CN106613663A - Sand-stabilization and water-retention method used in semi-desert windy and sandy area - Google Patents

Sand-stabilization and water-retention method used in semi-desert windy and sandy area Download PDF

Info

Publication number
CN106613663A
CN106613663A CN201611178645.XA CN201611178645A CN106613663A CN 106613663 A CN106613663 A CN 106613663A CN 201611178645 A CN201611178645 A CN 201611178645A CN 106613663 A CN106613663 A CN 106613663A
Authority
CN
China
Prior art keywords
sand
water
impounding
belts
retaining band
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611178645.XA
Other languages
Chinese (zh)
Inventor
房世平
秦国鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingyang Dunbo Technology Development Co Ltd
Original Assignee
Qingyang Dunbo Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingyang Dunbo Technology Development Co Ltd filed Critical Qingyang Dunbo Technology Development Co Ltd
Priority to CN201611178645.XA priority Critical patent/CN106613663A/en
Publication of CN106613663A publication Critical patent/CN106613663A/en
Pending legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G17/00Cultivation of hops, vines, fruit trees, or like trees
    • A01G17/005Cultivation methods
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01BSOIL WORKING IN AGRICULTURE OR FORESTRY; PARTS, DETAILS, OR ACCESSORIES OF AGRICULTURAL MACHINES OR IMPLEMENTS, IN GENERAL
    • A01B79/00Methods for working soil
    • A01B79/02Methods for working soil combined with other agricultural processing, e.g. fertilising, planting
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G13/00Protecting plants
    • A01G13/02Protective coverings for plants; Coverings for the ground; Devices for laying-out or removing coverings
    • A01G13/0256Ground coverings
    • A01G13/0262Mulches, i.e. covering material not-pre-formed in mats or sheets
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/10Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
    • Y02A40/22Improving land use; Improving water use or availability; Controlling erosion
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P60/00Technologies relating to agriculture, livestock or agroalimentary industries
    • Y02P60/40Afforestation or reforestation

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Environmental Sciences (AREA)
  • Soil Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Toxicology (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Botany (AREA)
  • Cultivation Of Plants (AREA)

Abstract

The invention discloses a sand-stabilization and water-retention method used in a semi-desert windy and sandy area. The sand-stabilization and water-retention method comprises the following steps that 1, sand-stabilization and water-retention work is performed, wherein an impounding belt is excavated in the windy and sandy area in the east-west direction and is divided into foundation-fixing impounding belts, foundations are established on the peripheries of the foundation-fixing impounding belts by using seepage-proof bricks, and seepage-proof processing is conducted on the bottoms of the impounding belts; then, the foundation-fixing impounding belts are filled with composite water-retention ingredients; the impounding belts are filled with dug-out sandy soil till the impounding belts are full; the terrains of the impounding belts are arranged to be wavy, the foundation-fixing impounding belts are wave troughs, hole positions among the foundation-fixing impounding belts are wave peaks, and the wave height is 0.5 m; 2, a protection forest is planted; 3, protection forest enclosure is performed. The sand-stabilization and water-retention method has the advantages of being high in impounding capability, high in sand-preventing vegetation survival rate and high in forest establishment speed, and the sand-stabilization and water-retention problems existing in existing air seeding and afforestation and sand-protecting barrier arrangement are effectively solved.

Description

A kind of Semi-desert Area sand-fixation, water-keeping method
Technical field
The invention belongs to sand-fixation, water-keeping technical field, more particularly to a kind of Semi-desert Area sand-fixation, water-keeping method.
Background technology
Desertification of land has become global big problem, under the double influence of mankind's activity and Natural Enviroment Evolution, entirely Ball desertification area is all being increased every year with certain speed.There is scholar to show through research, into 20th century since, China desertifies Land area increases year by year;By taking the eighties as an example, the average annual incrementss of China's desertification area are 2100km2, it is husky compared with before 10 years Change the average annual incrementss of area and increase 540km2, annual growth increases to 1.47% by 1.01%;Hereafter China's desertification situation heals Drill stronger, or even 3436km is up to the average annual incrementss of later stage nineties desertification area2.It was predicted that to the year two thousand thirty, China's arid The scope of area and semiarid zone will significantly extend, and diastrous weather more takes place frequently, and environmental destruction is even more serious.Desert The impact changed to China is huge, and the economic loss brought and ecological loss are huge, and related data shows, China desert, dagger-axe Wall and Desertification Soil area amount to 165.3 ten thousand km2, it is mainly distributed on that China is arid, semiarid and part Semi-humid area, its In the sandy land area that formed by mankind's activity leading role be about 370,000 km2.Increasingly serious desertification of land, is making While constantly decline into land resource quality and quantity for the survival of mankind, huge direct economic loss is even more brought And irremediable environmental destruction, cause a series of frequent natural calamities such as sandstorm to occur because of ecosystem destruction, Seriously threaten the living safety of the mankind.Therefore, under instant desertification of land situation, the restoration of the ecosystem to sandy land Build and environmental protection has become global human and paid close attention to big problem jointly, it is necessary to actively adopt an effective measure, arid area is entered Row is administered, and control sand ground spreads, and rebuilds the husky area ecosystem.
At present, desertification Treatment process is less, mainly has scattered seeds by airplane for afforestation and arranges two methods of sand-protecting barrier.Scattered seeds by airplane for afforestation That but scattered seeds by airplane for afforestation Technical comparing is extensive using aerial seeding kind grass, to reproducing area, seeds and plant seeds by airplane after manage and protect requirement It is higher, substantial amounts of denizen is easily brought, destroyed the ecosystem;Importantly, desert extremely water shortage, sapling is because tight Weight water shortage is difficult to survive.It is that blind is made on Shamian Island with plant haulms such as wheat straw, straw, reeds to arrange sand-protecting barrier, but is existed The shortcomings of easy aging, transport of material and constructional difficulties;Or the husky plot structure of transformation, build up hard concrete epidermal area, and Drought-enduring vegetation is planted between sand-protecting barrier, to prevent sandy soil from elapsing, the desert treatment technology as disclosed in the A of patent CN 101560759, CN A kind of quickly fixating sand, growth-promoting disclosed in 103798006 A protect raw, water saving desertification ground etc..Both the above method mainly with Based on seed bare area is sprouted naturally, seed is sprouted, growth of seedling is affected larger by local soil moisture and nutrient, it is impossible to ensure to plant Sub- germination rate and seedling percent.To solve the problems, such as above-mentioned sand control, the A of patent CN 1754414 discloses one kind and fixes the sand The method in water conservation breeding plant landscape desert, the method includes following methods:1) plant chinampa in desert surface and fix, Clearance position is reserved between lawn;2) kind of a tree hole is dug out in clearance position;3) water suction nail is got downwards in kind of a tree hole, water suction nail Absorbent material is filled with tubular cavity, is filled out in kind of a tree hole site and is put soil, absorbent material is extended in soil;4) in kind of a tree hole Position plants tree seedlings.The patent overcomes the low problem of sapling survival rate in scattered seeds by airplane for afforestation technology, meanwhile, overcome sand-protecting barrier technology The middle problem that desert epidermis is bleak and desolate and material is easily aging.
The content of the invention
It is an object of the invention to:A kind of Semi-desert Area sand-fixation, water-keeping method is provided, by setting up water conservation fortification simultaneously Transformation sandy soil surface texture, and sand and sandy soil passage are prevented using section connection means, then drought resisting vegetation is planted, both solve existing Have in scattered seeds by airplane for afforestation technology vegetation because of water shortage the low problem of survival rate, solve sand-protecting barrier is simply provided again and cause careless woods raw Problem.
For achieving the above object, the present invention is adopted the following technical scheme that:
A kind of Semi-desert Area sand-fixation, water-keeping method, it is characterised in that:Comprise the following steps:
1) sand-fixation, water-keeping fortification are set up:The retaining band of deep 1.5~2m, wide 3~5m is dug along east-west machinery in Wind-sandy Area, Retaining band being divided into into the solid base retaining band of 1m × 1m, and base is built in solid base retaining band periphery with antiseepage brick, capital construction highly is 1~ 1.2m, Gu base retaining 0.5~1m of belt distance, to retaining band bottom Anti-seeping technology is carried out;Then insert in solid base retaining band by Composite water conservation composition, inserts thickness for 5~10cm, wherein, described composite water conservation composition by diatomite, flyash, scale stone, Cripple, horsehit and sandy soil are mixed, and mixing match presses diatomite:Flyash:Scale stone:Cripple:Horsehit:Sandy soil are 1:1: 0.5:5:2:10;The sandy soil for digging out are inserted into retaining band, to filling up retaining band;By retaining band landform be made into it is wavy, it is described solid Base retaining band is trough, Gu being crest at base retaining interband hole, wave height is 0.5m;
2) shelter-forest is planted:After building up sand-fixation, water-keeping fortification, pour after water to trough, apply well-rotted farmyard manure, dose For 3~5kg/m3, then drought resisting trees are planted in trough;Simultaneously with crest as axle, the base that fixes the sand is set up, concrete grammar is:In ripple Timber is squeezed in peak position, and then 0.8~1m of depth lays wire netting, with timber as node, by whole Wind-sandy Area closing in case It is husky;
3) fencing shelter-forest:After drought resisting planting tree, manage with delicacy, water in time, apply fertilizer;Prevent from livestock from entering simultaneously to gnaw Food treelet, is grown into forest with protecting drought resisting trees.
Further, described retaining 10~15m of belt distance, retaining interband vacant lot is whole for terraced fields or riglet shape field.
Further, the vacant lot plantation drought resisting economic forest of described retaining interband.
Compared with prior art, the beneficial effects of the present invention is:
1) present invention digs retaining band in Wind-sandy Area machinery, and splits " independence " solid base retaining band in retaining band, then right Gu base retaining band carries out Anti-seeping technology, both prevent husky area's water penetration fast, rainwater is difficult to put aside, held so as to solve husky area plant water suction Continuous property is poor, the low problem of survival rate;Meanwhile, by setting up solid base retaining band to play a part of fixed sandy soil, prevent sandy soil from meeting Large wind and passage in heaps.
2) present invention insert composite water conservation composition in solid base retaining band, the composition by water imbibition it is strong, air permeability is good, nutrition Composition enriches comprehensive raw material and mixes, and after vegetation plantation, root system is deep in the composition, can fully absorb moisture, support Material and air, so as to accelerate the growth of sand prevention vegetation, realize the purpose quickly grown into forest.
3) present invention builds up in husky area wavy, and trough physical features is relatively low and lower floor is solid base retaining band, plants drought resisting sand prevention After vegetation, trough can be utilized as collecting-tank, and the water conservation composition of Gu Jishui bands is goed deep into after rainwater-collecting, so as to extend rainwater savings Time, improve vegetation water suction continuation, and then improve vegetation survival rate;And crest location is easily elapsed compared with sandy soil area, the present invention is logical Cross foundation fix the sand base closing sandy soil, to prevent movement in blocks.
4) sand-fixation, water-keeping method of the present invention has water-holding capacity strong, and sand prevention vegetation survival rate is high, fireballing advantage of growing into forest.
Specific embodiment
Technical scheme is described further with reference to specific embodiment, in order to same domain technical staff Understanding.
Embodiment 1
A kind of Semi-desert Area sand-fixation, water-keeping method, comprises the following steps:
1) sand-fixation, water-keeping fortification are set up:In April, 2010,10 mu of vacant lots are selected in Wind-sandy Area, dig deep along east-west machinery The retaining band of 1.5~2m, wide 3~5m, described retaining 10~15m of belt distance stays ground, retaining band to stay ground than sky at spacing for sky Low 20~the 30cm of physical features;Retaining band is divided into into the solid base retaining band of 1m × 1m, and is built in solid base retaining band periphery with antiseepage brick Base, capital construction is highly 1~1.2m, Gu base retaining 0.5~1m of belt distance, to retaining band bottom Anti-seeping technology is carried out;Then to admittedly Insert by composite water conservation composition in base retaining band, it is 5~10cm to insert thickness, wherein, described composite water conservation composition is by diatom Soil, flyash, scale stone, cripple, horsehit and sandy soil are mixed, and mixing match presses diatomite:Flyash:Scale stone:Cripple: Horsehit:Sandy soil are 1:1:0.5:5:2:10;The sandy soil for digging out are inserted into retaining band, to filling up retaining band;Retaining band landform is whole It is trough at the solid base retaining band position into wavy, solid is crest at base retaining interband hole, wave height is 0.5m, retaining band Between vacant lot it is whole for terraced fields or riglet shape field;
2) shelter-forest is planted:After building up sand-fixation, water-keeping fortification, pour after water to trough, apply well-rotted farmyard manure, dose For 3~5kg/m3, then drought resisting trees to be planted in trough, the drought resisting trees surviving rate planted first will not survived up to 92.3% Drought resisting trees seedling root out after water again, apply fertilizer, then secondary plantation is filled the gaps with seedlings, its survival rate 94.7%;The above-mentioned benefit of repetition Seedling step, so that sapling is complete;After sapling completion, with crest as axle, the base that fixes the sand is set up, concrete grammar is:Beat in crest location Enter timber, then 0.8~1m of depth lays wire netting, with timber as node, whole Wind-sandy Area is closed with sand prevention;
3) fencing shelter-forest:After drought resisting planting tree, manage with delicacy, water in time if long-term drying, apply fertilizer, if rainwater Interval time does not then water less than January;Prevent livestock from entering simultaneously and gnaw treelet, grown into forest with protecting drought resisting trees;The beginning of spring in 2012 Afterwards, for the plant that freezes to death is filled the gaps with seedlings, effective shelter-forest formed to ensure, and in October, carries out tree-like pruning, with medium tree Based on shape, unsuitable too high too short;Summer in 2013, you can form effective shelter-forest;
4) economic forest is planted:After 2014 beginning of springs, plantation drought resisting economic forest on the ground is stayed in the sky of retaining interband, and managed meticulously Reason, to ensure that economic forest is molded, after economic forest shaping, carries out tree-like pruning, based on dwarf trees, expects to produce economic effect Benefit.
By said method, effective shelter-forest can be formed within 3 years, economic forest can be formed within 5~6 years, so as to form shelter-forest With economic forest and the sand- prevention system deposited, desertification process is not only effectively prevented, moreover it is possible to obtain good economic benefit, realize falling into disuse The effect that utilizes.

Claims (4)

1. a kind of Semi-desert Area sand-fixation, water-keeping method, it is characterised in that:Comprise the following steps:
1) sand-fixation, water-keeping fortification are set up:The retaining band of deep 1.5~2m, wide 3~5m is dug along east-west machinery in Wind-sandy Area, will be stored Water band is divided into the solid base retaining band of 1m × 1m, and builds base in solid base retaining band periphery with antiseepage brick, and capital construction highly is 1~ 1.2m, Gu base retaining 0.5~1m of belt distance, to retaining band bottom Anti-seeping technology is carried out;Then insert in solid base retaining band by Composite water conservation composition, inserts thickness for 5~10cm, wherein, described composite water conservation composition by diatomite, flyash, scale stone, Cripple, horsehit and sandy soil are mixed, and mixing match presses diatomite:Flyash:Scale stone:Cripple:Horsehit:Sandy soil are 1:1: 0.5:5:2:10;The sandy soil for digging out are inserted into retaining band, to filling up retaining band;By retaining band landform be made into it is wavy, it is described solid Base retaining band is trough, Gu being crest at base retaining interband hole, wave height is 0.5m;
2) shelter-forest is planted:After building up sand-fixation, water-keeping fortification, to pour after water to trough, apply well-rotted farmyard manure, dose is 3~ 5kg/m3, then drought resisting trees are planted in trough;Simultaneously with crest as axle, the base that fixes the sand is set up, concrete grammar is:In crest location Timber is squeezed into, then 0.8~1m of depth lays wire netting, with timber as node, whole Wind-sandy Area is closed with sand prevention;
3) fencing shelter-forest:After drought resisting planting tree, manage with delicacy, water in time, apply fertilizer;Prevent livestock from entering simultaneously and gnaw children Tree, is grown into forest with protecting drought resisting trees.
2. a kind of Semi-desert Area sand-fixation, water-keeping method as claimed in claim 1, it is characterised in that:Retaining belt distance 10~ 15m, retaining interband vacant lot is whole for terraced fields or riglet shape field.
3. a kind of Semi-desert Area sand-fixation, water-keeping method as claimed in claim 1, it is characterised in that:The vacant lot of retaining interband Plantation drought resisting economic forest.
4. a kind of Semi-desert Area sand-fixation, water-keeping method as claimed in claim 1, it is characterised in that:Retaining band stays ground than sky Low 20~the 30cm of physical features.
CN201611178645.XA 2016-12-19 2016-12-19 Sand-stabilization and water-retention method used in semi-desert windy and sandy area Pending CN106613663A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611178645.XA CN106613663A (en) 2016-12-19 2016-12-19 Sand-stabilization and water-retention method used in semi-desert windy and sandy area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611178645.XA CN106613663A (en) 2016-12-19 2016-12-19 Sand-stabilization and water-retention method used in semi-desert windy and sandy area

Publications (1)

Publication Number Publication Date
CN106613663A true CN106613663A (en) 2017-05-10

Family

ID=58834956

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611178645.XA Pending CN106613663A (en) 2016-12-19 2016-12-19 Sand-stabilization and water-retention method used in semi-desert windy and sandy area

Country Status (1)

Country Link
CN (1) CN106613663A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107439078A (en) * 2017-06-26 2017-12-08 陕西省土地工程建设集团有限责任公司 A kind of sand ground soil body reconstructing method
CN108243651A (en) * 2018-01-17 2018-07-06 内蒙古云农实业有限公司 A kind of method of fix the sand adhesive material and improvement desertification land
CN108949183A (en) * 2017-08-24 2018-12-07 中国科学院寒区旱区环境与工程研究所 Desert greening method
CN115885799A (en) * 2022-11-18 2023-04-04 辽宁省农业科学院 Method for alleviating peanut continuous cropping obstacle and nitrogen repression by intercropping sunflower

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2599073Y (en) * 2002-12-24 2004-01-14 中国科学院寒区旱区环境与工程研究所 Hongecomb type plastic knitted sand fixing net
CN102388694A (en) * 2011-08-01 2012-03-28 西北永新集团集团有限公司 Method and plant pit for planting trees and saving degradation trees in arid and semiarid lands
CN202849993U (en) * 2012-09-28 2013-04-03 苏州市规划设计研究院有限责任公司 Water loving revetment system
CN105532228A (en) * 2015-12-17 2016-05-04 李积山 Water-saving planting method for sand-binding green plants
CN105815066A (en) * 2016-03-13 2016-08-03 孙明文 Plant planting soil moisture preservation water-saving fast growing method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2599073Y (en) * 2002-12-24 2004-01-14 中国科学院寒区旱区环境与工程研究所 Hongecomb type plastic knitted sand fixing net
CN102388694A (en) * 2011-08-01 2012-03-28 西北永新集团集团有限公司 Method and plant pit for planting trees and saving degradation trees in arid and semiarid lands
CN202849993U (en) * 2012-09-28 2013-04-03 苏州市规划设计研究院有限责任公司 Water loving revetment system
CN105532228A (en) * 2015-12-17 2016-05-04 李积山 Water-saving planting method for sand-binding green plants
CN105815066A (en) * 2016-03-13 2016-08-03 孙明文 Plant planting soil moisture preservation water-saving fast growing method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107439078A (en) * 2017-06-26 2017-12-08 陕西省土地工程建设集团有限责任公司 A kind of sand ground soil body reconstructing method
CN108949183A (en) * 2017-08-24 2018-12-07 中国科学院寒区旱区环境与工程研究所 Desert greening method
CN108243651A (en) * 2018-01-17 2018-07-06 内蒙古云农实业有限公司 A kind of method of fix the sand adhesive material and improvement desertification land
CN115885799A (en) * 2022-11-18 2023-04-04 辽宁省农业科学院 Method for alleviating peanut continuous cropping obstacle and nitrogen repression by intercropping sunflower
CN115885799B (en) * 2022-11-18 2024-05-07 辽宁省农业科学院 Method for reducing peanut continuous cropping obstacle and nitrogen repression by intercropping sunflower

Similar Documents

Publication Publication Date Title
CN105474938B (en) The restorative procedure of the western Funiu Shan Mountain Hills And Low Mountains degraded ecosystem in Henan
CN106900342A (en) Integrated half rockmass high slope revegetation guard method
CN101822159B (en) Method for artificially planting cistanche deserticola by saline water drip irrigation technology
CN206294619U (en) A kind of strand sandbank band revegetation system
CN104855114A (en) Method for planting walnuts and peppers in stony desertification soil
CN110859066B (en) Desertification land vegetation recovery method
CN105210770B (en) Dust storm forward position Desert Regions sacsaoul Ecology method of forestation
CN109392660B (en) Desert greening soil module and preparation and construction methods thereof
CN107624603A (en) One kind method of forestation on the salt-soda soil of inland
CN105519393B (en) A kind of Kiwi berry implantation methods
CN104737735B (en) Method for ecological afforestation of coastal saline-alkali areas by means of original soil cultivation
CN104186137A (en) Technology for cultivating and greening tall fescue grass on inshore mud flat saline-alkali soil
CN101822193A (en) Method for quickly planting sophora davidii
CN106613663A (en) Sand-stabilization and water-retention method used in semi-desert windy and sandy area
CN105359929A (en) Transplanting method for large-size Sabina prezewalskii nursery stocks in drought area
CN106717851A (en) A kind of method of tropical forest insect islands and reefs ecological afforestation
CN105027945A (en) High-yield and high-efficient cultivation method for water manure induction and root confinement of asparagus
CN111316853A (en) Stone mountain damaged surface vegetation and planting method thereof
CN109328805A (en) A kind of Rocky Desertification Region ecological treatment of slope method
CN104855223A (en) Method for intercropping honeysuckle and fructus cnidii in stony desertification soil
CN105165511A (en) Large-scale forestation method for shrub species for especially-poor saline and alkaline land
CN107232003A (en) The construction method of planting in water-fast wet arbor water
CN110249897B (en) Method for preventing and treating water and soil loss of sloping field by intercropping ginkgo biloba and peony
CN106165567B (en) A kind of method of stony desertification soil plantation birchleaf pear subtree
CN105325228A (en) Planting method for Chinese yew

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510