CN102953554A - 一种大跨度蜂窝形双层网壳结构的安装方法 - Google Patents
一种大跨度蜂窝形双层网壳结构的安装方法 Download PDFInfo
- Publication number
- CN102953554A CN102953554A CN2012104603850A CN201210460385A CN102953554A CN 102953554 A CN102953554 A CN 102953554A CN 2012104603850 A CN2012104603850 A CN 2012104603850A CN 201210460385 A CN201210460385 A CN 201210460385A CN 102953554 A CN102953554 A CN 102953554A
- Authority
- CN
- China
- Prior art keywords
- jack
- district
- jacking
- hydraulic jack
- straight section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 33
- 238000009434 installation Methods 0.000 title abstract description 14
- 238000003466 welding Methods 0.000 claims abstract description 5
- 230000001360 synchronised effect Effects 0.000 claims description 7
- 238000004458 analytical method Methods 0.000 claims description 3
- 238000006243 chemical reaction Methods 0.000 claims description 3
- 238000005498 polishing Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 claims description 2
- 238000010586 diagram Methods 0.000 description 3
- 230000001788 irregular Effects 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种大跨度蜂窝形双层网壳结构的安装方法,包括如下步骤:①根据结构平面和立面形状,将结构分成近似直段区和中间区;②将近似直段区先进行竖向分条,将每条网壳结构坐标旋转至水平,在平台上完成拼装,用吊车逐条吊装就位,焊接成片;③将中间区在地面从中心向外扩展拼装,扩展过程采用千斤顶多点顶升,顶升至一定区间,曲率变大,常规千斤顶行程不能满足要求时,采用多点穿芯式液压千斤顶同步提升,逐步扩拼完成后,采用多点穿芯式液压千斤顶同步提升到安装高度,与直段连成片。本发明提高了结构拼装精度、提高了结构安装安全度,最终保证了结构安装质量和安装工期。
Description
技术领域:
本发明属于一种钢结构建筑的安装技术,特别涉及一种大跨度蜂窝形双层网壳结构的安装方法。
背景技术:
网壳结构的常用安装方法有:高空散装法、分块或分条安装法、滑移法、整体吊装法、整体提升法、整体顶升法等,对于大跨度网壳结构可根据工程三维形状和网格构造不同,选用不同的安装方法。对于网格复杂、水平和立面形状不规则的大跨度工程,由于结构支撑点少,结构分块分条困难、平面形状不规则,不具备采用分块分条安装法和滑移法的条件,蜂窝形网格安全裕度低,不能采用整体吊装法、整体提升法、整体顶升法。
最常用的安装方法是高空散装法,这种安装方法是用脚手架搭设拼装支架和平台,平台标高低于结构下弦节点标高,逐点测量定位,构件吊装到高空进行拼装。由于大跨度建筑通常净高较高,采用这种方法,脚手架搭设时间长、费用高,节点定位准确性差,施工速度慢。
发明内容:
本发明的目的就在于克服上述现有技术中存在的不足,而提供一种大跨度蜂窝形双层网壳结构的安装方法,该方法提高了结构拼装精度、提高了结构安装安全度,最终保证了结构安装质量和安装工期。
如上构思,本发明的技术方案是:一种大跨度蜂窝形双层网壳结构的安装方法,其特征在于:包括如下步骤:
①根据结构平面和立面形状,将结构进行分区,靠近边缘基本直立的部位分成一个区,称近似直段区,中间曲率较小高度变化平缓的部位分成一个区,称中间区;
②近似直段区下部均为支座点,先进行竖向分条,将每条网壳结构坐标旋转至水平,在平台上完成拼装,用吊车逐条吊装就位,焊接成片;
③中间区在地面从中心向外扩展拼装,扩展过程采用千斤顶多点顶升,顶升至一定区间,曲率变大,常规千斤顶行程不能满足要求时,采用多点穿芯式液压千斤顶同步提升,逐步扩拼完成后,采用多点穿芯式液压千斤顶同步提升到安装高度,与直段连成片。
上述一种大跨度蜂窝形双层网壳结构的安装的方法,其特征在于:具体施工步骤如下:
①计算确定近似直立区和中间区的分区位置;
②将近似直立段进行计算分块,保证每块可吊装,并将分块下弦节点最内侧三点取一个平面,所有块上节点按所取面为XY面,与该面垂直为Z轴的坐标系进行坐标旋转转换,并在平台上拼装,用吊车安装;
③中心区网壳结构安装场地地面用外扩法拼装,从中心开始,边拼边顶,设置顶升支架,以两个为一组,用螺旋顶升千斤顶相互交替顶升,直到顶升用千斤顶行程在利用简单支架也无法满足顶升要求时,安装临时支柱,改用穿芯式液压千斤顶提升,逐步扩展至拼完全部中心区网壳;用穿芯式液压千斤顶提升,一次提升到位;
④补齐近似直段区与是中心区连接处的杆析;
⑤分步拆除穿芯式液压千斤顶处的临时支柱。
本发明通过将网壳结构分区,避免了直段区繁重的搭设脚手架工作;将高空作业移到地面,提高了结构拼装精度;采用多点同步提升,大大提高了结构安装安全度,最终保证了结构安装质量和安装工期。
附图说明:
图1是不规则网壳平面示意图;
图2是网壳断面示意图;
图3是中心区网壳外扩法拼装示意图;
图4是近似直立段分块示意图。
具体实施方式:
本发明一种大跨度蜂窝形双层网壳结构的安装方法的发明思路是:
1、根据结构平面和立面形状,将结构进行分区,靠近边缘基本直立的部位分成一个区,称近似直段区1,中间曲率较小高度变化平缓的部位分成一个区,称中间区2。(图1、图2)
2、大跨度网壳结构通常为周边支承,也即在边界处,上、下弦球均为结构支座点。
近似直段区下部均为支座点,先进行竖向分条,将每条网壳结构坐标旋转至水平,在平台上完成拼装,用吊车逐条吊装就位,焊接成片。(如图4所示)
3、中间区在地面从中心向外扩展拼装,扩展过程采用千斤顶多点顶升,顶升至一定区间,曲率变大,常规千斤顶行程不能满足要求时,采用多点穿芯式液压千斤顶同步提升,逐步扩拼完成后,采用多点穿芯式液压千斤顶同步提升到安装高度,与直段连成片。(如图2、3所示)附图3中箭头方向为焊接顺序。
本发明的实施条件:
1、结构为双层网壳。
2、结构近似直段区能满足结构站立情况下,杆件无超应力情况。
3、结构中间区网格为静定或超静定结构。当网格约束不足,为不稳定结构体系时,可进行局部加强并经设计人员同意。
本发明的具体实施步骤:
第一步,计算确定近似直立区和中间区的分区位置;(如图2所示)
第二步,将近似直立段进行计算分块,保证每块可吊装,并将分块下弦节点最内侧三点取一个平面,所有块上节点按所取面为XY面,与该面垂直为Z轴的坐标系进行坐标旋转转换,并在平台上拼装,用吊车安装;(如图4所示)
第三步,中心区网壳结构安装场地地面用外扩法拼装,从中心开始,边拼边顶,设置顶升支架,以两个为一组,用螺旋顶升千斤顶相互交替顶升,直到顶升用千斤顶行程在利用简单支架也无法满足顶升要求时,安装临时支柱,改用穿芯式液压千斤顶提升,逐步扩展至拼完全部中心区网壳。用穿芯式液压千斤顶提升,一次提升到位;
第四步,补齐近似直段区与是中心区连接处的杆析;
第五部,分步拆除穿芯式液压千斤顶处的临时支柱。
Claims (2)
1.一种大跨度蜂窝形双层网壳结构的安装方法,其特征在于:包括如下步骤:
①根据结构平面和立面形状,将结构进行分区,靠近边缘基本直立的部位分成一个区,称近似直段区,中间曲率较小高度变化平缓的部位分成一个区,称中间区;
②近似直段区下部均为支座点,先进行竖向分条,将每条网壳结构坐标旋转至水平,在平台上完成拼装,用吊车逐条吊装就位,焊接成片;
③中间区在地面从中心向外扩展拼装,扩展过程采用千斤顶多点顶升,顶升至一定区间,曲率变大,常规千斤顶行程不能满足要求时,采用多点穿芯式液压千斤顶同步提升,逐步扩拼完成后,采用多点穿芯式液压千斤顶同步提升到安装高度,与直段连成片。
2.根据权利要求1所述的一种大跨度蜂窝形双层网壳结构的安装方法,其特征在于:具体施工步骤如下:
①计算确定近似直立区和中间区的分区位置;
②将近似直立段进行计算分块,保证每块可吊装,并将分块下弦节点最内侧三点取一个平面,所有块上节点按所取面为XY面,与该面垂直为Z轴的坐标系进行坐标旋转转换,并在平台上拼装,用吊车安装;
③中心区网壳结构安装场地地面用外扩法拼装,从中心开始,边拼边顶,设置顶升支架,以两个为一组,用螺旋顶升千斤顶相互交替顶升,直到顶升用千斤顶行程在利用简单支架也无法满足顶升要求时,安装临时支柱,改用穿芯式液压千斤顶提升,逐步扩展至拼完全部中心区网壳;用穿芯式液压千斤顶提升,一次提升到位;
④补齐近似直段区与是中心区连接处的杆析;
⑤分步拆除穿芯式液压千斤顶处的临时支柱。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012104603850A CN102953554A (zh) | 2012-11-14 | 2012-11-14 | 一种大跨度蜂窝形双层网壳结构的安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012104603850A CN102953554A (zh) | 2012-11-14 | 2012-11-14 | 一种大跨度蜂窝形双层网壳结构的安装方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102953554A true CN102953554A (zh) | 2013-03-06 |
Family
ID=47762890
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012104603850A Pending CN102953554A (zh) | 2012-11-14 | 2012-11-14 | 一种大跨度蜂窝形双层网壳结构的安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102953554A (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103449318A (zh) * | 2013-09-26 | 2013-12-18 | 中联重科股份有限公司 | 顶升机构、顶升方法、及具有该顶升机构的塔式起重机 |
CN103603501A (zh) * | 2013-10-21 | 2014-02-26 | 中建钢构有限公司北京分公司 | 大跨度空间结构建筑施工的卸载方法 |
CN103982045A (zh) * | 2014-04-08 | 2014-08-13 | 浙江国盛钢结构有限公司 | 一种屋面网壳结构无支架悬挑安装施工方法 |
CN108532767A (zh) * | 2018-05-09 | 2018-09-14 | 中建七局安装工程有限公司 | 空间球面网架逐环扩大先顶后提升施工方法 |
CN108678180A (zh) * | 2018-05-09 | 2018-10-19 | 中建七局安装工程有限公司 | 空间球面网架阶梯提升施工方法 |
CN111625877A (zh) * | 2020-04-15 | 2020-09-04 | 浙江仁欣环科院有限责任公司 | 一种基于cad等高线提高大气污染预测准确性的方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05311882A (ja) * | 1992-05-13 | 1993-11-22 | Kajima Corp | 大スパン構造物のプッシュアップ工法及び装置 |
CN101718115A (zh) * | 2009-11-20 | 2010-06-02 | 徐玉平 | 大跨度柱面网壳安装方法 |
CN101839068A (zh) * | 2010-04-08 | 2010-09-22 | 宝厦建设(集团)股份有限公司 | 安装大跨度双层网壳结构的预应力方法 |
CN102071814A (zh) * | 2010-12-16 | 2011-05-25 | 中建二局第三建筑工程有限公司 | 高层大跨度门式桁架整体提升装置及其施工方法 |
CN102425260A (zh) * | 2011-11-25 | 2012-04-25 | 安徽鲁班建设投资集团有限公司 | 一种大跨度半球形屋顶钢构网架环形单点安装方法 |
-
2012
- 2012-11-14 CN CN2012104603850A patent/CN102953554A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05311882A (ja) * | 1992-05-13 | 1993-11-22 | Kajima Corp | 大スパン構造物のプッシュアップ工法及び装置 |
CN101718115A (zh) * | 2009-11-20 | 2010-06-02 | 徐玉平 | 大跨度柱面网壳安装方法 |
CN101839068A (zh) * | 2010-04-08 | 2010-09-22 | 宝厦建设(集团)股份有限公司 | 安装大跨度双层网壳结构的预应力方法 |
CN102071814A (zh) * | 2010-12-16 | 2011-05-25 | 中建二局第三建筑工程有限公司 | 高层大跨度门式桁架整体提升装置及其施工方法 |
CN102425260A (zh) * | 2011-11-25 | 2012-04-25 | 安徽鲁班建设投资集团有限公司 | 一种大跨度半球形屋顶钢构网架环形单点安装方法 |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103449318A (zh) * | 2013-09-26 | 2013-12-18 | 中联重科股份有限公司 | 顶升机构、顶升方法、及具有该顶升机构的塔式起重机 |
CN103449318B (zh) * | 2013-09-26 | 2015-11-04 | 中联重科股份有限公司 | 顶升机构、顶升方法、及具有该顶升机构的塔式起重机 |
CN103603501A (zh) * | 2013-10-21 | 2014-02-26 | 中建钢构有限公司北京分公司 | 大跨度空间结构建筑施工的卸载方法 |
CN103603501B (zh) * | 2013-10-21 | 2016-06-08 | 中建钢构有限公司 | 大跨度空间结构建筑施工的卸载方法 |
CN103982045A (zh) * | 2014-04-08 | 2014-08-13 | 浙江国盛钢结构有限公司 | 一种屋面网壳结构无支架悬挑安装施工方法 |
CN103982045B (zh) * | 2014-04-08 | 2016-08-24 | 浙江国盛钢结构有限公司 | 一种屋面网壳结构无支架悬挑安装施工方法 |
CN108532767A (zh) * | 2018-05-09 | 2018-09-14 | 中建七局安装工程有限公司 | 空间球面网架逐环扩大先顶后提升施工方法 |
CN108678180A (zh) * | 2018-05-09 | 2018-10-19 | 中建七局安装工程有限公司 | 空间球面网架阶梯提升施工方法 |
CN111625877A (zh) * | 2020-04-15 | 2020-09-04 | 浙江仁欣环科院有限责任公司 | 一种基于cad等高线提高大气污染预测准确性的方法 |
CN111625877B (zh) * | 2020-04-15 | 2023-05-23 | 浙江仁欣环科院有限责任公司 | 一种基于cad等高线提高大气污染预测准确性的方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102953554A (zh) | 一种大跨度蜂窝形双层网壳结构的安装方法 | |
CN208702197U (zh) | 一种大位移整体顶升水平限位装置 | |
CN111395532B (zh) | 大跨度半开口椭圆球面网壳安装施工方法 | |
CN101936536A (zh) | 一种船舶烟囱分段的建造方法 | |
CN104594201B (zh) | 一种利用单侧墩旁托架架设墩顶钢梁的方法 | |
CN102888894B (zh) | 内筒外框式回形钢框架建筑的结构及施工方法 | |
CN104196165B (zh) | 一种超大型多腔钢结构巨柱及其制作方法 | |
CN102877412A (zh) | 钢塔整体竖立式预拼装方法 | |
CN103061514A (zh) | 大跨度钢结构连廊施工方法 | |
CN201362952Y (zh) | 一种电梯井筒结构施工型钢平台 | |
CN203213019U (zh) | 长悬臂盖梁现浇施工支架体系 | |
CN103276909B (zh) | 弧形网架拼装方法及其使用的网架拼装胎架 | |
CN204310646U (zh) | 一种新型电梯井道 | |
CN104060838B (zh) | 一种通廊分组空中组对安装法 | |
CN207526141U (zh) | 一种小截面塔型钢结构拼装式操作平台 | |
CN202831628U (zh) | 浇筑大跨度混凝土梁用组合式贝雷架承重排架 | |
CN116163534A (zh) | 大直径铝合金网壳结构现场低空散拼方法 | |
CN101774516B (zh) | 更换耙式吊车桥架的顶升装置及施工方法 | |
CN205276472U (zh) | 一种大跨度钢桁架结构 | |
CN202055412U (zh) | 一种圆形十字柱脚 | |
CN204199691U (zh) | 一种螺旋楼梯的扶手浇筑模板结构 | |
CN203429888U (zh) | 一种大型目字型厚板组合箱形柱 | |
CN203201127U (zh) | 钢桁架临时支撑体系 | |
CN202388183U (zh) | H型钢数控切割机举升设备 | |
CN103510658B (zh) | 一种大型目字型厚板组合箱形柱及其制作方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20130306 |