CN105625176A - 支架预压施工工艺 - Google Patents
支架预压施工工艺 Download PDFInfo
- Publication number
- CN105625176A CN105625176A CN201410580843.3A CN201410580843A CN105625176A CN 105625176 A CN105625176 A CN 105625176A CN 201410580843 A CN201410580843 A CN 201410580843A CN 105625176 A CN105625176 A CN 105625176A
- Authority
- CN
- China
- Prior art keywords
- suspension ring
- precompressed
- size
- concrete block
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
支架预压施工工艺,在平整的场地上,铺设一层彩条布,测量放样,按尺寸支设模板,分层浇筑混凝土,浇筑至预埋吊环底部以上20cm时,插入预埋吊环,校正位置,继续浇筑完成剩余混凝土,顶面正中心预留10*10*10cm吊环槽,拆模养护;严格控制预制块的尺寸和平整度,确保构件的重量与设计相一致;存放时,场地应平整,金字塔是摆放,不得倾斜放置。本发明的优点在于:本发明中,利用定尺寸长方体混凝土块易于码放和质量可控的原理,合理选择吊点和吊环设施,使混凝土块成为支架预压最快速高效的一种荷载替代物。周转使用节约材料,经济。结构简单,安拆方便,环保。性能满足安全质量标准要求。
Description
技术领域
本发明涉及一种施工工艺,具体地说是支架预压施工工艺。
背景技术
青荣城际铁路QRZH-I标段第三项目部施工跨青威、青银、济青、上下行联络线等五座特大桥,连续梁多,支架多。支架预压时支架使用前必须进行的一个检测项目,通过预压对支架的非弹性变形进行消除,对支架的承载力进行了检测。混凝土预制块在使用过程中具有良好的周转使用性能。
发明内容
为解决上述问题,本发明的目的是提供一种支架预压施工工艺。
本发明为实现上述目的,通过以下技术方案实现:支架预压施工工艺,在平整的场地上,铺设一层彩条布,测量放样,按尺寸支设模板,分层浇筑混凝土,浇筑至预埋吊环底部以上20cm时,插入预埋吊环,校正位置,继续浇筑完成剩余混凝土,顶面正中心预留10*10*10cm吊环槽,拆模养护;严格控制预制块的尺寸和平整度,确保构件的重量与设计相一致;存放时,场地应平整,金字塔是摆放,不得倾斜放置。
为进一步实现本发明的目的,还可以采用以下技术方案:支架搭设完成并进行初步验收合格后,按照方案和技术交底的要求进行分级加载预压,预压块的数量、堆放高度、放置方法、预压时间均须符合要求;吊装、码放的作业人员与起重机司机等必须经培训考核合格后方可上岗;挂钩必须牢固可靠。预压完成后运至下一工点继续预压;使用过程中,对预压块进行常规检查,若发现吊环和构件有损坏的,应及时废弃处理,不得再次使用。
本发明的优点在于:本发明中,利用定尺寸长方体混凝土块易于码放和质量可控的原理,合理选择吊点和吊环设施,使混凝土块成为支架预压最快速高效的一种荷载替代物。周转使用节约材料,经济。结构简单,安拆方便,环保。性能满足安全质量标准要求。
附图说明
图1是本发明结构示意图。
附图标记:1混凝土块2吊环凹槽3预埋吊环。
具体实施方式
支架预压施工工艺,在平整的场地上,铺设一层彩条布,测量放样,按尺寸支设模板,分层浇筑混凝土,浇筑至预埋吊环底部以上20cm时,插入预埋吊环,校正位置,继续浇筑完成剩余混凝土,顶面正中心预留10*10*10cm吊环槽,拆模养护;严格控制预制块的尺寸和平整度,确保构件的重量与设计相一致;存放时,场地应平整,金字塔是摆放,不得倾斜放置。
支架搭设完成并进行初步验收合格后,按照方案和技术交底的要求进行分级加载预压,预压块的数量、堆放高度、放置方法、预压时间均须符合要求;吊装、码放的作业人员与起重机司机等必须经培训考核合格后方可上岗;挂钩必须牢固可靠。
预压完成后运至下一工点继续预压;使用过程中,对预压块进行常规检查,若发现吊环和构件有损坏的,应及时废弃处理,不得再次使用。
混凝土块采用C30混凝土浇筑,每块长0.8m,高0.7m,宽0.8m,顶面中心留0.10*0.10*0.10m,预埋HRB335Φ20mm“几”字型吊环。
利用定尺寸长方体混凝土块易于码放和质量可控的原理,合理选择吊点和吊环设施,使混凝土块成为支架预压最快速高效的一种荷载替代物。
优点:周转使用节约材料,经济。结构简单,安拆方便,环保。性能满足安全质量标准要求。
混凝土预压块经过多支架预压使用,其良好的码放性能和质量分级可控性能得到了良好的展现,大大节约了时间和人力物力投入,加快了施工生产速度,得到了业内各界广泛的好评。
本发明的技术方案并不限制于本发明所述的实施例的范围内。本发明未详尽描述的技术内容均为公知技术。
Claims (3)
1.支架预压施工工艺,其特征在于:在平整的场地上,铺设一层彩条布,测量放样,按尺寸支设模板,分层浇筑混凝土,浇筑至预埋吊环底部以上20cm时,插入预埋吊环,校正位置,继续浇筑完成剩余混凝土,顶面正中心预留10*10*10cm吊环槽,拆模养护;严格控制预制块的尺寸和平整度,确保构件的重量与设计相一致;存放时,场地应平整,金字塔是摆放,不得倾斜放置。
