04 | 新疆兵团水利水电工程集团有限公司 | High slope masonry building stones transporter |
CN108487267A (en) * | 2018-06-04 | 2018-09-04 | 山东交通学院 | A kind of roadbed side slope laying device |
CN109335980A (en) * | 2018-09-29 | 2019-02-15 | 中铁十六局集团铁运工程有限公司 | A kind of high slope building stones transport device and method |
CN109322308A (en) * | 2018-10-22 | 2019-02-12 | 昆明理工大学 | A kind of assembly type side slope climbing feed device |
CN110004952A (en) * | 2019-05-10 | 2019-07-12 | 中冶建工集团有限公司 | Auxiliary operation rack and its installation method for high gradient slope supporting |
CN112376938A (en) * | 2020-12-08 | 2021-02-19 | 中国二十冶集团有限公司 | Mountain material conveying device and method |
CN113235621A (en) * | 2021-04-29 | 2021-08-10 | 通号工程局集团有限公司 | Cross sliding type side slope paving machine |
CN114180279A (en) * | 2021-11-22 | 2022-03-15 | 中国一冶集团有限公司 | Mobile operating device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107268630A (en) | A kind of side slope protection construction material transport system and method | |
CN203269274U (en) | Slope section rail type conveying device | |
CN107575239A (en) | A kind of portable shield launching device for small space | |
CN201494438U (en) | Simple and fast installation cableway for maintenance and rush repair of mountain pipeline | |
CN109335980B (en) | High-slope stone transportation device and method | |
CN102454827A (en) | Pipeline transportation and installation method in tunnel or culvert | |
CN102060199B (en) | Transportation method for constructing high mountain building | |
CN103010949A (en) | Method for traveling and operating portal crane on large-angle slope | |
CN107255188A (en) | A kind of lifting pipeline method suitable at pipe gallery intersection node | |
CN110145333A (en) | A kind of intellect economy type section of jurisdiction construction tool and construction | |
CN212531167U (en) | Simple material conveying device under mountain abrupt slope condition | |
CN109681266B (en) | Large-gradient inclined shaft concrete transportation method | |
CN108590745A (en) | The transportation resources of shield method tunnel construction and its transport structure | |
CN205895274U (en) | A section of jurisdiction travelling bogie that is used for shield constituent body to start | |
CN204506935U (en) | Mining cross-country traveling ability heavier load transport hutching | |
CN102602398B (en) | Quick-transporting method and quick-transport device for foldable temporary cableways | |
CN110733847A (en) | automatic sand paving device on hydraulic engineering inclined plane | |
CN207245715U (en) | Material and dregs transportation system in shield separate launching tunnel | |
CN207986477U (en) | A kind of side slope protection construction material transport system | |
KR102040602B1 (en) | Construct Method of Subway Rail Track Panel | |
CN203114336U (en) | Device for transporting slag discharging vehicle in inclined shaft section and steep slope section | |
CN210087337U (en) | Intelligent economical segment construction tool | |
CN110529156B (en) | Tunnel excavation shield initial segment transportation system and method | |
CN110565531B (en) | Construction channel structure and installation method | |
CN103670416A (en) | Method for rapidly and stably arranging equipment on fully mechanized coal mining face |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20171020 |