CN103899337B - Wide tunnel waterproof board installation platform and installation method - Google Patents

Wide tunnel waterproof board installation platform and installation method Download PDF

Info

Publication number
CN103899337B
CN103899337B CN201410151201.1A CN201410151201A CN103899337B CN 103899337 B CN103899337 B CN 103899337B CN 201410151201 A CN201410151201 A CN 201410151201A CN 103899337 B CN103899337 B CN 103899337B
Authority
CN
China
Prior art keywords
splash guard
lifting pin
laying
dolly
jacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410151201.1A
Other languages
Chinese (zh)
Other versions
CN103899337A (en
Inventor
周立新
邓卫东
郑杭蓉
赵勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410151201.1A priority Critical patent/CN103899337B/en
Publication of CN103899337A publication Critical patent/CN103899337A/en
Application granted granted Critical
Publication of CN103899337B publication Critical patent/CN103899337B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a wide tunnel waterproof board installation platform and installation method. A front laying trolley and a rear laying trolley are arranged on a front laying rail and a rear laying rail of the platform respectively and are respectively provided with a supporting base, a reel used for containing a reeled waterproof board is installed between the supporting bases and is driven by a drive device to rotate for unreeling the waterproof board, multiple jacking rods are arranged between the front laying rail and the rear laying rail and are annularly and uniformly arranged along the arched laying rails, the two ends of each jacking rod are installed on installation supports through jacking devices, the unreeled waterproof board is laid on the jacking rods, the jacking rods are jacked up through the jacking devices, and the waterproof board laid on the jacking rods is lifted to be attached to a tunnel contour surface. According to the platform, mechanization and automation of construction technology processes and the whole construction process are achieved, manual high-altitude lifting working strength is reduced, construction quality and construction efficiency are greatly improved, and security risk in the construction process is reduced.

Description

Tunnel wide splash guard mounting platform and installation method
Technical field
The present invention relates to a kind of anchor bar of waterproof plate in tunnels mounting platform, specifically a kind of tunnel wide splash guard mounting platform.This Invention further relates to the installation method of above-mentioned mounting platform.
Background technology
Anchor bar of waterproof plate in tunnels typically adopts 1-1.5 millimeters thick polyethylene waterproof board, this splash guard fabric width 3-7 rice at present, often puts down 1.5 kilograms of square meter Chong Liang;The double track tunnel of 3 meters of fabric widths, single width weight reaches 150 kilograms;The single-track tunnel of 3 meters of fabric widths, single width Weight reaches 100 kilograms;The double track tunnel of 7 meters of fabric widths, single width weight reaches 330 kilograms;The single-track tunnel of 7 meters of fabric widths, single width Weight reaches 220 kilograms.
Mostly the mounting means of splash guard is to adopt at present(Simple chassis)Support Method coordinates manually installed mode, weight lifting of being commissioned Amount limits the splash guard that can only adopt 3-4 rice fabric width, and because fabric width is narrower, seam is more, when overlapping the slot quality of connection is not in place Shi Jiyi brings the risk of percolating water, and welding job amount is larger, reduces safety guarantee coefficient, and efficiency of construction is low, installs matter Amount cannot be guaranteed.And the splash guard for 6-7 rice fabric width, because single width weight is too heavy, original mounting process is restricted, no Method uses.
In order to solve the installation question of splash guard particularly wide cut splash guard, there has been proposed multiple installation splash guard chassis Mentality of designing, such as CN20372800Y, CN102359385A, CN202090925U, CN202187780U, CN202300428U, Scheme disclosed in the patents such as CN201768021.But all these patents all relate only to the lifting of splash guard and in tunnel Traction, fail solve splash guard install when moulding, especially non-type to tunnel excavation profile in the case of how to make splash guard Jacking is to accurate location and difficult during concrete perfusion is installed to adjustment of sag that splash guard impact is reserved etc. by compensating With the technical barrier realized.Suspension after splash guard jacking is fixed, prior art does not find solution well yet.
Specially promote the use of the mounting means that chassis coordinates manually installed 3.5 meters of splash guards in expensive wide visitor at present, achieved Must be in progress, solve the double track tunnel feasibility problems installing 3.5 meters of fabric widths, but, installation efficiency and installation quality are asked Topic people is unsatisfactory.
And current tunnel lining reinforcing steel bar net adopts the simple chassis of hand fit's construction bracket, using manually single lifting, The mode of colligation is constructed, and amount of high-altitude operation is big, and artificial lifting work amount is big, and construction quality is difficult to ensure that, high labor intensive, Efficiency is low.
Content of the invention
The technical problem to be solved is to provide a kind of tunnel wide(Particularly(3-7 rice fabric width))Splash guard is pacified Assembling platform, this mounting platform can achieve splash guard, the installation of geotextiles, multiple process procedure such as bar-mat reinforcement colligation.The present invention is also Provide the installation method of above-mentioned tunnel wide splash guard mounting platform.
In order to solve above-mentioned technical problem, the technical scheme is that:
A kind of tunnel wide splash guard mounting platform, including mounting bracket, described mounting bracket bottom is provided with road wheel, Arch laying track is provided with mounting bracket, laying dolly laying track up walk, described laying track is two, respectively Lay track and rear laying track for front, front laying track is arranged on the front end of mounting bracket, laying track is arranged on installation afterwards The rear end of support, front laying track up walked before laying dolly, afterwards laying track up walked after lay dolly, front laying is little Support base is provided with car, rear laying dolly, between the support base on the support base on front laying dolly and rear laying dolly The spool placing rolling splash guard is installed, described spool is unreeled by driving means driving rotation and launches splash guard;Front Between laying track and rear laying track, multiple lifting pins are set, described lifting pin is evenly arranged along arch laying track ring, The two ends of each lifting pin are arranged in mounting bracket by jacking apparatus, and the splash guard of expansion is laid on lifting pin, jacking Lifting pin jacking, the splash guard being laid on lifting pin are lifted tunnel contour face by device.
Software jacking head is provided with described lifting pin, described software jacking head is connect with splash guard positioned at lifting pin surface Touch.
Described software jacking head is in netted dot matrix distribution on lifting pin.Described software jacking head is ring-type, and it is set in On lifting pin.
The jacking apparatus at each lifting pin two ends are one group, and every group of jacking apparatus individually control or Synchronization Control jacking.
It is provided with steel bar positioning frame on described lifting pin.
Described jacking apparatus are hydraulic cylinder.
A kind of waterproof method of plate installation of tunnel wide splash guard mounting platform, comprises the following steps:
(1)Tunnel wide splash guard mounting platform is placed on splash guard installation site;
(2)The front laying dolly of tunnel wide splash guard mounting platform, rear laying dolly are placed on side, in front laying Place spool on dolly, the support base of rear laying dolly, spool places rolling splash guard, and the head end that splash guard is launched is solid Fixed;Along front laying dolly, the rear direction laying carriage walking, by lifting pin successively referred to as the first lifting pin, the second jacking Bar ..., the n-th lifting pin, n be positive integer;
(3)Front laying dolly, rear laying dolly with spool laying track up walk, spool is driven by driving means Rotation unreels, and crosses the first lifting pin in front laying dolly, rear laying dolly with waterproof coiled sheet, the splash guard of expansion is layered on After on first lifting pin, the splash guard being layered on the first lifting pin is fixed on the first lifting pin;
(4)Front laying dolly, rear laying dolly are with waterproof coiled sheet opposite direction walking predetermined distance d;Described walking is predetermined Variable apart from d;
(5)Front laying dolly, rear laying dolly continue positive direction walking with waterproof coiled sheet, in front laying dolly, Hou Pu If dolly is crossed after the first lifting pin with waterproof coiled sheet, by step(3)In be fixed on splash guard on the first lifting pin and release Fixing, and the splash guard being now in above the first lifting pin is fixed on the first lifting pin;
(6)Front laying dolly, rear laying dolly continue positive direction walking with waterproof coiled sheet, according to step(3)~(5)'s Mode splash guard is laid and is fixed on successively the second lifting pin ..., on the n-th lifting pin;
(7)The head end that splash guard is launched releases to be fixed, the jacking apparatus at lifting pin two ends by lifting pin jacking, by waterproof Plate is raised to installation site, and splash guard is connected on tunnel contour face.
The present invention also provides the waterproof method of plate installation of another kind of tunnel wide splash guard mounting platform, walks including following Suddenly:
(1)Tunnel wide splash guard mounting platform is placed on splash guard installation site;
(2)The front laying dolly of tunnel wide splash guard mounting platform, rear laying dolly are placed on side, in front laying Place spool on dolly, the support base of rear laying dolly, spool places rolling splash guard, and the head end that splash guard is launched is solid Fixed;Along front laying dolly, the rear direction laying carriage walking, by lifting pin successively referred to as the first lifting pin, the second jacking Bar ..., the n-th lifting pin, n be positive integer;
(3)Front laying dolly, rear laying dolly with spool laying track up walk, spool is driven by driving means Rotation unreels;
(4)Before controlling, laying dolly, rear laying carriage walking speed and spool velocity of rotation, make the speed of expansion splash guard Speed more than carriage walking;
(5)Cross the first lifting pin in front laying dolly, rear laying dolly with spool, the splash guard of expansion is layered on the After on one lifting pin, the splash guard being layered on the first lifting pin is fixed on the first lifting pin;As gripped by fixture On lifting pin;
(6)Front laying dolly, rear laying dolly walk on waterproof coiled sheet, according to step(3)~(5)Mode according to Secondary splash guard is laid and is fixed on the second lifting pin ..., on the n-th lifting pin;
(7)The head end that splash guard is launched releases to be fixed, the jacking apparatus at lifting pin two ends by lifting pin jacking, by waterproof Plate is raised to installation site, and splash guard is connected on tunnel contour face.
The function of tunnel wide splash guard mounting platform of the present invention:
(1)Waterproof layer integrally launches, integral jacking, improves installation positioning precision, improves splash guard(Geotextiles)Apply Working medium amount, significantly improves construction effect, decreases operation of ascending a height in hole, greatly reduces labor intensity, improves work effect Rate.
It is capable of jacking(Splash guard)The arbitrariness of surface modeling, meets the irregular spy of Tunnel profile Point;Using the point way of contact of software jacking head, overcome the scraggly contact of Tunnel contour surface difficult it is ensured that Waterproof layer and the closely connected stationary positioned of tunnel contour.
(2)By tunnel reinforcing bar annular steel bar overall binding technique, it is placed in chassis jack-up system(I.e. lifting apparatus and jacking Bar)On, form the jacking rod lift arch colligation platform that can freely up and down move, overcome work high above the ground and the work that bears a heavy burden The constructional difficulties of industry, after the completion of colligation on the height of suitable manual work, jacking is to design attitude for reinforcing bar.On jack-up system (Specifically on lifting pin)Devise steel bar positioning frame, be automatically positioned bar spacing, and effectively fixing.Had using jack-up system Entirety and separating action function it is achieved that the adaptability of steel hoop net and tunnel contour positioning.
(3)Tunnel geotextiles are constructed, splash guard is constructed, bar-mat reinforcement colligation construction, is effectively combined a job flat On platform, save construction space in tunnel, optimized construction process, improve technique and automatization level, substantially reduce the number height Idle job, saves labour cost, improves construction quality, improve operating condition, breach the construction of 3-7 rice fabric width splash guard Installation question, improves work efficiency, reduces labor intensity, decreases weld seam quantity, overlaps quantity, improves splash guard and installs matter Amount.Take construction channel time short, be that construction and excavation provides the time, comprehensively improve construction efficiency.Change steel in tunnel The construction technology of the artificial single colligation of muscle net colligation, significantly improves construction quality, reduces labor intensity, improve constructor The construction operation condition of member and construction safety.
The tunnel wide splash guard mounting platform of the present invention realize construction technology process and construction overall process mechanization, from Dynamicization, reduces artificial high-altitude lifting work intensity, construction quality and efficiency of construction greatly improve, and reduce the peace in work progress Full blast danger.
Brief description
The present invention is further detailed explanation with reference to the accompanying drawings and detailed description.
Fig. 1 is mounting platform structural representation of the present invention.
Fig. 2 is that in installation method of the present invention, splash guard fixes schematic diagram one.
Fig. 3 is that in installation method of the present invention, splash guard fixes schematic diagram two.
Specific embodiment
As shown in figure 1, a kind of tunnel wide splash guard mounting platform, including mounting bracket, described mounting bracket bottom sets It is equipped with road wheel 8, mounting bracket is provided with front laying track 1 and rear laying track 2, front laying track 1 is arranged on installation The front end of frame 7, lays the rear end that track 2 is arranged on mounting bracket 7 afterwards, laying dolly 3 before on front laying track 1 there being walking, after On laying track 2, walking lays dolly 4 after having.
Support base 5,6 is provided with front laying dolly 3, rear laying dolly 4, the support base 5 on front laying dolly 3 with after Between support base 6 on laying dolly 4, the spool 11 placing rolling splash guard is installed, described spool 11 is driven by driving means Dynamic rotation unreels and launches splash guard 12.The driving means of spool 11 can adopt motor, motor rotation axis and spool 11 to connect, Motor rotation axis rotate and drive spool 11 to rotate.
The driving means of the front laying dolly 3 of the present invention, rear laying dolly 4 and driving spool 11 adopt control system control System, laying dolly 3, the walking of rear laying dolly 4, stopping, the speed of walking etc. before can controlling, can be by controlling spool 11 driving means, thus controlling spool 11 velocity of rotation, finally control splash guard 12 unreels speed.Driving as spool 11 When device adopts motor, the rotating speed of controlled motor just can control the rotating speed of spool 11.
Multiple lifting pins 9 are set between front laying track 1 and rear laying track 2, described lifting pin 9 is along arch laid rail Road ring is evenly arranged, and the two ends of each lifting pin 9 are arranged in mounting bracket 7 by jacking apparatus 10, the splash guard of expansion 12 are laid on lifting pin 9, and lifting pin 9 jacking, the splash guard 12 being laid on lifting pin 9 are lifted by jacking apparatus 10 Tunnel contour face.The position of lifting bar 9 can be corresponding with the mount point position of splash guard 12 or be not correspond to.
Jacking apparatus 10 are with tunnel contour shape(Sub-circular is identical with laying track)Uniformly, the position of jacking apparatus 10 Angle faces corresponding tunnel contour face.
Front laying dolly 3, rear laying dolly 4 are walked with spool 11, and the splash guard 12 that spool 11 launches is laid on top On rising stem 9, lifting pin 9 jacking, the splash guard 12 being laid on lifting pin 9 are lifted tunnel contour by jacking apparatus 10 Face.Jacking apparatus 10 are the elevating mechanism of hydraulic cylinder one class, and here is not limited.
Often, Tunnel contour surface is rough and uneven in surface, because tunnel contour surface relief is uneven, and splash guard 12 It is smooth entirety, so, the tunnel contour face of depressed area is difficult to contact with splash guard 12, therefore it is difficult to ensure that splash guard 12 Closely connected stationary positioned with tunnel contour.In order to solve this problem, software jacking 13 is provided with described lifting pin 9, soft Body jacking 13 is the jacking head that soft material does, and quality is soft, has certain retractility, such as silica gel material.Software jacking 13 are located at lifting pin 9 surface, and software jacking 13 contacts with splash guard 12, form point and contact.
During splash guard 12 jacking, in the tunnel contour face of protruding parts:Software jacking 13 is in lifting pin 9 and splash guard Between 12, software jacking 13 is subject to lifting pin 9 and the compressing of splash guard 12 to support splash guard 12 with deformation state.
Tunnel contour face in depressed area:Because splash guard 12 top is depressed area, there is no support force, now software The dynamics of lifting pin 9 suffered by jacking 13 is transferred on splash guard 12, and the splash guard 12 at this position is just fitted in depressed area On tunnel contour face.
Described software jacking 13 can be specifically ring-type, so can directly be set on lifting pin, can basis The concrete depressed area in tunnel contour face adjusts the position of software jacking 13.Can also divide in netted dot matrix on lifting pin Cloth.
The jacking apparatus 10 at each lifting pin two ends are one group, and every group of jacking apparatus 10 individually control or Synchronization Control top Rise, or independent control coordinates together with Synchronization Control jacking.I.e. control system can be as needed to every group of jacking apparatus 10 Control with synchronizing, it is sent with jacking signal so as to synchronization of jacking up;As needed every group of jacking apparatus 10 can also be entered Row is individually controlled, and individually sends jacking signal to it, makes single group jacking apparatus 10 jacking, it is possible to achieve jacking surface modeling Arbitrariness, meets the irregular feature of Tunnel profile, realizes closely connected with Tunnel profile.For jacking dress Put 10 independent control to coordinate with above-mentioned software jacking 13, carry out for the tunnel contour face with larger depressed area Rational process.
Above-mentioned various schemes are all applied to following two installation methods.
Splash guard 12 installation method of above-mentioned tunnel wide splash guard 12 mounting platform, comprises the following steps:
(1)Tunnel wide splash guard 12 mounting platform is placed on splash guard 12 installation site.
(2)The front laying dolly 3 of tunnel wide splash guard 12 mounting platform, rear laying dolly 4 are placed on side, front Place spool 11 on laying dolly 3, the support base 5,6 of rear laying dolly 4, rolling splash guard 12 placed by spool 11, and will prevent The head end that water plate 12 launches is fixed;Along the direction of front laying dolly 3, rear laying dolly 4 walking, lifting pin is referred to as successively first Lifting pin, the second lifting pin ..., the n-th lifting pin, n be positive integer;N size is actual according to splash guard 12 length and sag size To determine, such as using 5 lifting pins.
(3)Front laying dolly 3, rear laying dolly 4 with spool 11 laying track up walk, spool 11 is filled by driving Put driving rotation to unreel, volume 12 cross the first lifting pin in front laying dolly 3, rear laying dolly 4 with splash guard, by launch After splash guard 12 is layered on the first lifting pin, the splash guard 12 being layered on the first lifting pin is fixed on the first lifting pin.
(4)Front laying dolly 3, rear laying dolly 4 are with splash guard volume 12 opposite directions walking predetermined distance d;Described walking Predetermined distance d is variable, and the size with specific reference to requirement of engineering sag to determine its size.
(5)Front laying dolly 3, rear laying dolly 4 continue positive directions walking by volume 12 with splash guard, front laying dolly 3, Laying dolly 4 is crossed after the first lifting pin by volume 12 with splash guard, by step afterwards(3)In be fixed on waterproof on the first lifting pin Plate 12 releases to be fixed, and the splash guard 12 being now in above the first lifting pin is fixed on the first lifting pin;
(6)Front laying dolly 3, rear laying dolly 4 continue positive direction walking by volume 12 with splash guard, according to step(3)~ (5)Mode successively splash guard 12 is laid and is fixed on the second lifting pin ..., on the n-th lifting pin.
As, as shown in Figure 2,3, in front laying dolly 3, lay dolly 4 afterwards with spool 11 taking the second lifting pin as a example(Volume Axle 11 drives rotation to unreel by driving means)Cross the second lifting pin, the splash guard 12 of expansion is layered on the second lifting pin Afterwards, the splash guard 12 being layered on the first lifting pin is fixed on the second lifting pin by fixture, is fixed on splash guard 12 Fixing point is A;Front laying dolly 3, rear laying dolly 4 are with splash guard volume 12 opposite directions walking predetermined distance d;Front laying dolly 3rd, rear laying dolly 4 continues positive direction walking by volume 12 with splash guard, in front laying dolly 3, rear laying dolly 4 with splash guard After volume 12 cross the second lifting pin, the splash guard 12 being fixed on the second lifting pin is released fixation, that is, release A on splash guard 12 Fixed relationship between point and the second lifting pin, and the splash guard 12 being now in above the second lifting pin is fixed on the second jacking On bar, that is, the B point on splash guard 12 is fixed with the second lifting pin, now just can form the sag of 2d length.
(7)The head end that splash guard 12 is launched releases to be fixed, and the jacking apparatus 10 at lifting pin two ends, will by lifting pin jacking Splash guard 12 is raised to installation site, and splash guard 12 is connected on tunnel contour face.
The distance of 2d is the sag of splash guard 12, can be realized easily by the inventive method.Solve splash guard 12 to pacify Dress sag is difficult to reserve, even if achieving, reserved erection dip also uneven problem.Sag alleged by the present invention refers to prevent When water plate 12 is fixed on tunnel contour face, between two neighboring fixing point, the length of splash guard 12 is more than two neighboring fixing point The distance between, under gravity, the cambered surface of the sagging formation of splash guard 12 between two fixing points.Sag is used for compensating filling Note concrete impacts to splash guard 12.
Another kind of installation method of splash guard 12 of tunnel wide splash guard 12 mounting platform of the present invention, comprises the following steps:
(1)Tunnel wide splash guard 12 mounting platform is placed on splash guard 12 installation site.
(2)The front laying dolly 3 of tunnel wide splash guard 12 mounting platform, rear laying dolly 4 are placed on side, front Place spool 11 on laying dolly 3, the support base 5,6 of rear laying dolly 4, rolling splash guard 12 placed by spool 11, and will prevent The head end that water plate 12 launches is fixed;Along the direction of front laying dolly 3, rear laying dolly 4 walking, lifting pin is referred to as successively first Lifting pin, the second lifting pin ..., the n-th lifting pin, n be positive integer.
(3)Front laying dolly 3, rear laying dolly 4 with spool 11 laying track up walk, spool 11 is filled by driving Put driving rotation to unreel.
(4)Before controlling, laying dolly 3, rear laying dolly 4 speed of travel and spool 11 velocity of rotation, make expansion splash guard 12 Speed be more than carriage walking speed;The purpose of above-mentioned speed difference is to make to unreel speed to be more than carriage walking speed, so just Splash guard 12 can be made to have certain sag, the sag according to specific requirement just may be used adjusting above-mentioned speed difference.
(5)Cross the first lifting pin in front laying dolly 3, rear laying dolly 4 with spool 11, the splash guard 12 that will launch After being layered on the first lifting pin, the splash guard 12 being layered on the first lifting pin is fixed on the first lifting pin;Splash guard 12 can To be clamped on lifting pin by fixture.
(6)Front laying dolly 3, rear laying dolly 4 volume 12 walk on splash guard, according to step(3)~(5)Side Formula successively splash guard 12 is laid and is fixed on the second lifting pin ..., on the n-th lifting pin.
(7)The head end that splash guard 12 is launched releases to be fixed, and the jacking apparatus 10 at lifting pin two ends, will by lifting pin jacking Splash guard 12 is raised to installation site, and splash guard 12 is connected on tunnel contour face.
Mounting platform of the present invention can effectively reduce high-altitude heavy burden task difficulty, can achieve splash guard 12 in conjunction with automatic technology (Geotextiles)Automatically draw and launch, automatically control and realize sag and lay, jacking is lifted, and realizes wide cut(As 7 meters)Splash guard 12(Soil Work cloth)Installation, reduce 50% overlapping the slot welding, improve tunnel water proofing reliability, and save more than 10% splash guard 12 material Material, reduces weld seam leak risk 55%.
On mounting platform of the present invention, it is integrated with geotextiles installation, splash guard 12 installation, reinforced mesh colligation The multinomial construction function such as construction, enclosing rock measure, improves the automatization level of construction technology technology, during a large amount of minimizing work high above the ground Between, save labor cost.
With the customization of tunnel excavation overall size, according to the classification of single two-wire, tunnel is widened with the tunnel of section and differing heights Section strong applicability.This platform have automatically move, elevating function, the conformability with various surrounding rock category tunneling profiles Good, to narrow space operation strong adaptability in tunnel.
Improve operating condition, improve installation efficiency, reduce manpower consumption in work progress, material consumption and machinery and consume, Reduce the damage probability to splash guard 12.
Described lifting pin can carry out jacking as reinforcing bar jacking bracket to reinforcing bar, can also be provided with steel on lifting pin Muscle locating rack, is automatically positioned to bar spacing.
Above-described embodiment limits the present invention never in any form, every is obtained by the way of equivalent or equivalent transformation Technical scheme all fall within protection scope of the present invention.

Claims (10)

1. a kind of tunnel wide splash guard mounting platform, including mounting bracket, described mounting bracket bottom is provided with road wheel, peace Dress support on be provided with arch laying track, laying dolly laying track up walk it is characterised in that:Described laying track be Article two, respectively front laying track and rear laying track, front laying track is arranged on the front end of mounting bracket, laying track peace afterwards Be contained in the rear end of mounting bracket, front laying track up walked before laying dolly, afterwards laying track up walked after lay dolly, Support base is provided with front laying dolly, rear laying dolly, on the support base on front laying dolly and rear laying dolly Between support seat, the spool placing rolling splash guard is installed, described spool drives rotation to unreel splash guard exhibition by driving means Open;Multiple lifting pins are set between front laying track and rear laying track, described lifting pin is equal along arch laying track ring Even arrangement, the two ends of each lifting pin are arranged in mounting bracket by jacking apparatus, and the splash guard of expansion is laid on lifting pin On, lifting pin jacking, the splash guard being laid on lifting pin are lifted tunnel contour face by jacking apparatus.
2. tunnel wide splash guard mounting platform according to claim 1 it is characterised in that:It is provided with described lifting pin Software jacking head, described software jacking head is contacted with splash guard positioned at lifting pin surface.
3. tunnel wide splash guard mounting platform according to claim 2 it is characterised in that:Described software jacking head is ring Shape is set on lifting pin, and it is in netted dot matrix distribution on lifting pin.
4. tunnel wide splash guard mounting platform according to claim 2 it is characterised in that:The top at each lifting pin two ends Rise device and be one group, every group of jacking apparatus individually control or Synchronization Control jacking.
5. tunnel wide splash guard mounting platform according to claim 1 it is characterised in that:It is provided with described lifting pin Steel bar positioning frame.
6. tunnel wide splash guard mounting platform according to claim 1 it is characterised in that:Described jacking apparatus are hydraulic pressure Cylinder.
7. the waterproof method of plate installation of the tunnel wide splash guard mounting platform described in a kind of employing any one of claim 1-6, It is characterized in that comprising the following steps:
(1)Tunnel wide splash guard mounting platform is placed on splash guard installation site;
(2)The front laying dolly of tunnel wide splash guard mounting platform, rear laying dolly are placed on side, little in front laying Place spool on car, the support base of rear laying dolly, spool places rolling splash guard, and the head end that splash guard is launched is solid Fixed;Along front laying dolly, the rear direction laying carriage walking, by lifting pin successively referred to as the first lifting pin, the second jacking Bar ..., the n-th lifting pin, n be positive integer;
(3)Front laying dolly, rear laying dolly with spool laying track up walk, spool passes through driving means and drives rotation Unreel, cross the first lifting pin in front laying dolly, rear laying dolly with waterproof coiled sheet, the splash guard of expansion is layered on first After on lifting pin, the splash guard being layered on the first lifting pin is fixed on the first lifting pin;
(4)Front laying dolly, rear laying dolly are with waterproof coiled sheet opposite direction walking predetermined distance d;
(5)Front laying dolly, rear laying dolly continue positive direction walking with waterproof coiled sheet, little in front laying dolly, rear laying Car is crossed after the first lifting pin with waterproof coiled sheet, by step(3)In be fixed on splash guard on the first lifting pin and release and fix, And the splash guard being now in above the first lifting pin is fixed on the first lifting pin;
(6)Front laying dolly, rear laying dolly continue positive direction walking with waterproof coiled sheet, according to step(3)~(5)Mode Splash guard is laid and is fixed on successively the second lifting pin ..., on the n-th lifting pin;
(7)The head end that splash guard is launched releases to be fixed, and the jacking apparatus at lifting pin two ends, by lifting pin jacking, splash guard are lifted Rise to installation site, splash guard is connected on tunnel contour face.
8. waterproof method of plate installation according to claim 7 it is characterised in that:In step(4)In, the pre- spacing of described walking Variable from d.
9. the waterproof method of plate installation of the tunnel wide splash guard mounting platform described in a kind of employing any one of claim 1-6, It is characterized in that comprising the following steps:
(1)Tunnel wide splash guard mounting platform is placed on splash guard installation site;
(2)The front laying dolly of tunnel wide splash guard mounting platform, rear laying dolly are placed on side, little in front laying Place spool on car, the support base of rear laying dolly, spool places rolling splash guard, and the head end that splash guard is launched is solid Fixed;Along front laying dolly, the rear direction laying carriage walking, by lifting pin successively referred to as the first lifting pin, the second jacking Bar ..., the n-th lifting pin, n be positive integer;
(3)Front laying dolly, rear laying dolly with spool laying track up walk, spool passes through driving means and drives rotation Unreel;
(4)Before controlling, laying dolly, rear laying carriage walking speed and spool velocity of rotation, make the speed of expansion splash guard be more than The speed of carriage walking;
(5)Cross the first lifting pin in front laying dolly, rear laying dolly with spool, the splash guard of expansion is layered on the first top After on rising stem, the splash guard being layered on the first lifting pin is fixed on the first lifting pin;
(6)Front laying dolly, rear laying dolly walk on waterproof coiled sheet, according to step(3)~(5)Mode successively will Splash guard lay and be fixed on the second lifting pin ..., on the n-th lifting pin;
(7)The head end that splash guard is launched releases to be fixed, and the jacking apparatus at lifting pin two ends, by lifting pin jacking, splash guard are lifted Rise to installation site, splash guard is connected on tunnel contour face.
10. waterproof method of plate installation according to claim 9 it is characterised in that:Described splash guard is solid by fixture clamping It is scheduled on lifting pin.
CN201410151201.1A 2014-04-09 2014-04-15 Wide tunnel waterproof board installation platform and installation method Expired - Fee Related CN103899337B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410151201.1A CN103899337B (en) 2014-04-09 2014-04-15 Wide tunnel waterproof board installation platform and installation method

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
CN201410138494.X 2014-04-09
CN201410138494 2014-04-09
CN201410138494X 2014-04-09
CN201410151201.1A CN103899337B (en) 2014-04-09 2014-04-15 Wide tunnel waterproof board installation platform and installation method

Publications (2)

Publication Number Publication Date
CN103899337A CN103899337A (en) 2014-07-02
CN103899337B true CN103899337B (en) 2017-02-15

Family

ID=50990881

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201420182404.2U Expired - Lifetime CN203809019U (en) 2014-04-09 2014-04-15 Tunnel wide waterproof plate mounting platform
CN201410151201.1A Expired - Fee Related CN103899337B (en) 2014-04-09 2014-04-15 Wide tunnel waterproof board installation platform and installation method

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201420182404.2U Expired - Lifetime CN203809019U (en) 2014-04-09 2014-04-15 Tunnel wide waterproof plate mounting platform

Country Status (2)

Country Link
CN (2) CN203809019U (en)
WO (1) WO2015154698A1 (en)

Families Citing this family (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203809019U (en) * 2014-04-09 2014-09-03 邓卫东 Tunnel wide waterproof plate mounting platform
CN104879142B (en) * 2015-04-24 2017-03-15 邓卫东 Tunnel wide splash guard mounting platform pin-lift arrangement
CN105422143B (en) * 2015-12-25 2018-01-05 德阳思远重工有限公司 Constructing tunnel intelligence chassis
CN105443148A (en) * 2015-12-25 2016-03-30 德阳思远重工有限公司 Jacking mechanism and trolley using same
CN105422144B (en) * 2015-12-25 2018-01-19 德阳思远重工有限公司 Waterproof material conveying mechanism for chassis
CN107091719B (en) * 2017-04-01 2019-04-26 招商局重庆交通科研设计院有限公司 A kind of Tunnel splash guard weld seam airtight detection method
CN107100651B (en) * 2017-05-13 2023-05-26 山东佳信机械设备有限公司 Tunnel lining seamless connection reinforcing steel bar positioning and waterproof board laying trolley
CN106996298A (en) * 2017-05-19 2017-08-01 龚岗 The positioning of tunnel double-lining reinforcing bar, laying and liftout attachment
CN107893671A (en) * 2017-08-28 2018-04-10 北京建工土木工程有限公司 A kind of large cross-section tunnel waterproof construction method
CN107882582A (en) * 2017-12-13 2018-04-06 中铁十七局集团第二工程有限公司 Mobile hydraulic Work protection platform in a kind of tunnel
CN108194111A (en) * 2018-01-26 2018-06-22 中国水利水电第七工程局有限公司 A kind of umbrella arch splash guard, reinforced mesh are laid with ancillary equipment
CN108756892B (en) * 2018-04-03 2023-08-18 中南大学 Work platform, continuous operation system and continuous operation method for tunnel construction
CN108468558B (en) * 2018-05-31 2023-06-06 中铁隧道集团二处有限公司 Tunnel waterproof board laying trolley with multiple degrees of freedom adjusting function
CN109051848B (en) * 2018-07-18 2024-01-05 湖南进军隧道智能装备有限公司 Excavation grudging post hoist mechanism
CN108843350A (en) * 2018-07-23 2018-11-20 中铁十七局集团第三工程有限公司 A kind of coiled material hangs fixed device
CN108798727B (en) * 2018-08-02 2024-04-02 甘肃路桥第三公路工程有限责任公司 Tunnel self-propelled waterproof board cloth hanging steel bar positioning integrated multifunctional trolley and application
CN109026081B (en) * 2018-09-03 2023-07-04 湖南五新隧道智能装备股份有限公司 A device for waterproofing membrane
CN109098734B (en) * 2018-10-23 2023-09-15 中铁一局集团有限公司 Self-contained track laying device for tunnel lining trolley and application method of self-contained track laying device
CN109505632A (en) * 2018-12-24 2019-03-22 长安大学 A kind of novel tunnel waterproof layer is laid with trolley and its application method
CN109899094B (en) * 2019-04-04 2024-02-27 涪特智能装备(重庆)有限公司 Comprehensive trolley for laying geotextile and waterproof board and mechanical laying method
CN110159320B (en) * 2019-06-28 2024-05-10 中铁隧道集团二处有限公司 Waterproof board, geotextile spreading device and construction method of geotextile spreading device
CN111911192A (en) * 2020-07-25 2020-11-10 林志鹏 Highway tunnel section steel concrete supporting construction
CN112145209B (en) * 2020-09-30 2023-03-31 中铁二十局集团有限公司 Waterproof board laying method
CN112160775B (en) * 2020-09-30 2023-03-31 中铁二十局集团有限公司 Waterproof board laying method
CN112228126B (en) * 2020-10-26 2021-10-01 昆明理工大学 Contractibility power transmission connecting device suitable for primary support of large-deformation tunnel
CN112502748A (en) * 2020-10-29 2021-03-16 将乐县国通隧道机械有限公司 Tunnel waterproof cloth trolley climbing device
CN112726302A (en) * 2020-12-30 2021-04-30 洛阳腾誉隧道机械有限公司 Automatic laying device of lining cutting platform truck rail
CN112943316A (en) * 2021-02-26 2021-06-11 成都建工路桥建设有限公司 Waterproof board trolley waterproof coiled material laying auxiliary device and laying method thereof
CN112963180A (en) * 2021-02-26 2021-06-15 成都建工路桥建设有限公司 Semi-automatic waterproof coiled material laying device and method for waterproof board trolley
CN113446035A (en) * 2021-08-03 2021-09-28 四川路桥盛通建筑工程有限公司 Tunnel waterproof plate mounting trolley structure and construction method thereof
CN114183176A (en) * 2021-12-10 2022-03-15 洛阳中天建工机械有限公司 Telescopic cloth hanging trolley and cloth hanging control method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061927A (en) * 2010-12-10 2011-05-18 中铁隧道集团有限公司 Tunnel waterproof material laying equipment and method
CN203441504U (en) * 2013-09-15 2014-02-19 中铁一局集团有限公司 Construction platform used for hanging waterproof board in tunnel
CN203463116U (en) * 2013-07-25 2014-03-05 重庆广播电视大学 Self-propelled tunnel waterproof board laying rack
CN203809019U (en) * 2014-04-09 2014-09-03 邓卫东 Tunnel wide waterproof plate mounting platform

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04130400U (en) * 1991-05-24 1992-11-30 謙一 小谷 Formwork device for pasting tunnel inner wall materials
JP3467653B2 (en) * 1994-05-19 2003-11-17 株式会社ケー・エフ・シー Tunnel waterproofing sheet construction method and its construction frame
DE50003291D1 (en) * 1999-07-06 2003-09-18 Tecton Holding Ag Luzern DEVICE FOR LAYING SEALING FILMS BY ADHESIVE ON WALLS OF CONSTRUCTIONS
JP3338878B2 (en) * 2000-08-25 2002-10-28 株式会社ケー・エフ・シー Apparatus and method for applying anticorrosion sheet
CN202202872U (en) * 2011-05-26 2012-04-25 中铁七局集团第四工程有限公司 Railway tunnel lining jacking frame
CN202300428U (en) * 2011-10-28 2012-07-04 成都市新筑路桥机械股份有限公司 Trolley for installing tunnel waterproof plate
CN203081468U (en) * 2013-01-23 2013-07-24 湘潭光威机械科技有限公司 Tunnel waterproof layer laying trolley

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061927A (en) * 2010-12-10 2011-05-18 中铁隧道集团有限公司 Tunnel waterproof material laying equipment and method
CN203463116U (en) * 2013-07-25 2014-03-05 重庆广播电视大学 Self-propelled tunnel waterproof board laying rack
CN203441504U (en) * 2013-09-15 2014-02-19 中铁一局集团有限公司 Construction platform used for hanging waterproof board in tunnel
CN203809019U (en) * 2014-04-09 2014-09-03 邓卫东 Tunnel wide waterproof plate mounting platform

Also Published As

Publication number Publication date
WO2015154698A1 (en) 2015-10-15
CN103899337A (en) 2014-07-02
CN203809019U (en) 2014-09-03

Similar Documents

Publication Publication Date Title
CN103899337B (en) Wide tunnel waterproof board installation platform and installation method
CN105951994B (en) A kind of expansion installation method of cylindrical reticulated shell closing awning
CN106522112B (en) Cable-stayed bridge end bay beam section construction system and its method
CN104532843B (en) A kind of steel column location straightening method of stand column pile
CN108678752B (en) Shaft equipment rapid installation process
CN109736844B (en) Rapid construction method for tunnel primary support
CN104060844A (en) Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof
CN108756892B (en) Work platform, continuous operation system and continuous operation method for tunnel construction
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN104264999A (en) Large roof grid structure assembling and installing method
CN103318768A (en) Assembling method of quayside with low posture
CN110820774A (en) Device for rolling steel wire meshes laid on side slopes and using method thereof
CN110499702A (en) A kind of cable saddle positioning reinforcing device of Cable-stayed Bridge Pylon
CN207998792U (en) A kind of Hanging Basket rack mounting structure
CN104879142B (en) Tunnel wide splash guard mounting platform pin-lift arrangement
CN202707071U (en) Unfolded type tunnel construction lining trolley
CN105569054A (en) Device and method for controlling direction and elevation of lattice column below ground
CN205662832U (en) Under hold formula beiLei beam steel suspension bridge
CN102444275A (en) Silo flexible slip form torsion resistance construction device
CN107780952A (en) Tunnel anti-seep water laser positioning geotextiles mount method
CN107587885A (en) Two lining trolley structures and assembling method in a kind of standard cross-section of tunnel
CN106800245B (en) A kind of floorings lifting hanger, hanging apparatus and hanging method
CN204282843U (en) The sliding hoisted in position device of steel girder erection in a kind of stiffness combination construction
CN201738936U (en) Flexible metal mesh bracket and laying device
CN207293976U (en) A kind of cantilever crane set up for bridge subsection transport

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170215