2.根据权利要求1所述的支架预压施工工艺,其特征在于:支架搭设完成并进行初步验收合格后,按照方案和技术交底的要求进行分级加载预压,预压块的数量、堆放高度、放置方法、预压时间均须符合要求;吊装、码放的作业人员与起重机司机等必须经培训考核合格后方可上岗;挂钩必须牢固可靠。
3.根据权利要求1所述的支架预压施工工艺,其特征在于:预压完成后运至下一工点继续预压;使用过程中,对预压块进行常规检查,若发现吊环和构件有损坏的,应及时废弃处理,不得再次使用。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410580843.3A CN105625176A (zh) | 2014-10-27 | 2014-10-27 | 支架预压施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410580843.3A CN105625176A (zh) | 2014-10-27 | 2014-10-27 | 支架预压施工工艺 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105625176A true CN105625176A (zh) | 2016-06-01 |
Family
ID=56040487
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410580843.3A Pending CN105625176A (zh) | 2014-10-27 | 2014-10-27 | 支架预压施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105625176A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106592437A (zh) * | 2016-12-16 | 2017-04-26 | 曹晓滨 | 一种现浇混凝土桥梁的现浇施工方法 |
CN107460827A (zh) * | 2017-08-09 | 2017-12-12 | 中国十七冶集团有限公司 | 一种现浇箱梁模板支撑体系预压的方法 |
-
2014
- 2014-10-27 CN CN201410580843.3A patent/CN105625176A/zh active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106592437A (zh) * | 2016-12-16 | 2017-04-26 | 曹晓滨 | 一种现浇混凝土桥梁的现浇施工方法 |
CN106592437B (zh) * | 2016-12-16 | 2018-02-16 | 曹晓滨 | 一种现浇混凝土桥梁的现浇施工方法 |
CN107460827A (zh) * | 2017-08-09 | 2017-12-12 | 中国十七冶集团有限公司 | 一种现浇箱梁模板支撑体系预压的方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105603917B (zh) | 一种护栏钢筋的制作胎架及护栏的施工方法 | |
CN108277716A (zh) | 一种可循环利用的装配式混凝土预制道路及其施工工艺 | |
CN107974944A (zh) | 一种y型公铁两用桥梁桥面板吊装装置及吊装方法 | |
CN106192781A (zh) | 预应力单箱三室板梁的拆除方法 | |
CN103787087A (zh) | 一种预制桩钢筋笼自动堆放系统 | |
CN108004929A (zh) | 一种h型公铁两用桥梁桥面板吊装装置及吊装方法 | |
CN104947561A (zh) | 预制混凝土拼装道路施工方法 | |
CN204876601U (zh) | 滑轮式悬挑卸料平台 | |
CN105625176A (zh) | 支架预压施工工艺 | |
CN102633126A (zh) | 辊压彩瓦生产设备中的自动码垛系统 | |
CN104675112A (zh) | 用于建筑楼梯间一次浇筑成形的钢楼梯模板及施工方法 | |
CN202401753U (zh) | 一种滑模装置 | |
CN105936423A (zh) | 一种烧结砖码坯机 | |
CN105480477A (zh) | 一种升降式砖块自动打包机 | |
CN103243912B (zh) | 多层无板框架结构施工方法 | |
JP2007205130A (ja) | 橋梁側方からのエレクションガータによる桁架設工法 | |
CN107313356A (zh) | 一种双层桥建造的运梁方法 | |
CN204530499U (zh) | 用于公路桥梁预制梁板混凝土布料的自动行走装置 | |
CN206940278U (zh) | 一种o形龙门吊运装置 | |
CN108675116A (zh) | Pc构件的施工方法 | |
CN115506371A (zh) | 一种深基坑超高内支撑拆除的施工方法 | |
CN203903414U (zh) | 一种传送装置上的限宽装置 | |
CN106853943A (zh) | 一种小型船舶检修吊运装置 | |
CN105971295A (zh) | 一种高层建筑楼层卸料装置 | |
CN105568859B (zh) | 一种大吨位钢梁跨堤转运方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |