KR102040602B1 - Construct Method of Subway Rail Track Panel - Google Patents

Construct Method of Subway Rail Track Panel Download PDF

Info

Publication number
KR102040602B1
KR102040602B1 KR1020190000430A KR20190000430A KR102040602B1 KR 102040602 B1 KR102040602 B1 KR 102040602B1 KR 1020190000430 A KR1020190000430 A KR 1020190000430A KR 20190000430 A KR20190000430 A KR 20190000430A KR 102040602 B1 KR102040602 B1 KR 102040602B1
Authority
KR
South Korea
Prior art keywords
panel
track
concrete
panels
temporary
Prior art date
Application number
KR1020190000430A
Other languages
Korean (ko)
Inventor
한상천
유명철
Original Assignee
한상천
유명철
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한상천, 유명철 filed Critical 한상천
Application granted granted Critical
Publication of KR102040602B1 publication Critical patent/KR102040602B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/32Installing or removing track components, not covered by the preceding groups, e.g. sole-plates, rail anchors
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/14Way of locomotion or support
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/11Embedded tracks, using prefab elements or injecting or pouring a curable material

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to a method for constructing an underground railway track panel and, more specifically, to a method for constructing a precast concrete slab track (PST) on a concrete roadway. According to one of various embodiments of the present invention, a method for constructing an underground railway track panel comprises the steps of: (a′) installing temporary tracks wider than PST panels (hereinafter referred to as panels) on a concrete roadway of a main track tunnel; (b′) carrying a dedicated truck having the panels in a connection path connected to the main track tunnel through a vertical hole with a car lift provided on the ground, wherein the dedicated truck is moved to the main track tunnel along the connection path; (c′) moving the panels loaded on the dedicated truck through a forklift, unloading the same at an exact location by using a disposition carrying lift, and disposing the same; (d′) lifting the unloaded panels with a conveyance carrying lift, conveying the same to a panel landing place along a temporary track, and then landing the same on wooden props placed on the concrete roadway; and (e′) receiving a filler in a concrete mixer-mounted trolley conveyed along the temporary track through vertical pipes installed in the vertical hole, conveying the trolley to a filler injection place, temporarily installing casts on both sides of the panels, fixing the casts to the concrete roadway, and injecting the filler into the concrete roadway, the bottom surface of the panels, and upper surfaces of injection holes formed in the centers of the panels. Thus, the method can construct high-quality PST panels having satisfactory linearity.

Description

지하철도 궤도패널 시공방법 {Construct Method of Subway Rail Track Panel}{Construct Method of Subway Rail Track Panel}

본 발명은 지하철도 궤도패널 시공방법에 관한 것으로서, 더욱 상세하게는 콘크리트 도상에 사전제작형 콘크리트궤도(PST; Precast concrete Slab Track) 패널을 시공하는 방법에 관한 것이다.The present invention relates to a method for constructing a subway track track, and more particularly, to a method for constructing a precast concrete slab track (PST) panel on a concrete road.

PST(사전제작형 콘크리트궤도)는 현장 타설 공법보다 시공속도 향상, 균일한 품질, 공사 및 유지관리비용 절감 등의 장점이 있어 선진국은 1970년대부터 개발하여 광범위하게 적용 중에 있고, 우리나라는 1996년부터 개발하고 있다.PST (prefabricated concrete track) has advantages such as improved construction speed, uniform quality, and reduction of construction and maintenance cost than on-site casting method. Developed countries have been developed since 1970s and have been widely applied. Developing.

즉, 이미 여러 나라에서 철도궤도를 PST 패널 구조로 많이 시공하고 있다.In other words, many countries have already built railroad tracks in PST panels.

이들의 시공방법은 상세히 살펴보면 콘크리트 도상에 고임목을 놓고 그 위에 패널을 올려놓게 된다.In detail, these construction methods place stubble on a concrete floor and put a panel on it.

그리고 PST 패널을 실은 대형화물트럭은 운송수단으로 그 PST 패널 상부를 지나다니면서 PST 패널을 운반하게 된다.The large cargo truck carrying the PST panel carries the PST panel as it travels through the top of the PST panel.

이것은 콘크리트 도상과 PST 패널 사이에 충전재로 채워 완전히 양생되어 고정되었을 때 가능한 것이나, 종래에는 그렇지 않은(고정되지 않은) 상태에서 PST 패널 상부를 지나다니게 되므로 PST 패널이 움직여 선형이 맞지 않고 좋은 품질의 패널을 시공할 수 없는 문제점이 있었다.This is possible when it is fully cured and fixed by filling it between the concrete bed and the PST panel, but in the past, the PST panel moves because it does not fit (unfixed). There was a problem that can not be constructed.

공개번호 제10-2016-0017999호(공개일자 2016년02월17일)Publication No. 10-2016-0017999 (published February 17, 2016)

본 발명은 상술한 문제점을 해결하기 위하여 안출된 것으로서, 콘크리트 도상에 PST 패널 폭보다 더 넓게 임시궤도를 설치하여 패널을 고임목 상에 착지하여 콘크리트 도상과 PST 패널 바닥 사이에 채워진 충전재가 양생될 때까지 본 발명에 적용되는 장비들이 임시궤도를 따라 이송되고 PST 패널 상부를 지나다니지 않으므로 PST 패널의 선형이 맞는 좋은 품질의 PST 패널을 시공할 수 있는 지하철도 궤도패널 시공방법을 제공하는데 그 목적이 있다.The present invention has been made to solve the above-mentioned problems, the temporary track is installed on the concrete road wider than the width of the PST panel to land the panel on the stump until the filler filled between the concrete bed and the bottom of the PST panel is cured. Since the equipments applied to the present invention are transported along a temporary track and do not pass through the upper part of the PST panel, an object of the present invention is to provide a method for constructing a subway road track panel that can construct a PST panel having a good quality of linear alignment.

상술한 목적을 달성하기 위한 본 발명의 일 실시예에 따른 지하철도 궤도패널 시공방법은, (a) 지하 터널의 콘크리트 도상에 PST 패널(이하 패널)보다 더 넓게 임시궤도를 설치하는 단계;Subway road track panel construction method according to an embodiment of the present invention for achieving the above object comprises the steps of (a) installing a temporary track more wider than the PST panel (hereinafter referred to as a panel) on the concrete of the underground tunnel;

(b) 지상에 설비된 겐트리크레인으로 패널을 스프레더 행거에 걸어 수직구를 통해 지하 터널에 반입하되, 상기 임시궤도를 따라 이송하는 운반용대차에 적재하는 단계;(b) hooking the panel to a spreader hanger with a gantry crane mounted on the ground and carrying it into a underground tunnel through a vertical hole, and loading it into a transport trolley for transporting along the temporary track;

(c) 상기 운반용대차에 적재된 패널을 패널착지 장소로 임시궤도를 따라 이송하는 단계;(c) transferring the panel loaded on the transport trolley along a temporary track to a panel landing place;

(d) 상기 운반용대차에 적재된 패널을 부설크레인이 탑재된 운반용대차에 구비된 윈치로 끌어당겨 부설크레인 탑재 운반용대차에 옮기고, 부설크레인의 스프레더 또는 밸트슬링을 이용하여 패널을 하나씩 콘크리트 도상에 놓인 고임목 위에 착지시키는 단계; 및(d) The panel loaded on the transport cart is pulled by the winch provided on the transport crane on which the laying crane is mounted, and transferred to the transportation crane on the laying crane, and the panels are laid one by one using the spreading crane or the belt sling of the laying crane. Landing on the dead wood; And

(e) 상기 수직구에 설치된 수직관을 통해 상기 임시궤도를 따라 이송하는 콘크리트믹서 탑재 대차에 충전재를 공급받아 충전재 주입장소로 이송한 후, 상기 패널 양측면에 거푸집을 가설하여 콘크리트 도상에 고정하고, 상기 콘크리트 도상과 패널 바닥면 그리고 패널 중앙에 형성된 주입구 상면까지 상기 충전재를 주입하는 단계; 를(e) Receiving the filling material in the concrete mixer loading cart to be transported along the temporary track through the vertical pipe installed in the vertical sphere, and transported to the filling material injection site, and then form the formwork on both sides of the panel to be fixed on the concrete drawing, Injecting the filler to the concrete bed, the bottom surface of the panel and the top of the injection hole formed in the center of the panel; To

포함하여 구성된다.It is configured to include.

또한, 상기 운반용대차와 부설크레인이 탑재된 운반용대차의 상판에는 길이방향 좌우 양측에 롤러가 장착되고 그 롤러에는 철도레일이 뒤집어 놓이게 되며 패널은 그 철도레일 바닥면에 적재되는 것을 특징으로 한다.In addition, a roller is mounted on both sides of the left and right sides in the longitudinal direction in the upper plate of the transport cart on which the transport cart and the laying crane are mounted, and the roller is placed upside down, and the panel is loaded on the bottom of the railroad rail.

또한, 상기 수직관의 하단부에 플렉시블 호스가 연결되고 상단부에 반입호퍼가 설치되며, 그 내부에 소정 간격마다 스파이럴 스크류가 형성된 것을 특징으로 한다.In addition, the flexible hose is connected to the lower end of the vertical pipe and the carry-in hopper is installed at the upper end, it characterized in that the spiral screw is formed at predetermined intervals therein.

또한, 상기 지하철도가 복선인 경우 제1임시궤도에 (d)단계를 수행하고 제2임시궤도에 (e)단계를 수행하는 것을, 번갈아가며 반복 수행하는 것을 특징으로 한다.In addition, when the subway map is a double track, performing step (d) on the first temporary track and step (e) on the second temporary track are alternately repeated.

그리고 (f) 상기 (e)단계 이후에 임시궤도로 사용하던 레일을 본선궤도 레일로 사용하여 레일을 설치하는 단계를 더 수행하는 것을 특징으로 한다.And (f) installing the rail using the rail used as the temporary track after the step (e) as the main track rail.

본 발명의 다른 실시예에 따른 지하철도 궤도패널 시공방법은, (a') 본선터널의 콘크리트 도상에 PST 패널(이하 패널)보다 더 넓게 임시궤도를 설치하는 단계;Subway road track panel construction method according to another embodiment of the present invention, (a ') installing the temporary tracks wider than the PST panel (hereinafter referred to as a panel) on the concrete road of the main ship tunnel;

(b') 지상에 설비된 카리프트로 패널이 실린 전용트럭을 수직구를 통해 본선터널에 연결된 연결통로에 반입하되, 상기 전용트럭을 연결통로를 따라 본선터널까지 이동하는 단계;(b ') carrying a dedicated truck loaded with a panel with a car lift installed on the ground into a connecting passage connected to the main tunnel through a vertical port, and moving the dedicated truck along the connecting passage to the main tunnel;

(c') 상기 전용트럭에 실린 패널을 지게차를 통해 옮긴 후 배치 캐리리프트를 이용하여 정확한 위치에 배치하는 단계;(c ') transferring the panel loaded on the dedicated truck through a forklift and placing the panel in the correct position using a batch carry lift;

(d') 상기 배치된 패널을 운송 캐리리프트로 들어올려 임시궤도를 따라 패널착지 장소까지 이송한 후 콘크리트 도상에 놓인 고임목 위에 착지시키는 단계; 및(d ') lifting the disposed panel by a transport carry lift to transport the panel along a temporary track to the panel landing site and landing on the timber placed on concrete; And

(e') 상기 수직구에 설치된 수직관을 통해 상기 임시궤도를 따라 이송하는 콘크리트믹서 탑재 대차에 충전재를 공급받아 충전재 주입장소로 이송한 후, 상기 패널 양측면에 거푸집을 가설하여 콘크리트 도상에 고정하고, 상기 콘크리트 도상과 패널 바닥면 그리고 패널 중앙에 형성된 주입구 상면까지 상기 충전재를 주입하는 단계; 를(e ') Receiving the filling material in the concrete mixer loading cart to be transported along the temporary track through the vertical pipe installed in the vertical sphere and transported to the filling material injection site, and then form the formwork on both sides of the panel to fix the concrete Injecting the filler up to the upper surface of the inlet formed in the center of the concrete panel and the panel; To

포함하여 구성된다.It is configured to include.

그리고 상기 패널에는 짝수개의 관통홀이 상부는 넓고 하부는 좁도록 테이퍼지게 형성되는 것을 특징으로 한다.And the panel is characterized in that the even through holes are tapered so that the upper portion is wider and the lower portion is narrower.

상술한 과제의 해결 수단에 의하면, 콘크리트 도상에 PST 패널 폭보다 더 넓게 임시궤도를 설치하여 패널을 고임목 상에 착지하여 콘크리트 도상과 PST 패널 바닥 사이에 채워진 충전재가 양생될 때까지 본 발명에 적용되는 장비들이 임시궤도를 따라 이송되고 PST 패널 상부를 지나다니지 않으므로 PST 패널의 선형이 맞는 좋은 품질의 PST 패널을 시공할 수 있다.According to the above-mentioned means of solving the problem, the temporary tracks are installed on the concrete road wider than the width of the PST panel, so that the panels are landed on the stump and applied to the present invention until the filled filler is cured between the concrete roof and the PST panel floor. Since the equipment is transported along a temporary track and does not pass over the top of the PST panel, it is possible to construct a good quality PST panel that fits the linearity of the PST panel.

