CN103206089A - 装配式铝合金模板体系施工方法 - Google Patents

装配式铝合金模板体系施工方法 Download PDF

Info

Publication number
CN103206089A
CN103206089A CN2013101353754A CN201310135375A CN103206089A CN 103206089 A CN103206089 A CN 103206089A CN 2013101353754 A CN2013101353754 A CN 2013101353754A CN 201310135375 A CN201310135375 A CN 201310135375A CN 103206089 A CN103206089 A CN 103206089A
Authority
CN
China
Prior art keywords
template
wall
installation
earlier
design
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101353754A
Other languages
English (en)
Inventor
成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2013101353754A priority Critical patent/CN103206089A/zh
Publication of CN103206089A publication Critical patent/CN103206089A/zh
Pending legal-status Critical Current

Links

Abstract

本发明公开了一种装配式铝合金模板体系施工方法,包括模板系统设计、模板安装、混凝土浇筑与养护、模板拆除等步骤。本发明施工方便,效果好。

Description

装配式铝合金模板体系施工方法
技术领域
本发明涉及一种装配式铝合金模板体系施工方法。
背景技术
模板作为建筑工程中使用最多的周转材料,目前以木质模板居多,随着低碳、节能越来越被社会所重视,人们把眼光投向了金属模板,如全钢模板等,全钢模板解决了对木材的损耗并在一定程度上加快了施工速度,但全钢模板自重大、对垂直运输体系依赖大,操作不方便等缺点影响了其推广。
发明内容
本发明的目的在于提供一种施工方便、效果好的装配式铝合金模板体系施工方法。
本发明的技术解决方案是:
一种装配式铝合金模板体系施工方法,其特征是:包括下列步骤:
(一)模板系统设计
(1)配板设计
a)铝模板采用模数制设计,通用模板的宽度模数以50mm进级;
b)绘制配板图时,标出模板的位置、规格型号,标绘出单元分界线;有特殊构造时,加以标明并出详细加工图;
c)预埋件和预留孔的位置,在配板图上标明,并注明其固定方法;
d)为设置对拉螺栓或其他拉筋,根据所需位置采用电钻钻孔;
(2)支承系统的设计
a)钢背楞的配置方向与模板的长度方向相垂直,直接承受模板传递的荷载;
b)钢背楞悬挑部分的端部分的挠度与跨中挠度相等,悬挑长度不大于50mm;
c)模板端缝齐平布置时,每块模板有两个支承点;
d)当模板底的净高不大于3.10米时,使用不加水平连杆的单支顶作为支承;
e)单支顶采用内外管设计,外管采用Φ60×2.5的钢管,内管采用Φ48×2.0的钢管;
(二)模板安装
(1)墙、柱模板安装
a)铝合金模板安装前保证设计的预埋件、预留洞口已留置好,管线已铺设完毕;剪力墙的端柱、角柱、暗柱钢筋绑扎安装完毕并已验收合格; 
b)铝合金模板的安装按照先内墙、后外墙的顺序安装,安装完毕后进行垂直及水平标高的调整;安装内墙模板从内角模开始,或从墙头封板开始,安装外墙模板之前先安装外围导墙板,用固定螺丝锚固到混凝土结构中,外墙模板的重量支撑在导墙板上,安装时使用塔吊整体吊装就位;
c)安装洞口模板,按工程要求设置门窗洞口模板,洞口四边与墙模板连接牢固;
d)墙、柱模板的加固处理,墙、柱模板安装完毕后,在模板上预留孔穿上对拉螺杆,对拉螺杆外边附背楞,转角处设置直角背楞,防止墙模板发生扭转、错台,保证结构的顺直光滑;
e)墙、柱模板安装完毕后,安装斜向支撑;
(2)梁、板模板安装
a)安装梁模板及校正:安装时在地面拼接完毕后,整体安装,两边通过转角模固定在墙模板上,安装时先安装模板支撑立杆和底模板,后安装侧模板;
b)楼面龙骨的安装:在所有墙身模板调整完毕后,开始安装楼面龙骨,安装时同样在底端拼装完毕后,整体安装;
c)安装楼面板及调平:楼面模板的安装沿墙边平行逐件安装,先用销子临时固定,再次用水平仪检测梁板模板的平整度,不平的地方通过调节立杆的底托来达到水平度允许范围,最后再统一打紧销子; 
d)防止漏浆:底部用石膏堵缝堵缝,空隙较大处用方木填堵,方木贴在铝合金模板的下端,平直放置,保证层间墙体的平滑过度;铝合金模板安装完毕后,对模板进行一次完整的检查并安装水平拉杆及剪刀撑;
(3)模板校正及固定
模板安装完毕后,对所有墙、柱、梁板进行平整度与垂直度的校核,校核完在墙柱模板上加双方钢背楞并用高强螺栓固定;
(4)模板工程的安装符合下列要求:
1)墙两侧模板的对拉螺栓孔平直相对,钻孔采用机具;
2)钢背楞取用整根杆件,接头错开设置,搭接长度不应少于200mm;
(三)混凝土浇筑与养护
(1)模板工程安装完毕,经检查验收后,进行下道工序; 
(2)处理完毕经过钢筋的隐蔽验收后进行混凝土浇筑; 
(3)混凝土浇筑采用泵送方式进行,施工时先浇筑剪力墙、柱、梁,然后再浇筑水平楼板;混凝土的浇筑采用分层浇筑,并连续进行;
(四)模板拆除
(1)模板拆除
a)混凝土浇筑完毕后,在强度达到规范规定的强度后进行,梁板模板的早拆头及立杆支撑待混凝土强度达到100%后拆除;
b)模板的拆除顺序按模板的设计来,遵循“先支后拆、后支先拆”,先拆除非承重模板、后拆除承重模板的原则;
c)铝合金模板和配件拆除后,清除粘结砂浆杂物,板面涂刷油,对变形及损坏的模板及配件,进行整形和修补; 
d) 模板倒运
模板通过楼板上预留的传料口由人工倒运至上一层,分类整齐堆放,进入下一层的循环施工。
本发明施工方便,效果好。拆除后混凝土表面质量好。按照本工法施工,可确保模板安装平整、牢固,确保混凝土表面达到清水混凝土效果;自重轻、在模板设计时留有供模板倒运的传料口,方便模板通过人工往上倒运,无需占用垂直运输设备;技术含量高、实用性强、周转次数多( 理论上能达到300 次) ,能显著降低工程模板费用,缩短工程施工工期; 经济效益、社会效益显著,具有广阔的应用前景;文明施工程度高,减少建筑废料处理,使用铝合金模板体系的工地文明程度高,而且模板的每一个配件都能重复使用及回收,从而减少了废料处理的成本。
下面结合实施例对本发明作进一步说明。
具体实施方式
一种装配式铝合金模板体系施工方法,包括下列步骤:
(一)模板系统设计
(1)配板设计
a)铝模板采用模数制设计,通用模板的宽度模数以50mm进级;
b)绘制配板图时,标出模板的位置、规格型号,标绘出单元分界线;有特殊构造时,加以标明并出详细加工图;
c)预埋件和预留孔的位置,在配板图上标明,并注明其固定方法;
d)为设置对拉螺栓或其他拉筋,根据所需位置采用电钻钻孔;
(2)支承系统的设计
a)钢背楞的配置方向与模板的长度方向相垂直,直接承受模板传递的荷载;
b)钢背楞悬挑部分的端部分的挠度与跨中挠度相等,悬挑长度不大于50mm;
c)模板端缝齐平布置时,每块模板有两个支承点;
d)当模板底的净高不大于3.10米时,使用不加水平连杆的单支顶作为支承;
e)单支顶采用内外管设计,外管采用Φ60×2.5的钢管,内管采用Φ48×2.0的钢管;
(二)模板安装
(1)墙、柱模板安装
a)铝合金模板安装前保证设计的预埋件、预留洞口已留置好,管线已铺设完毕;剪力墙的端柱、角柱、暗柱钢筋绑扎安装完毕并已验收合格; 
b)铝合金模板的安装按照先内墙、后外墙的顺序安装,安装完毕后进行垂直及水平标高的调整;安装内墙模板从内角模开始,或从墙头封板开始,安装外墙模板之前先安装外围导墙板,用固定螺丝锚固到混凝土结构中,外墙模板的重量支撑在导墙板上,安装时使用塔吊整体吊装就位;
c)安装洞口模板,按工程要求设置门窗洞口模板,洞口四边与墙模板连接牢固;
d)墙、柱模板的加固处理,墙、柱模板安装完毕后,在模板上预留孔穿上对拉螺杆,对拉螺杆外边附背楞,转角处设置直角背楞,防止墙模板发生扭转、错台,保证结构的顺直光滑;
e)墙、柱模板安装完毕后,安装斜向支撑;
(2)梁、板模板安装
a)安装梁模板及校正:安装时在地面拼接完毕后,整体安装,两边通过转角模固定在墙模板上,安装时先安装模板支撑立杆和底模板,后安装侧模板;
b)楼面龙骨的安装:在所有墙身模板调整完毕后,开始安装楼面龙骨,安装时同样在底端拼装完毕后,整体安装;
c)安装楼面板及调平:楼面模板的安装沿墙边平行逐件安装,先用销子临时固定,再次用水平仪检测梁板模板的平整度,不平的地方通过调节立杆的底托来达到水平度允许范围,最后再统一打紧销子; 
d)防止漏浆:底部用石膏堵缝堵缝,空隙较大处用方木填堵,方木贴在铝合金模板的下端,平直放置,保证层间墙体的平滑过度;铝合金模板安装完毕后,对模板进行一次完整的检查并安装水平拉杆及剪刀撑;
(3)模板校正及固定
模板安装完毕后,对所有墙、柱、梁板进行平整度与垂直度的校核,校核完在墙柱模板上加双方钢背楞并用高强螺栓固定;
(4)模板工程的安装符合下列要求:
1)墙两侧模板的对拉螺栓孔平直相对,钻孔采用机具;
2)钢背楞取用整根杆件,接头错开设置,搭接长度不应少于200mm;
(三)混凝土浇筑与养护
(1)模板工程安装完毕,经检查验收后,进行下道工序; 
(2)处理完毕经过钢筋的隐蔽验收后进行混凝土浇筑; 
(3)混凝土浇筑采用泵送方式进行,施工时先浇筑剪力墙、柱、梁,然后再浇筑水平楼板;混凝土的浇筑采用分层浇筑,并连续进行;
(四)模板拆除
(1)模板拆除
a)混凝土浇筑完毕后,在强度达到规范规定的强度后进行,梁板模板的早拆头及立杆支撑待混凝土强度达到100%后拆除;
b)模板的拆除顺序按模板的设计来,遵循“先支后拆、后支先拆”,先拆除非承重模板、后拆除承重模板的原则;
c)铝合金模板和配件拆除后,清除粘结砂浆杂物,板面涂刷油,对变形及损坏的模板及配件,进行整形和修补; 
d) 模板倒运
模板通过楼板上预留的传料口由人工倒运至上一层,分类整齐堆放,进入下一层的循环施工。

Claims (1)

1.一种装配式铝合金模板体系施工方法,其特征是:包括下列步骤:
(一)模板系统设计
(1)配板设计
a)铝模板采用模数制设计,通用模板的宽度模数以50mm进级;
b)绘制配板图时,标出模板的位置、规格型号,标绘出单元分界线;有特殊构造时,加以标明并出详细加工图;
c)预埋件和预留孔的位置,在配板图上标明,并注明其固定方法;
d)为设置对拉螺栓或其他拉筋,根据所需位置采用电钻钻孔;
(2)支承系统的设计
a)钢背楞的配置方向与模板的长度方向相垂直,直接承受模板传递的荷载;
b)钢背楞悬挑部分的端部分的挠度与跨中挠度相等,悬挑长度不大于50mm;
c)模板端缝齐平布置时,每块模板有两个支承点;
d)当模板底的净高不大于3.10米时,使用不加水平连杆的单支顶作为支承;
e)单支顶采用内外管设计,外管采用Φ60×2.5的钢管,内管采用Φ48×2.0的钢管;
(二)模板安装
(1)墙、柱模板安装
a)铝合金模板安装前保证设计的预埋件、预留洞口已留置好,管线已铺设完毕;剪力墙的端柱、角柱、暗柱钢筋绑扎安装完毕并已验收合格; 
b)铝合金模板的安装按照先内墙、后外墙的顺序安装,安装完毕后进行垂直及水平标高的调整;安装内墙模板从内角模开始,或从墙头封板开始,安装外墙模板之前先安装外围导墙板,用固定螺丝锚固到混凝土结构中,外墙模板的重量支撑在导墙板上,安装时使用塔吊整体吊装就位;
c)安装洞口模板,按工程要求设置门窗洞口模板,洞口四边与墙模板连接牢固;
d)墙、柱模板的加固处理,墙、柱模板安装完毕后,在模板上预留孔穿上对拉螺杆,对拉螺杆外边附背楞,转角处设置直角背楞,防止墙模板发生扭转、错台,保证结构的顺直光滑;
e)墙、柱模板安装完毕后,安装斜向支撑;
(2)梁、板模板安装
a)安装梁模板及校正:安装时在地面拼接完毕后,整体安装,两边通过转角模固定在墙模板上,安装时先安装模板支撑立杆和底模板,后安装侧模板;
b)楼面龙骨的安装:在所有墙身模板调整完毕后,开始安装楼面龙骨,安装时同样在底端拼装完毕后,整体安装;
c)安装楼面板及调平:楼面模板的安装沿墙边平行逐件安装,先用销子临时固定,再次用水平仪检测梁板模板的平整度,不平的地方通过调节立杆的底托来达到水平度允许范围,最后再统一打紧销子; 
d)防止漏浆:底部用石膏堵缝堵缝,空隙较大处用方木填堵,方木贴在铝合金模板的下端,平直放置,保证层间墙体的平滑过度;铝合金模板安装完毕后,对模板进行一次完整的检查并安装水平拉杆及剪刀撑;
(3)模板校正及固定
模板安装完毕后,对所有墙、柱、梁板进行平整度与垂直度的校核,校核完在墙柱模板上加双方钢背楞并用高强螺栓固定;
(4)模板工程的安装符合下列要求:
1)墙两侧模板的对拉螺栓孔平直相对,钻孔采用机具;
2)钢背楞取用整根杆件,接头错开设置,搭接长度不应少于200mm;
(三)混凝土浇筑与养护
(1)模板工程安装完毕,经检查验收后,进行下道工序; 
(2)处理完毕经过钢筋的隐蔽验收后进行混凝土浇筑; 
(3)混凝土浇筑采用泵送方式进行,施工时先浇筑剪力墙、柱、梁,然后再浇筑水平楼板;混凝土的浇筑采用分层浇筑,并连续进行;
(四)模板拆除
(1)模板拆除
a)混凝土浇筑完毕后,在强度达到规范规定的强度后进行,梁板模板的早拆头及立杆支撑待混凝土强度达到100%后拆除;
b)模板的拆除顺序按模板的设计来,遵循“先支后拆、后支先拆”,先拆除非承重模板、后拆除承重模板的原则;
c)铝合金模板和配件拆除后,清除粘结砂浆杂物,板面涂刷油,对变形及损坏的模板及配件,进行整形和修补; 
d) 模板倒运
模板通过楼板上预留的传料口由人工倒运至上一层,分类整齐堆放,进入下一层的循环施工。
CN2013101353754A 2013-04-18 2013-04-18 装配式铝合金模板体系施工方法 Pending CN103206089A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101353754A CN103206089A (zh) 2013-04-18 2013-04-18 装配式铝合金模板体系施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101353754A CN103206089A (zh) 2013-04-18 2013-04-18 装配式铝合金模板体系施工方法

Publications (1)

Publication Number Publication Date
CN103206089A true CN103206089A (zh) 2013-07-17

Family

ID=48753479

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101353754A Pending CN103206089A (zh) 2013-04-18 2013-04-18 装配式铝合金模板体系施工方法

Country Status (1)

Country Link
CN (1) CN103206089A (zh)

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018675A (zh) * 2014-06-13 2014-09-03 富于安(福建)环保模板有限公司 一种剪力墙混凝土模板及柱子混凝土模板的施工方法
CN104727547A (zh) * 2013-12-21 2015-06-24 中建四局第三建筑工程有限公司 浇筑上层墙或柱铝合金模板的定位方法及铝合金模板底座
CN106320693A (zh) * 2016-08-31 2017-01-11 沈阳欣荣基建筑工程有限公司 一种塑模体系施工方法
CN106351439A (zh) * 2016-08-29 2017-01-25 中国建筑第七工程局有限公司 铝模板施工工艺及方法
CN106869494A (zh) * 2016-12-30 2017-06-20 上海建工七建集团有限公司 一种钢柱模加固结构施工方法
CN106988525A (zh) * 2017-04-25 2017-07-28 中国水利水电第十工程局有限公司 一种高层建筑铝合金模板施工方法
CN107130791A (zh) * 2017-06-03 2017-09-05 二十二冶集团精密锻造有限公司 组合铝合金模板用于装配式混凝土预制结构的施工方法
CN107366303A (zh) * 2017-08-01 2017-11-21 江苏燕宁建设工程有限公司 铝合金模板作为公路重力式挡土墙模板的施工方法及挡土墙
CN107503513A (zh) * 2017-07-17 2017-12-22 海南职业技术学院 墙身模板对拉螺栓施工装置及施工方法
CN108914965A (zh) * 2018-08-11 2018-11-30 中冶重工(唐山)有限公司 用于综合管廊的铝合金模板的连续施工方法
CN109680938A (zh) * 2018-12-28 2019-04-26 中天建设集团有限公司 一种非标层铝木钢结合模板及其施工方法、建筑物
CN109868923A (zh) * 2019-03-11 2019-06-11 深圳市建工集团股份有限公司 一种散拼木模板清水混凝土施工方法
CN110259126A (zh) * 2019-06-28 2019-09-20 深圳市科羿科技有限公司 一种装配式建筑施工方法
CN110499915A (zh) * 2018-05-18 2019-11-26 东宏建设股份有限公司 一种铝模板施工工法
WO2019222896A1 (zh) * 2018-05-21 2019-11-28 增城市碧桂园物业发展有限公司 楼板及其建造方法
CN110629934A (zh) * 2019-09-04 2019-12-31 东莞市建筑科学研究所 基于bim的成型钢筋与定型模板组合应用施工方法
CN110821148A (zh) * 2019-10-21 2020-02-21 中国航天建设集团有限公司 一种用于非标层的模板组合体系施工方法
CN110847596A (zh) * 2019-12-04 2020-02-28 成都建工第一建筑工程有限公司 高层混凝土竖向装饰线条复合支模施工方法
CN111230478A (zh) * 2020-01-19 2020-06-05 中国十七冶集团有限公司 大截面异形混凝土墩柱结构的施工定型模板的加工方法
CN113863655A (zh) * 2021-09-01 2021-12-31 中兆建工集团有限公司 一种铝合金模板系统的施工方法
CN114509025A (zh) * 2022-02-15 2022-05-17 中交四公局第一工程有限公司 一种铝合金模板装配施工工艺质量检测方法及系统

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6044614A (en) * 1996-05-08 2000-04-04 Newtec Concrete Construction Pty Limited Sequential formwork system for concrete buildings
CN102561695A (zh) * 2012-01-04 2012-07-11 广东建星建筑工程有限公司 利用铝模板建造建筑物的施工方法
CN102828611A (zh) * 2011-06-17 2012-12-19 深圳汇林达科技有限公司 一种早拆模板体系及其施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6044614A (en) * 1996-05-08 2000-04-04 Newtec Concrete Construction Pty Limited Sequential formwork system for concrete buildings
CN102828611A (zh) * 2011-06-17 2012-12-19 深圳汇林达科技有限公司 一种早拆模板体系及其施工方法
CN102561695A (zh) * 2012-01-04 2012-07-11 广东建星建筑工程有限公司 利用铝模板建造建筑物的施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘雪红等: "铝合金模板体系施工技术及其效益分析", 《施工技术》, vol. 41, no. 23, 31 December 2012 (2012-12-31) *
郑少瑛等: "《建筑工程施工技术与管理》", 30 June 2010, 徐州:中国矿业大学出版社, article "建筑工程施工技术与管理", pages: 91 - 114-116 *

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727547A (zh) * 2013-12-21 2015-06-24 中建四局第三建筑工程有限公司 浇筑上层墙或柱铝合金模板的定位方法及铝合金模板底座
CN104018675B (zh) * 2014-06-13 2016-06-22 富于安(福建)环保模板有限公司 一种剪力墙混凝土模板的施工方法
CN104018675A (zh) * 2014-06-13 2014-09-03 富于安(福建)环保模板有限公司 一种剪力墙混凝土模板及柱子混凝土模板的施工方法
CN106351439B (zh) * 2016-08-29 2019-04-16 中国建筑第七工程局有限公司 铝模板施工工艺
CN106351439A (zh) * 2016-08-29 2017-01-25 中国建筑第七工程局有限公司 铝模板施工工艺及方法
CN106320693A (zh) * 2016-08-31 2017-01-11 沈阳欣荣基建筑工程有限公司 一种塑模体系施工方法
CN106869494A (zh) * 2016-12-30 2017-06-20 上海建工七建集团有限公司 一种钢柱模加固结构施工方法
CN106988525A (zh) * 2017-04-25 2017-07-28 中国水利水电第十工程局有限公司 一种高层建筑铝合金模板施工方法
CN107130791A (zh) * 2017-06-03 2017-09-05 二十二冶集团精密锻造有限公司 组合铝合金模板用于装配式混凝土预制结构的施工方法
CN107503513A (zh) * 2017-07-17 2017-12-22 海南职业技术学院 墙身模板对拉螺栓施工装置及施工方法
CN107503513B (zh) * 2017-07-17 2018-12-21 海南职业技术学院 墙身模板对拉螺栓施工装置及施工方法
CN107366303A (zh) * 2017-08-01 2017-11-21 江苏燕宁建设工程有限公司 铝合金模板作为公路重力式挡土墙模板的施工方法及挡土墙
CN110499915A (zh) * 2018-05-18 2019-11-26 东宏建设股份有限公司 一种铝模板施工工法
WO2019222896A1 (zh) * 2018-05-21 2019-11-28 增城市碧桂园物业发展有限公司 楼板及其建造方法
CN108914965B (zh) * 2018-08-11 2020-09-11 中冶重工(唐山)有限公司 用于综合管廊的铝合金模板的连续施工方法
CN108914965A (zh) * 2018-08-11 2018-11-30 中冶重工(唐山)有限公司 用于综合管廊的铝合金模板的连续施工方法
CN109680938A (zh) * 2018-12-28 2019-04-26 中天建设集团有限公司 一种非标层铝木钢结合模板及其施工方法、建筑物
CN109868923A (zh) * 2019-03-11 2019-06-11 深圳市建工集团股份有限公司 一种散拼木模板清水混凝土施工方法
CN110259126A (zh) * 2019-06-28 2019-09-20 深圳市科羿科技有限公司 一种装配式建筑施工方法
CN110629934A (zh) * 2019-09-04 2019-12-31 东莞市建筑科学研究所 基于bim的成型钢筋与定型模板组合应用施工方法
CN110821148A (zh) * 2019-10-21 2020-02-21 中国航天建设集团有限公司 一种用于非标层的模板组合体系施工方法
CN110821148B (zh) * 2019-10-21 2022-01-28 中国航天建设集团有限公司 一种用于非标层的模板组合体系施工方法
CN110847596A (zh) * 2019-12-04 2020-02-28 成都建工第一建筑工程有限公司 高层混凝土竖向装饰线条复合支模施工方法
CN111230478A (zh) * 2020-01-19 2020-06-05 中国十七冶集团有限公司 大截面异形混凝土墩柱结构的施工定型模板的加工方法
CN113863655A (zh) * 2021-09-01 2021-12-31 中兆建工集团有限公司 一种铝合金模板系统的施工方法
CN114509025A (zh) * 2022-02-15 2022-05-17 中交四公局第一工程有限公司 一种铝合金模板装配施工工艺质量检测方法及系统

Similar Documents

Publication Publication Date Title
CN103206089A (zh) 装配式铝合金模板体系施工方法
CN102444203B (zh) 一种高空大跨度悬挑连廊型钢混凝土结构及施工方法
CN101886466B (zh) 捣固式焦炉煤塔模板支撑结构的施工方法
CN202227476U (zh) 一种高空大跨度悬挑连廊型钢混凝土结构
CN106320691B (zh) 铝木模板施工方法
CN109779225A (zh) 一种悬挑式外脚手架及施工方法
CN104895318A (zh) 铝合金模板系统及其施工方法
CN105926942A (zh) 组合铝/钢框木塑模板体系的施工方法
CN104895279B (zh) 预制外墙板与预制梁的干挂连接结构及其施工方法
CN112854745A (zh) 一种装配式建筑铝合金模板施工工艺
CN103758348B (zh) 型钢框架结构混凝土楼板悬模浇筑施工方法
CN102661019B (zh) 建筑物外墙保温装饰一体化施工方法及专用吊装机
CN102953546A (zh) 双墙处变形缝模板安装施工方法
CN111236604A (zh) 圆筒主体结构上悬挑平台的安全施工方法
CN105178604A (zh) 一种装配式叠合楼板施工方法
CN113605771B (zh) 一种预应力装配式框架结构体系
CN104264920A (zh) 超高大曲率圆形螺旋清水楼梯的施工方法
CN206352391U (zh) 承插型键槽式快拆支撑体系
CN112627497A (zh) 高精度的铝框木模板建造方法
CN111576856A (zh) 一种铝合金模板组装系统及组装方法
CN104775606A (zh) 一种用于预制装配式住宅建筑墙板施工的操作平台及施工方法
CN104912231B (zh) 预制外墙板与剪力墙的干挂连接结构及其施工方法
CN202865996U (zh) 一种核电厂房间模块结构
CN111576878A (zh) 铝合金模板快拆体系施工工艺
CN102392534B (zh) 铝合金建筑模板组件

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130717