CN206409240U - A kind of track traffic bored tunnel electric railcar transports corollary system - Google Patents

A kind of track traffic bored tunnel electric railcar transports corollary system Download PDF

Info

Publication number
CN206409240U
CN206409240U CN201621463249.7U CN201621463249U CN206409240U CN 206409240 U CN206409240 U CN 206409240U CN 201621463249 U CN201621463249 U CN 201621463249U CN 206409240 U CN206409240 U CN 206409240U
Authority
CN
China
Prior art keywords
track
rail
steel frame
transportation
supporting system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621463249.7U
Other languages
Chinese (zh)
Inventor
吴宝华
陈树禹
刘春宇
张天泽
张万里
袁柯柯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN201621463249.7U priority Critical patent/CN206409240U/en
Application granted granted Critical
Publication of CN206409240U publication Critical patent/CN206409240U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本实用新型涉及地铁施工技术领域,提供了一种轨道交通暗挖隧道电动有轨运输配套系统,包括轨道、皮带转载机、蓄电式牵引车、矿斗车、刮板输送机;皮带转载机包括钢架、皮带输送机、扒渣机;钢架内部可通行矿斗车,钢架一端连接扒渣机,另一端底部设置有行走轮,钢架与扒渣机共同形成可行走机构;钢架顶部设皮带输送机;轨道用于蓄电式牵引车和矿斗车行进,矿斗车为多个,顺序连接;刮板输送机用于渣土由作业面到竖井的运输。本实用新型的有益效果为:本系统在隧道一侧,占地小,轨道的铺设不影响通过性。不需要会车,风险低;单次运输方量、运输速度、运行时间提升显著,效率大幅提高;系统使用寿命增长;人工配备减少;适用性强,应用前景广阔。

The utility model relates to the technical field of subway construction, and provides an electric rail transport supporting system for rail transit underground excavation tunnels. It includes a steel frame, a belt conveyor, and a slag remover; a mine bucket truck can pass through the inside of the steel frame, one end of the steel frame is connected to the slag remover, and the bottom of the other end is equipped with a walking wheel, and the steel frame and the slag remover together form a walking mechanism; A belt conveyor is installed on the top of the frame; the track is used for the electric storage tractor and the mine bucket truck to travel, and there are multiple mine bucket trucks connected in sequence; the scraper conveyor is used for the transportation of the muck from the working face to the shaft. The beneficial effects of the utility model are: the system is located on one side of the tunnel, occupies a small area, and the laying of the track does not affect the passability. There is no need to meet cars, and the risk is low; the amount of single transportation, transportation speed, and running time have been significantly improved, and the efficiency has been greatly improved; the service life of the system has been increased; manual equipment has been reduced; strong applicability and broad application prospects.

Description

一种轨道交通暗挖隧道电动有轨运输配套系统A supporting system for electric rail transportation in underground excavation tunnels for rail transit

技术领域technical field

本实用新型涉及地铁施工技术领域,特别涉及一种轨道交通暗挖隧道电动有轨运输配套系统。The utility model relates to the technical field of subway construction, in particular to an electric rail transportation supporting system for rail transit underground excavation tunnels.

背景技术Background technique

当前地铁暗挖隧道长度多集中在1Km左右,施工所需材料及开挖产生的渣土需进行洞内运输,通过对地铁暗挖隧道施工现状的调查,施工运输系统早期采用人工装载,人力双轮车运输;现阶段多采用人工或内燃小型挖掘机装载,农用自卸内燃三轮车运输;北京市于2015年规定禁止在暗挖轨道工程中使用内燃机械施工,现多采用人工装载,电动自卸三轮车运输。At present, the length of subway underground excavation tunnels is mostly concentrated at about 1Km, and the materials required for construction and the muck generated by excavation need to be transported inside the tunnel. According to the investigation of the construction status of subway underground excavation tunnels, manual loading was adopted in the early construction and transportation system, and the manpower Wheeled vehicle transportation; at this stage, manual or small internal combustion excavators are mostly used for loading, and agricultural self-unloading internal combustion tricycles are transported; Beijing stipulated in 2015 that the use of internal combustion machinery construction in underground track engineering is prohibited, and manual loading and electric self-unloading are now mostly used Tricycle transport.