도 1은 본 발명의 일 실시예에 따른 지하철도 궤도패널 시공방법을 나타내는 개략적인 순서도이다.
도 2는 본 발명의 일 실시예에 따른 전체 시공공정을 보인 정면도와 평면도이다.
도 3 내지 도 6은 도 1에 나타낸 각 단계별 시공방법을 나타내는 도면이다.
도 7a와 도 7b는 본 발명의 다른 실시예에 따른 궤도패널 반입 및 배열공정을 보인 평면도와 정면도이다.
도 8a 내지 도 8b는 도 7에 나타낸 운송 캐리리프트에 의한 운송 방법을 나타내는 도면이다.
도 9a와 도 9b는 도 7에 나타낸 운송 캐리리프트를 나타내는 정면도와 측면도이다.
도 10a와 도 10b는 도 7에 나타낸 배치 캐리리프트를 나타내는 정면도와 측면도이다.
1 is a schematic flowchart showing a method for constructing a subway track track panel according to an embodiment of the present invention.
2 is a front view and a plan view showing the entire construction process according to an embodiment of the present invention.
3 to 6 are views showing the construction method for each step shown in FIG.
7A and 7B are a plan view and a front view showing a track panel loading and arranging process according to another embodiment of the present invention.
8A to 8B are diagrams showing a transportation method by the transportation carry lift shown in FIG.
9A and 9B are front and side views showing the transport carry lift shown in FIG.
10A and 10B are front and side views illustrating the arrangement carry lift shown in FIG. 7.

이하 본 발명의 실시예에 대하여 첨부된 도면을 참고로 그 구성 및 작용을 설명하기로 한다.Hereinafter, the configuration and operation of the present invention will be described with reference to the accompanying drawings.

도면들 중 동일한 구성요소들에 대해서는 비록 다른 도면상에 표시되더라도 가능한 한 동일한 참조번호 및 부호들로 나타내고 있음에 유의해야 한다.It should be noted that the same elements among the drawings are denoted by the same reference numerals and symbols as much as possible even though they are shown in different drawings.

하기에서 본 발명을 설명함에 있어, 관련된 공지 기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명을 생략할 것이다.In the following description of the present invention, if it is determined that a detailed description of a related known function or configuration may unnecessarily obscure the subject matter of the present invention, the detailed description thereof will be omitted.

또한, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다.In addition, when a part is said to "include" a certain component, this means that it may further include other components, except to exclude other components unless otherwise stated.

도 1은 본 발명의 일 실시예에 따른 지하철도 궤도패널 시공방법을 나타내는 개략적인 순서도이고, 도 2는 본 발명의 일 실시예에 따른 전체 시공공정을 보인 정면도와 평면도이며, 도 3 내지 도 6은 도 1에 나타낸 각 단계별 시공방법을 나타내는 도면이다.1 is a schematic flowchart showing a method for constructing a subway track track panel according to an embodiment of the present invention, Figure 2 is a front view and a plan view showing the entire construction process according to an embodiment of the present invention, Figures 3 to 6 Is a view showing the construction method for each step shown in FIG.

도 1 내지 도 6을 참고로 본 발명을 시공 공정순으로 설명하면 다음과 같다.Referring to Figures 1 to 6 the present invention will be described in the order of construction process as follows.

<패널반입 단계(S10)><Panel Import Step (S10)>

지하철도를 시공하기 위해 먼저, 토목 공사를 통해 지하에 터널(3)과 이 터널에 지상과 연통되는 수직구(1)를 형성하며, 상기 수직구(1)에 모르타르 반입을 위한 수직관(2)을 설치하여, 그 하단부에 플렉시블 호스를 연결하고 상단부에 반입호퍼를 설치한다.In order to construct a subway road, first, through a civil construction, a tunnel 3 and a vertical sphere 1 are formed in communication with the ground in this tunnel, and a vertical pipe 2 for carrying mortar into the vertical sphere 1 is formed. ), Connect the flexible hose to the lower part and install the hopper at the upper part.

상기 수직구(1)는 정거장 근처에 만들어질 수 있고 이 수직구를 이용하여 인승용 승강기가 설치될 수 있다.The vertical sphere (1) can be made near the station and using this vertical sphere can be installed a passenger lift.

또한, 지하 터널(3)에는 바닥면에 콘크리트 도상을 설치하고, 상기 콘크리트 도상에 후술할 PST 패널 폭보다 더 넓게 임시궤도(31,32)를 설치한다.In addition, the concrete tunnel is installed on the bottom surface of the underground tunnel 3, and the temporary tracks 31 and 32 are installed on the concrete road wider than the width of the PST panel to be described later.

이와 같은 상태에서 도 3에 도시된 바와 같이 지상에 설비된 겐트리크레인(10)으로 대형 운반용트레일러(12)에 실려온 PST 패널(이하 '패널'이라 한다.)(20)을 크레인에 매달린 스프레더(Spreader) 행거에 걸어 상기 수직구(1)를 통해 지하 터널(3)에 내려놓아 반입한다.In this state, as shown in FIG. 3, a spreader that suspended a PST panel (hereinafter referred to as a 'panel') 20 mounted on a large transport trailer 12 as a gantry crane 10 installed on the ground ( Spreader) It hangs and hangs in the underground tunnel 3 through the vertical hole 1, and carries it in.

이와 같은 패널 반입 작업은 도심일 경우 번잡함을 고려하여 야간에 진행하며, 수직구(1) 아래에 대기중인 운반용대차(16)에 적재한다.Such a panel carrying operation is carried out at night in consideration of the busyness in the city center, and is loaded in the transport trolley 16 waiting under the vertical sphere (1).

물론 이 운반용대차(16)는 앞쪽에 연결된 동력궤도차(14)에 의해 견인되어 이송하며, 이때 콘크리트 도상에 패널 폭보다 더 넓게 설치된 임시궤도(31,32)를 따라 이송한다.Of course, the transport trolley 16 is towed and transported by the power track 14 connected to the front, at this time is transported along the temporary tracks 31 and 32 installed wider than the panel width on the concrete.

<패널운반 단계(S11)><Panel Transport Step (S11)>

도 4에 도시된 바와 같이 상기 임시궤도(31,32)를 따라 이송하는 장비들은 제일 후미에 부설크레인(18a)이 탑재된 운반용대차(18) 그 앞쪽에 다수의 운반용대차(16) 그리고 그 앞쪽에 동력궤도차(14) 순으로 연결되어 배열된다.As shown in FIG. 4, the equipment for transporting along the temporary tracks 31 and 32 includes a plurality of transport trolleys 16 in front of the transport trolley 18 on which the laying crane 18a is mounted at the fore end, and in front of the front tracks 31 and 32. The power tracks 14 are arranged in order.

상기 모든 운반용대차(16,18)의 상판에는 적당한 간격으로 길이방향 좌우 양측에 롤러가 장착되고 그 롤러에는 철도레일이 뒤집어 놓이게 되며 패널은 그 철도레일 바닥면(정상으로 놓인 상태에서의 바닥면, 즉 뒤집어 놓인 상태에서의 상면)에 놓이게 된다.The upper plates of all the transport trolleys 16 and 18 are equipped with rollers on both sides in the longitudinal direction at appropriate intervals, and the rails are placed upside down on the rollers, and the panel is the bottom of the railroad rails (the bottom surface in the normal state, In other words, it is placed upside down (upside down).

이것은 끌어당기기 용이함과 패널과 철도레일 간의 접촉면적을 크게 하기 위함이다.This is to ease the pulling and increase the contact area between the panel and the rail.

상기 패널반입 단계(S10)에서 겐트리크레인(10)에 의해 매달려 반입되는 패널(20)은 착지 장소로 임시궤도(31,32)를 따라 이송된다.In the panel loading step (S10), the panel 20 suspended and carried by the gantry crane 10 is transferred along the temporary tracks 31 and 32 to the landing place.

<패널착지 단계(S12)><Panel landing step (S12)>

계속하여 도 4에 도시된 바와 같이 착지장소로 패널이 이송된 후 후미 다음에 있는 운반용대차(16)에 실려진 패널(20)은 부설크레인(18a)이 탑재된 운반용대차(18) 후미에 설비된 윈치(Winch)(18b)로 끌어당겨 부설크레인 탑재 운반용대차(18)에 옮긴다.Subsequently, after the panel is transferred to the landing site as shown in FIG. 4, the panel 20 mounted on the transport trolley 16 next to the rear end is installed at the rear of the transport trolley 18 on which the laying crane 18a is mounted. It is pulled by the winch 18b and moved to the installation crane 18 for laying cranes.

다음 부설크레인(18a)의 스프레더를 이용하여 패널을 하나씩 콘크리트 도상에 충전재 두께만큼(예를 들어 약 40mm) 고임목을 놓고 그 위에 선형을 잡아 착지시킨다.Next, using the spreader of the laying crane 18a, the panels are placed one by one on the concrete sheet by the thickness of the filler material (for example, about 40 mm), and the linear wood is placed on the ground.

이때 캔트(Cant) 구간에서 선형이 맞지 않을 경우 부설크레인(18a)이 탑재된 운반용대차(18) 앞뒤에 있는 아웃트리거(outrigger)를 조정하여 선형을 바로 잡는다.At this time, if the linearity does not fit in the cant section, the linearity is corrected by adjusting the outrigger in front and rear of the transport cart 18 on which the laying crane 18a is mounted.

상기 동력궤도차(14)를 이용하여 패널착지 공간을 확보하면서 상기한 방법으로 패널(20)을 착지하되, 부설크레인(18a)이 탑재된 운반용대차(18)에 옮겨진 패널(20)이 모두 소진되면, 부설크레인(18a)이 탑재된 운반용대차(18) 후미에 부착된 윈치(18b)를 이용하여 앞쪽 운반용대차(16)에 있는 패널(20)을 끌어당겨 부설크레인 탑재 운반용대차(18)에 가져와서 패널착지 작업을 계속한다.When the panel 20 is landed by the above method while securing the panel landing space by using the power track 14, when all the panels 20 transferred to the transport cart 18 on which the laying crane 18a is mounted are exhausted. By using the winch 18b attached to the rear end of the transport cart 18 on which the laying crane 18a is mounted, the panel 20 on the front transport trolley 16 is pulled and brought to the laying crane mounting transport trolley 18. Continue with panel landing.

이와 같이 하여 콘크리트 도상의 고임목 상에 패널착지 작업이 완료되면 다음 작업을 위해 견인용 동력궤도차(14), 운반용대차(16), 부설크레인 탑재 운반용대차(18)는 수직구(1) 아래에 도착하여 다음 패널운반을 대기한다.In this way, when the panel landing work is completed on the solid wood on the concrete road, the traction power track 14, the transport trolley 16, and the laying crane-mounted transport trolley 18 arrive under the vertical sphere 1. Wait for the next panel transport.

이때 도 2에 도시된 바와 같이 패널(20)은 임시궤도(31,32)보다 폭이 좁게 형성되어 임시궤도(31,32) 내부에 착지된다.In this case, as shown in FIG. 2, the panel 20 is formed to have a smaller width than the temporary tracks 31 and 32 to be landed inside the temporary tracks 31 and 32.

<패널측량 및 고정단계(S13)>Panel Surveying and Fixing Steps (S13)

다음 콘크리트 도상의 고임목 상에 착지된 패널(20)들은 GPS(Global Positioning System)를 사용하여 높낮이와 선형 등을 측정해서 래일잭(Jack) 등의 기구를 이용하여 고정금구 등으로 고정시킨다.Next, the panels 20 mounted on the stumps of concrete are measured by height and linearity using a GPS (Global Positioning System), and then fixed using a fixture such as a rail jack.

<충전재주입 및 반입단계(S14)><Filling and refilling stage (S14)>

도 5에 도시된 바와 같이 임시궤도(31,32) 상에 있는 충전재장비(콘크리트믹서) 탑재 대차(13)는 그 앞쪽에 연결된 동력궤도차(11)에 의해 임시궤도(31,32)를 따라 이송한다.As shown in FIG. 5, the filling equipment (concrete mixer) loading truck 13 on the temporary tracks 31 and 32 is transported along the temporary tracks 31 and 32 by a power track 11 connected to the front side thereof. do.

전술한 바와 같이 지상과 지하 터널(3)을 연결하는 수직구(1)에 수직관(2)이 설치되고 지상에서는 모르타르 반입호퍼가 수직관(2) 상부에 형성된다.As described above, the vertical pipe 2 is installed in the vertical sphere 1 connecting the ground and the underground tunnel 3, and the mortar carrying hopper is formed on the vertical pipe 2 above the ground.

이때 수직관(2) 내부는 모르타르가 낙하하면서 생기는 가속도를 방지하기 위해, 약 1m마다 스파이럴 스크류가 만들어진다.At this time, in order to prevent the acceleration generated when the mortar falls inside the vertical pipe (2), a spiral screw is made every about 1m.

이 수직관(2)을 통해 지상의 레미콘 차량(15)으로부터 지하 터널(3)의 콘크리트믹서 탑재 대차(13)에 충전재를 공급받는다(S14a)Filling material is supplied to the concrete mixer-mounted trolley 13 of the underground tunnel 3 from the ground concrete vehicle 15 through the vertical pipe 2 (S14a).

다음 패널 양측면에 목재 또는 철재 등으로 된 거푸집을 가설하여 충전재 주입시 충전재가 패널 양 측면으로 세어나가지 않도록 한다.Next, formwork made of wood or steel on both sides of the panel to prevent the filler from counting on both sides of the panel.

이때 거푸집은 경량 철재 구조로 콘크리트 도상에 앵카볼트를 삽입하여 고정시켜 주는 것이 바람직하다.At this time, it is preferable that the formwork is fixed by inserting the anchor bolt on the concrete structure as a lightweight steel structure.

다음, 도 6에 도시된 바와 같이 충전재장비(콘크리트믹서) 탑재 대차(13)를 통해 충전재 주입장소에 도착된 충전재를, 콘크리트 펌프에 의해 콘크리트 도상과 패널 바닥면 그리고 패널 중앙에 형성된 주입구 상면까지 충분히 주입한다(S14b).Next, as shown in FIG. 6, the filling material arrived at the filling material injection place through the filling equipment loading device 13 (concrete mixer) to the filling site formed by the concrete pump and the upper surface of the inlet formed at the center of the panel and the panel center is sufficiently filled. Inject (S14b).

이때 1회에 약 6m3 정도 공급받아 충전재 주입장소로 이동하여 콘크리트 펌프로 충전한다.At this time, about 6m 3 is supplied at a time, and it is moved to the filling place and filled with concrete pump.

한편, 지하철도를 복선으로 시공하는 경우 도 2에 도시된 바와 같이, 제1임시궤도(31)에서 패널착지 작업시에는 제2임시궤도(32)에서 충전재 주입작업을 시행하고, 이것을 번갈아가며 시공하는 것이 공사비를 절감하면서 시공을 빠르게 할 수 있어 바람직하다.On the other hand, when constructing a subway road in a double line, as shown in Figure 2, when the panel landing work in the first temporary track 31, the filling material is injected in the second temporary track 32, alternately construction It is desirable to speed up construction while reducing construction costs.

<레일설치 단계(S15)><Rail installation step (S15)>

이 단계에서는 임시궤도로 사용하던 레일을 본선궤도 레일로 사용한다.At this stage, the rail used as the temporary track is used as the main track rail.

굴삭기(Excavator)를 이용하여 시공된 패널 위에 레일을 걷어 올려놓고 레일과 레일 간의 이음은 현장 맞댐용접으로 하며 용접부의 오버랩은 그라인딩 처리하여 레일체결구로 패널과 레일을 체결하여 마감 시공한다.The rail is rolled up on the constructed panel using an excavator, and the joint between the rail and the rail is welded on site. The overlap between the welds is ground, and the panel and rail are fastened with rail fasteners to finish the construction.

한편, 임시궤도 시공시에 레일과 레일을 이음매없이 용접시공하여 임시궤도로 사용하면 본선궤도 레일 시공이 편리할 수도 있는 것으로, 이 경우 굴삭기로 레일을 패널 위에 걷어올려 레일체결구로 체결하면 본선궤도 레일 시공을 간단히 완료할 수 있다.On the other hand, when the rail and rail are welded seamlessly and used as a temporary track during temporary track construction, the main track rail construction may be convenient. In this case, when the rail is lifted on a panel with an excavator and fastened with a rail fastener, the main track track Construction can be completed simply.

<응력제거 단계(S16)><Stress Removal Step (S16)>

상기 레일설치 단계(S15)에서 레일이 이리저리 구부려 인장과 압축 응력이 쌓여 있다.In the rail installation step (S15), the rail is bent around and the tensile and compressive stress is accumulated.

이 응력을 금속이 아닌 합성수지 계열의 해머 등으로 약 1m 간격으로 안쪽과 바깥쪽으로 두들겨 주면 제거된다.This stress is removed by tapping inwards and outwards at intervals of about 1m with a non-metal synthetic hammer.

이때 해머의 무게는 2kg이고 해머 자루의 길이는 약 60cm 정도가 적당하다.At this time, the weight of the hammer is 2kg and the length of the hammer bag is about 60cm.

도 7a와 도 7b는 본 발명의 다른 실시예에 따른 궤도패널 반입 및 배열공정을 보인 평면도와 정면도이고, 도 8a 내지 도 8b는 도 7에 나타낸 운송 캐리리프트에 의한 운송 방법을 나타내는 도면이며, 도 9a와 도 9b는 도 7에 나타낸 운송 캐리리프트를 나타내는 정면도와 측면도이며, 도 10a와 도 10b는 도 7에 나타낸 배치 캐리리프트를 나타내는 정면도와 측면도이다.7a and 7b are a plan view and a front view showing a track panel loading and arranging process according to another embodiment of the present invention, Figures 8a to 8b is a view showing a transport method by the transport carriage shown in Figure 7, 9A and 9B are front and side views showing the transport carry lift shown in FIG. 7, and FIGS. 10A and 10B are front and side views showing the layout carry lift shown in FIG. 7.

도 1의 일 실시예와는 패널반입 단계(S10)와 패널운반 단계(S11) 및 패널착지 단계(S12)만 상이하고 나머지 단계는 동일하므로, 이하에서는 패널반입 단계(S10)와 패널운반 단계(S11) 및 패널착지 단계(S12)에 대해서만 상술한다.1 is different from the panel import step S10, the panel transport step S11, and the panel landing step S12, and the remaining steps are the same, so that the panel import step S10 and the panel transport step are as follows. Only the S11) and the panel landing step S12 will be described in detail.

<패널반입 단계(S10)><Panel Import Step (S10)>

지하철도를 시공하기 위해 먼저, 토목 공사를 통해 지하에 연결통로(4)와 이 연결통로(4)에 지상과 연통되는 수직구(1)를 형성하며, 상기 수직구(1)에 모르타르 반입을 위한 수직관(미도시)을 설치하여, 그 하단부에 플렉시블 호스를 연결하고 상단부에 반입호퍼를 설치한다.In order to construct a subway road, first, through a civil engineering work, a connecting passage 4 is formed in the basement and a vertical sphere 1 is formed in communication with the ground in the connecting passage 4, and mortar is carried in the vertical sphere 1. Install a vertical pipe (not shown) for connecting the flexible hose to the lower end and the loading hopper is installed on the upper end.

상기 수직구(1)는 정거장 근처에 만들어질 수 있고 이 수직구(1)에 인승용 승강기가 설치될 수 있다.The vertical sphere 1 can be made near a station and a vertical lift can be installed in the vertical sphere 1.

또한, 상기 지하의 연결통로(4)에 연통되는 본선터널(5)을 형성하여 그 바닥면에 콘크리트 도상을 설치하고, 상기 콘크리트 도상에 후술할 PST 패널 폭보다 더 넓게 임시궤도(31,32)를 설치한다.In addition, the main tunnel (5) to communicate with the connection passage 4 of the basement is formed to install a concrete icon on the bottom surface, the temporary tracks (31, 32) wider than the width of the PST panel to be described later on the concrete diagram Install it.

또한, 상기 수직구(1)에 카리프트(40)를 설치하여 대형 운송트럭(41)에 실려 제작공장에서 수직구(1)가 형성된 설치현장까지 운반된 PST 패널('패널(20)')을 중형 전용트럭(42)에 옮겨싣은 후, 상기 카리프트(40)를 이용해서 패널(20)이 실린 전용트럭(42)을 수직구(1)를 통해 연결통로(4)에 내려놓는다.In addition, the PST panel ('panel 20') installed on the vertical sphere (1) is carried to the installation site where the vertical sphere (1) is formed in a large transport truck 41 is installed on the large transport truck (41) After transporting to the medium dedicated truck 42, the dedicated truck 42 on which the panel 20 is loaded using the car lift 40 is lowered to the connecting passage 4 through the vertical hole (1).

계속하여 패널(20)이 실린 전용트럭(42)은 연결통로(4)를 통해 본선터널(5)이 있는 곳까지 운송되며 이때 패널(20)은 지게차(43)에 의해 옮겨진 후 콘크리트 도상에 패널 폭보다 더 넓게 설치된 임시궤도(31,32)를 따라 이동하는 배치 캐리리프트(60)에 의해 정확한 바닥 위치에 배치한다.The dedicated truck 42 carrying the panel 20 is transported through the connecting passage 4 to the main tunnel 5 where the panel 20 is moved by the forklift 43 and then the panel on the concrete road. It is placed in the correct floor position by the placement carrylift 60 moving along the temporary tracks 31 and 32 installed wider than the width.

상기 배치 캐리리프트(60)는 도 10a와 도 10b에 도시된 바와 같이 수평과 수직으로 일정한 틀을 형성하는 프레임(61)과, 상기 수직 프레임 양측 하부에 구비되어 임시궤도(31,32)를 따라 이송하는 주행장치(63)와, 상기 수평 프레임에 설치되어 패널(20)을 상하로 이동하고 정확한 위치에 배치하는 호이스트(62)와, 상기 호이스트(62)의 하부에 결합되고 패널(20)을 들어 올리는 벨트슬링(64) 또는 스프레더를 구비한다.The arrangement carrylift 60 is a frame 61 forming a constant frame horizontally and vertically, as shown in Figs. 10a and 10b, and is provided on the lower side of both sides of the vertical frame along the temporary tracks (31, 32) The traveling device 63 for transporting, the hoist 62 mounted on the horizontal frame to move the panel 20 up and down and disposed at the correct position, and coupled to the lower portion of the hoist 62 and the panel 20 A lifting belt sling 64 or a spreader is provided.

상기 주행장치(63)에는 미도시된 동력장치가 구비되어 배치 캐리리프트(60)의 독자적인 이동이 가능하여, 패널(20)이 정확한 위치에 배치될 수 있도록 패널을 들어올려 정확한 위치로 이동한다.The traveling device 63 is provided with a power unit, not shown, to enable the independent movement of the arrangement carry lift 60, and lift the panel to move to the correct position so that the panel 20 can be disposed at the correct position.

이와 같은 배치 캐리리프트(60)를 이용하여 패널(20)을 배치하되, 상기 배치 캐리리프트(60)는 후술할 운송 캐리리프트(50)가 패널(20)을 싣고 설치(착지)할 위치까지 이동할 동안, 다시 전용트럭(42)에서 패널(20)을 지게차(43)로 내리고 내린 패널(20)을 정확하게 배치해서 운송 캐리리프트(50)가 바로 싣고서 이동할 수 있게 해주는 역할을 한다.The panel 20 is disposed using the batch carrylift 60 as described above, but the batch carrylift 60 moves to a position where the transport carry lift 50 to be described later will be loaded (installed). During this time, the dedicated truck 42 lowers the panel 20 to the forklift 43 and accurately positions the lowered panel 20 so that the transport carry lift 50 can be directly loaded and moved.

한편, 패널(20)을 내려놓은 빈 전용트럭(42)은 연결통로(4)를 따라 수직구(1) 하부까지 운송된 후 카리프트(40)를 통해 상승하여 지상에서 대기한다.Meanwhile, the empty dedicated truck 42 which puts down the panel 20 is transported to the lower portion of the vertical hole 1 along the connection passage 4 and then ascends through the car lift 40 to stand on the ground.

<패널운반 단계(S11)><Panel Transport Step (S11)>

상기 임시궤도(31,32)를 따라 이동하는 운송 캐리리프트(50)는 앞쪽에 연결된 견인차(51)에 의해 임시궤도(31,32)를 따라 패널(20)을 설치(착지)장소까지 이송한다.The transport carry lift 50 moving along the temporary tracks 31 and 32 transfers the panel 20 along the temporary tracks 31 and 32 to the installation (landing) location by the tow truck 51 connected to the front side. .

상기 운송 캐리리프트(50)는 도 9a와 도 9b에 도시된 바와 같이 수평과 수직 및 경사지게 형성되어 일정한 틀을 형성하는 프레임(55)과, 상기 수직 프레임 양측 하부에 구비되어 임시궤도(31,32)를 따라 이송하는 주행장치(53)와, 상기 수평 프레임에 설치되어 패널(20)을 상하로 이동하고 배열하는 호이스트(52)와, 상기 호이스트(52)의 하부에 결합되고 패널(20)을 들어 올리는 벨트슬링(54)를 구비한다.As shown in FIGS. 9A and 9B, the transport carry lift 50 includes a frame 55 formed horizontally and vertically and inclined to form a constant frame, and provided on both lower sides of the vertical frame to provide temporary tracks 31 and 32. A traveling device 53 for conveying along the circumference, a hoist 52 installed on the horizontal frame to move and arrange the panel 20 up and down, and coupled to a lower portion of the hoist 52, And a belt sling 54 for lifting.

이를 위해 상기 패널(20)에는 벨트슬링(54)을 끼워 달아 올릴 수 있도록 짝수개의 관통홀(21)이 상부는 넓고 하부는 좁도록 테이퍼지게 형성되며, 상기 주행장치(53)에는 동력장치가 구비되어 있지않아 운송 캐리리프트(50)는 독자적인 운송이 불가능하므로 운송 캐리리프트를 서로 연결하여 견인차(또는 궤육견인차)를 통해 이동한다.To this end, an even number of through-holes 21 are tapered so that the upper and lower portions of the panel 20 are tapered so that the belt sling 54 can be fitted into the panel 20. The driving device 53 is provided with a power unit. Since it is not possible to transport the carriage 50 is not possible to transport independently, the transport carry lifts are connected to each other to move through a tow truck (or dog dog car).

<패널착지 단계(S12)><Panel landing step (S12)>

계속하여 운송 캐리리프트(50)에 의해 설치(착지)장소까지 패널(20)이 이송된 후 콘크리트 도상에 충전재 두께만큼(예를 들어 약 40mm) 고임목을 놓고 그 위에 선형을 잡아 착지시킨다(배치한다).Subsequently, after the panel 20 is transferred to the place of installation (landing) by the transport carry lift 50, the solid wood is placed on the concrete road (for example, about 40 mm) by the thickness of the filling material, and the linear wood is placed on the ground (to be placed). ).

이때 도 2에 도시된 바와 같이 패널(20)은 임시궤도(31,32)보다 폭이 좁게 형성되어 임시궤도(31,32) 내부에 착지된다.In this case, as shown in FIG. 2, the panel 20 is formed to have a smaller width than the temporary tracks 31 and 32 to be landed inside the temporary tracks 31 and 32.

이상에서 본 발명에 대한 기술 사상을 첨부 도면과 함께 서술하였지만, 이는 본 발명의 바람직한 실시예를 예시적으로 설명한 것이지 본 발명을 한정하는 것은 아니다.Although the technical spirit of the present invention has been described above with reference to the accompanying drawings, the present invention has been described by way of example and is not intended to limit the present invention.

또한, 이 기술 분야의 통상의 지식을 가진 자라면 누구나 본 발명의 기술 사상의 범주를 이탈하지 않는 범위 내에서 다양한 변형 및 모방이 가능함은 명백한 사실이다.In addition, it is obvious that any person skilled in the art may make various modifications and imitations without departing from the scope of the technical idea of the present invention.

1: 수직구 2: 수직관
3: 지하 터널 10: 겐트리크레인
11,14: 동력궤도차 12: 운반용 트레일러
13: 콘크리트믹서 탑재 대차 15: 레미콘 차량
16: 운반용대차 18: 부설크레인 탑재 운반용대차
20: 패널 31,32: 임시궤도
1: vertical sphere 2: vertical tube
3: Underground Tunnel 10: Gantry Crane
11,14: Power railcar 12: Transport trailer
13: truck with concrete mixer 15: ready-mixed vehicle
16: transport cart 18: transport crane with laying crane
20: Panel 31, 32: Temporary track

Claims (7)

(a) 지하 터널의 콘크리트 도상에 PST 패널(이하 패널)보다 더 넓게 임시궤도를 설치하는 단계;
(b) 지상에 설비된 겐트리크레인으로 패널을 스프레더 행거에 걸어 수직구를 통해 지하 터널에 반입하되, 상기 임시궤도를 따라 이송하는 운반용대차에 적재하는 단계;
(c) 상기 운반용대차에 적재된 패널을 패널착지 장소로 임시궤도를 따라 이송하는 단계;
(d) 상기 운반용대차에 적재된 패널을 부설크레인이 탑재된 운반용대차에 구비된 윈치로 끌어당겨 부설크레인 탑재 운반용대차에 옮기고, 부설크레인의 스프레더 또는 밸트슬링을 이용하여 패널을 하나씩 콘크리트 도상에 놓인 고임목 위에 착지시키는 단계; 및
(e) 상기 수직구에 설치되고, 하단부에 플렉시블 호스가 연결되며 상단부에 반입호퍼가 설치되고, 그 내부에 소정 간격마다 스파이럴 스크류가 형성된 수직관을 통해 상기 임시궤도를 따라 이송하는 콘크리트믹서 탑재 대차에 충전재를 공급받아 충전재 주입장소로 이송한 후, 상기 패널 양측면에 거푸집을 가설하여 콘크리트 도상에 고정하고, 상기 콘크리트 도상과 패널 바닥면 그리고 패널 중앙에 형성된 주입구 상면까지 상기 충전재를 주입하는 단계; 를
포함하는 지하철도 궤도패널 시공방법.
(a) installing a temporary track on the concrete roadway of the underground tunnel more widely than a PST panel (hereinafter referred to as panel);
(b) hooking the panel to a spreader hanger with a gantry crane mounted on the ground and carrying it into a underground tunnel through a vertical hole, and loading it into a transport trolley for transporting along the temporary track;
(c) transferring the panel loaded on the transport trolley along a temporary track to a panel landing place;
(d) The panel loaded on the transport cart is pulled by the winch provided on the transport crane on which the laying crane is mounted, and transferred to the transportation crane on the laying crane, and the panels are laid one by one using the spreading crane or the belt sling of the laying crane. Landing on the dead wood; And
(e) a concrete mixer loading truck which is installed in the vertical sphere, a flexible hose is connected to the lower end, and an import hopper is installed at the upper end, and is transported along the temporary track through a vertical pipe formed with spiral screws at predetermined intervals therein. Receiving a filler and transporting the filler to a filler injection site, and installing formwork on both sides of the panel to fix the mold on the concrete island, and injecting the filler to the concrete island, the bottom surface of the panel and the top of the injection hole formed in the center of the panel; To
Subway track track panel construction method.
제1항에 있어서,
상기 운반용대차와 부설크레인이 탑재된 운반용대차의 상판에는 길이방향 좌우 양측에 롤러가 장착되고 그 롤러에는 철도레일이 뒤집어 놓이게 되며 패널은 그 철도레일 바닥면에 적재되는 것을 특징으로 하는 지하철도 궤도패널 시공방법.
The method of claim 1,
The upper plate of the transport trolley on which the transport trolley and the laying crane are mounted is equipped with rollers on both sides in the longitudinal direction, and the rails are placed upside down on the rollers, and the panel is loaded on the bottom surface of the railway rail. Construction method.
삭제delete 제1항에 있어서,
상기 지하철도가 복선인 경우 제1임시궤도에 (d)단계를 수행하고 제2임시궤도에 (e)단계를 수행하는 것을, 번갈아가며 반복 수행하는 것을 특징으로 하는 지하철도 궤도패널 시공방법.
The method of claim 1,
And (d) performing the step 1d on the first temporary track and performing the step (e) on the second temporary track when the subway is a double track.
제1항에 있어서,
(f) 상기 (e)단계 이후에 임시궤도로 사용하던 레일을 본선궤도 레일로 사용하여 레일을 설치하는 단계를 더 수행하는 것을 특징으로 하는 지하철도 궤도패널 시공방법.
The method of claim 1,
(f) using the rail used as a temporary track after the step (e) as a main track rail installation step further comprising the step of installing the rail track panel construction method.
(a') 본선터널의 콘크리트 도상에 PST 패널(이하 패널)보다 더 넓게 임시궤도를 설치하는 단계;
(b') 지상에 설비된 카리프트로 패널이 실린 전용트럭을 수직구를 통해 본선터널에 연결된 연결통로에 반입하되, 상기 전용트럭을 연결통로를 따라 본선터널까지 이동하는 단계;
(c') 상기 전용트럭에 실린 패널을 지게차를 통해 옮긴 후 배치 캐리리프트를 이용하여 정확한 위치에 하역하여 배치하는 단계;
(d') 상기 하역된 패널을 운송 캐리리프트로 들어올려 임시궤도를 따라 패널착지 장소까지 이송한 후 콘크리트 도상에 놓인 고임목 위에 착지시키는 단계; 및
(e') 상기 수직구에 설치된 수직관을 통해 상기 임시궤도를 따라 이송하는 콘크리트믹서 탑재 대차에 충전재를 공급받아 충전재 주입장소로 이송한 후, 상기 패널 양측면에 거푸집을 가설하여 콘크리트 도상에 고정하고, 상기 콘크리트 도상과 패널 바닥면 그리고 패널 중앙에 형성된 주입구 상면까지 상기 충전재를 주입하는 단계; 를
포함하는 지하철도 궤도패널 시공방법.
(a ') installing a temporary track on a concrete roadway of a main tunnel more widely than a PST panel (hereinafter referred to as a panel);
(b ') carrying a dedicated truck loaded with a panel with a car lift installed on the ground into a connecting passage connected to the main tunnel through a vertical port, and moving the dedicated truck along the connecting passage to the main tunnel;
(c ') transferring the panel loaded on the dedicated truck through a forklift and unloading and placing the panel in an accurate position using a batch carry lift;
(d ') lifting the unloaded panel by a transport carry lift and transporting it along the temporary track to the panel landing site and landing it on the timber placed on the concrete island; And
(e ') Receiving the filler in the concrete mixer loading cart to be transported along the temporary track through the vertical pipe installed in the vertical sphere, and transported to the filling material injection site, and then form the formwork on both sides of the panel to fix the concrete Injecting the filler up to the upper surface of the inlet formed in the center of the concrete panel and the panel; To
Subway track track panel construction method.
제6항에 있어서,
상기 패널에는 짝수개의 관통홀이 상부는 넓고 하부는 좁도록 테이퍼지게 형성되는 것을 특징으로 하는 지하철도 궤도패널 시공방법.
The method of claim 6,
The method of claim 1, wherein the panel is tapered so that the even through holes are wider at the top and narrower at the bottom.
KR1020190000430A 2018-07-25 2019-01-02 Construct Method of Subway Rail Track Panel KR102040602B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020180086489 2018-07-25
KR20180086489 2018-07-25

Publications (1)

Publication Number Publication Date
KR102040602B1 true KR102040602B1 (en) 2019-11-06

Family

ID=68541549

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190000430A KR102040602B1 (en) 2018-07-25 2019-01-02 Construct Method of Subway Rail Track Panel

Country Status (1)

Country Link
KR (1) KR102040602B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111139697A (en) * 2020-01-15 2020-05-12 中铁十一局集团第三工程有限公司 Self-compacting concrete pouring method and device for subway plate type turnout
CN111254760A (en) * 2020-03-05 2020-06-09 中铁九局集团第七工程有限公司 Construction method for laying track slab by using gantry crane
KR102616318B1 (en) 2022-12-28 2023-12-22 삼표레일웨이 주식회사 Deep underground tunnel PST construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040008615A (en) * 2002-07-19 2004-01-31 궤도공영 주식회사 method for shoting ready mixed concrete to a mold for construct concrete roadbed in a railway tunnel
KR101401995B1 (en) * 2013-08-29 2014-05-30 (주)네비엔 The railway construction method using the precast slab track
JP2015229829A (en) * 2014-06-03 2015-12-21 大成建設株式会社 Track for railway vehicle and construction method for the track
KR20160017999A (en) 2014-08-07 2016-02-17 주식회사 포스코건설 Precast slab floating railway structure and construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040008615A (en) * 2002-07-19 2004-01-31 궤도공영 주식회사 method for shoting ready mixed concrete to a mold for construct concrete roadbed in a railway tunnel
KR101401995B1 (en) * 2013-08-29 2014-05-30 (주)네비엔 The railway construction method using the precast slab track
JP2015229829A (en) * 2014-06-03 2015-12-21 大成建設株式会社 Track for railway vehicle and construction method for the track
KR20160017999A (en) 2014-08-07 2016-02-17 주식회사 포스코건설 Precast slab floating railway structure and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111139697A (en) * 2020-01-15 2020-05-12 中铁十一局集团第三工程有限公司 Self-compacting concrete pouring method and device for subway plate type turnout
CN111254760A (en) * 2020-03-05 2020-06-09 中铁九局集团第七工程有限公司 Construction method for laying track slab by using gantry crane
KR102616318B1 (en) 2022-12-28 2023-12-22 삼표레일웨이 주식회사 Deep underground tunnel PST construction method

Similar Documents

Publication Publication Date Title
KR102040602B1 (en) Construct Method of Subway Rail Track Panel
CN106638687B (en) A kind of accurate quick-assembling technique of precast assembly pipe gallery
WO2019080824A1 (en) Novel track laying machine for urban rail transport project and construction method therefor
JP5507383B2 (en) Heavy load erection machine and heavy load erection method
CN104790295A (en) Construction method of tire type gantry crane frame beam
KR101573369B1 (en) Slabs railway track repair equipment and slabs railway track repair method using the same
CN110230261B (en) Mounting construction method for upper frame beam of double-layer synchronous beam
CN207498754U (en) A kind of novel track-laying machine of city track traffic engineering
CN113957793A (en) Construction method for prefabricating box girder support in complex urban environment
CN106400693A (en) Slope ramp steel box beam conveying vehicle and method
CN206245344U (en) A kind of installation car assembled for precast assembly pipe gallery
JP2007205130A (en) Girder construction method by erection garter from side of bridge
CN110318308B (en) System and method for paving magnetic levitation track panel in complex section
CN105781108B (en) A kind of construction method for being used to close on large-scale steel-mould trolley entirety transition between place
CN110316662B (en) Installation and construction method of large-span portal crane
CN106320181A (en) Construction method for installing precast beam slabs by adopting bridge girder erection machine
CN115636225A (en) Platform channel wall and ground stone transportation device and transportation method
CN214217958U (en) Subway station drawer type track panel hoisting structure
CN215591798U (en) Curtain wall plate traction transfer device for tower crane dismantling part
CN210439082U (en) Complicated district magnetic levitation track section laying system
JP3497670B2 (en) Apparatus and method for constructing anti-vibration subway tunnel
CN113502750A (en) Construction process of pouring-preventing bubbles for pouring highway engineering bridge
CN113818478A (en) Overweight prefabricated pipe gallery installation system and construction method thereof
CN111270577A (en) Assembly machine suitable for narrow space of subway underground line and overhead line cross-track section and construction method thereof
CN217323268U (en) Material transferring and lifting system suitable for slope supporting operation

Legal Events

Date Code Title Description
GRNT Written decision to grant