CN106153288A - 一种风洞试验用攻角机构及其波纹管分段式支撑机构 - Google Patents
一种风洞试验用攻角机构及其波纹管分段式支撑机构 Download PDFInfo
- Publication number
- CN106153288A CN106153288A CN201610715092.0A CN201610715092A CN106153288A CN 106153288 A CN106153288 A CN 106153288A CN 201610715092 A CN201610715092 A CN 201610715092A CN 106153288 A CN106153288 A CN 106153288A
- Authority
- CN
- China
- Prior art keywords
- column
- corrugated tube
- supporting mechanism
- attack angle
- wind tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01M—TESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
- G01M9/00—Aerodynamic testing; Arrangements in or on wind tunnels
- G01M9/02—Wind tunnels
- G01M9/04—Details
Abstract
本发明属于风洞试验设备技术领域,公开了一种波纹管分段式支撑机构,用于支撑风洞试验用攻角机构;包括:第一立柱、第二立柱以及波纹管;所述第一立柱固定在所述第二立柱顶端;所述波纹管套接在所述第一立柱和所述第二立柱外;所述第一立柱顶端固定在所述攻角机构底部。本发明提供的支撑结构,能够简化波纹管维护操作。
Description
技术领域
本发明涉及风洞试验设备技术领域,特别涉及一种风洞试验用攻角机构及其波纹管分段式支撑机构。
背景技术
目前试验段攻角机构的支撑立柱一般采用整体式结构,即一根支撑立柱一端连接攻角机构底座下法兰、一端连接地基法兰。
但是这种一体式支撑结构导致更换维修波纹管时,需要将试验段前部上下壳体及攻角设备大幅向上抬升,然后将支撑立柱上下端紧固结构拆除,而后将大重量支撑立柱平移,而后再拆除更换波纹管,工作量大且维修劳动强度大。
发明内容
本发明提供一种风洞试验用攻角机构及其波纹管分段式支撑机构,解决了现有技术中风洞试验段中的支撑结构造成,波纹管维护更换劳动强度大,操作复杂,工作量大。
为解决上述技术问题,本发明提供了一种波纹管分段式支撑机构,用于支撑风洞试验用攻角机构;包括:第一立柱、第二立柱以及波纹管;
所述第一立柱固定在所述第二立柱顶端;
所述波纹管套接在所述第一立柱和所述第二立柱外;
所述第一立柱顶端固定在所述攻角机构底部。
进一步地,所述支撑机构还包括:紧固法兰;
所述紧固法兰设置在所述第一立柱和所述第二立柱之间,紧固所述第一立柱和所述第二立柱。
进一步地,所述支撑机构还包括:顶接法兰;
所述顶接法兰固定在所述第一立柱顶端,用于连接所述攻角机构底部。
进一步地,所述支撑机构还包括:立柱底座;
所述第二立柱底端固定在所述立柱底座上。
进一步地,所述支撑机构还包括:密封结构;
所述密封结构设置在所述波纹管底部与所述立柱底座之间,密封波纹管与所述支柱底座。
一种风洞试验用攻角机构,包括:支架、位于所述支架上的攻角设备以及支撑机构;
所述支撑机构包括:第一立柱、第二立柱以及波纹管;
所述第一立柱固定在所述第二立柱顶端;
所述波纹管套接在所述第一立柱和所述第二立柱外;
所述第一立柱顶端固定在所述攻角机构底部。
进一步地,所述支撑机构还包括:紧固法兰;
所述紧固法兰设置在所述第一立柱和所述第二立柱之间,紧固所述第一立柱和所述第二立柱。
进一步地,所述支撑机构还包括:顶接法兰;
所述顶接法兰固定在所述第一立柱顶端,用于连接所述攻角机构底部。
进一步地,所述支撑机构还包括:立柱底座;
所述第二立柱底端固定在所述立柱底座上。
进一步地,所述支撑机构还包括:密封结构;
所述密封结构设置在所述波纹管底部与所述立柱底座之间,密封波纹管与所述支柱底座。
本申请实施例中提供的一个或多个技术方案,至少具有如下技术效果或优点:
本申请实施例中提供的波纹管分段式支撑机构,通过设置分段式立柱结构;在波纹管更换维护操作时,将波纹管压下,拆卸第二立柱并整体移除,更换后在平移安装。过程中,大幅降低操作重量和强度,使得劳动强度大幅降低,提升了工作效率。
附图说明
图1为本发明实施例提供的立柱结构示意图;
图2为本发明实施例提供的波纹管分段式支撑机构主视图;
图3为图2的剖视图。
具体实施方式
本申请实施例通过提供一种风洞试验用攻角机构及其波纹管分段式支撑机构,解决了现有技术中风洞试验段中的支撑结构造成,波纹管维护更换劳动强度大,操作复杂,工作量大;达到了提升工作效率,降低劳动强度和操作难度的技术效果。