地铁盾构施工隧道洞内运输系统多采用电力有轨运输,盾构螺旋输送机装渣,龙门吊车卸渣。该系统对施工竖井净空尺寸及地面施工场地面积要求较高。The transportation system in the tunnel of subway shield construction mostly adopts electric rail transportation, slag is loaded by shield screw conveyor, and slag is unloaded by gantry crane. The system has high requirements on the clearance size of the construction shaft and the area of the ground construction site.

现有技术一:暗挖施工现有运输系统:在京项目通过人工装车+电动自卸三轮车+桥式起重机组成;京外项目通过小型内燃挖掘机装车+内燃自卸三轮车+桥式起重机组成。Existing technology 1: underground excavation construction The existing transportation system: the project in Beijing is composed of manual loading + electric self-unloading tricycle + bridge crane; the project outside Beijing is composed of small internal combustion excavator loading + internal combustion self-unloading tricycle + bridge crane .

现有技术一的缺点:在京项目,首先,人工装渣功效低,现有电动自卸车需频繁充电,使用过程中半途动力丧失情况多;其次,工人劳动强度大;再次,作业时占用劳力(司机)较多。京外项目:内燃设备作业时产生尾气严重影响作业工人身体健康。Disadvantages of prior art 1: In the project in Beijing, firstly, the efficiency of manual slag loading is low, the existing electric dump truck needs to be charged frequently, and there are many cases of power loss during use; secondly, the labor intensity of workers is high; thirdly, labor is occupied during operation ( driver) more. Projects outside Beijing: Exhaust gas generated during operation of internal combustion equipment seriously affects the health of workers.

现有技术二:盾构施工洞内有轨运输系统:通过盾构机螺旋输送机+轻型轨道+蓄电池式牵引车+矿斗车+龙门吊车组成。Existing technology 2: The rail transportation system in the shield construction tunnel: consists of shield machine screw conveyor + light rail + battery tractor + mine bucket truck + gantry crane.

现有技术二的缺点:盾构施工洞内有轨运输系统存在以下不足:首先,需配套盾构中的螺旋输送机提供装渣功能;其次,该系统渣斗车对既有工程结构要求较高,须有井后停车线以便矿斗车就位到竖井中心,竖井净空尺寸需求大,以方便矿斗车起吊,龙门吊配置要求高;再次,该系统需在轨道线路上方提升,所以在市区内使用时,要求用地灵活,占地空间较大。Disadvantages of the second prior art: the rail transportation system in the shield construction tunnel has the following deficiencies: first, the screw conveyor in the shield tunnel needs to provide the slag loading function; High, there must be a parking line behind the shaft so that the mine truck can be positioned at the center of the shaft. The clearance of the shaft needs to be large to facilitate the lifting of the mine truck. When used in the area, flexible use of land is required and the land occupation is relatively large.

现有技术三:采矿作业洞内有轨运输系统:通过采矿机+皮带输送机组成,或通过采矿机+轻型轨道+蓄电池式牵引车+矿斗车+卸料塔架组成。Existing technology 3: rail transportation system in mining operation cave: composed of mining machine + belt conveyor, or mining machine + light rail + battery tractor + mine truck + unloading tower.

现有技术三的缺点:采矿作业洞内有轨运输系统存在以下不足,首先,需配套采矿机提供装渣功能;其次,该系统卸料作业时需提升架空,所以在市区内使用时,用地要求不够灵活,占地难度较大,且扬尘严重,无法做到全封闭作业。Disadvantages of the existing technology 3: the rail transportation system in the mining operation hole has the following deficiencies. First, it needs to be equipped with a mining machine to provide the slag loading function; The land use requirements are not flexible enough, the land occupation is difficult, and the dust is serious, so it is impossible to achieve fully enclosed operations.

实用新型内容Utility model content

本实用新型的目的就是克服现有技术的不足,提供了一种轨道交通暗挖隧道电动有轨运输配套系统,解决了地铁暗挖隧道洞内运输功效低、充电等待时间长、故障率高、占用劳力多、劳动强度大及改善洞内作业空气环境等问题。The purpose of this utility model is to overcome the deficiencies of the prior art, to provide an electric rail transport supporting system for rail transit underground excavation tunnels, which solves the problems of low transportation efficiency, long charging waiting time, high failure rate, Occupying a lot of labor, high labor intensity and improving the working air environment in the cave.

本实用新型一种轨道交通暗挖隧道电动有轨运输配套系统,包括轨道、皮带转载机、蓄电式牵引车、矿斗车、刮板输送机;The utility model relates to an electric rail transportation supporting system for underground excavation tunnels of rail traffic, which includes rails, belt reloaders, electric storage tractors, mining bucket cars, and scraper conveyors;

所述皮带转载机为装料平台,包括钢架、皮带输送机、扒渣机;所述钢架内部为可通行所述矿斗车的中空结构,所述钢架一端连接所述扒渣机,另一端底部设置有行走轮,所述钢架与所述扒渣机共同形成可行走机构;所述钢架顶部安装有皮带输送机;土方经扒渣机出口卸至所述皮带输送机的皮带上,经所述皮带输送机卸至所述矿斗车内;The belt reloader is a loading platform, including a steel frame, a belt conveyor, and a slag remover; the inside of the steel frame is a hollow structure that can pass the mine bucket truck, and one end of the steel frame is connected to the slag remover , the bottom of the other end is provided with a walking wheel, and the steel frame and the slag scraper jointly form a walking mechanism; a belt conveyor is installed on the top of the steel frame; the earth is discharged to the belt conveyor through the slag scraper outlet On the belt, it is unloaded into the mine bucket car through the belt conveyor;

所述轨道用于所述蓄电式牵引车牵引所述矿斗车行进,所述矿斗车为多个,顺序连接;The track is used for the electric storage tractor to tow the mine bucket trucks, and there are multiple mine bucket trucks connected in sequence;

所述刮板输送机用于渣土由作业面到竖井的运输。The scraper conveyor is used for transporting muck from the working face to the shaft.

进一步的,所述钢架由型钢焊接或螺栓连接而成,现场制作或工厂制作、现场装配。Further, the steel frame is formed by welded or bolted section steels, manufactured on site or manufactured in a factory, and assembled on site.

进一步的,所述矿斗车的料斗侧翻卸料至所述刮板输送机上,所述刮板输送机将渣土刮至竖井内;所述刮板输送机为链条式刮板输送机。Further, the hopper of the ore bucket truck turns over and discharges to the scraper conveyor, and the scraper conveyor scrapes the muck into the shaft; the scraper conveyor is a chain scraper conveyor.

进一步的,所述蓄电式牵引车型号为CY5/6GB型。Further, the model of the electric storage tractor is CY5/6GB.

进一步的,所述矿斗车数量为4个,单个所述矿斗车的容积为1.5m3Further, the number of mine bucket cars is 4, and the volume of a single mine bucket car is 1.5m 3 .

进一步的,所述轨道为轻型轨道,采用双轨道岔来改变行驶路线。Further, the track is a light track, and double track switches are used to change the driving route.

进一步的,所述轻型轨道采用采用15#轻质钢轨双轨铺设,槽钢枕木。Further, the light track adopts double-track laying of 15# light steel rails and channel steel sleepers.

进一步的,所述轨道为重型轨道、单轨运输道或悬吊轨道。Further, the track is a heavy track, a monorail transport track or a suspension track.

本实用新型的有益效果为:本轨道运输系统在隧道一侧,占地不大,轨道的铺设不影响任何的通过性。不需要会车,降低了风险;单次运输方量、运输速度、运行时间提升显著,效率大幅提高;系统使用寿命增长;人工配备减少;适用性强,应用前景广阔。The beneficial effects of the utility model are: the track transportation system is located on one side of the tunnel, occupies a small area, and the laying of the track does not affect any passability. There is no need for meeting cars, which reduces the risk; the amount of single transportation, transportation speed, and running time are significantly improved, and the efficiency is greatly improved; the service life of the system is increased; manual equipment is reduced; the applicability is strong, and the application prospect is broad.

附图说明Description of drawings

图1所示为本实用新型实施例一种轨道交通暗挖隧道电动有轨运输配套系统结构示意图。Fig. 1 is a schematic structural diagram of an electric rail transportation supporting system for a rail transit underground excavation tunnel according to an embodiment of the utility model.

图2所示为刮板输送机与轨道位置关系示意图。Figure 2 is a schematic diagram of the relationship between the scraper conveyor and the track position.

图3所示为刮板输送机结构示意图。Figure 3 shows a schematic diagram of the structure of the scraper conveyor.

其中:1-矿斗车、2-钢架、3-皮带运输机、4、扒渣机、5轨道、6-皮带转载机行走轮、7-蓄电式牵引车、11-刮板输送机、12-传动链条、13-刮板、14-电机及减速器。Among them: 1-mine bucket truck, 2-steel frame, 3-belt conveyor, 4, slag removal machine, 5 track, 6-belt transfer machine walking wheel, 7-electric storage tractor, 11-scraper conveyor, 12-drive chain, 13-scraper, 14-motor and reducer.

具体实施方式detailed description

下文将结合具体附图详细描述本实用新型具体实施例。应当注意的是,下述实施例中描述的技术特征或者技术特征的组合不应当被认为是孤立的,它们可以被相互组合从而达到更好的技术效果。在下述实施例的附图中,各附图所出现的相同标号代表相同的特征或者部件,可应用于不同实施例中。Specific embodiments of the present utility model will be described in detail below in conjunction with specific drawings. It should be noted that the technical features or combinations of technical features described in the following embodiments should not be regarded as isolated, and they can be combined with each other to achieve better technical effects. In the drawings of the following embodiments, the same reference numerals appearing in each drawing represent the same features or components, which can be applied in different embodiments.

如图1所示,本实用新型实施例一种轨道交通暗挖隧道电动有轨运输配套系统,包括轨道5、皮带转载机、蓄电式牵引车7、矿斗车1、刮板输送机11;蓄电式牵引车7为该系统车辆组的行驶动力部分;矿斗车1为该系统物料承载部分。As shown in Figure 1, the embodiment of the utility model is an electric rail transportation supporting system for a rail transit underground excavation tunnel, including a track 5, a belt reloader, an electric storage tractor 7, a mine bucket car 1, and a scraper conveyor 11 ; Electric storage tractor 7 is the driving power part of the vehicle group of the system; mine bucket truck 1 is the material carrying part of the system.

所述皮带转载机为装料平台(由于暗挖隧道断面普遍较小,且矿斗车组较长,这样就需要皮带转载机架空依次给矿斗车1输料),包括钢架2、皮带输送机3、扒渣机4;所述钢架2内部为可通行所述矿斗车1的中空结构,所述钢架2一端连接所述扒渣机4,另一端底部设置有行走轮6,所述钢架2与所述扒渣机4共同形成可行走机构;所述钢架2顶部安装有皮带运输机3;土方经扒渣机4出口卸至所述皮带运输机3的皮带上,经所述皮带运输机3卸至所述矿斗车1内;The belt reloading machine is a loading platform (because the section of the tunnel is generally small, and the mine bucket car group is long, so the belt reloading machine needs to be overhead and sequentially feed the mine bucket car 1), including steel frame 2, belt Conveyor 3, slag remover 4; the inside of the steel frame 2 is a hollow structure that can pass the mine bucket car 1, one end of the steel frame 2 is connected to the slag remover 4, and the bottom of the other end is provided with a walking wheel 6 , the steel frame 2 and the slag remover 4 jointly form a walkable mechanism; the top of the steel frame 2 is equipped with a belt conveyor 3; The belt conveyor 3 is unloaded into the mine bucket car 1;

所述轨道5用于所述蓄电式牵引车7牵引所述矿斗车1行进,所述矿斗车1为多个,顺序连接;The track 5 is used for the electric storage type tractor 7 to pull the mine bucket truck 1 forward, and there are multiple mine bucket trucks 1 connected in sequence;

如图2、3所示,所述刮板输送机11用于渣土由作业面到竖井的运输,包括传动链条12、刮板13、电机及减速器14;所述电机及减速器14位于所述轨道5一端,为所述刮板输送机11提供动力,所述传动链条12带动所述刮板13运输渣土;所述刮板输送机11的长度根据所述矿斗车1的数量确定;所述刮板输送机的作用:所述矿斗车1就位后,其料斗侧翻卸料至所述刮板输送机上,所述刮板输送机将渣土刮至竖井内;优选的,所述刮板输送机为链条式刮板输送机,长度10 -12m。As shown in Figures 2 and 3, the scraper conveyor 11 is used for the transportation of muck from the working face to the shaft, including a transmission chain 12, a scraper 13, a motor and a reducer 14; the motor and the reducer 14 are located at One end of the track 5 provides power for the scraper conveyor 11, and the transmission chain 12 drives the scraper 13 to transport muck; Determine; the function of the scraper conveyor: after the mine bucket truck 1 is in place, its hopper turns over and unloads on the scraper conveyor, and the scraper conveyor scrapes the muck into the shaft; preferably Yes, the scraper conveyor is a chain scraper conveyor with a length of 10-12m.

所述钢架2由型钢焊接或螺栓连接而成,现场制作或工厂制作、现场装配。The steel frame 2 is welded or bolted by section steel, and is fabricated on-site or factory-made and assembled on-site.

优选的,所述蓄电式牵引车7型号为CY5/6GB型,为该系统车辆组的行驶动力部分。Preferably, the model of the electric storage tractor 7 is CY5/6GB, which is the driving power part of the system vehicle group.

优选的,所述矿斗车1数量为4个,单个所述矿斗车1的容积为1.5m3Preferably, the number of mine bucket trucks 1 is four, and the volume of a single mine bucket truck 1 is 1.5m 3 .

所述轨道5优选为轻型轨道,采用双轨道岔来改变行驶路线;供蓄电式牵引车7及矿斗车1行驶使用;所述轻型轨道采用15#轻质钢轨双轨铺设,槽钢枕木。所述轨道5也可以选择重型轨道、单轨运输道或悬吊轨道作为轻型轨道的替代方案。The track 5 is preferably a light track, which adopts double track switches to change the driving route; it is used for driving the electric storage tractor 7 and the mine bucket car 1; Described track 5 also can select heavy-duty track, monorail transport track or suspension track as the alternative of light-duty track.

本实用新型的安全性分析:Safety analysis of the present utility model:

轨道运输系统在隧道一侧,占地不大,轨道5的铺设不影响任何的通过性;不需要会车,降低了风险。刹车采用了机械制动模式,采用双轨道岔来改变行驶路线,不需要掉头,向前向后都可行驶;传统三轮车比较笨重,惯性比较大,刹车质量跟不上,且洞内路况差,轮胎容易爆胎,导致危险性大大增加。转向系统沉重,导致拐弯容易撞墙。洞内场地狭长,不方便调头行驶,倒土过程需要倒车至竖井,若安全防护不到位,三轮车坠入竖井对于司机是极其危险的。The rail transportation system is on the side of the tunnel, occupying a small area, and the laying of track 5 does not affect any passability; there is no need for passing cars, which reduces the risk. The brake adopts the mechanical brake mode, and the double-track switch is used to change the driving route. It does not need to turn around, and can drive forward and backward; the traditional tricycle is relatively heavy, the inertia is relatively large, the braking quality cannot keep up, and the road conditions in the cave are poor. It is easy to blow out the tire, resulting in a greatly increased risk. Steering is heavy, making it easy to hit walls in corners. The site in the cave is narrow and long, making it inconvenient to turn around and drive. The process of dumping soil requires reversing to the shaft. If the safety protection is not in place, it is extremely dangerous for the driver to fall into the shaft when the tricycle falls into the shaft.

本实用新型的经济性分析:Economic analysis of the utility model:

1)单次运输方量提升:轨道运输采用矿斗车1装土,配备四辆矿斗车1,每车容积1.5m³,每次6m³。传统三轮车容积1.05m³。1) Improvement of single transportation volume: Rail transportation uses mining bucket truck 1 to load soil, equipped with four mining bucket trucks 1, each with a volume of 1.5m³, and each time 6m³. The volume of traditional tricycle is 1.05m³.

2)速度及运行时间的提升:轨道运输的速度11.4km/h。据统计每分钟行驶200米左右,连续工作6个小时以上;传统三轮车速度10km/h。在本标段区间距离长且有2.85‰的坡度,三轮车电池运行时间1小时左右(满载上坡电量消耗比较大)。正常开挖出土时间三辆电动三轮不停运输需要2个小时左右,所以传统三轮车要想满足施工需要,就必须大量购买电动三轮车,造成了资金的浪费。2) Improvement of speed and running time: the speed of rail transportation is 11.4km/h. According to statistics, it can drive about 200 meters per minute and work continuously for more than 6 hours; the speed of traditional tricycle is 10km/h. In this bidding section, the distance is long and there is a slope of 2.85‰, and the battery running time of the tricycle is about 1 hour (the power consumption of going uphill with a full load is relatively large). It takes about 2 hours for the three electric tricycles to be transported non-stop during normal excavation. Therefore, if the traditional tricycles want to meet the construction needs, they must purchase a large number of electric tricycles, resulting in a waste of funds.

3)使用寿命增长,减少了资金投入:传统电动三轮车使用时间一般坚持6个月左右报废。轨道运输系统电池一般可保证正常使用2年,蓄电式牵引车7使用寿命5年以上。3) Increased service life and reduced capital investment: Traditional electric tricycles are generally scrapped after about 6 months of use. The battery of the rail transportation system can generally be guaranteed to be used normally for 2 years, and the service life of the electric storage tractor 7 is more than 5 years.

4)人工配备减少:传统三轮车运输方式一个掌子面需要三名司机运土;轨道运输系统只需要一人就可以完成运输任务并且可以满足两个掌子面同时运输,也就是说过去6名工人6辆三轮车干的工作现在一个人就可以完成。驾驶安全便捷轻松简单。大大减低了劳动强度,且节省了多辆三轮车充电的占用空间。4) Reduction of manpower: the traditional tricycle transportation method requires three drivers to transport soil for one working surface; the rail transportation system only needs one person to complete the transportation task and can satisfy the simultaneous transportation of two working surfaces, that is to say, 6 workers in the past The work done by 6 tricycles can now be done by one person. Driving is safe and convenient, easy and simple. The labor intensity is greatly reduced, and the space occupied by multiple tricycles for charging is saved.

本实用新型的有益效果为:本轨道运输系统在隧道一侧,占地不大,轨道的铺设不影响任何的通过性。不需要会车,降低了风险;单次运输方量、运输速度、运行时间提升显著,效率大幅提高;系统使用寿命增长;人工配备减少;适用性强,应用前景广阔。The beneficial effects of the utility model are: the track transportation system is located on one side of the tunnel, occupies a small area, and the laying of the track does not affect any passability. There is no need for meeting cars, which reduces the risk; the amount of single transportation, transportation speed, and running time are significantly improved, and the efficiency is greatly improved; the service life of the system is increased; manual equipment is reduced; the applicability is strong, and the application prospect is broad.

本文虽然已经给出了本实用新型的几个实施例,但是本领域的技术人员应当理解,在不脱离本实用新型精神的情况下,可以对本文的实施例进行改变。上述实施例只是示例性的,不应以本文的实施例作为本实用新型权利范围的限定。Although several embodiments of the present invention have been given herein, those skilled in the art should understand that the embodiments herein can be changed without departing from the spirit of the present invention. The above-mentioned embodiments are only exemplary, and the embodiments herein should not be taken as limiting the scope of rights of the present utility model.

Claims (8)

1.一种轨道交通暗挖隧道电动有轨运输配套系统,其特征在于,包括轨道、皮带转载机、蓄电式牵引车、矿斗车、刮板输送机;1. An electric rail transport supporting system for rail transit underground excavation tunnels, characterized in that it includes tracks, belt loaders, electric storage tractors, mine bucket cars, and scraper conveyors; 所述皮带转载机为装料平台,包括钢架、皮带输送机、扒渣机;所述钢架内部为可通行所述矿斗车的中空结构,所述钢架一端连接所述扒渣机,另一端底部设置有行走轮,所述钢架与所述扒渣机共同形成可行走机构;所述钢架顶部安装有皮带输送机;土方经扒渣机出口卸至所述皮带输送机的皮带上,经所述皮带输送机卸至所述矿斗车内;The belt reloader is a loading platform, including a steel frame, a belt conveyor, and a slag remover; the inside of the steel frame is a hollow structure that can pass the mine bucket truck, and one end of the steel frame is connected to the slag remover , the bottom of the other end is provided with a walking wheel, and the steel frame and the slag scraper jointly form a walking mechanism; a belt conveyor is installed on the top of the steel frame; the earth is discharged to the belt conveyor through the slag scraper outlet On the belt, it is unloaded into the mine bucket car through the belt conveyor; 所述轨道用于所述蓄电式牵引车牵引所述矿斗车行进,所述矿斗车为多个,顺序连接;The track is used for the electric storage tractor to tow the mine bucket trucks, and there are multiple mine bucket trucks connected in sequence; 所述刮板输送机用于渣土由作业面到竖井的运输。The scraper conveyor is used for transporting muck from the working face to the shaft. 2.如权利要求1所述的轨道交通暗挖隧道电动有轨运输配套系统,其特征在于,所述钢架由型钢焊接或螺栓连接而成,现场制作或工厂制作、现场装配。2. The electric rail transportation supporting system for rail transit underground excavation tunnels according to claim 1, characterized in that the steel frame is welded or bolted by section steel, manufactured on site or manufactured in a factory, and assembled on site. 3.如权利要求1所述的轨道交通暗挖隧道电动有轨运输配套系统,其特征在于,所述矿斗车的料斗侧翻卸料至所述刮板输送机上,所述刮板输送机将渣土刮至竖井内;所述刮板输送机为链条式刮板输送机。3. The electric rail transportation supporting system for rail transit underground excavation tunnels as claimed in claim 1, characterized in that, the hopper of the mine bucket car is turned over and discharged onto the scraper conveyor, and the scraper conveyor The muck is scraped into the shaft; the scraper conveyor is a chain scraper conveyor. 4.如权利要求1所述的轨道交通暗挖隧道电动有轨运输配套系统,其特征在于,所述蓄电式牵引车型号为CY5/6GB型。4. The supporting system for rail transit tunnel electric rail transportation according to claim 1, characterized in that the model of the electric storage tractor is CY5/6GB. 5.如权利要求1所述的轨道交通暗挖隧道电动有轨运输配套系统,其特征在于,所述矿斗车数量为4个,单个所述矿斗车的容积为1.5m35 . The supporting system for electric rail transportation of underground excavation tunnels for rail transit according to claim 1 , wherein the number of said mining bucket cars is 4, and the volume of a single said mining bucket truck is 1.5m 3 . 6.如权利要求1-5任一项所述的轨道交通暗挖隧道电动有轨运输配套系统,其特征在于,所述轨道为轻型轨道,采用双轨道岔来改变行驶路线。6. The rail transit underground excavation tunnel electric rail transport supporting system according to any one of claims 1-5, wherein the track is a light track, and double track switches are used to change the driving route. 7.如权利要求6所述的轨道交通暗挖隧道电动有轨运输配套系统,其特征在于,所述轻型轨道采用采用15#轻质钢轨双轨铺设,槽钢枕木。7. The rail transit underground excavation tunnel electric rail transportation supporting system as claimed in claim 6, characterized in that, the light rail adopts 15# light-weight steel rail double-track laying, and channel steel sleepers. 8.如权利要求1-5任一项所述的轨道交通暗挖隧道电动有轨运输配套系统,其特征在于,所述轨道为重型轨道、单轨运输道或悬吊轨道。8. The rail transit underground excavation tunnel electric rail transport supporting system according to any one of claims 1-5, wherein the track is a heavy-duty track, a monorail transport track or a suspension track.
CN201621463249.7U 2016-12-28 2016-12-28 A kind of track traffic bored tunnel electric railcar transports corollary system Expired - Fee Related CN206409240U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621463249.7U CN206409240U (en) 2016-12-28 2016-12-28 A kind of track traffic bored tunnel electric railcar transports corollary system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621463249.7U CN206409240U (en) 2016-12-28 2016-12-28 A kind of track traffic bored tunnel electric railcar transports corollary system

Publications (1)

Publication Number Publication Date
CN206409240U true CN206409240U (en) 2017-08-15

Family

ID=59553321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621463249.7U Expired - Fee Related CN206409240U (en) 2016-12-28 2016-12-28 A kind of track traffic bored tunnel electric railcar transports corollary system

Country Status (1)

Country Link
CN (1) CN206409240U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106761808A (en) * 2016-12-28 2017-05-31 中铁十六局集团有限公司 A kind of track traffic bored tunnel electric railcar transports corollary system
CN116374483A (en) * 2023-06-05 2023-07-04 四川皓德斯新材料科技有限公司 Conveyor

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106761808A (en) * 2016-12-28 2017-05-31 中铁十六局集团有限公司 A kind of track traffic bored tunnel electric railcar transports corollary system
CN116374483A (en) * 2023-06-05 2023-07-04 四川皓德斯新材料科技有限公司 Conveyor
CN116374483B (en) * 2023-06-05 2023-08-04 四川皓德斯新材料科技有限公司 Conveyor

Similar Documents

Publication Publication Date Title
CN107100639B (en) Shield transportation system for large-particle-size sand pebbles
CN106761808A (en) A kind of track traffic bored tunnel electric railcar transports corollary system
CN100494635C (en) Method of filling goaf with gangue
AU2014202712B2 (en) Ore removal production line, twin ramps and ground support installation method
CN101434346A (en) Scraper bucket type transloader
CN201087428Y (en) Bucket type transloader
US20160186566A1 (en) Apparatus, system and method for material extraction in underground hard rock mining
CN101363324A (en) Improvement method of slag extraction in inclined shaft of main tunnel
CN206409240U (en) A kind of track traffic bored tunnel electric railcar transports corollary system
CN105715280A (en) Mucking and transporting method and device applied to double-shield tunnel boring machine
CN201952821U (en) Novel loader
CN103821530A (en) Continuous tunnel excavation equipment and technology
CN100419211C (en) The Method of Quickly Excavating Mine in Three-dimensional Operation in Mine Excavation
CN201024361Y (en) Coal mine down-hole floating crossing
CN203382232U (en) Large ultra-long single-arm material discharging and distributing machine
CN209493982U (en) A kind of scoop loader suitable for complex working condition
CN109372575B (en) Device and method for long-distance consignment in main drive tunnel of TBM shield
CN105173673A (en) Soil dumping process for multi-directional transferring and machine head dead zone eliminating by waste soil field rubber belt machines
CN103043077B (en) Quick shunting system for tunneling slag discharge mining cars in underground roadway of mine
CN205638467U (en) Be applied to two shield tunnel boring machine's play cause of a quarrel conveyor
CN210851911U (en) Rubber-tired vehicle capable of running on underground straight track
CN202866886U (en) Bridge beam transshipment belt conveyor
CN204999164U (en) On -vehicle portable sealing -tape machine
CN103332503A (en) Large-scale ultra-long one-armed spreader
CN203382233U (en) Large ultra-long double-arm material discharging and distributing machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170815

CF01 Termination of patent right due to non-payment of annual fee