CN107237923A - 一种受限空间管线离线组装快速安装方法 - Google Patents

一种受限空间管线离线组装快速安装方法 Download PDF

Info

Publication number
CN107237923A
CN107237923A CN201710409226.0A CN201710409226A CN107237923A CN 107237923 A CN107237923 A CN 107237923A CN 201710409226 A CN201710409226 A CN 201710409226A CN 107237923 A CN107237923 A CN 107237923A
Authority
CN
China
Prior art keywords
pipeline
pipe network
frame
restricted clearance
offline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710409226.0A
Other languages
English (en)
Inventor
董健
魏尚起
蔡联河
胡斯楞
周丽华
安腾跃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201710409226.0A priority Critical patent/CN107237923A/zh
Publication of CN107237923A publication Critical patent/CN107237923A/zh
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Pipeline Systems (AREA)

Abstract

本发明提供了一种受限空间管线离线组装快速安装方法,旨在减小受限空间管道安装、焊接难度,改变常规工艺流程,缩短工期,提高生产效率。本发明其特征在于,包括:步骤S1,根据管道安装图,确定管道安装的位置、种类、数量和安装区域;步骤S2,在制作场地,根据相关数据将受限空间内的管道制作成框架式管网;步骤S3,在结构、平台或设备吊装前,将框架式管网分为若干部分或整体安装在相应部件上;步骤S4,将带有框架式管网的设备安装就位;步骤S5,将框架式管网末端管道与介质管道进行连接。新技术采用提前预制组装管道,再将管道离线拼装在设备上,与设备一同进行安装的施工工序。相应的缩短了受限空间内的施工时间,提高了质量及安装精度。

Description

一种受限空间管线离线组装快速安装方法
技术领域
本发明涉及管道安装技术领域,具体而言,涉及一种受限空间管线离线组装快速安装方法。
背景技术
在工业管道安装工作中,一些受限空间的管道安装难度在于,空间受限,工作界面狭窄。施工时,一般前道工序完毕后,在空间有限的范围内倒运材料、现场安装和焊接;或者在制造场地,将部分部件焊接完毕后,再倒运部件至安装现场进行后续工作。由于空间受限进行施工,给安装工作增加了难度,工作效率降低,管道焊接质量相对较差,而且产生了相应的后续质量隐患。
发明内容
鉴于此,本发明提出了一种受限空间管线离线组装快速安装方法,旨在减小受限空间管道安装、焊接难度,改变常规工艺流程,缩短工期,提高生产效率。
本发明提出了一种受限空间管线离线组装快速安装方法,其特征在于,包括:
步骤S1,根据管道安装图,确定管道安装的位置、种类、数量和安装区域;
步骤S2,在制作场地,根据相关数据将受限空间内的管道制作成框架式管网;
步骤S3,在结构、平台或设备吊装前,将框架式管网分为若干部分或整体安装在相应部件上;
步骤S4,将带有框架式管网的设备安装就位;
步骤S5,将框架式管网末端管道与介质管道进行连接。
进一步地,上述受限空间管线离线组装快速安装方法中,其特征在于,制作框架式管网时,预先焊制支撑架,并且根据不同粗细和位置的管道在支撑架上设置卡箍。
进一步地,上述受限空间管线离线组装快速安装方法中,其特征在于,安装框架式管网时,先将不同组的支撑架焊接连接,然后再连接各个管道。
进一步地,上述受限空间管线离线组装快速安装方法中,其特征在于,安装设备时,先将设备安装在指定位置固定,再连接支撑架和各个管道。
进一步地,上述受限空间管线离线组装快速安装方法中,其特征在于,连接框架式管网和介质管道使用法兰连接。
本发明的有益效果:(1)提高效率、优化工序,新技术采用提前预制组装管道,再将管道离线拼装在设备上,与设备一同进行安装的施工工序。相应的缩短了受限空间内的施工时间。(2)提高了质量及安装精度:新技术采用预制的方法,减少了受限空间内安装及焊接工作,提高安装精度,减少质量隐患。
附图说明
通过阅读下文优选实施方式的详细描述,各种其他的优点和益处对于本领域普通技术人员将变得清楚明了。附图仅用于示出优选实施方式的目的,而并不认为是对本发明的限制。而且在整个附图中,用相同的参考符号表示相同的部件。在附图中:
图1为本发明实施例示意图一
图2为本发明实施例示意图二
具体实施方式
下面将参照附图更详细地描述本公开的示例性实施例。虽然附图中显示了本公开的示例性实施例,然而应当理解,可以以各种形式实现本公开而不应被这里阐述的实施例所限制。相反,提供这些实施例是为了能够更透彻地理解本公开,并且能够将本公开的范围完整的传达给本领域的技术人员。需要说明的是,在不冲突的情况下,本发明中的实施例及实施例中的特征可以相互组合。下面将参考附图并结合实施例来详细说明本发明。
下面结合河南中原特钢二冷室(结晶段、振动段)管道安装过程说明本实施例。首先根据管道安装图,确定管道安装的位置、种类、数量、安装区域等因素,然后借助相关专业设备,根据现场实际情况,复测相关重要数据。在制作场地,根据相关数据将受限空间内的管道制作成框架式管网。
制作框架式管网时,如果出现需要安装大量管道时,预先焊制支撑架1,并且根据不同粗细和位置的管道在支撑架上设置卡箍,同时需要根据不同管道2的走向和粗细在支撑架上进行合理的预铺设管道布局。当出现主管道上连接大量支管道时,可以先将支管道预先焊接在主管道上,然后直接将主管道固定在支撑架上,减少支撑架的使用。
在结构、平台或设备吊(安)装前,根据空间大小视条件将框架式管网分为若干部分或整体安装在相应部件上。
安装好管网,并将各个管道建立连接后,再安装带有框架式管网的设备,将设备固定好之后,再将设备上的管网连接相应的管网。
最后将框架式管网末端管道与介质管道3进行连接,连接框架式管网和介质管道使用法兰连接。
本实施例中如图1所示,框架式管网部分安装在结晶区域二冷室壳体4外壁上,如图2所示,框架式管网部分安装在结晶区域二冷室壳体4底部上,二冷室壳体上还设置有其他管道和设备5。
显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包含这些改动和变型在内。

Claims (5)

1.一种受限空间管线离线快速组装安装方法,其特征在于,包括:
步骤S1,根据管道安装图,确定管道安装的位置、种类、数量和安装区域;
步骤S2,在制作场地,根据相关数据将受限空间内的管道制作成框架式管网;
步骤S3,在结构、平台或设备吊装前,将框架式管网分为若干部分或整体安装在相应部件上;
步骤S4,将带有框架式管网的设备安装就位;
步骤S5,将框架式管网末端管道与介质管道进行连接。
2.根据权利要求1所述的受限空间管线离线组装快速安装方法,其特征在于,制作框架式管网时,预先焊制支撑架,并且根据不同粗细和位置的管道在支撑架上设置卡箍。
3.根据权利要求1所述的受限空间管线离线组装快速安装方法,其特征在于,安装框架式管网时,先将不同组的支撑架焊接连接,然后再连接各个管道。
4.根据权利要求1所述的受限空间管线离线组装快速安装方法,其特征在于,安装设备时,先将设备安装在指定位置固定,再连接支撑架和各个管道。
5.根据权利要求1所述的受限空间管线离线组装快速安装方法,其特征在于,连接框架式管网和介质管道使用法兰连接。
CN201710409226.0A 2017-06-02 2017-06-02 一种受限空间管线离线组装快速安装方法 Pending CN107237923A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710409226.0A CN107237923A (zh) 2017-06-02 2017-06-02 一种受限空间管线离线组装快速安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710409226.0A CN107237923A (zh) 2017-06-02 2017-06-02 一种受限空间管线离线组装快速安装方法

Publications (1)

Publication Number Publication Date
CN107237923A true CN107237923A (zh) 2017-10-10

Family

ID=59985265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710409226.0A Pending CN107237923A (zh) 2017-06-02 2017-06-02 一种受限空间管线离线组装快速安装方法

Country Status (1)

Country Link
CN (1) CN107237923A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108004120A (zh) * 2018-01-16 2018-05-08 江苏丰泽生物工程设备制造有限公司 一体化管路布置立式大型发酵罐及其管路布置方法
CN109160416A (zh) * 2018-10-30 2019-01-08 北京机械设备研究所 一种液压管网整体吊装的方法及装置

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85106422A (zh) * 1984-10-18 1986-06-10 比奇特尔国际公司 管线或电缆的嵌装方法和装置
CN1030972A (zh) * 1987-07-27 1989-02-08 克瓦纳尔海底工程承建公司 管道或电缆的制造或水下敷设方法
CN2586034Y (zh) * 2002-11-16 2003-11-12 胜利油田胜利石油化工建设有限责任公司三分公司 预制海底管道芯管穿套管装置
CN2605446Y (zh) * 2002-05-01 2004-03-03 四川石油管理局油气田建设工程总公司第二公司 江河穿越走线吊装整体发送装置
JP2010038231A (ja) * 2008-08-04 2010-02-18 Capty Co Ltd 測定定規及び埋設樹脂管の扁平矯正方法
CN204478334U (zh) * 2014-12-22 2015-07-15 中船重工环境工程有限公司 模块式集成冷冻站

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85106422A (zh) * 1984-10-18 1986-06-10 比奇特尔国际公司 管线或电缆的嵌装方法和装置
CN1030972A (zh) * 1987-07-27 1989-02-08 克瓦纳尔海底工程承建公司 管道或电缆的制造或水下敷设方法
CN2605446Y (zh) * 2002-05-01 2004-03-03 四川石油管理局油气田建设工程总公司第二公司 江河穿越走线吊装整体发送装置
CN2586034Y (zh) * 2002-11-16 2003-11-12 胜利油田胜利石油化工建设有限责任公司三分公司 预制海底管道芯管穿套管装置
JP2010038231A (ja) * 2008-08-04 2010-02-18 Capty Co Ltd 測定定規及び埋設樹脂管の扁平矯正方法
CN204478334U (zh) * 2014-12-22 2015-07-15 中船重工环境工程有限公司 模块式集成冷冻站

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108004120A (zh) * 2018-01-16 2018-05-08 江苏丰泽生物工程设备制造有限公司 一体化管路布置立式大型发酵罐及其管路布置方法
CN108004120B (zh) * 2018-01-16 2020-10-13 江苏丰泽生物工程设备制造有限公司 一体化管路布置立式大型发酵罐及其管路布置方法
CN109160416A (zh) * 2018-10-30 2019-01-08 北京机械设备研究所 一种液压管网整体吊装的方法及装置

Similar Documents

Publication Publication Date Title
CN107237923A (zh) 一种受限空间管线离线组装快速安装方法
CN107587643B (zh) 快速插接装配的吊顶结构
US9752708B2 (en) Method for manufacturing an exhaust system and exhaust system
JP2008073739A (ja) 金属管の成形方法、管材に管継手を取り付ける方法、及び管継手を用いた継手方法
CN205096775U (zh) 燃机燃烧室燃气管道模拟组装平台
KR20130087297A (ko) 공기 조화기 설치용 배관 장치
CN111354069A (zh) 利用3d扫描技术进行模块预拼装的方法
CN109755060A (zh) 按键和按键的制作方法
CN112131650B (zh) 一种曲面结构的建造方法
KR20110093481A (ko) 선박의 블록 배관 연결 방법
CN209145005U (zh) 一种箱型梁柱十字节点结构
CN112733229A (zh) 一种基于bim技术的机电综合管线支吊架设计方法
RU169354U1 (ru) Термоизолирующий корпус бурильной колонны
CN112854666A (zh) 一种装配式一体化管井及其施工方法
CN111266728A (zh) 一种基于激光焊接的不锈钢管式油冷器焊接工艺
CN112329176A (zh) 管道的组合支吊架的设计方法
CN100445550C (zh) 不等厚壳节蜗壳的制造工艺
KR100566508B1 (ko) 배관용 분기관부재
JP2001153280A (ja) 免震建物の配管設置方法および免震継手構造
JP3250935B2 (ja) 建物ユニットの配管方法
JP2012117233A (ja) 鋼管杭の継手構造および継手付き鋼管杭
CN101625054A (zh) 一种径向挤压式接头
CN205241022U (zh) 一种适用于电梯的小门套
CN102853180A (zh) 一种连接管及其制造方法和空调系统
RU2473832C2 (ru) Способ компенсации отклонений при монтаже трубопроводных систем

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171010

RJ01 Rejection of invention patent application after publication