为了更好的理解上述技术方案,下面将结合说明书附图以及具体的实施方式对上述技术方案进行详细说明,应当理解本发明实施例以及实施例中的具体特征是对本申请技术方案的详细的说明,而不是对本申请技术方案的限定,在不冲突的情况下,本申请实施例以及实施例中的技术特征可以相互组合。
参见图1和图3,本发明实施例提供的一种波纹管分段式支撑机构,用于支撑风洞试验用攻角机构;包括:第一立柱1、第二立柱2以及波纹管4。
所述第一立柱1固定在所述第二立柱2顶端;所述波纹管4套接在所述第一立柱1和所述第二立柱2外;所述第一立柱1顶端固定在所述攻角机构底部。
具体来说,进行波纹管4更换操作时,将波纹管4压下到第一立柱1和第二立柱2的紧固位置以下,拆除紧固结构;将第二立柱2连同波纹管4水平移出,更换波纹管4,而后重新移到第一立柱1下方紧固,完成更换操作。这个过程,大幅降低了抬升距离和平移重量,拆装更为简化,使得波纹管的更化操作,劳动强度大幅降低,工作效率大幅提升。
为了便于两个立柱的拆装,优选的,所述支撑机构还包括:紧固法兰3。
所述紧固法兰3设置在所述第一立柱1和所述第二立柱2之间,紧固所述第一立柱1和所述第二立柱2。拆装操作,仅在于操作法兰,操作简化,效率更高。
所述支撑机构还包括:顶接法兰;所述顶接法兰固定在所述第一立柱1顶端,用于连接所述攻角机构底部,增强稳定性。
优选的,所述支撑机构还包括:立柱底座5;所述第二立柱2底端固定在所述立柱底座5上,从而实现立柱的稳定支撑,提升支撑可靠性和稳定性。
进一步地,所述支撑机构还包括:密封结构;所述密封结构设置在所述波纹管底部与所述立柱底座之间,密封波纹管与所述支柱底座;以适应风洞试验过程的真空需要。
本实施例还提供了一种基于上述支撑机构的风洞试验用攻角机构。
一种风洞试验用攻角机构,包括:支架6、位于所述支架6上的攻角设备以及支撑机构。
所述支撑机构包括:第一立柱1、第二立柱2以及波纹管4。
所述第一立柱1固定在所述第二立柱2顶端;所述波纹管4套接在所述第一立柱1和所述第二立柱2外;所述第一立柱1顶端固定在所述攻角机构底部。
具体来说,进行波纹管4更换操作时,将波纹管4压下到第一立柱1和第二立柱2的紧固位置以下,拆除紧固结构;将第二立柱2连同波纹管4水平移出,更换波纹管4,而后重新移到第一立柱1下方紧固,完成更换操作。这个过程,大幅降低了抬升距离和平移重量,拆装更为简化,使得波纹管的更化操作,劳动强度大幅降低,工作效率大幅提升。
为了便于两个立柱的拆装,优选的,所述支撑机构还包括:紧固法兰3。
所述紧固法兰3设置在所述第一立柱1和所述第二立柱2之间,紧固所述第一立柱1和所述第二立柱2。拆装操作,仅在于操作法兰,操作简化,效率更高。
所述支撑机构还包括:顶接法兰;所述顶接法兰固定在所述第一立柱1顶端,用于连接所述攻角机构底部,增强稳定性。
优选的,所述支撑机构还包括:立柱底座5;所述第二立柱2底端固定在所述立柱底座5上,从而实现立柱的稳定支撑,提升支撑可靠性和稳定性。
进一步地,所述支撑机构还包括:密封结构;所述密封结构设置在所述波纹管底部与所述立柱底座之间,密封波纹管与所述支柱底座;以适应风洞试验过程的真空需要。
本申请实施例中提供的一个或多个技术方案,至少具有如下技术效果或优点:
本申请实施例中提供的波纹管分段式支撑机构,通过设置分段式立柱结构;在波纹管更换维护操作时,将波纹管压下,拆卸第二立柱并整体移除,更换后在平移安装。过程中,大幅降低操作重量和强度,使得劳动强度大幅降低,提升了工作效率。
最后所应说明的是,以上具体实施方式仅用以说明本发明的技术方案而非限制,尽管参照实例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,而不脱离本发明技术方案的精神和范围,其均应涵盖在本发明的权利要求范围当中。
Claims (10)
1.一种波纹管分段式支撑机构,用于支撑风洞试验用攻角机构;其特征在于,包括:第一立柱、第二立柱以及波纹管;
所述第一立柱固定在所述第二立柱顶端;
所述波纹管套接在所述第一立柱和所述第二立柱外;
所述第一立柱顶端固定在所述攻角机构底部。
2.如权利要求1所述的波纹管分段式支撑机构,其特征在于,所述支撑机构还包括:紧固法兰;
所述紧固法兰设置在所述第一立柱和所述第二立柱之间,紧固所述第一立柱和所述第二立柱。
3.如权利要求2所述的波纹管分段式支撑机构,其特征在于,所述支撑机构还包括:顶接法兰;
所述顶接法兰固定在所述第一立柱顶端,用于连接所述攻角机构底部。
4.如权利要求3所述的波纹管分段式支撑机构,其特征在于,所述支撑机构还包括:立柱底座;
所述第二立柱底端固定在所述立柱底座上。
5.如权利要求4所述的波纹管分段式支撑机构,其特征在于,所述支撑机构还包括:密封结构;
所述密封结构设置在所述波纹管底部与所述立柱底座之间,密封波纹管与所述支柱底座。
6.一种风洞试验用攻角机构,其特征在于,包括:支架、位于所述支架上的攻角设备以及支撑机构;
