CN106437093A - Architectural decoration and finishing concealed installation tile skirting structure and construction technology thereof - Google Patents

Architectural decoration and finishing concealed installation tile skirting structure and construction technology thereof Download PDF

Info

Publication number
CN106437093A
CN106437093A CN201610806133.7A CN201610806133A CN106437093A CN 106437093 A CN106437093 A CN 106437093A CN 201610806133 A CN201610806133 A CN 201610806133A CN 106437093 A CN106437093 A CN 106437093A
Authority
CN
China
Prior art keywords
ceramic tile
construction
wall
frid
combination
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610806133.7A
Other languages
Chinese (zh)
Other versions
CN106437093B (en
Inventor
李琴琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Qiangxiong Construction Group Co ltd
Original Assignee
Guangdong Million Cattle Intellectual Property Operation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Million Cattle Intellectual Property Operation Co Ltd filed Critical Guangdong Million Cattle Intellectual Property Operation Co Ltd
Priority to CN201610806133.7A priority Critical patent/CN106437093B/en
Publication of CN106437093A publication Critical patent/CN106437093A/en
Application granted granted Critical
Publication of CN106437093B publication Critical patent/CN106437093B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • E04F19/04Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • E04F19/04Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings
    • E04F19/0459Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings characterised by the fixing method
    • E04F19/0477Plinths fixed by means of adhesive

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

Disclosed is an architectural decoration and finishing concealed installation tile skirting structure. The tile skirting structure comprises a framed grider, a floorslab, a masonry wall, a wall surface layer, a floor cushion layer, a pure cement paste smearing and pasting layer, a ceramic file and a ceramic file skirting. The wall surface layer comprises a cement sand slurry plastering layer and a finishing coat structure. The ceramic file skirting is parallel and level to the wall surface layer structure, and the construction finished thickness of the ceramic file skirting and the pure cement paste smearing and pasting layer are the same as that of the wall surface layer; after standards of concealed grooves necessary to the concealed installation of the stile skirting are calculated and determined through a designing, construction on the concealed installation of the stile skirting is carried out. The architectural decoration and finishing concealed installation tile skirting structure can not only improve sharply esthetic effects of interior trims, but also overcome a problem that the a seam between the upper end of the skirting and a wall space can not be cleaned well after a long term use.

Description

A kind of construction and decoration concealed installation ceramic tile lower margin line structure and its construction technology
Technical field
The invention belongs to architectural engineering interior decoration technical field of construction, and in particular to a kind of construction and decoration concealed installation ceramic tile ground Payment to a porter structure and its construction technology.
Background technology
During traditional-family's interior decoration, after floor ground construction paving installs flooring ceramic tile, subsequently can be to metope With floor ground junction, ceramic tile baseboard is installed, body of wall surface layer structure on the one hand can be protected, on the other hand can be also greatly improved Indoor beauty effect.Ceramic tile baseboard, generally also all adopts bright patch construction, i.e. ceramic tile baseboard protrudes metope way;Baseboard Concealed installation construction using less, i.e. ceramic tile baseboard way concordant with metope.Although it is simple to be stated clearly patch construction operation, can be certain Degree affects indoor beauty, and at rear lower margin line upper end and wall joints, Health Maintenance is also more difficult by long-term use;Baseboard is dark Dress construction, its working procedure is also not very complicated through reasonable planning and designing, but which can be substantially improved interior decoration aesthetic, and Because there is no inner corner trim setting at baseboard upper end and wall joints, overcoming life-time service rear lower margin line upper end very well and connecing with metope A difficult problem for Health Maintenance at seam.
Content of the invention
For reaching above-mentioned purpose, the technical solution used in the present invention is:A kind of construction and decoration concealed installation ceramic tile lower margin line structure, Paste layer, ceramic tile, ceramic tile baseboard are applied including Vierendeel girder, floor, masonry wall, body of wall surface layer, flooring bed course, neat slurry;Described Body of wall surface layer includes cement mortar coat of plaster, finish coat structure composition, and the body of wall surface thickness is set to 20-30mm;Described Ceramic tile baseboard is concordant with body of wall surface layer structure, and the construction that the ceramic tile baseboard applies paste layer with neat slurry completes thickness with wall Honorable layer keeps identical;The height of the ceramic tile baseboard is set to 80-150mm.
Preferably, the body of wall surface thickness is set to 25mm;The height of the ceramic tile baseboard is set to 10mm.
For realizing above-mentioned construction and decoration concealed installation ceramic tile baseboard structure technology scheme, the present invention also provides a kind of self-stabilization type height Degree Combined adjustable frid, the combination frid includes L-type lower basal plate, inverted L shape top top board;The L-type lower basal plate by under Base plate and lower wall composition, are provided with hold-open catch in the lower wall;Inverted L shape top top board is by upper plate and upper side wall Composition, the upper side wall is provided with hole clipping in differing heights position, and the hole clipping is mated with bayonet lock specification;The inverted L shape top Top board inner corner trim position, is provided with movable heel brace;In actually used, docked with bayonet lock by the hole clipping for selecting differing heights position, Realize the height adjustable of combination frid;By the supporting role of masonry wall and movable heel brace, the self-stabilization of combination frid is realized Function.
Preferably, the lower wall of the combination frid is highly 120mm with upper side wall, the differing heights position Hole clipping spacing is set to 10mm, and the actually used height of the combination frid is set to 120-220mm, under the combination frid Base plate is disposed as 25-50mm with upper plate width.
Preferably, in the upper plate plate face of the combination frid, it is additionally provided with a millimeter graduation mark in the width direction, so as to Masonry wall carries out cement mortar coat of plaster and determines that thickness is used.
A kind of construction and decoration concealed installation ceramic tile baseboard structure construction technique, specific as follows:
A remove masonry wall metope impurity, to especially clean out masonry wall the foot of a wall contact inner corner trim with flooring at residual cement Mortar block;According to design requirement, determine body of wall surface thickness and flooring ceramic tile surface with respect to slab surfaces absolute altitude, i.e., true further Determine cement mortar coat of plaster thickness and combination frid adjusts height;
B combination frid adjusts height and obtains according to equation below calculating:
Combination frid adjusts height=ceramic tile surface with respect to slab surfaces absolute altitude+ceramic tile baseboard height;
If it is H that combination frid adjusts height, ceramic tile surface is h1, a height of h2 of ceramic tile baseboard with respect to slab surfaces absolute altitude, Computing formula is then obtained:H=h1+h2;
C adjusts height H according to the combination frid for calculating acquisition and sets, and opens movable heel brace to appropriate location, will combination Frid is arranged at the masonry wall the foot of a wall that will carry out cement mortar coat of plaster construction;
D calculates the cement mortar coat of plaster thickness for obtaining according to design, and sectional carries out plastering construction;By combining frid Millimeter tick marks in upper plate plate face, control the thickness of cement mortar coat of plaster;Treat that in section, cement mortar is plastered After construction is finished and checks preliminarily stabilised, dismountable combination frid continues next section plastering construction;And regular water seasoning;
E reserves good neat slurry painting paste layer and ceramic tile according to the relative slab surfaces elevation location of ceramic tile surface of design Construction thickness laying flooring bed course, then tile laying construction is carried out using neat slurry, it is ensured that ceramic tile surface is with respect to slab surfaces Absolute altitude h1 is consistent with design load;
F clears up debris at flooring surrounding the foot of a wall after the flooring ceramic tile maintenance of paving is firm, checks according to design requirement standby After ceramic tile baseboard height h2 is consistent with design load, ceramic tile baseboard paving construction is carried out using neat slurry;Guarantee porcelain Tile floor payment to a porter is concordant with masonry wall cement mortar coat of plaster;
G checks the masonry wall cement mortar coat of plaster no phenomenon such as hollowing, crack, can carry out finish coat construction, and such as putty is looked for Flat bed, emulsion paint construction etc..
Since then, whole baseboard concealed installation structure construction is completed.
The invention has the beneficial effects as follows:Undercut specification needed for ceramic tile baseboard concealed installation is determined by designing to calculate, by certainly Undercut height accurately reserved by steady formula height adjustable combination frid, then carries out the construction of ceramic tile baseboard concealed installation, is not only able to big Width lifts interior decoration aesthetic, and because there is no inner corner trim setting at concealed installation baseboard upper end and wall joints, overcomes very well A difficult problem for Health Maintenance at life-time service rear lower margin line upper end and wall joints.
Description of the drawings
Fig. 1 is concealed installation ceramic tile baseboard structural representation;
Fig. 2 combines frid schematic diagram for self-stabilization type height adjustable;
Fig. 3 is combination frid use state schematic diagram.
Wherein:1 is Vierendeel girder, 2 is floor, 3 is masonry wall, 4 is body of wall surface layer, 5 is combination frid, 6 is flooring bed course, 7 be ceramic tile and neat slurry apply paste layer, 8 be neat slurry apply paste layer, 9 be.
Specific embodiment
For helping further understand the present invention program, now describe in detail as follows.
Refering to Fig. 1, a kind of construction and decoration concealed installation ceramic tile lower margin line structure, including Vierendeel girder, floor, masonry wall, body of wall face Layer, flooring bed course, neat slurry apply paste layer, ceramic tile, ceramic tile baseboard;The body of wall surface layer includes cement mortar coat of plaster, decorations Surface layer structure constitutes, and the body of wall surface thickness is set to 20-30mm;The ceramic tile baseboard is concordant with body of wall surface layer structure, It is identical with body of wall surface layer holding that the construction that the ceramic tile baseboard applies paste layer with neat slurry completes thickness;The ceramic tile baseboard Height be set to 80-150mm.
In being embodied as, the body of wall surface thickness is set to 25mm;The height of the ceramic tile baseboard is set to 10mm.
In being embodied as, a kind of self-stabilization type height adjustable combination frid that the present invention is adopted, the combination frid includes L-type Lower basal plate, inverted L shape top top board;The L-type lower basal plate is made up of lower shoe and lower wall, is provided with the lower wall Hold-open catch;Inverted L shape top top board is made up of upper plate and upper side wall, and the upper side wall is arranged in differing heights position There is hole clipping, the hole clipping is mated with bayonet lock specification;The inverted L shape top top board inner corner trim position, is provided with movable heel brace;Actually make With in, by select differing heights position hole clipping dock with bayonet lock, realize combine frid height adjustable;By masonry wall with And the supporting role of movable heel brace, realize the self-stabilization function of combination frid.
In being embodied as, the lower wall of the combination frid is highly 120mm with upper side wall, the differing heights position Hole clipping spacing be set to 10mm, the actually used height of the combination frid is set to 150mm, the going to the bottom of the combination frid Plate is disposed as 25mm with upper plate width.
In being embodied as, in the upper plate plate face of the combination frid, a millimeter graduation mark is additionally provided with the width direction, with Just masonry wall carry out cement mortar coat of plaster determine thickness use.
A kind of construction and decoration concealed installation ceramic tile baseboard structure construction technique, specific as follows:
A remove masonry wall metope impurity, to especially clean out masonry wall the foot of a wall contact inner corner trim with flooring at residual cement Mortar block;According to design requirement, determine body of wall surface thickness and flooring ceramic tile surface with respect to slab surfaces absolute altitude, i.e., true further Determine cement mortar coat of plaster thickness and combination frid adjusts height;
B combination frid adjusts height and obtains according to equation below calculating:
Combination frid adjusts height=ceramic tile surface with respect to slab surfaces absolute altitude+ceramic tile baseboard height;
I.e.:It is H that combination frid adjusts height, and the relative slab surfaces absolute altitude of ceramic tile surface is 50mm, ceramic tile baseboard for h1 A height of h2 is 100mm, then:H=150mm;
C adjusts height H according to the combination frid for calculating acquisition and sets 150mm, opens movable heel brace to appropriate location, will Combination frid is arranged at the masonry wall the foot of a wall that will carry out cement mortar coat of plaster construction;
D calculates the cement mortar coat of plaster thickness for obtaining according to design, and sectional carries out plastering construction;By combining frid Millimeter tick marks in upper plate plate face, control the thickness of cement mortar coat of plaster;Treat that in section, cement mortar is plastered After construction is finished and checks preliminarily stabilised, dismountable combination frid continues next section plastering construction;And regular water seasoning;
E reserves good neat slurry painting paste layer and ceramic tile according to the relative slab surfaces elevation location of ceramic tile surface of design Construction thickness laying flooring bed course, then tile laying construction is carried out using neat slurry, it is ensured that ceramic tile surface is with respect to slab surfaces Absolute altitude is 50mm;
F clears up debris at flooring surrounding the foot of a wall after the flooring ceramic tile maintenance of paving is firm, checks according to design requirement standby Ceramic tile baseboard height h2 is 100mm, carries out ceramic tile baseboard paving construction using neat slurry;Guarantee ceramic tile baseboard Concordant with masonry wall cement mortar coat of plaster;
G checks the masonry wall cement mortar coat of plaster no phenomenon such as hollowing, crack, carries out finish coat construction, and such as putty is levelling Layer, emulsion paint construction.
Since then, whole baseboard concealed installation structure construction is completed.

Claims (3)

1. a kind of construction and decoration concealed installation ceramic tile lower margin line structure, it is characterised in that:The ceramic tile lower margin line structure include Vierendeel girder, Floor, masonry wall, body of wall surface layer, flooring bed course, neat slurry apply paste layer, ceramic tile, ceramic tile baseboard;The body of wall surface layer includes Cement mortar coat of plaster, finish coat structure composition, the body of wall surface thickness is set to 20-30mm;The ceramic tile baseboard with Body of wall surface layer structure is concordant, and the construction that the ceramic tile baseboard applies paste layer with neat slurry completes thickness and keeps phase with body of wall surface layer With;The height of the ceramic tile baseboard is set to 80-150mm;
A kind of construction and decoration concealed installation ceramic tile baseboard structure construction technique, it is characterised in that:
A remove masonry wall metope impurity, to especially clean out masonry wall the foot of a wall contact inner corner trim with flooring at residual cement mortar Block;According to design requirement, determine that body of wall surface thickness and flooring ceramic tile surface with respect to slab surfaces absolute altitude, that is, further determine that water Cement mortar coat of plaster thickness and combination frid adjust height;
B combination frid adjusts height and obtains according to equation below calculating:
Combination frid adjusts height=ceramic tile surface with respect to slab surfaces absolute altitude+ceramic tile baseboard height;
If it is H that combination frid adjusts height, ceramic tile surface is h1, a height of h2 of ceramic tile baseboard with respect to slab surfaces absolute altitude, then Computing formula:H=h1+h2;
C adjusts height H according to the combination frid for calculating acquisition and sets, and opens movable heel brace to appropriate location, will combine frid Being arranged on will be carried out at masonry wall the foot of a wall of cement mortar coat of plaster construction;
D calculates the cement mortar coat of plaster thickness for obtaining according to design, and sectional carries out plastering construction;Pushed up by combining on frid Millimeter tick marks in plate plate face, control the thickness of cement mortar coat of plaster;Treat cement mortar plastering construction in section After finishing and checking preliminarily stabilised, dismountable combination frid continues next section plastering construction;And regular water seasoning;
E reserves, according to the ceramic tile surface for designing with respect to slab surfaces elevation location, the construction that good neat slurry applies paste layer and ceramic tile Thickness lays flooring bed course, then carries out tile laying construction using neat slurry, it is ensured that ceramic tile surface is with respect to slab surfaces absolute altitude H1 is consistent with design load;
F clears up debris at flooring surrounding the foot of a wall after the flooring ceramic tile maintenance of paving is firm, checks according to design requirement standby After ceramic tile baseboard height h2 is consistent with design load, ceramic tile baseboard paving construction is carried out using neat slurry;Guarantee ceramic tile ground Payment to a porter is concordant with masonry wall cement mortar coat of plaster;
G checks the masonry wall cement mortar coat of plaster no phenomenon such as hollowing, crack, can carry out finish coat construction, levelling including putty Layer, emulsion paint construction.
2. a kind of construction and decoration concealed installation ceramic tile lower margin line structure according to claim 1, it is characterised in that:The body of wall face Thickness degree is set to 25mm;The height of the ceramic tile baseboard is set to 10mm.
3. a kind of construction and decoration concealed installation ceramic tile baseboard structure construction technique according to claim 1, it is characterised in that:One Self-stabilization type height adjustable combination frid is planted, the combination frid includes L-type lower basal plate, inverted L shape top top board;Under the L-type Portion's substrate is made up of lower shoe and lower wall, is provided with hold-open catch in the lower wall;Inverted L shape top top board is by upper top Plate and upper side wall composition, the upper side wall is provided with hole clipping in differing heights position, and the hole clipping is mated with bayonet lock specification;Institute Inverted L shape top top board inner corner trim position is stated, is provided with movable heel brace;The lower wall of the combination frid is highly with upper side wall 120mm, the hole clipping spacing of the differing heights position is set to 10mm, and the actually used height of the combination frid is set to 120-220mm, the lower shoe of the combination frid is disposed as 25-50mm with upper plate width.
CN201610806133.7A 2016-09-06 2016-09-06 Building decoration concealed installation ceramic tile baseboard structure and construction process thereof Expired - Fee Related CN106437093B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610806133.7A CN106437093B (en) 2016-09-06 2016-09-06 Building decoration concealed installation ceramic tile baseboard structure and construction process thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610806133.7A CN106437093B (en) 2016-09-06 2016-09-06 Building decoration concealed installation ceramic tile baseboard structure and construction process thereof

Publications (2)

Publication Number Publication Date
CN106437093A true CN106437093A (en) 2017-02-22
CN106437093B CN106437093B (en) 2020-01-03

Family

ID=58164781

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610806133.7A Expired - Fee Related CN106437093B (en) 2016-09-06 2016-09-06 Building decoration concealed installation ceramic tile baseboard structure and construction process thereof

Country Status (1)

Country Link
CN (1) CN106437093B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859283A (en) * 2017-10-11 2018-03-30 詹焕辉 A kind of building(Ground)The construction method of face skirting waterproof
CN108708515A (en) * 2018-08-10 2018-10-26 金螳螂精装科技(苏州)有限公司 A kind of splits closing device
CN110528912A (en) * 2019-08-13 2019-12-03 广东良固住工科技有限公司 A kind of construction method of monoblock type bathroom
CN113503048A (en) * 2021-08-04 2021-10-15 北京城建六建设集团有限公司 Wall plastering reserved skirting line adjustable control device and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5595041A (en) * 1990-12-17 1997-01-21 Step Loc Corporation Carpet installation method using flexible carpet base
CN201539085U (en) * 2009-11-06 2010-08-04 黔西南州银燕地板有限公司 Foot line with environmental protection function
CN203113729U (en) * 2013-01-09 2013-08-07 都启虎 Base board bayonet structure with base board capable of being conveniently installed and replaced
CN204662895U (en) * 2015-04-15 2015-09-23 浙江建设职业技术学院 Payment to a porter removably
CN205399972U (en) * 2016-02-29 2016-07-27 清远市鑫叶新型装饰材料有限公司 Buckle connection mode baseboard
CN205476342U (en) * 2016-02-04 2016-08-17 青岛有住信息技术有限公司 Skirting line structure
CN205475724U (en) * 2016-03-25 2016-08-17 天津华锡环保科技有限公司 At bottom of compound energy -conserving board of light and floor ground connection structure
CN205857629U (en) * 2016-05-24 2017-01-04 刘玉贵 A kind of embedded timber floor skirting

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5595041A (en) * 1990-12-17 1997-01-21 Step Loc Corporation Carpet installation method using flexible carpet base
CN201539085U (en) * 2009-11-06 2010-08-04 黔西南州银燕地板有限公司 Foot line with environmental protection function
CN203113729U (en) * 2013-01-09 2013-08-07 都启虎 Base board bayonet structure with base board capable of being conveniently installed and replaced
CN204662895U (en) * 2015-04-15 2015-09-23 浙江建设职业技术学院 Payment to a porter removably
CN205476342U (en) * 2016-02-04 2016-08-17 青岛有住信息技术有限公司 Skirting line structure
CN205399972U (en) * 2016-02-29 2016-07-27 清远市鑫叶新型装饰材料有限公司 Buckle connection mode baseboard
CN205475724U (en) * 2016-03-25 2016-08-17 天津华锡环保科技有限公司 At bottom of compound energy -conserving board of light and floor ground connection structure
CN205857629U (en) * 2016-05-24 2017-01-04 刘玉贵 A kind of embedded timber floor skirting

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859283A (en) * 2017-10-11 2018-03-30 詹焕辉 A kind of building(Ground)The construction method of face skirting waterproof
CN108708515A (en) * 2018-08-10 2018-10-26 金螳螂精装科技(苏州)有限公司 A kind of splits closing device
CN110528912A (en) * 2019-08-13 2019-12-03 广东良固住工科技有限公司 A kind of construction method of monoblock type bathroom
CN110528912B (en) * 2019-08-13 2021-07-13 广东良固住工科技有限公司 Construction method of integral bathroom
CN113503048A (en) * 2021-08-04 2021-10-15 北京城建六建设集团有限公司 Wall plastering reserved skirting line adjustable control device and construction method thereof

Also Published As

Publication number Publication date
CN106437093B (en) 2020-01-03

Similar Documents

Publication Publication Date Title
CN208792663U (en) A kind of room finishing system
CN106437093A (en) Architectural decoration and finishing concealed installation tile skirting structure and construction technology thereof
CN106284929A (en) A kind of furring tile anti-hollowing edge patch construction method
CN104499614B (en) Wall heat-preservation integration point hanging system and mounting method thereof
CN217580989U (en) Assembled built-in integral bathroom structure
CN106223566A (en) A kind of construction method for indoor light blockwork stone material dry suspending
CN208235730U (en) Waterproof construction with surrounding edge pedestal
CN204126156U (en) For ceiling and the closing-in structure vertically between metope
CN110499904A (en) Indoor wall face brick base exempts from plaster post-grouting wet combining construction method and vertical adjustment upright bar
CN109864644A (en) A kind of toilet shower tray and its construction method
CN205063277U (en) Zero clearance mounting structure between marble or ceramic tile skirting line and wall body
CN208202203U (en) A kind of toilet wall body structure
CN206448501U (en) A kind of floor covering layers locating rack
CN108978851A (en) A kind of improvement room finishing system and decoration method
CN206646784U (en) A kind of ceramic tile mounting bracket of house ornamentation
CN211007488U (en) Indoor ground overhead structure
CN203783097U (en) Integrated bathroom ground
CN208347208U (en) A kind of new indoor walling system
CN207332617U (en) A kind of doorframe structure
CN109914812A (en) A kind of floor leveling construction accessory part and its application method
CN110067352A (en) A kind of decoration of exterior wall method and device
CN207739536U (en) A kind of indoor wall system
CN202899562U (en) Paving structure of thin-type floor decorative materials
CN204252494U (en) Reduce deviation building structure
CN112324106A (en) Combined structure for wall decoration

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190923

Address after: 524400 No. 36 West Construction Avenue, Lianjiang City, Zhanjiang City, Guangdong Province

Applicant after: Guangdong Qiangxiong Construction Group Co.,Ltd.

Address before: 511400 Guangdong city of Guangzhou province Panyu District Xiaoguwei Street Outer Ring Road No. 232 building 13 B220-5

Applicant before: GUANGDONG WANNIU INTELLECTUAL PROPERTY OPERATION CO.,LTD.

GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200103