CN104196178B - Hollow double structure layer water-proof roofing and construction method thereof - Google Patents

Hollow double structure layer water-proof roofing and construction method thereof Download PDF

Info

Publication number
CN104196178B
CN104196178B CN201410395572.4A CN201410395572A CN104196178B CN 104196178 B CN104196178 B CN 104196178B CN 201410395572 A CN201410395572 A CN 201410395572A CN 104196178 B CN104196178 B CN 104196178B
Authority
CN
China
Prior art keywords
lower floor
upper strata
waterproofing course
cast
parapet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410395572.4A
Other languages
Chinese (zh)
Other versions
CN104196178A (en
Inventor
康杰
孙翔
李春宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Petroleum East China
Original Assignee
China University of Petroleum East China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Petroleum East China filed Critical China University of Petroleum East China
Priority to CN201410395572.4A priority Critical patent/CN104196178B/en
Publication of CN104196178A publication Critical patent/CN104196178A/en
Application granted granted Critical
Publication of CN104196178B publication Critical patent/CN104196178B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention belongs to building engineering field, particularly, relate to a kind of hollow double structure layer water-proof roofing and construction method thereof.Hollow double structure layer water-proof roofing, comprising: substructure waterproofing course, superstructure waterproofing course, and substructure waterproofing course and superstructure waterproofing course carry out anatomical connectivity by deck post, vapour barrier in the middle of being formed between substructure waterproofing course, superstructure waterproofing course.The present invention fundamentally can solve roof leakaging problem, and relative to occurring that seepage reprocessing wants economical a lot; Middle vapour barrier also has the effect of heat-insulation and heat-preservation, makes top layer cool in summer and warm in winter.

Description

Hollow double structure layer water-proof roofing and construction method thereof
Technical field
The invention belongs to building engineering field, particularly, relate to a kind of hollow double structure layer water-proof roofing and construction method thereof.
Background technology
Roof leakaging problem annoyings vast building circle personage always.Each R&D institution have developed a lot of waterproofing materials for this reason, and relevant departments also summarize some roof waterproof ways, but all fundamentally can not solve roof leakaging problem.Although existing waterproofing materials and waterproofing process can play a role within a period of time, often do not reach reasonable using period and just there will be seepage, the time can playing waterproof action from Practical Project is very short.No matter be that waterproof coiled material or coating waterproofing all can not effect a radical cure roof leakage from waterproofing materials.Coiled material waterproof roof is a kind of main method of current roof waterproof, and its shortcoming is easy aging poor durability, repairs and look for Lou difficulty when there is seepage.The another one problem that seepage is brought be exactly rainwater enter insulation layer cause insulation greatly lost efficacy.Therefore present real estate market, top layer is cheaply more a lot of than other layer.
Summary of the invention
For the deficiency of prior art and method, the invention provides a kind of hollow double structure layer waterproof roof structure and construction method thereof, effectively can eradicate roof leakaging problem, have that construction is simple, insulation, heat insulation advantage.
For achieving the above object, the present invention adopts following proposal:
Hollow double structure layer water-proof roofing, comprising: substructure waterproofing course, superstructure waterproofing course, and substructure waterproofing course and superstructure waterproofing course carry out anatomical connectivity by deck post, vapour barrier in the middle of being formed between substructure waterproofing course, superstructure waterproofing course.
Relative to prior art, the present invention has following beneficial effect: fundamentally can solve roof leakaging problem, and relative to occurring that seepage reprocessing wants economical a lot; Middle vapour barrier also has the effect of heat-insulation and heat-preservation, makes top layer cool in summer and warm in winter.
Accompanying drawing explanation
Fig. 1 is hollow double structure layer waterproof roof structure schematic diagram;
Fig. 2 is the leader structural representation of hollow double structure layer waterproof roof structure;
In figure: 1, lower floor's reinforced concrete roof board, 2, lower floor's leveling layer, 3, lower floor's insulation layer; 4, lower floor's waterproofing course, 5, lower floor's topping, 6, middle vapour barrier; 7, sliding sash, 8, top reinforcement concrete slab, 9, upper strata leveling layer; 10, upper strata waterproofing course, 11, upper strata topping, 12, lower floor's leader; 13, lower floor's cast-iron bend, 14, upper strata leader, 15, upper strata cast-iron bend; 16, deck post, 17, parapet, 18, upper strata space enclosing structure.
Detailed description of the invention:
As shown in Figure 1, hollow double structure layer water-proof roofing, comprise: substructure waterproofing course, superstructure waterproofing course, substructure waterproofing course and superstructure waterproofing course carry out anatomical connectivity by deck post 16, vapour barrier 6 in the middle of being formed between substructure waterproofing course, superstructure waterproofing course; Whether the height of middle vapour barrier 6 can according to being accessible roof adjustment; Wherein:
Substructure waterproofing course, comprising: lower floor's reinforced concrete roof board 1, lower floor's leveling layer 2, lower floor's insulation layer 3, lower floor's waterproofing course 4, lower floor's topping 5, and substructure waterproofing course is supported by frame column; Lower floor's reinforced concrete roof board 1, lower floor's leveling layer 2, lower floor's insulation layer 3, lower floor's waterproofing course 4, lower floor's topping 5 are cascading from top to bottom; Parapet 17 is positioned on lower floor's reinforced concrete roof board 1, and concordant with external wall; Lower floor's cast-iron bend 13 is located at the intersection of parapet 17 and lower floor's topping 5, and runs through parapet 17, as shown in Figure 1; The upper end of lower floor's leader 12 is arranged on lower floor's cast-iron bend 13, and lower end extends to construction bottom; Parapet 17 is provided with sliding sash 7 and can opens sliding sash 7 summer, form air flowing by middle vapour barrier 6, just can keep the ventilation of roofing, play heat insulation effect, solve the problem on hot roof; Close sliding sash 7 winter, form the middle vapour barrier 6 closed, play insulation effect.
Superstructure waterproofing course, comprising: top reinforcement concrete slab 8, upper strata leveling layer 9, upper strata waterproofing course 10, upper strata topping 11; Deck post 16 is upwards extended to form by top-level boxes trestle, top with top reinforcement concrete slab 8 is whole water together with, bottom with lower floor reinforced concrete roof board 1 is whole water together with; Top reinforcement concrete slab 8, upper strata leveling layer 9, upper strata waterproofing course 10, upper strata topping 11 are cascading from top to bottom, and upper strata space enclosing structure 18 is located on top reinforcement concrete slab 8, and concordant with external wall; Upper strata cast-iron bend 15 is located at the intersection of upper strata space enclosing structure 18 and upper strata topping 11, and runs through upper strata space enclosing structure 18, as shown in Figure 1; The upper end of upper strata leader 14 is arranged on upper strata cast-iron bend 15, and lower end extends in the gutter spout funnel on lower floor's leader 12 top, as shown in Figure 2; Upper structurally waterproof layer is supported by deck post 16.
Being formed on nominal " roof " by setting up top reinforcement concrete slab 8, upper strata leveling layer 9, upper strata waterproofing course 10 and upper strata topping 11, playing the effect of awning, therefore fundamentally solving roof leakaging problem.
Rainwater enters upper strata cast iron pipe 15 through superstructure waterproofing course under normal circumstances, then enters upper strata leader 14 and finally enters lower floor's leader 12 and drain.A small amount of rainwater may be had after the time limit is permanent and penetrate into middle vapour barrier, then because the effect of waterproofing course 4 enters lower floor's leader 12 by lower floor's cast-iron bend 13.
The construction method of above-mentioned hollow double structure layer water-proof roofing, comprises following construction sequence:
1, build lower floor's reinforced concrete roof board 1, then build parapet 17 by laying bricks or stones, when building parapet 17 by laying bricks or stones, reserving hole is to install lower floor's cast-iron bend 13, leaves certain distance to install sliding sash 7 between parapet 17 and superstructure waterproofing course; Lower floor's reinforced concrete roof board 1 is laid lower floor's leveling layer 2, lower floor's insulation layer 3, lower floor's waterproofing course 4, lower floor's topping 5 successively.
2, build deck post 16 and build top reinforcement concrete slab 8 in pre-designed position, top reinforcement concrete slab 8 takes turns doing upper strata leveling layer 9, upper strata waterproofing course 10, upper strata topping 11; The construction of upper strata space enclosing structure 18 is carried out in place concordant with external wall on top reinforcement concrete slab 8, when carrying out the construction of upper strata space enclosing structure 18, reserving hole installs upper strata cast-iron bend 15, and reserving hole will keep vertical with the reserving hole of substructure waterproofing course cast-iron bend on vertical plane.
3, between parapet 17 and superstructure waterproofing course, all sliding sash 7 is installed; The upper end of upper strata leader 14 is arranged on upper strata cast-iron bend 15, and lower end reaches in the gutter spout funnel of lower floor's leader 12; The upper end of lower floor's leader 12 is arranged on lower floor's cast-iron bend 13, and lower end extends to the aproll place of building.

Claims (6)

1. a hollow double structure layer water-proof roofing, comprise: substructure waterproofing course, superstructure waterproofing course, it is characterized in that: substructure waterproofing course and superstructure waterproofing course carry out anatomical connectivity by deck post, vapour barrier in the middle of being formed between substructure waterproofing course, superstructure waterproofing course;
Substructure waterproofing course, comprising: lower floor's reinforced concrete roof board, lower floor's leveling layer, lower floor's insulation layer, lower floor's waterproofing course, lower floor's topping, and lower structurally waterproof layer is supported by frame column; Lower floor's reinforced concrete roof board, lower floor's leveling layer, lower floor's insulation layer, lower floor's waterproofing course, lower floor's topping are cascading from top to bottom;
Parapet is positioned on lower floor's reinforced concrete roof board, and concordant with external wall, and parapet is provided with sliding sash; Lower floor's cast-iron bend is located at the intersection of parapet and lower floor's topping, and runs through parapet; The upper end of lower floor's leader is arranged on lower floor's cast-iron bend, and lower end extends to construction bottom.
2. hollow double structure layer water-proof roofing according to claim 1, it is characterized in that, superstructure waterproofing course, comprising: top reinforcement concrete slab, upper strata leveling layer, upper strata waterproofing course, upper strata topping; Top reinforcement concrete slab, upper strata leveling layer, upper strata waterproofing course, upper strata topping are cascading from top to bottom.
3. hollow double structure layer water-proof roofing according to claim 2, it is characterized in that, deck post is upwards extended to form by top-level boxes trestle, top with top reinforcement concrete slab is whole water together with, bottom with lower floor reinforced concrete roof board is whole water together with.
4. hollow double structure layer water-proof roofing according to claim 3, it is characterized in that, upper strata space enclosing structure is located on top reinforcement concrete slab, and concordant with external wall; Upper strata cast-iron bend is located at the intersection of upper strata space enclosing structure and upper strata topping, and runs through upper strata space enclosing structure.
5. hollow double structure layer water-proof roofing according to claim 4, is characterized in that, the upper end of upper strata leader is arranged on the cast-iron bend of upper strata, and lower end extends in the gutter spout funnel on lower floor's leader top.
6. the construction method of hollow double structure layer water-proof roofing according to claim 5, comprises following construction sequence:
(1) lower floor's reinforced concrete roof board, parapet, is built, lower floor's reinforced concrete roof board is laid successively and smears lower floor's leveling layer, lower floor's insulation layer, lower floor's waterproofing course, lower floor's topping, then build parapet by laying bricks or stones, when building parapet by laying bricks or stones, reserving hole is to install lower floor's cast-iron bend; Certain distance is left to install sliding sash between parapet and superstructure waterproofing course;
(2), build deck post and build top reinforcement concrete slab in pre-designed position, top reinforcement concrete slab takes turns doing upper strata leveling layer, upper strata waterproofing course, upper strata topping; The construction of upper strata space enclosing structure is carried out in place concordant with external wall on top reinforcement concrete slab, when carrying out the construction of upper strata space enclosing structure, reserving hole installs upper strata cast-iron bend, and reserving hole will keep vertical with the reserving hole of substructure waterproofing course cast-iron bend on vertical plane;
(3), between parapet and superstructure waterproofing course, all sliding sash is installed; The upper end of upper strata leader is arranged on the cast-iron bend of upper strata, and lower end reaches in the gutter spout funnel of lower floor's leader; The upper end of lower floor's leader is arranged on lower floor's cast-iron bend, and lower end extends to the aproll place of building.
CN201410395572.4A 2014-08-12 2014-08-12 Hollow double structure layer water-proof roofing and construction method thereof Expired - Fee Related CN104196178B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410395572.4A CN104196178B (en) 2014-08-12 2014-08-12 Hollow double structure layer water-proof roofing and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410395572.4A CN104196178B (en) 2014-08-12 2014-08-12 Hollow double structure layer water-proof roofing and construction method thereof

Publications (2)

Publication Number Publication Date
CN104196178A CN104196178A (en) 2014-12-10
CN104196178B true CN104196178B (en) 2015-12-30

