CN207245715U - Material and dregs transportation system in shield separate launching tunnel - Google Patents

Material and dregs transportation system in shield separate launching tunnel Download PDF

Info

Publication number
CN207245715U
CN207245715U CN201720906659.2U CN201720906659U CN207245715U CN 207245715 U CN207245715 U CN 207245715U CN 201720906659 U CN201720906659 U CN 201720906659U CN 207245715 U CN207245715 U CN 207245715U
Authority
CN
China
Prior art keywords
section
jurisdiction
dregs
transportation system
panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720906659.2U
Other languages
Chinese (zh)
Inventor
马云新
赵洪岩
张汉岭
王锡军
王利民
邵翔宇
李生光
丁贵松
王浩
李森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BCEG Civil Engineering Co Ltd
Original Assignee
BCEG Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BCEG Civil Engineering Co Ltd filed Critical BCEG Civil Engineering Co Ltd
Priority to CN201720906659.2U priority Critical patent/CN207245715U/en
Application granted granted Critical
Publication of CN207245715U publication Critical patent/CN207245715U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides material and dregs transportation system in a kind of shield separate launching tunnel, it includes:Battery truck, dregs bucket, the segment car for carrying dregs bucket, section of jurisdiction trolley and low orbit, wherein described battery truck draws the segment car for carrying the dregs bucket and the section of jurisdiction trolley for carrying section of jurisdiction successively, and the battery truck, segment car and section of jurisdiction trolley are run on low orbit.The utility model uses low orbit+section of jurisdiction trolley+dregs bucket, can quickly and easily transport section of jurisdiction, slag tap, and accelerates separate launching progress, saves the construction period.

