CN103556575A - 跨越铁路主干线的钢箱梁落梁施工方法 - Google Patents
跨越铁路主干线的钢箱梁落梁施工方法 Download PDFInfo
- Publication number
- CN103556575A CN103556575A CN201310555114.8A CN201310555114A CN103556575A CN 103556575 A CN103556575 A CN 103556575A CN 201310555114 A CN201310555114 A CN 201310555114A CN 103556575 A CN103556575 A CN 103556575A
- Authority
- CN
- China
- Prior art keywords
- falls
- steel case
- steel
- construction method
- pad
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 70
- 239000010959 steel Substances 0.000 title claims abstract description 70
- 238000010276 construction Methods 0.000 title claims abstract description 24
- 239000003351 stiffener Substances 0.000 claims description 12
- 241000218652 Larix Species 0.000 claims description 6
- 235000005590 Larix decidua Nutrition 0.000 claims description 6
- 239000011229 interlayer Substances 0.000 claims description 5
- 239000002023 wood Substances 0.000 claims description 5
- 238000000465 moulding Methods 0.000 claims description 4
- 239000010410 layer Substances 0.000 claims description 3
- 239000004575 stone Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 5
- 238000010586 diagram Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
Images
Landscapes
- Heat Treatment Of Steel (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
一种跨越铁路主干线的钢箱梁落梁施工方法,它包括:第一阶段:首先采用步履式顶推设备直接落梁20-40cm;然后,用顶推设备下部的顶升装置落梁40-60cm,钢箱梁落在工型钢上;第二阶段:在钢箱梁永久支座上搭设至少三个落梁支垫,钢箱梁落在支座位置的落梁支垫上,落梁8-15cm;以后每次落梁10-20cm,落梁100cm第三阶段:用三向千斤顶落梁直至到位。采用上述技术方案的本发明,在该施工方法中,钢箱梁采用单箱整体式断面结构,能够保证在落梁过程中箱梁的整体稳定性;同时,在箱梁底板受力位置增设20mmX850mmX850mm以钢板减小箱梁底板局部应力。
Description
技术领域
本发明涉及一种桥梁落梁施工方法,具体地说是涉及一种针对跨越铁路主干线的钢箱梁落梁施工方法。
背景技术
在桥梁施工时,受所建设地的环境影响特别大。若桥梁处于机场飞机起降航道位置,且跨越铁路主干线时,现行没有特别好的落梁施工方法。
而且在落梁过程中,还需要解决箱梁整体及局部稳定性的问题,这些在现有技术中均没有体现。
发明内容
本发明的目的是提供一种针对跨越铁路主干线的钢箱梁落梁施工方法。
为实现上述目的,本发明采用以下技术方案:
一种跨越铁路主干线的钢箱梁落梁施工方法,包括如下三个阶段:
第一阶段:首先采用步履式顶推设备直接落梁20--40cm,钢箱梁落于顶推设备梁段的箱型垫梁上;然后,拆除顶推设备上部水平滑块及水平滑块四周反力座,用顶推设备下部的顶升装置落梁40--60cm,钢箱梁落在工型钢上;
第二阶段:将第一阶段采用的顶推设备拆除,在支座垫石之间搭设三个垫墩,垫墩上放置单向千斤顶,单向千斤顶将钢箱梁顶起,油缸锁死;拆除原放置顶推设备的悬臂梁支架;在钢箱梁永久支座上搭设至少三个落梁支垫,钢箱梁落在支座位置的落梁支垫上,落梁8--15cm;以后每次落梁10--20cm,落梁100cm。
第三阶段:将单向千斤顶改为三向千斤顶,用三向千斤顶落梁,直至到位。
所述的垫墩长100cm,宽150cm,高100cm。
在钢箱梁永久支座上搭设四个落梁支垫,落梁支垫长100cm,宽150cm,高120cm。
所述的落梁支垫包括位于钢箱梁底部的至少两层支垫,层间支垫纵横交错布置;且所述的支垫为落叶松方木。
所述的钢箱梁为单箱整体式结构,且在箱室内竖直设置腹板,箱室底板水平;其中,钢箱梁高3000--3500mm,箱室底板总宽10000--12000 mm,腹板间距3000-4000 mm,顶板顶面横坡同路线横坡。
所述的钢箱梁主体采用Q345qENH钢,顶底板支座段厚度15--25mm,其余厚度13--18mm;腹板厚度13--18mm,支座处隔板厚度15--25mm,其余隔板厚度8--12mm。
在钢箱梁的箱室底板受力位置增设20mmX850mmX850mm加强板。
在钢箱梁内部的千斤顶位置支座隔板两侧增加三道加劲板。
所述的加劲板为倒U型结构。
采用上述技术方案的本发明,提供了一种针对跨越铁路主干线的钢箱梁落梁施工方法,同时在该施工方法中,钢箱梁采用单箱整体式断面结构,能够保证在落梁过程中箱梁的整体稳定性;同时,在箱梁底板受力位置增设20mmX850mmX850mm以钢板减小箱梁底板局部应力,同时在箱梁内部千斤顶位置支座隔板两侧增加三道加劲板,从而确保了落梁施工过程中的梁体局部稳定性。另外,支垫采用落叶松方木层间纵横交错,确保了落梁过程中箱梁的整体稳定,增大了支垫的抗倾覆。
附图说明
图1为第一阶段中用步履式顶推设备直接落梁,钢箱梁落于顶推设备梁段的箱型垫块上的结构示意图。
图2为第一阶段中拆除顶推设备上部水平滑块及滑块四周反力座,用顶推设备下部顶升装置落梁,钢箱梁落在工56型钢上的结构示意图。
图3为第二阶段的落梁示意图。
图4为第二阶段完成后的落梁示意图。、
图5为第三阶段的落梁示意图。
图6为落梁完成后的结构示意图。
图7为钢箱梁的断面结构图。
图8为加劲板的结构图。
具体实施方式
一种跨越铁路主干线的钢箱梁落梁施工方法,它包括如下三个阶段:
第一阶段:首先采用步履式顶推设备101直接落梁20--40cm,钢箱梁落于顶推设备101梁段的箱型垫梁102上,如图1所示;然后,拆除顶推设备上部水平滑块103及水平滑块四周反力座,用顶推设备下部的顶升装置104落梁40--60cm,钢箱梁落在工型钢上,如图2所示;
第二阶段:将第一阶段采用的顶推设备101拆除,在支座垫石106之间搭设三个垫墩106,所述的垫墩106长100cm,宽150cm,高100cm。垫墩106上放置单向千斤顶107,单向千斤顶107将钢箱梁顶起,油缸锁死;拆除原放置顶推设备的悬臂梁支架;在钢箱梁永久支座上搭设至少三个落梁支垫108,落梁支垫108长100cm,宽150cm,高120cm,钢箱梁落在支座位置的落梁支垫上,落梁8--15cm。以后每次落梁10--20cm,落梁100cm。所述的落梁支垫108包括位于钢箱梁底部的至少两层支垫,层间支垫纵横交错布置,且支垫为落叶松方木。本发明中支垫采用落叶松方木层间纵横交错。根据《公路桥涵钢结构及木结构设计规范》(JTJ025)并通过现场对落叶松进行压力实验,压强5.5MPa时压缩变形5mm,压强6.6MPa时压缩变形10mm。
第三阶段:将单向千斤顶107改为三向千斤顶109,用三向千斤顶109落梁,直至到位。
如图7所示,上述的钢箱梁为单箱整体式结构,且在箱室1内竖直设置腹板2,箱室1底板水平;其中,钢箱梁高3000--3500mm,箱室底板3总宽10000--12000 mm,腹板2间距3000-4000 mm,顶板顶面4横坡同路线横坡。也就是说,钢箱梁高可以为3000mm、3112.5mm、3300mm、3500mm中的任意值,箱室1底板总宽为10000mm、11250 mm、11500mm、12000 mm中的任意值,腹板2间距为3000mm、3500mm、3750mm、4000 mm中的任意值。
箱梁主体均采用Q345qENH钢,顶底板5支座段厚度15mm、20mm、25mm中的任意值,其余厚度13--18mm;腹板2厚度为13mm、16mm、18mm中的任意值,支座处隔板厚度为15mm、20mm、25mm中的任意值,其余隔板厚度8--12mm。
如图8所示,为了确保落梁施工过程中的梁体局部稳定,通过计算确定在箱梁底板3受力位置增设20mmX850mmX850mm加强板6以减小箱梁底板局部应力,加强板6为钢板;同时在箱梁内部千斤顶位置支座隔板7两侧增加三道加劲板8,加劲板8为倒U型结构。
Claims (9)
1.一种跨越铁路主干线的钢箱梁落梁施工方法,其特征在于,它包括如下三个阶段:
第一阶段:首先采用步履式顶推设备(101)直接落梁20--40cm,钢箱梁落于顶推设备(101)梁段的箱型垫梁(102)上;然后,拆除顶推设备上部水平滑块(103)及水平滑块四周反力座,用顶推设备下部的顶升装置(104)落梁40--60cm,钢箱梁落在工型钢上;
第二阶段:将第一阶段采用的顶推设备(101)拆除,在支座垫石(105)之间搭设三个垫墩(106),垫墩上放置单向千斤顶(107),单向千斤顶(107)将钢箱梁顶起,油缸锁死;拆除原放置顶推设备的悬臂梁支架;在钢箱梁永久支座上搭设至少三个落梁支垫(108),钢箱梁落在支座位置的落梁支垫(108)上,落梁8--15cm;以后每次落梁10--20cm,落梁100cm;第三阶段:将单向千斤顶改为三向千斤顶(109),用三向千斤顶落梁,直至到位。
2.根据权利要求1所述的跨越铁路主干线的钢箱梁落梁施工方法,其特征在于:所述的垫墩长100cm,宽150cm,高100cm。
3.根据权利要求1所述的跨越铁路主干线的钢箱梁落梁施工方法,其特征在于:在钢箱梁永久支座上搭设四个落梁支垫,落梁支垫长100cm,宽150cm,高120cm。
4.根据权利要求3所述的跨越铁路主干线的钢箱梁落梁施工方法,其特征在于:所述的落梁支垫包括位于钢箱梁底部的至少两层支垫,层间支垫纵横交错布置;且所述的支垫为落叶松方木。
5.根据权利要求1所述的跨越铁路主干线的钢箱梁落梁施工方法,其特征在于:所述的钢箱梁为单箱整体式结构,且在箱室(1)内竖直设置腹板(2),箱室底板(3)水平;其中,钢箱梁高3000--3500mm,箱室底板(3)总宽10000--12000 mm,腹板(2)间距3000-4000 mm,顶板顶面(4)横坡同路线横坡。
6.根据权利要求5所述的跨越铁路主干线的钢箱梁落梁施工方法,其特征在于:所述的钢箱梁主体采用Q345qENH钢,顶底板(5)支座段厚度15--25mm,其余厚度13--18mm;腹板(2)厚度13--18mm,支座处隔板厚度15--25mm,其余隔板厚度8--12mm。
7.根据权利要求5所述的跨越铁路主干线的钢箱梁落梁施工方法,其特征在于:在钢箱梁的箱室底板(3)受力位置增设20mmX850mmX850mm加强板(6)。
8.根据权利要求5所述的跨越铁路主干线的钢箱梁落梁施工方法,其特征在于:在钢箱梁内部的千斤顶位置支座隔板(7)两侧增加三道加劲板(8)。
9.根据权利要求8所述的跨越铁路主干线的钢箱梁落梁施工方法,其特征在于:所述的加劲板(8)为倒U型结构。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310555114.8A CN103556575B (zh) | 2013-11-11 | 2013-11-11 | 跨越铁路主干线的钢箱梁落梁施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310555114.8A CN103556575B (zh) | 2013-11-11 | 2013-11-11 | 跨越铁路主干线的钢箱梁落梁施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103556575A true CN103556575A (zh) | 2014-02-05 |
CN103556575B CN103556575B (zh) | 2015-07-29 |
Family
ID=50010911
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310555114.8A Expired - Fee Related CN103556575B (zh) | 2013-11-11 | 2013-11-11 | 跨越铁路主干线的钢箱梁落梁施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103556575B (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103981809A (zh) * | 2014-05-15 | 2014-08-13 | 宝鸡中铁宝桥天元实业发展有限公司 | 中小桥梁桥面支撑落梁方法及专用支撑装置 |
CN105350457A (zh) * | 2015-11-13 | 2016-02-24 | 中铁大桥局集团第一工程有限公司 | 一种桥梁步履式顶推施工中钢槽梁落梁的方法 |
CN109537460A (zh) * | 2018-11-30 | 2019-03-29 | 中建五局第三建设有限公司 | 一种用于顶推桥梁高位落梁施工方法 |
CN109610345A (zh) * | 2018-12-31 | 2019-04-12 | 中铁六局集团太原铁路建设有限公司 | 转体桥落梁施工方法 |
CN111005324A (zh) * | 2020-01-03 | 2020-04-14 | 中建七局安装工程有限公司 | 一种装配式节段箱梁无支架悬吊与锁定施工工法 |
CN112431140A (zh) * | 2020-12-03 | 2021-03-02 | 武汉思力特种工程机械施工有限公司 | 一种依靠步履机进行大型桥梁高位落梁的施工工法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070175166A1 (en) * | 2005-12-30 | 2007-08-02 | Matthew Ley | Partially prefabricated structural concrete beam |
CN101725115A (zh) * | 2009-12-18 | 2010-06-09 | 中铁大桥局集团第二工程有限公司 | 一种顶推钢箱梁的固定起吊支架装置及施工方法 |
WO2011014291A1 (en) * | 2009-07-27 | 2011-02-03 | Encon Solutions, Llc | Apparatus and method for replacing a bridge using pre-cast construction techniques |
CN102535347A (zh) * | 2012-03-09 | 2012-07-04 | 中铁四局集团第二工程有限公司 | 连续落梁系统及连续落梁方法 |
CN202492807U (zh) * | 2012-03-27 | 2012-10-17 | 中交四航局第一工程有限公司 | 钢箱梁步履式多点顶推施工系统 |
-
2013
- 2013-11-11 CN CN201310555114.8A patent/CN103556575B/zh not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070175166A1 (en) * | 2005-12-30 | 2007-08-02 | Matthew Ley | Partially prefabricated structural concrete beam |
WO2011014291A1 (en) * | 2009-07-27 | 2011-02-03 | Encon Solutions, Llc | Apparatus and method for replacing a bridge using pre-cast construction techniques |
CN101725115A (zh) * | 2009-12-18 | 2010-06-09 | 中铁大桥局集团第二工程有限公司 | 一种顶推钢箱梁的固定起吊支架装置及施工方法 |
CN102535347A (zh) * | 2012-03-09 | 2012-07-04 | 中铁四局集团第二工程有限公司 | 连续落梁系统及连续落梁方法 |
CN202492807U (zh) * | 2012-03-27 | 2012-10-17 | 中交四航局第一工程有限公司 | 钢箱梁步履式多点顶推施工系统 |
Non-Patent Citations (2)
Title |
---|
唐湖北: "大跨度悬索桥落梁法成桥施工技术研究", 《中外建筑》 * |
谢伟伟: "大跨度悬索桥落梁法成桥施工技术", 《中国新技术新产品》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103981809A (zh) * | 2014-05-15 | 2014-08-13 | 宝鸡中铁宝桥天元实业发展有限公司 | 中小桥梁桥面支撑落梁方法及专用支撑装置 |
CN103981809B (zh) * | 2014-05-15 | 2016-01-20 | 宝鸡中铁宝桥天元实业发展有限公司 | 中小桥梁桥面支撑落梁方法及专用支撑装置 |
CN105350457A (zh) * | 2015-11-13 | 2016-02-24 | 中铁大桥局集团第一工程有限公司 | 一种桥梁步履式顶推施工中钢槽梁落梁的方法 |
CN109537460A (zh) * | 2018-11-30 | 2019-03-29 | 中建五局第三建设有限公司 | 一种用于顶推桥梁高位落梁施工方法 |
CN109537460B (zh) * | 2018-11-30 | 2021-06-22 | 中建五局第三建设有限公司 | 一种用于顶推桥梁高位落梁施工方法 |
CN109610345A (zh) * | 2018-12-31 | 2019-04-12 | 中铁六局集团太原铁路建设有限公司 | 转体桥落梁施工方法 |
CN111005324A (zh) * | 2020-01-03 | 2020-04-14 | 中建七局安装工程有限公司 | 一种装配式节段箱梁无支架悬吊与锁定施工工法 |
CN112431140A (zh) * | 2020-12-03 | 2021-03-02 | 武汉思力特种工程机械施工有限公司 | 一种依靠步履机进行大型桥梁高位落梁的施工工法 |
Also Published As
Publication number | Publication date |
---|---|
CN103556575B (zh) | 2015-07-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103556575B (zh) | 跨越铁路主干线的钢箱梁落梁施工方法 | |
CN207160062U (zh) | 一种地下无柱叠合墙车站 | |
CN103410103B (zh) | 铁路既有线快速换梁施工方法 | |
CN107476341A (zh) | 采用装配整体式结构地铁车站预制板拼装方法 | |
CN103938534A (zh) | 高架轨交车站一体化桥梁结构及其应用方法 | |
CN103966947B (zh) | 一种基于桥梁梁体减震的防落梁装置 | |
CN103410062B (zh) | 单线铁路隧道托架式钢轨法施工整体道床的方法 | |
CN101922158A (zh) | 一种地铁下穿越建筑物基础的整体托换隔振装置及方法 | |
CN105350409B (zh) | 城市轨道交通长枕式钢弹簧浮置板道床道岔施工方法 | |
CN202359511U (zh) | 一种地铁隧道水沟与道床一次性浇筑模板结构 | |
CN207793771U (zh) | 中低速磁悬浮交通工程低置线路承轨梁 | |
CN203795460U (zh) | 一种压重式塔式起重机基础结构 | |
CN203958138U (zh) | 利用高架桥底净空建设的高架轻型轨道 | |
CN203654154U (zh) | 一种钢箱梁 | |
CN202369930U (zh) | 用于多层混凝土箱梁的门洞式承重排架装置 | |
CN106274556B (zh) | 一种接触网杆改移方法 | |
CN204457786U (zh) | 一种b管片拆除后的扩挖大直径盾构隧道建造地铁车站 | |
CN204059184U (zh) | 铁路桥梁跨墩 | |
CN207512621U (zh) | 小半径连续梁桥更换支座装置 | |
CN203383151U (zh) | 桥体两侧注浆装置 | |
CN105236265B (zh) | 一种门式起重机轨道加固方法及加固结构 | |
CN206888997U (zh) | 隧道素混凝土衬砌施工用辅助设施 | |
CN204899041U (zh) | 板筋上下保护层控制马凳 | |
CN203878479U (zh) | 架桥机横移支撑 | |
CN105839920B (zh) | 站端临时钢支撑换撑的施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150729 Termination date: 20211111 |