Family

ID=52081528

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410395572.4A Expired - Fee Related CN104196178B (en) 2014-08-12 2014-08-12 Hollow double structure layer water-proof roofing and construction method thereof

Country Status (1)

Country Link
CN (1) CN104196178B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989040B (en) * 2015-06-15 2017-03-01 哈尔滨理工大学 The cold area roofing antiseep drainage system practice
CN108149859A (en) * 2017-12-18 2018-06-12 中冶天工集团有限公司 The water discharge method of special-shaped curved moulding roofing

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29701072U1 (en) * 1997-01-22 1997-03-27 Nutz Theo Lateral end element for flat roofs
CN2441898Y (en) * 2000-09-18 2001-08-08 余建新 Multifunction double roof structure member
CN201087508Y (en) * 2007-05-14 2008-07-16 陈济达 Double-roof roofing
CN101349077A (en) * 2008-09-05 2009-01-21 朱永发 Anti-vibration energy-saving building structure
CN101831994A (en) * 2010-04-30 2010-09-15 唐山德生防水材料有限公司 Double-layer waterproof and double-layer water exhaust structure of heat insulation house surface and construction method thereof
CN203475669U (en) * 2012-08-23 2014-03-12 李门乾 Roof structure of building
CN204001469U (en) * 2014-08-12 2014-12-10 中国石油大学(华东) Hollow double structure layer water-proof roofing

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29701072U1 (en) * 1997-01-22 1997-03-27 Nutz Theo Lateral end element for flat roofs
CN2441898Y (en) * 2000-09-18 2001-08-08 余建新 Multifunction double roof structure member
CN201087508Y (en) * 2007-05-14 2008-07-16 陈济达 Double-roof roofing
CN101349077A (en) * 2008-09-05 2009-01-21 朱永发 Anti-vibration energy-saving building structure
CN101831994A (en) * 2010-04-30 2010-09-15 唐山德生防水材料有限公司 Double-layer waterproof and double-layer water exhaust structure of heat insulation house surface and construction method thereof
CN203475669U (en) * 2012-08-23 2014-03-12 李门乾 Roof structure of building
CN204001469U (en) * 2014-08-12 2014-12-10 中国石油大学(华东) Hollow double structure layer water-proof roofing

Also Published As

Publication number Publication date
CN104196178A (en) 2014-12-10

Similar Documents

Publication Publication Date Title
CN204753940U (en) A concrete structure for sloping open valley
CN203546762U (en) Triple waterproof advance water stop structure for post-cast strip
CN103334554A (en) Construction method of laid tiles of sloping roof
CN206752862U (en) Inverted roof waterproof construction based on durability
CN204435958U (en) A kind of greening parking lot
CN203716414U (en) Straight double-layer drainage device
CN108729595A (en) A kind of structurally stable heat-isolating antiseepage pitched roof and its method of construction
CN104196178B (en) Hollow double structure layer water-proof roofing and construction method thereof
CN204001469U (en) Hollow double structure layer water-proof roofing
Curtis et al. Short guide-Climate change adaptation for traditional buildings
CN111350315A (en) Waterproof closing-in pre-embedding method for roof parapet
KR101275273B1 (en) apparatus for draining subsurface water
CN103790400A (en) Greening energy-saving public toilet in parks and at streets
CN202899319U (en) Waterproof panel point of side wall of existing building and roof of new-built building
CN104120837A (en) Construction method of waterproof roof
CN202483092U (en) Vapor-proof thermal insulation walkable roof
CN103556764A (en) Self-balancing extra-large-area roof reservoir and building method thereof
CN209837491U (en) Parapet antiseep node
CN103572783B (en) Comprehensive method for preventing crack and water of basement project
CN208950185U (en) Low outer high access point node waterproof construction in a kind of inverted insulating roof
CN203531205U (en) Self-balancing extra-large-area roof reservoir
CN203846694U (en) Water saving and energy saving building
CN208266929U (en) Prefabricated assembled concrete aproll component system
CN106854918B (en) The general pre-stress hollow pan tile of the flat roof superstructure of ne-leakage
CN205663110U (en) Piece together formula futilely from waterproof double T board

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Kang Jie

Inventor after: Sun Xiang

Inventor after: Li Chunbao

Inventor before: Liu Xiaohui

Inventor before: Yan Qingzhi

Inventor before: Li Chunbao

Inventor before: Zhao Jingjing

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151230

Termination date: 20160812