所述支撑机构包括:第一立柱、第二立柱以及波纹管;
所述第一立柱固定在所述第二立柱顶端;
所述波纹管套接在所述第一立柱和所述第二立柱外;
所述第一立柱顶端固定在所述攻角机构底部。
7.如权利要求6所述的风洞试验用攻角机构,其特征在于,所述支撑机构还包括:紧固法兰;
所述紧固法兰设置在所述第一立柱和所述第二立柱之间,紧固所述第一立柱和所述第二立柱。
8.如权利要求7所述的风洞试验用攻角机构,其特征在于,所述支撑机构还包括:顶接法兰;
所述顶接法兰固定在所述第一立柱顶端,用于连接所述攻角机构底部。
9.如权利要求8所述的风洞试验用攻角机构,其特征在于,所述支撑机构还包括:立柱底座;
所述第二立柱底端固定在所述立柱底座上。
10.如权利要求9所述的风洞试验用攻角机构,其特征在于,所述支撑机构还包括:密封结构;
所述密封结构设置在所述波纹管底部与所述立柱底座之间,密封波纹管与所述支柱底座。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610715092.0A CN106153288B (zh) | 2016-08-24 | 2016-08-24 | 一种风洞试验用攻角机构及其波纹管分段式支撑机构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610715092.0A CN106153288B (zh) | 2016-08-24 | 2016-08-24 | 一种风洞试验用攻角机构及其波纹管分段式支撑机构 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106153288A true CN106153288A (zh) | 2016-11-23 |
CN106153288B CN106153288B (zh) | 2018-10-12 |
Family
ID=57342777
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610715092.0A Active CN106153288B (zh) | 2016-08-24 | 2016-08-24 | 一种风洞试验用攻角机构及其波纹管分段式支撑机构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106153288B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111426447A (zh) * | 2020-05-08 | 2020-07-17 | 湖北三江航天红阳机电有限公司 | 一种风洞试验段底部支撑装置 |
CN113029497A (zh) * | 2021-03-26 | 2021-06-25 | 中国空气动力研究与发展中心超高速空气动力研究所 | 一种用于大口径高超声速风洞的模块化试验段 |
CN113074174A (zh) * | 2021-04-21 | 2021-07-06 | 中国科学院力学研究所 | 激波风洞试验舱和波纹管连接方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05172691A (ja) * | 1991-12-25 | 1993-07-09 | Ishikawajima Harima Heavy Ind Co Ltd | 衝撃波風洞試験装置 |
JPH10185759A (ja) * | 1996-12-27 | 1998-07-14 | Nkk Corp | 空気力測定装置並びにその測定装置を用いた揚力・モーメント測定システム装置 |
CN201487467U (zh) * | 2009-06-24 | 2010-05-26 | 河南送变电建设公司 | 一种波纹管 |
CN102518891A (zh) * | 2011-12-22 | 2012-06-27 | 安徽省蚌埠华益导电膜玻璃有限公司 | 真空管道连接装置 |
CN103115746A (zh) * | 2013-01-21 | 2013-05-22 | 中国科学院力学研究所 | 一种激波风洞模型支撑装置 |
CN105157949A (zh) * | 2015-10-16 | 2015-12-16 | 中国空气动力研究与发展中心低速空气动力研究所 | 一种模型迎角机构 |
CN206038271U (zh) * | 2016-08-24 | 2017-03-22 | 湖北三江航天红阳机电有限公司 | 一种风洞试验用攻角机构及其波纹管分段式支撑机构 |
-
2016
- 2016-08-24 CN CN201610715092.0A patent/CN106153288B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05172691A (ja) * | 1991-12-25 | 1993-07-09 | Ishikawajima Harima Heavy Ind Co Ltd | 衝撃波風洞試験装置 |
JPH10185759A (ja) * | 1996-12-27 | 1998-07-14 | Nkk Corp | 空気力測定装置並びにその測定装置を用いた揚力・モーメント測定システム装置 |
CN201487467U (zh) * | 2009-06-24 | 2010-05-26 | 河南送变电建设公司 | 一种波纹管 |
CN102518891A (zh) * | 2011-12-22 | 2012-06-27 | 安徽省蚌埠华益导电膜玻璃有限公司 | 真空管道连接装置 |
CN103115746A (zh) * | 2013-01-21 | 2013-05-22 | 中国科学院力学研究所 | 一种激波风洞模型支撑装置 |
CN105157949A (zh) * | 2015-10-16 | 2015-12-16 | 中国空气动力研究与发展中心低速空气动力研究所 | 一种模型迎角机构 |
CN206038271U (zh) * | 2016-08-24 | 2017-03-22 | 湖北三江航天红阳机电有限公司 | 一种风洞试验用攻角机构及其波纹管分段式支撑机构 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111426447A (zh) * | 2020-05-08 | 2020-07-17 | 湖北三江航天红阳机电有限公司 | 一种风洞试验段底部支撑装置 |
CN111426447B (zh) * | 2020-05-08 | 2021-10-08 | 湖北三江航天红阳机电有限公司 | 一种风洞试验段底部支撑装置 |
CN113029497A (zh) * | 2021-03-26 | 2021-06-25 | 中国空气动力研究与发展中心超高速空气动力研究所 | 一种用于大口径高超声速风洞的模块化试验段 |
CN113074174A (zh) * | 2021-04-21 | 2021-07-06 | 中国科学院力学研究所 | 激波风洞试验舱和波纹管连接方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106153288B (zh) | 2018-10-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106153288A (zh) | 一种风洞试验用攻角机构及其波纹管分段式支撑机构 | |
CN104929148B (zh) | 风力发电塔基础环基础的倒装加固系统及其加固方法 | |
CN209457425U (zh) | 一种古建筑墙体修复支架 | |
CN102393003B (zh) | 一种蒸汽发生器组装方法 | |
CN206038271U (zh) | 一种风洞试验用攻角机构及其波纹管分段式支撑机构 | |
CN102679139B (zh) | 煤气柜悬索式柔性活塞拱及橡胶膜密封煤气柜 | |
JP2015034627A (ja) | ガスホルダの修繕方法 | |
CN106223377A (zh) | 一种用于逆作法立柱垂直度调整的叠拼式加强型调垂机构 | |
CN206326887U (zh) | 一种液压机 | |
CN104878146B (zh) | 用于重力除尘器顶部波纹补偿器更换的施工方法 | |
CN205421366U (zh) | 一种用于逆作法立柱垂直度调整的叠拼式加强型调垂机构 | |
CN206234610U (zh) | 减震器充气机 | |
CN205476584U (zh) | 一种可拆卸支撑结构 | |
CN205709666U (zh) | 一种臂架安装支撑装置 | |
CN205781955U (zh) | 由曼型煤气柜改造的单段式橡胶膜密封型煤气柜 | |
CN205735023U (zh) | 一种电力巡检机器人多节伸缩云台检测系统 | |
CN205654332U (zh) | 撬装式二氧化碳输气装置 | |
CN107270124B (zh) | 一种方便移动、取放的气瓶规范化管理装置 | |
CN206998186U (zh) | 简易液压油缸修复装置 | |
CN106049845A (zh) | 滑动提升架以及采用该滑动提升架施工的方法 | |
CN108265964A (zh) | 设液压支撑脚指示灯的爬架 | |
CN107355244B (zh) | 采充联合液压支架系统 | |
CN205412325U (zh) | 一种层析装置 | |
CN201218415Y (zh) | 从中间进煤气的布帘干式煤气柜 | |
CN108217521A (zh) | 一种铁塔液压提升装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |