CN103982045A - 一种屋面网壳结构无支架悬挑安装施工方法 - Google Patents

一种屋面网壳结构无支架悬挑安装施工方法 Download PDF

Info

Publication number
CN103982045A
CN103982045A CN201410137987.1A CN201410137987A CN103982045A CN 103982045 A CN103982045 A CN 103982045A CN 201410137987 A CN201410137987 A CN 201410137987A CN 103982045 A CN103982045 A CN 103982045A
Authority
CN
China
Prior art keywords
net shell
installation
unit
bearing
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410137987.1A
Other languages
English (en)
Other versions
CN103982045B (zh
Inventor
徐国引
赵民华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG GUOSHENG STEEL STRUCTURE CO Ltd
Original Assignee
ZHEJIANG GUOSHENG STEEL STRUCTURE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG GUOSHENG STEEL STRUCTURE CO Ltd filed Critical ZHEJIANG GUOSHENG STEEL STRUCTURE CO Ltd
Priority to CN201410137987.1A priority Critical patent/CN103982045B/zh
Publication of CN103982045A publication Critical patent/CN103982045A/zh
Application granted granted Critical
Publication of CN103982045B publication Critical patent/CN103982045B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

一种屋面网壳结构无支架悬挑安装施工方法。现有的安装方法需要很多安装工具及脚手架,工作成本高,速度慢。本发明方法首先对预埋件进行地上安装,永久固定后对网壳进行地面拼装,然后通过汽车吊将网壳吊起安装第一区块网壳,第一区块安装好按照顺序依次安装剩余区块。本发明的优点是网壳按照设计在地面进行拼装,汽车吊提升悬挑安装所有网壳,无需大型起重设备和脚手架,不影响内部的平行作业,施工时进行多面作业、多工种同时交叉施工,大大节约施工工期,安装速度快。

Description

一种屋面网壳结构无支架悬挑安装施工方法
技术领域
本发明涉及一种建筑施工方法,具体涉及一种屋面网壳结构无支架悬挑安装施工方法。
背景技术
热电厂的储煤、储料设施屋面结构大多采用了螺栓球网壳结构,由于煤场内部大型的设备基础和铲煤输送系统的安装在上部网壳施工前已完成或同步完成,采用满堂脚手架高空散装法、脚手架滑移法和整体顶升法均无法实施,而网壳逐条积累滑移法施工需要增加较多的施工工具和滑移轨道装备,成本高,不是最佳的施工方法。
发明内容
本发明针对现有技术需要较多施工工具和滑移轨道装备,成本高的问题,提供一种屋面网壳结构无支架悬挑安装施工方法。
本发明方法包括以下步骤:
步骤(1)预埋件安装
根据设计图纸的要求,将预埋件按照图纸位置和定位尺寸用定位模板控制进行埋设,为防止预埋件在混凝土浇注过程中发生移位,对网壳安装造成不利影响,对预埋件及模板采用固定支架进行永久性固定;预埋件定位后,立即进行测量复核,在满足规范和设计允许偏差要求后,进行混凝土浇注施工,预埋件轴线尺寸和标高确认无误后在基础侧面打出基准标高点,作为安装调整用,在预埋件上放出中心轴线,然后画出支座的定位线,以便安装调整用;
步骤(2)网壳地面拼装
网壳的预拼单元分为上弦单元和下弦单元,下弦单元包括一颗下弦球、两根下弦杆和两根腹杆,上弦单元包括一颗上弦球、两根上弦杆和两根腹杆;上弦单元和下弦单元分别进行拼接,杆件同螺栓球按照设计和施工规范要求拧紧到位并进行检查,拼接完成后按照安装的先后顺序堆放;
步骤(3)第一区块网壳安装
网壳安装分为多个区块分别进行,首先进行第一区块网壳安装;第一区块网壳利用网壳螺栓球与柱顶支座未焊接固定能够绕柱顶支座转动的特点,将在地面拼装好的网壳拼装单元通过吊车提升的方式进行安装;地面拼装单元将支座按轴线位置固定在预埋件支承柱上,再将支承点螺栓球直接搁置在支座中,以便螺栓球在支座中转动;以支座上的螺栓球为支承旋转点,将网壳预拼单元拼起几节,然后利用小吨位吊车将拼好的网壳末端抬高继续拼放,吊车向未拼放方向移位后将拼好的网壳末端抬高继续拼放,以此类推;为保证端部第一区块网壳的安全稳定性,控制网壳扭曲变形,网壳支座处支承旋转点扩大至端部第二区块;在第一区块网壳安装过程中,由于网壳单元弧度大、跨度大,为保障安装的顺利进行,控制网壳扭曲变形,在支座与提升吊点位置处下弦球之间用5T倒链和钢丝绳拉两道张紧绳,始终保持张紧绳刚好绷紧;拼接起吊前应对吊车展位场地进行硬化确保吊车吊装时支点不下陷,对吊装索具及钢丝绳进行检查,确认符合吊装要求;吊装用的钢丝绳、卸扣及长进钢丝绳根据构件的重量、角度选择;吊装过程中所有的着力点要集中在螺栓球正中部位,拼装完成后对该区块进行测量调整,合格后将支座与预埋件全部焊接固定,采用预埋螺栓连接时,合格后将支座垫片与支座底板焊接固定;
步骤(4)剩余区块网壳安装
第一区块网壳安装完成后,沿与第一区块网壳面垂直的方向依次安装剩余区块网壳;首先是第二区块安装,安装时先将两端支座节点部分网壳安装,然后由两端制作部分向中间安装,直至安装完毕;安装时,先安装网壳下弦单元,下弦单元安装采用汽吊将拼接单元提升到相应网格位置,就位后,将下弦杆高强螺栓与已安装的下弦球拧紧,同时再把两腹杆的高强螺栓与已安装的上弦球拧入,并拧紧然后松吊点;再安装上弦单元,上弦单元采用汽吊将拼接单元提升到相应网格位置,二腹杆高强螺栓与已安装的下弦球拧紧,再把两上弦杆高强螺栓与已安装的上弦球拧紧,形成一个网格,检查并使其符合设计及规范要求;安装就位后接着安装第二个网格,继续边安装边检查,并做好记录;第二区块安装完成后,按照从两端支座节点到中间安装的步骤,依次安装剩余区块网壳。
本发明的有益效果:网壳按照设计在地面进行拼装,汽车吊提升悬挑安装所有网壳,无需大型起重设备且无需使用任何脚手架,不影响内部的平行作业,施工时,地面拼装和高空安装同时进行,进行多面作业、多工种同时交叉施工,大大节约施工工期,安装速度快。
附图说明
图1为本发明的下弦单元示意图;
图2为本发明的上弦单元示意图;
图3为本发明的安装方向示意图;
图4为本发明的安装状态示意图;
图5为本发明的剩余区块网壳安装示意图。
具体实施方式
下面结合附图和实施例对本发明进一步说明。
一种屋面网壳结构无支架悬挑安装施工方法,包括以下步骤:
步骤(1)预埋件安装
根据设计图纸的要求,将预埋件按照图纸位置和定位尺寸用定位模板控制进行埋设,为防止预埋件在混凝土浇注过程中发生移位,对网壳安装造成不利影响,对预埋件及模板采用固定支架进行永久性固定;预埋件定位后,立即进行测量复核,在满足规范和设计允许偏差要求后,进行混凝土浇注施工,预埋件轴线尺寸和标高确认无误后在基础侧面打出基准标高点,作为安装调整用,在预埋件上放出中心轴线,然后画出支座的定位线,以便安装调整用;
步骤(2)网壳地面拼装
如图1、图2所示,网壳的预拼单元分为上弦单元和下弦单元,下弦单元包括一颗下弦球1、两根下弦杆2和两根腹杆3,上弦单元包括一颗上弦球4、两根上弦杆5和两根腹杆6;上弦单元和下弦单元分别进行拼接,杆件同螺栓球按照设计和施工规范要求拧紧到位并进行检查,拼接完成后按照安装的先后顺序堆放;
步骤(3)第一区块网壳安装
如图3、图4所示,网壳安装分为多个区块分别进行,首先进行第一区块网壳安装;第一区块网壳利用网壳螺栓球与柱顶支座未焊接固定能够绕柱顶支座转动的特点,将在地面拼装好的网壳拼装单元通过吊车提升的方式进行安装;地面拼装单元将支座按轴线位置固定在预埋件支承柱上,再将支承点螺栓球直接搁置在支座中,以便螺栓球在支座中转动;以支座上的螺栓球为支承旋转点,将网壳预拼单元拼起几节,然后利用小吨位吊车将拼好的网壳末端抬高继续拼放,吊车向未拼放方向移位后将拼好的网壳末端抬高继续拼放,以此类推;为保证端部第一区块I网壳的安全稳定性,控制网壳扭曲变形,网壳支座处支承旋转点扩大至端部第二区块II;在第一区块网壳安装过程中,由于网壳单元弧度大、跨度大,为保障安装的顺利进行,控制网壳扭曲变形,在支座与提升吊点位置处下弦球之间用5T倒链和钢丝绳拉两道张紧绳,始终保持张紧绳刚好绷紧;拼接起吊前应对吊车展位场地进行硬化确保吊车吊装时支点不下陷,对吊装索具及钢丝绳进行检查,确认符合吊装要求;吊装用的钢丝绳、卸扣及长进钢丝绳根据构件的重量、角度选择;吊装过程中所有的着力点要集中在螺栓球正中部位,拼装完成后对该区块进行测量调整,合格后将支座与预埋件全部焊接固定,采用预埋螺栓连接时,合格后将支座垫片与支座底板焊接固定;
步骤(4)剩余区块网壳安装
如图5所示,第一区块网壳安装完成后,沿与第一区块网壳面垂直的方向依次安装剩余区块网壳;首先是第二区块安装,安装时先将两端支座节点部分网壳安装,然后由两端制作部分向中间安装,直至安装完毕;安装时,先安装网壳下弦单元,下弦单元安装采用汽吊将拼接单元提升到相应网格位置,就位后,将下弦杆高强螺栓与已安装的下弦球拧紧,同时再把两腹杆的高强螺栓与已安装的上弦球拧入,并拧紧然后松吊点;再安装上弦单元,上弦单元采用汽吊将拼接单元提升到相应网格位置,二腹杆高强螺栓与已安装的下弦球拧紧,再把两上弦杆高强螺栓与已安装的上弦球拧紧,形成一个网格,检查并使其符合设计及规范要求;安装就位后接着安装第二个网格,继续边安装边检查,并做好记录;第二区块安装完成后,按照从两端支座节点到中间安装的步骤,依次安装剩余区块网壳。
本发明还可以有其他实施例,在不背离本发明精神及其实质情况下进行的改变和变形都应属于本发明权利要求的保护范围。

Claims (1)

1. 一种屋面网壳结构无支架悬挑安装施工方法,其特征在于该方法包括以下步骤:
步骤(1)预埋件安装
根据设计图纸的要求,将预埋件按照图纸位置和定位尺寸用定位模板控制进行埋设,为防止预埋件在混凝土浇注过程中发生移位,对网壳安装造成不利影响,对预埋件及模板采用固定支架进行永久性固定;预埋件定位后,进行测量复核,在满足规范和设计允许偏差要求后,进行混凝土浇注施工,预埋件轴线尺寸和标高确认无误后在基础侧面打出基准标高点,作为安装调整用,在预埋件上放出中心轴线,然后画出支座的定位线,以便安装调整用;
步骤(2)网壳地面拼装
网壳的预拼单元分为上弦单元和下弦单元,下弦单元包括一颗下弦球、两根下弦杆和两根腹杆,上弦单元包括一颗上弦球、两根上弦杆和两根腹杆;上弦单元和下弦单元分别进行拼接,杆件同螺栓球按照设计和施工规范要求拧紧到位并进行检查,拼接完成后按照安装的先后顺序堆放;
步骤(3)第一区块网壳安装
网壳安装分为多个区块分别进行,首先进行第一区块网壳安装;第一区块网壳利用网壳螺栓球与柱顶支座未焊接固定能够绕柱顶支座转动的特点,将在地面拼装好的网壳拼装单元通过吊车提升的方式进行安装;地面拼装单元将支座按轴线位置固定在预埋件支承柱上,再将支承点螺栓球直接搁置在支座中,以便螺栓球在支座中转动;以支座上的螺栓球为支承旋转点,将网壳预拼单元拼起几节,然后利用小吨位吊车将拼好的网壳末端抬高继续拼放,吊车向未拼放方向移位后将拼好的网壳末端抬高继续拼放;为保证端部第一区块网壳的安全稳定性,控制网壳扭曲变形,网壳支座处支承旋转点扩大至端部第二区块;在第一区块网壳安装过程中,由于网壳单元弧度大、跨度大,为保障安装的顺利进行,控制网壳扭曲变形,在支座与提升吊点位置处下弦球之间用5T倒链和钢丝绳拉两道张紧绳,始终保持张紧绳刚好绷紧;拼接起吊前应对吊车展位场地进行硬化确保吊车吊装时支点不下陷,对吊装索具及钢丝绳进行检查,确认符合吊装要求;吊装用的钢丝绳、卸扣及钢丝绳根据构件的重量、角度选择;吊装过程中所有的着力点要集中在螺栓球正中部位,拼装完成后对该区块进行测量调整,合格后将支座与预埋件全部焊接固定,采用预埋螺栓连接时,合格后将支座垫片与支座底板焊接固定;
步骤(4)剩余区块网壳安装
第一区块网壳安装完成后,沿与第一区块网壳面垂直的方向依次安装剩余区块网壳;首先是第二区块安装,安装时先将两端支座节点部分网壳安装,然后由两端制作部分向中间安装,直至安装完毕;安装时,先安装网壳下弦单元,下弦单元安装采用汽吊将拼接单元提升到相应网格位置,就位后,将下弦杆高强螺栓与已安装的下弦球拧紧,同时再把两腹杆的高强螺栓与已安装的上弦球拧入,拧紧后松吊点;再安装上弦单元,上弦单元采用汽吊将拼接单元提升到相应网格位置,二腹杆高强螺栓与已安装的下弦球拧紧,再把两上弦杆高强螺栓与已安装的上弦球拧紧,形成一个网格,检查并使其符合设计及规范要求;安装就位后接着安装第二个网格,继续边安装边检查,并做好记录;第二区块安装完成后,按照从两端支座节点到中间安装的步骤,依次安装剩余区块网壳。
CN201410137987.1A 2014-04-08 2014-04-08 一种屋面网壳结构无支架悬挑安装施工方法 Active CN103982045B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410137987.1A CN103982045B (zh) 2014-04-08 2014-04-08 一种屋面网壳结构无支架悬挑安装施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410137987.1A CN103982045B (zh) 2014-04-08 2014-04-08 一种屋面网壳结构无支架悬挑安装施工方法

Publications (2)

Publication Number Publication Date
CN103982045A true CN103982045A (zh) 2014-08-13
CN103982045B CN103982045B (zh) 2016-08-24

Family

ID=51274192

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410137987.1A Active CN103982045B (zh) 2014-04-08 2014-04-08 一种屋面网壳结构无支架悬挑安装施工方法

Country Status (1)