Description

Material and dregs transportation system in shield separate launching tunnel
Technical field
Shield Construction Technique field is the utility model is related to, material and slag in more particularly to a kind of shield separate launching tunnel Native transportation system.
Background technology
Shield launching refers to shield in installation vertical shaft or misses the stop in vertical shaft, positions since the shield host, cutterhead is forward Injection country rock is promoted, is tunneled forward along designed lines, until shield enters safely running tunnel, hole reaction frame and negative endless tube piece Untill dismounting.
Shield launching is divided into overall originate and separate launching.Entirety, which originates, to be referred to shield body and whole trolleys are installed on and are originated Underground, the construction technology for driving whole trolleys to move ahead together when shield launching tunnels;Separate launching refer to by shield body with all or Used between the trolley of part and lengthen pipeline connection, shield body separately moves ahead with all or part of trolley, treats after the completion of initially tunneling again Shield body and trolley are installed to the construction technology for connecting and normally being tunneled in tunnel.Wherein, due in city by narrow construction The limitation of the factors such as place, execution conditions, it is also more and more difficult that shield integrally originates condition.Separate launching is used as shield launching side One kind of formula, is widely used in construction site narrow in bustling city.
During shield separate launching, feed the piece machine and unearthed belt feeder etc. of storing section of jurisdiction are not connected with shield machine main body, because The transport of materials such as this section of jurisdiction, to slag tap etc. be one of key issue whether shield separate launching smoothly completes.Solve these at present The mode of problem is varied, how fast and effectively section of jurisdiction is placed under assembling machine snatch head, dregs bucket is transported to screw machine Soil outlet is current problem to be solved.
Therefore, the utility model people of the application is in order to quickly and easily transporting the materials such as section of jurisdiction, slag tap, it is proposed that one Material and dregs transportation system in kind shield separate launching tunnel.
Utility model content
The purpose of this utility model is to provide material and dregs transportation system in a kind of shield separate launching tunnel, it can Quickly and easily transport the materials such as section of jurisdiction, slag tap, effectively lift work efficiency.
In order to achieve the above object, the utility model provides material and dregs transportation system in a kind of shield separate launching tunnel, It includes:Battery truck, dregs bucket, the segment car for carrying dregs bucket, section of jurisdiction trolley and low orbit, wherein the battery truck Traction is used for the segment car for carrying the dregs bucket and the section of jurisdiction trolley for carrying section of jurisdiction, the battery truck, section of jurisdiction successively Car and section of jurisdiction trolley are run on low orbit.
Material and dregs transportation system in the shield separate launching tunnel, wherein, the low orbit includes low sleeper And track, the low sleeper are set along spaced at predetermined intervals, two tracks are vertically arranged relative to low sleeper in parallel to each other On low sleeper.
Material and dregs transportation system in the shield separate launching tunnel, wherein, below the both ends of every low sleeper It is fixedly installed one piece of floor.
Material and dregs transportation system in the shield separate launching tunnel, wherein, the low sleeper is made by channel steel, There is bolt hole at channel steel both ends.
Material and dregs transportation system in the shield separate launching tunnel, wherein, the low sleeper is connected with track There is vertical steel plate at position inside sleeper as floor.
Material and dregs transportation system in the shield separate launching tunnel, wherein, the track is fixed by pressing plate.
Material and dregs transportation system in the shield separate launching tunnel, wherein, the spacing between low sleeper is equal to The width of the section of jurisdiction to be transported.
Material and dregs transportation system in the shield separate launching tunnel, wherein, the section of jurisdiction trolley includes having The panel of predetermined arc, the longitudinal direction of the panel are provided at both ends with end plate, and the panel bottom is equally spaced at least along longitudinal direction Twice floor, floor is parallel with end plate, and the panel two bottom sides are respectively provided with slideway along longitudinal direction, at the end plate of section of jurisdiction trolley front end It is additionally provided with tractive unit.
Material and dregs transportation system in the shield separate launching tunnel, wherein, the section of jurisdiction trolley includes having The panel of predetermined arc, panel are made of upper and lower two-layered steel plates, and crisscross vertical floor, institute are provided between two-layered steel plates State panel two bottom sides and be provided with four traveling wheels, tractive unit is additionally provided with the end plate of section of jurisdiction trolley front end.
Material and dregs transportation system in the shield separate launching tunnel, wherein, insertion pin among the traveling wheel Axis, traveling wheel both sides are provided with the walking wheel support being fixed on the downside of the panel of lower section, and axis pin is inserted into the hole of walking wheel support.
Material and dregs transportation system in the shield separate launching tunnel, wherein, the both sides of the walking wheel support It is welded with ribbed panel.
Material and dregs transportation system in the shield separate launching tunnel, wherein, the dregs bucket is made of steel plate, The opening for containing dregs is left in top, and the opposite sides of dregs bucket short side is provided with channel steel, and channel steel is fixedly arranged in the middle of axis pin, Surrounding is mounted on angle bar on the inside of dregs hopper opening, and the both sides up and down of channel steel are also equipped with ribbed panel.
The beneficial effects of the utility model are:The utility model uses low orbit+section of jurisdiction trolley+dregs bucket, can quickly just Prompt transport section of jurisdiction, slags tap, and accelerates separate launching progress, saves the construction period.
Brief description of the drawings
The utility model will be hereinafter described in more detail based on embodiment and refer to the attached drawing.Wherein:
Fig. 1 is material and the front view of dregs transportation system in shield separate launching tunnel according to the present utility model;
Fig. 2A is the front view of low orbit;
Fig. 2 B are the top views with cut-away section of Fig. 2A;
Fig. 3 A are the front views of 1.2m sections of jurisdiction trolley;
Fig. 3 B are the bottom views of Fig. 3 A;
Fig. 3 C are the sectional views of 1-1 sections in Fig. 3 A;
Fig. 3 D are the sectional views of 2-2 sections in Fig. 3 A;
Fig. 4 A are the front views of 1.5m sections of jurisdiction trolley;
Fig. 4 B are the bottom views of Fig. 4 A;
Fig. 4 C are the sectional views of 1-1 sections in Fig. 4 A;
Fig. 4 D are the sectional views of 2-2 sections in Fig. 4 A;
Fig. 5 A are the front views of wheeled 1.2m sections of jurisdiction trolley;
Fig. 5 B are the bottom views of Fig. 5 A;
Fig. 5 C are the sectional views of 1-1 sections in Fig. 5 A;
Fig. 5 D are the sectional views of 2-2 sections in Fig. 5 A;
Fig. 6 A are the front views of wheeled 1.5m sections of jurisdiction trolley;
Fig. 6 B are the bottom views of Fig. 6 A;
Fig. 6 C are the sectional views of 1-1 sections in Fig. 6 A;
Fig. 6 D are the sectional views of 2-2 sections in Fig. 6 A;
Fig. 7 is the figure of the details of traveling wheel;
Fig. 8 is the schematic diagram that traveling wheel is walked on low orbit;
Fig. 9 A are the front views of dregs bucket;
Fig. 9 B are the side views of Fig. 9 A.
In the accompanying drawings, identical component uses identical reference numeral.Attached drawing is not according to actual ratio.
Embodiment
Below in conjunction with attached drawing, the utility model is described in further detail.
As shown in Figure 1, the utility model provides material and dregs transportation system in a kind of shield separate launching tunnel, its Mainly include:One section battery truck 1, one saves 2 and one section section of jurisdiction trolley 3 of dregs bucket, and the wherein described battery truck 1 is drawn successively For carrying the segment car 6 of dregs bucket and section of jurisdiction trolley 3 for carrying section of jurisdiction, the battery truck 1, segment car 6 and pipe Piece trolley 3 is run on low orbit 4.Such arrangement is in order at the consideration of the limitation to starting well length condition, therefore begins The slagging tap of hair stage, transport and employ so special classification type.It should be noted that in view of mainly there is top to hang in well Dress and two kinds of means of transportation of lower track operation, therefore " low orbit " word mentioned in this article refers in particular to be laid on bottom in well With the track of tunnel bottom.
Transport of slagging tap is carried out by the dregs bucket 2, and common segment car can be selected in the segment car 6 for carrying dregs bucket 2, Common segment car is bigger than the size of the section of jurisdiction trolley of the utility model and structure is different, to meet the needs that are unearthed, and need not It is separately fabricated.Dregs bucket 2 is passed in and out by gap between reaction frame and structure, gantry crane slag dumping, the known technology of those skilled in the art, Therefore it will not go into details.
Section of jurisdiction transport is carried out using a section section of jurisdiction trolley 3, and the section of jurisdiction on the trolley of section of jurisdiction is laterally disposed, transports 1 pipe every time Piece, unloads section of jurisdiction trolley 3 after assembled, to facilitate dregs bucket 2 to be unearthed.
As shown in Figure 2 A and 2 B, the low orbit 4 mainly includes:Low sleeper 41, floor 42 and track 43.It is described low Sleeper 41 is set along spaced at predetermined intervals, and two tracks 43 are vertically disposed at low sleeper relative to low sleeper 41 in parallel to each other On 41.One piece of floor 42 is fixedly installed below the both ends of every low sleeper 41, for strengthening the stability of low sleeper.It is preferred that Ground, the low sleeper 41 select No. 16 channel steels to be made, and the floor 42 selects 12mm steel plates to be made, and the low sleeper 41 Provided with the floor 42 by forms such as welding.More preferably, the track 43 is fixed by pressing plate 44, specifically, described Low 41 both ends of sleeper are each provided with 4 bolts hole, and the lower end of the track 43 is compressed from pressing plate 44 to low sleeper 41, the pressing plate 44 are fixed by bolt through the bolt hole on low sleeper 41.
In addition, the spacing between low sleeper 41 depends on the width of section of jurisdiction.For example, when the width of section of jurisdiction is 1.2m, then Need to set 5 low sleepers, and the track 43 for each side installing a 6m long on low sleeper;When the width of section of jurisdiction For 1.5m when, then need set 4 low sleepers, and on low sleeper each side install a 6m long track 43. It will be run by the low orbit that low sleeper and track are formed as the segment car 6 of section of jurisdiction trolley 3, battery truck 1, dregs bucket bottom Track.
As shown in Fig. 3 A to Fig. 4 D, the section of jurisdiction trolley 3 can be divided into 1.2m and 1.5m sections of jurisdiction trolley according to the width of section of jurisdiction, The architectural feature of 1.2m sections of jurisdiction trolley is shown in wherein Fig. 3 A to Fig. 3 D, and 1.5m sections of jurisdiction trolley is shown in Fig. 4 A to Fig. 4 D Architectural feature.Specifically, section of jurisdiction trolley 3 includes the panel 31 with certain radian, it is preferable that angle is in centered on the panel 30 degree of arc structure, and be made of the steel plate of 12mm thickness.The longitudinal direction of the panel 31 is provided at both ends with end plate 32, and end plate 32 is excellent Elect height 90mm as, the steel plate of thickness 12mm is made, and the effect of end plate 32 is to prevent that the section of jurisdiction 5 (see Fig. 1) on panel 31 is sliding Fall.In addition, 31 bottom of panel of 1.2m sections of jurisdiction trolley 3 is equally spaced 2 floors 33 along longitudinal direction, floor 33 and end plate 32 are flat OK.Preferably, the floor selects the steel plate of 12mm thickness to be made.31 bottom of panel of 1.5m sections of jurisdiction trolley 3 is equidistant along longitudinal direction Arrange 3 floors 33, floor 33 is parallel with end plate 32.31 two bottom sides of panel (along longitudinal direction) of section of jurisdiction trolley 3 set slideway 34, Slideway can be formed with 10mm channel steel button systems, it is also possible to which steel plate is welded into inverted U catching groove.
In addition, being additionally provided with tractive unit 35 at the end plate of 3 front end of section of jurisdiction trolley, specifically, the tractive unit 35 includes upper 4 12mm steel plates of lower and symmetrical welding, open diameter 50mm holes among upper lower steel plate, connecting rod are inserted into 4 pieces In the babinet of steel plate composition, then axis pin is inserted into, section of jurisdiction trolley 3 is dragged by battery truck.
During shield separate launching, one piece of section of jurisdiction is placed on the trolley of section of jurisdiction, is drawn and transported using battery truck.
For another example shown in Fig. 5 A to Fig. 6 D, the utility model also improves section of jurisdiction trolley, and then provides a kind of band row Walk the section of jurisdiction trolley 3 of wheel.It is small that wheeled section of jurisdiction trolley 3 according to the width of section of jurisdiction can be divided into 1.2m and 1.5m sections of jurisdiction The architectural feature of wheeled 1.2m sections of jurisdiction trolley is shown in car, wherein Fig. 5 A to Fig. 5 D, and Fig. 4 A to Fig. 4 D are shown The architectural feature of wheeled 1.5m sections of jurisdiction trolley.The knot of wheeled section of jurisdiction trolley and not wheeled section of jurisdiction trolley Structure is roughly the same, it is differed only in:The panel 31 of section of jurisdiction trolley 3 is made of upper and lower two-layered steel plates, and floor 33 is arranged at two layers Between steel plate, and original slideway is substituted with traveling wheel 36.
Specifically, there is preset space length between two-layered steel plates (spacing is preferably 36mm).In addition, set between two-layered steel plates Crisscross vertical steel plate is put as floor 33, the stability and robustness of reinforcement section of jurisdiction trolley 3.Wherein, floor 33 is by steel Plate (preferably 12mm steel plates) makes, and longitudinal floor center line aligns with the traveling wheel center line that lower part is installed.1.2m sections of jurisdiction trolley Horizontal ribbed is 2, its center line and 36 median perpendicular of traveling wheel, and directly over traveling wheel 36.1.5m the horizontal stroke of section of jurisdiction trolley It is 3 to floor, its center line and 36 median perpendiculars of walking, the horizontal line floor on both sides are located at the surface of traveling wheel 36, centre 1 It is horizontal ribbed positioned at the middle part of section of jurisdiction trolley.
Slided for ease of section of jurisdiction trolley, section of jurisdiction trolley panel bottom uses 4 traveling wheels 36 (as shown in Figure 7 and Figure 8), OK Insertion axis pin 361 among wheel is walked, 36 both sides of traveling wheel are provided with the walking wheel support 362 being fixed on the downside of the panel of lower section, axis pin 361 are inserted into the hole of walking wheel support 363.Wherein, walking wheel support 362 can be selected steel plate and (preferably 20mm steel plates) be made, The lower section panel 31 of steel plate and section of jurisdiction trolley 3 can be by being welded and fixed.To ensure the stability of traveling wheel, in walking wheel support 362 both sides can also weld ribbed panel 363 (the preferably steel plate of 12mm).The both sides of traveling wheel 36 and walking wheel support 362 it Between be equipped with axle sleeve 364.
In addition, being additionally provided with tractive unit 35 at the end plate of 3 front end of section of jurisdiction trolley, specifically, the tractive unit 35 includes upper 4 12mm steel plates of lower and symmetrical welding, open diameter 50mm holes among upper lower steel plate, connecting rod are inserted into 4 pieces In the babinet of steel plate composition, then axis pin is inserted into, section of jurisdiction trolley 3 is dragged by battery truck.
During shield separate launching, one piece of section of jurisdiction is placed on the trolley of section of jurisdiction, is drawn and transported using battery truck.
As illustrated in figures 9a and 9b, dregs bucket 2 is made of steel plate 21, and the opening 22 for containing dregs is left in top finally, and The opposite sides of 2 short side of dregs bucket is provided with channel steel 23, and channel steel 23 is fixedly arranged in the middle of axis pin 24, the stress as the lifting of dregs bucket Point.In addition, 22 inner side surrounding of dregs hopper opening is mounted on angle bar 25, to strengthen the stability of dregs bucket.Above and below channel steel 23 Both sides are also equipped with ribbed panel 26, so as to be reinforced to channel steel position.
In conclusion the utility model provides material and dregs transportation system in a kind of shield separate launching tunnel, it is adopted With low orbit+section of jurisdiction trolley+dregs bucket, section of jurisdiction can be quickly and easily transported, is slagged tap, accelerate separate launching progress, save construction Duration.
Although the present utility model has been described by reference to the preferred embodiments, but the model of the utility model is not being departed from In the case of enclosing, various improvement can be carried out to it and component therein can be replaced with equivalent.Especially, as long as not depositing In structural conflict, items technical characteristic mentioned in the various embodiments can be combined in any way.The utility model It is not limited to specific embodiment disclosed herein, but all technical solutions including falling within the scope of the appended claims.

Claims (10)

1. material and dregs transportation system in a kind of shield separate launching tunnel, it is characterised in that including:Battery truck, dregs bucket, For carrying the segment car, section of jurisdiction trolley and low orbit of dregs bucket, wherein the battery truck draw successively it is described for carrying The segment car of dregs bucket and the section of jurisdiction trolley for carrying section of jurisdiction, the battery truck, segment car and section of jurisdiction trolley are low Run on track.
2. material and dregs transportation system in shield separate launching tunnel according to claim 1, it is characterised in that described Low orbit includes low sleeper and track, and the low sleeper is set along spaced at predetermined intervals, in parallel to each other two tracks relative to Low sleeper is vertically disposed on low sleeper, and the low sleeper inside sleeper at track link position with having vertical steel plate as rib Plate.
3. material and dregs transportation system in shield separate launching tunnel according to claim 2, it is characterised in that every One piece of floor is fixedly installed below the both ends of low sleeper, and the track is fixed by pressing plate.
4. material and dregs transportation system in shield separate launching tunnel according to claim 2, it is characterised in that described Low sleeper is made by channel steel, and there is bolt hole at channel steel both ends.
5. material and dregs transportation system in shield separate launching tunnel according to claim 2, it is characterised in that low rail Spacing between pillow is equal to the width of the section of jurisdiction to be transported.
6. material and dregs transportation system in shield separate launching tunnel according to claim 1, it is characterised in that described Section of jurisdiction trolley includes the panel with predetermined arc, and the longitudinal direction of the panel is provided at both ends with end plate, and the panel bottom is along vertical To at least twice floor is equally spaced, floor is parallel with end plate, and the panel two bottom sides are respectively provided with slideway, section of jurisdiction along longitudinal direction Tractive unit is additionally provided with the end plate of trolley front end.
7. material and dregs transportation system in shield separate launching tunnel according to claim 1, it is characterised in that described Section of jurisdiction trolley includes the panel with predetermined arc, and panel is made of upper and lower two-layered steel plates, is provided with length and breadth between two-layered steel plates Vertical floor staggeredly, the panel two bottom sides are provided with four traveling wheels, are additionally provided with the end plate of section of jurisdiction trolley front end Tractive unit.
8. material and dregs transportation system in shield separate launching tunnel according to claim 7, it is characterised in that described Insertion axis pin among traveling wheel, traveling wheel both sides are provided with the walking wheel support being fixed on the downside of the panel of lower section, and axis pin is inserted into In the hole of walking wheel support.
9. material and dregs transportation system in shield separate launching tunnel according to claim 8, it is characterised in that described The both sides of walking wheel support are welded with ribbed panel.
10. material and dregs transportation system in shield separate launching tunnel according to any one of claim 1 to 9, its It is characterized in that, the dregs bucket is made of steel plate, and the opening for containing dregs, and the opposite sides of dregs bucket short side are left in top Channel steel is installed, channel steel is fixedly arranged in the middle of axis pin, and surrounding is mounted on angle bar on the inside of dregs hopper opening, and the both sides up and down of channel steel are also Ribbed panel is installed.
CN201720906659.2U 2017-07-25 2017-07-25 Material and dregs transportation system in shield separate launching tunnel Expired - Fee Related CN207245715U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720906659.2U CN207245715U (en) 2017-07-25 2017-07-25 Material and dregs transportation system in shield separate launching tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720906659.2U CN207245715U (en) 2017-07-25 2017-07-25 Material and dregs transportation system in shield separate launching tunnel

Publications (1)

Publication Number Publication Date
CN207245715U true CN207245715U (en) 2018-04-17

Family

ID=61878018

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720906659.2U Expired - Fee Related CN207245715U (en) 2017-07-25 2017-07-25 Material and dregs transportation system in shield separate launching tunnel

Country Status (1)

Country Link
CN (1) CN207245715U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107269291A (en) * 2017-07-25 2017-10-20 北京建工土木工程有限公司 Material and dregs transportation system in shield separate launching tunnel
CN109083653A (en) * 2018-08-12 2018-12-25 周莉 A kind of marshalling locomotive
CN109098737A (en) * 2018-08-12 2018-12-28 周莉 A kind of duct piece conveyor vehicle

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107269291A (en) * 2017-07-25 2017-10-20 北京建工土木工程有限公司 Material and dregs transportation system in shield separate launching tunnel
CN109083653A (en) * 2018-08-12 2018-12-25 周莉 A kind of marshalling locomotive
CN109098737A (en) * 2018-08-12 2018-12-28 周莉 A kind of duct piece conveyor vehicle
CN109083653B (en) * 2018-08-12 2020-10-02 蔡天明 Marshalling locomotive

Similar Documents

Publication Publication Date Title
CN107269291A (en) Material and dregs transportation system in shield separate launching tunnel
CN207245715U (en) Material and dregs transportation system in shield separate launching tunnel
CN107031663B (en) Walking platform and walking method of shield machine marshalling train and matched trailer behind shield machine
CN203269274U (en) Slope section rail type conveying device
CN108590660A (en) A kind of outdoor highwall coal mining transport device and its fast transfer working face method
CN107268630A (en) A kind of side slope protection construction material transport system and method
CN205895274U (en) A section of jurisdiction travelling bogie that is used for shield constituent body to start
CN210483756U (en) Trackless major diameter steel pipe transportation installation platform truck in tunnel
CN106761808A (en) A kind of track traffic bored tunnel electric railcar transports corollary system
CN206015442U (en) A kind of removable compound shield-tunneling construction sleeper
CN108590745A (en) The transportation resources of shield method tunnel construction and its transport structure
CN101858221A (en) Continuous belt mucking method suitable for drilling and blasting tunnel construction and application system and equipment thereof
CN208415013U (en) track fast dismounting device
CN202063155U (en) Transitional rail changing device for mine empty wagons
CN108899807A (en) Subway long steep grade entrance electromechanics construction method of installation
CN205953062U (en) Row's device is changeed in waste material transportation
CN205805587U (en) A kind of Miniature portable section of jurisdiction flat bed transport vehicle
CN208516876U (en) A kind of chimney emission inner cylinder shell ring Orbital Transport Systems
CN202937278U (en) Rapid duct piece back conveying mechanism for subway shield tunnel construction
CN103397889A (en) Starting trolley for split starting of shield
CN203740486U (en) Bridge equipment of slag discharge belt for underground mine transportation
CN206409240U (en) A kind of track traffic bored tunnel electric railcar transports corollary system
CN108640035A (en) A kind of chimney emission inner cylinder shell ring Orbital Transport Systems
CN210365676U (en) Rail tunnel slag discharging device
CN209875170U (en) Rail-mounted slurry spraying mine car for primary support of large-slope inclined shaft

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180417

Termination date: 20180725