Country Link
CN (1) CN103982045B (zh)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727564A (zh) * 2015-04-17 2015-06-24 中亿丰建设集团股份有限公司 超高层建筑屋顶自由曲面单层网壳结构安装施工方法
CN105386604A (zh) * 2015-10-09 2016-03-09 多维联合集团有限公司 一种高空网架安装方法
CN107246153A (zh) * 2017-06-14 2017-10-13 东南大学 一种环形索承网格结构的无支架施工方法
CN108571077A (zh) * 2018-05-18 2018-09-25 中国二十二冶集团有限公司 网架起步跨转动轴拼装就位方法
CN108643357A (zh) * 2018-05-21 2018-10-12 中国二十二冶集团有限公司 拱形网架起步跨地面拼装方法及其专用基础结构
CN108643584A (zh) * 2018-04-02 2018-10-12 中国十七冶集团有限公司 一种钢结构超长悬挑大梁无支撑安装的施工方法
CN108952242A (zh) * 2018-08-11 2018-12-07 中国电建集团贵州电力设计研究院有限公司 一种干煤棚弧形网架的施工方法
CN110029828A (zh) * 2019-04-30 2019-07-19 广东省水利水电第三工程局有限公司 一种自稳平衡桁架装置
CN111042541A (zh) * 2019-12-18 2020-04-21 徐州中煤(宁夏)钢结构建设有限公司 大跨度焊接球柱面网壳顶升施工方法
CN111424822A (zh) * 2020-04-03 2020-07-17 浙江东南网架股份有限公司 环形大悬挑索承网格结构的无支架施工方法
CN112411760A (zh) * 2020-11-10 2021-02-26 上海宝冶集团有限公司 首吊单元的整体吊装结合悬挑安装的施工方法
CN113389267A (zh) * 2021-06-17 2021-09-14 北京工业大学 一种可快速安装的球面网格结构
CN114837440A (zh) * 2022-05-24 2022-08-02 通号建设集团第一工程有限公司 一种大跨度弓式钢桁架屋盖施工方法

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111058538B (zh) * 2019-12-18 2021-02-02 安徽百甲科技有限责任公司 一种大跨度门式网壳塔架支撑施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05230891A (ja) * 1992-02-21 1993-09-07 Takenaka Komuten Co Ltd 超高層建物の構築工法
CN1472408A (zh) * 2003-05-23 2004-02-04 浙江大学 柱面网壳支座水平滑移结构整体成形施工方法
CN101169001A (zh) * 2007-10-30 2008-04-30 浙江大学 四角锥球面网壳无脚手架施工安装方法及吊装机具
CN102953554A (zh) * 2012-11-14 2013-03-06 中冶天工集团有限公司 一种大跨度蜂窝形双层网壳结构的安装方法
CN103075016A (zh) * 2013-01-22 2013-05-01 北京工业大学 可扩展网壳结构的安装方法
CN103276908A (zh) * 2013-06-06 2013-09-04 四川电力建设三公司 一种用于组装钢网架筒壳结构干煤棚的施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05230891A (ja) * 1992-02-21 1993-09-07 Takenaka Komuten Co Ltd 超高層建物の構築工法
CN1472408A (zh) * 2003-05-23 2004-02-04 浙江大学 柱面网壳支座水平滑移结构整体成形施工方法
CN101169001A (zh) * 2007-10-30 2008-04-30 浙江大学 四角锥球面网壳无脚手架施工安装方法及吊装机具
CN102953554A (zh) * 2012-11-14 2013-03-06 中冶天工集团有限公司 一种大跨度蜂窝形双层网壳结构的安装方法
CN103075016A (zh) * 2013-01-22 2013-05-01 北京工业大学 可扩展网壳结构的安装方法
CN103276908A (zh) * 2013-06-06 2013-09-04 四川电力建设三公司 一种用于组装钢网架筒壳结构干煤棚的施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
徐国引: "干煤棚网壳悬挑法施工技术", 《浙江建筑》 *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727564A (zh) * 2015-04-17 2015-06-24 中亿丰建设集团股份有限公司 超高层建筑屋顶自由曲面单层网壳结构安装施工方法
CN105386604A (zh) * 2015-10-09 2016-03-09 多维联合集团有限公司 一种高空网架安装方法
CN105386604B (zh) * 2015-10-09 2018-03-16 多维联合集团有限公司 一种高空网架安装方法
CN107246153A (zh) * 2017-06-14 2017-10-13 东南大学 一种环形索承网格结构的无支架施工方法
CN108643584A (zh) * 2018-04-02 2018-10-12 中国十七冶集团有限公司 一种钢结构超长悬挑大梁无支撑安装的施工方法
CN108571077A (zh) * 2018-05-18 2018-09-25 中国二十二冶集团有限公司 网架起步跨转动轴拼装就位方法
CN108643357A (zh) * 2018-05-21 2018-10-12 中国二十二冶集团有限公司 拱形网架起步跨地面拼装方法及其专用基础结构
CN108952242A (zh) * 2018-08-11 2018-12-07 中国电建集团贵州电力设计研究院有限公司 一种干煤棚弧形网架的施工方法
CN110029828A (zh) * 2019-04-30 2019-07-19 广东省水利水电第三工程局有限公司 一种自稳平衡桁架装置
CN110029828B (zh) * 2019-04-30 2021-04-02 广东省水利水电第三工程局有限公司 一种自稳平衡桁架装置
CN111042541A (zh) * 2019-12-18 2020-04-21 徐州中煤(宁夏)钢结构建设有限公司 大跨度焊接球柱面网壳顶升施工方法
CN111424822A (zh) * 2020-04-03 2020-07-17 浙江东南网架股份有限公司 环形大悬挑索承网格结构的无支架施工方法
CN112411760A (zh) * 2020-11-10 2021-02-26 上海宝冶集团有限公司 首吊单元的整体吊装结合悬挑安装的施工方法
CN112411760B (zh) * 2020-11-10 2022-08-09 上海宝冶集团有限公司 首吊单元的整体吊装结合悬挑安装的施工方法
CN113389267A (zh) * 2021-06-17 2021-09-14 北京工业大学 一种可快速安装的球面网格结构
CN114837440A (zh) * 2022-05-24 2022-08-02 通号建设集团第一工程有限公司 一种大跨度弓式钢桁架屋盖施工方法

Also Published As

Publication number Publication date
CN103982045B (zh) 2016-08-24

Similar Documents

Publication Publication Date Title
CN103982045A (zh) 一种屋面网壳结构无支架悬挑安装施工方法
CN103061506B (zh) 一种钢结构穹顶的施工方法
CN103291076B (zh) 弧形框架内多层次钢桁架分片逆向吊装施工方法
CN104060544B (zh) 一种管道悬索跨越桥桥身安装的施工工艺
CN203947771U (zh) 一种贝雷梁悬吊模板支撑体系
CN103774854A (zh) 一种重型超高钢构件的吊装施工方法
CN104674665B (zh) 大空间钢结构连廊桥安装方法
CN103437563B (zh) 一种用于大型钢结构厂房钢骨架的安装方法
CN104695715A (zh) 一种屋面张弦梁结构施工方法
CN101284628A (zh) 大吨位压力机架的吊装方法
CN104477788A (zh) 风力发电塔跨越自爬式平移吊机
CN111172892A (zh) 一种钢结构框架桥双边平衡牵引装置及其方法
CN110318468B (zh) 偏心空间网架安装辅助装置及安装方法
CN111561175A (zh) 一种预应力托换静力切割拔柱施工工艺
CN202658590U (zh) 整体装配式钻孔平台
CN102486051A (zh) 大面积球形网架人工拆除方法
CN204938800U (zh) 塔式起重机十字梁基础
CN205369229U (zh) 适用于人工挖孔桩钢筋笼安放的可行走式提升架
CN104060838B (zh) 一种通廊分组空中组对安装法
CN105274940A (zh) 一种桥梁拱肋整体安装方法
CN104264781A (zh) 网格状柱面钢结构网壳及其施工方法
CN202347884U (zh) 水轮机检修平台
CN104045014A (zh) 一种用于电杆焊接的排杆架
CN212224666U (zh) 钢桁架组装体系
CN210420898U (zh) 一种新型钢箱梁0号块支架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant