CN102605941A - 围护板吊装平台 - Google Patents
围护板吊装平台 Download PDFInfo
- Publication number
- CN102605941A CN102605941A CN2012100940592A CN201210094059A CN102605941A CN 102605941 A CN102605941 A CN 102605941A CN 2012100940592 A CN2012100940592 A CN 2012100940592A CN 201210094059 A CN201210094059 A CN 201210094059A CN 102605941 A CN102605941 A CN 102605941A
- Authority
- CN
- China
- Prior art keywords
- platform
- truss
- steel
- winches
- hoisting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明涉及一种用于高跨钢结构厂房屋面内板和墙面内板的高空安装工程的围护板吊装平台,其整体为钢结构平台,它包括主桁架、次桁架、平台梁和四个卷扬机,所述主桁架与所述次桁架相铰接形成安装平台的主体框架;所述平台梁均匀分布在所述主体框架内,一方面加固钢平台,另一方面使安装的围护板更平稳;所述卷扬机分别装在平台沿长度两侧1/3跨度处,卷扬机吊线上部固定在相邻的屋架梁上,通过卷扬机来操作整个平台的升降,本发明不需要预先对厂房地面进行处理,简化了施工程序,这种钢平台吊装结构能在更高的高度施工并能保持稳定性。
Description
技术领域:
本发明属于一种移动式的工作平台,具体说是适用于建筑钢结构工程高跨厂房围护彩板的高空安装吊装平台。
背景技术:
目前,大多数高跨钢结构厂房屋面内板和墙面内板的高空安装,往往需要厂房先做好地面处理,再利用可移动脚手架或可移动桁架,人工将彩板从地面运输到高空进行安装,其方法为:
a.厂房地面在彩板安装前的预先处理,进行地面夯实平整或地面混凝土浇注完毕。其问题是:受土建施工进度或者大型设备基础施工时间较长的影响,彩板安装前地面很难达到夯实平整的要求;
b.利用可移动脚手架(或可移动桁架),人工将彩板从地面运输至高空进行安装,其问题是:1.可移动脚手架不宜过重,否则地面人工平移难度较大;2.可移动脚手架不宜过高,高度超过10米,地面人工平移时需特别考虑脚手架的稳定问题;3.当厂房高度加大时,人工在空中运输彩板易造成折弯和损坏。
发明内容:
为了解决现有技术中存在的问题,本发明旨在提供一种简化施工程序,承重力更大,能在更大的高度施工并能保持稳定性的高空施工围护板吊装平台。
本发明所说的围护板吊装平台为钢结构平台,它包括主桁架、次桁架、平台梁和四个卷扬机,所述主桁架与所述次桁架相铰接形成安装平台的主体框架;所述平台梁均匀分布在所述主体框架内,一方面加固钢平台,另一方面使安装的围护板更平稳;所述卷扬机分别装在平台沿长度两侧1/3跨度处,卷扬机吊线上部固定在相邻的屋架梁上,通过卷扬机来操作整个平台的升降。
本发明主要用于高跨钢结构厂房屋面内板和墙面内板的高空安装工程,不需要预先对厂房地面进行处理,简化了施工程序,这种钢平台吊装结构能在更高的高度施工并能保持稳定性。
附图说明:
图1为本发明整体结构示意图。
图2为本发明主桁梁的结构示意图。
图3为本发明次桁梁的结构示意图。
图4(a)为本发明A点放大图。
图4(b)为本发明B点放大图。
图4(c)为本发明C点放大图。
图中:主桁梁1,次桁梁2,平台梁3,卷扬机4。
具体实施方式:
如图1、2、3、4所示,一种围护板吊装平台,包括主桁架1、次桁架2、平台梁3和四个卷扬机4,所述主桁架1与所述次桁架2相铰接形成安装平台的主体框架;所述平台梁3均匀分布在所述主体框架内使安装平台更稳固;所述卷扬机4分别装在平台沿长度两侧1/3跨度处,卷扬机4吊线上部固定在相邻的屋架梁上,通过卷扬机4来操作整个平台的升降。
作为本发明的一个实例:
装配式围护板吊装平台包括主桁架1三榀、次桁架2八榀、平台梁3十八根和卷扬机4四个,主桁架1、次桁架2和平台梁3采用高强螺栓连接,其中主桁架1与次桁架2、次桁架2与平台梁3均为铰接。主桁架1长度13050mm,采用普通运输车即可;次桁架2和平台梁3最大长度分别为3950mm和5000mm,便于现场的人工搬运和安装。吊装平台边沿长度两侧1/3跨度处各安装一台卷扬机4,卷扬机4吊线上部固定在相邻的屋架梁上,安装人员通过卷扬机4来操作整个吊装平台的升降,以便于满足现场安装的需要,另外四台卷扬机4在使用过程中应同步,保证钢平台整体的稳定和平衡;还要做好钢平台四周的安全设施的安装,并把需安装的彩板及安装工具放置在平台上。安装人员在吊装平台就位后,遵照指挥人员的口令统一启动卷扬机4进行提升,吊装平台提升至需要位置,安装人员做好安全防护工作后开始进行彩板的安装。
Claims (1)
1.一种围护板吊装平台,其特征是:包括主桁架、次桁架、平台梁和四个卷扬机,所述主桁架与所述次桁架相铰接形成安装平台的主体框架;所述平台梁均匀分布在所述主体框架内使安装平台更稳固;所述卷扬机分别装在平台边沿长度两侧,卷扬机吊线上部固定在相邻的屋架梁上,通过卷扬机来操作整个平台的升降。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100940592A CN102605941A (zh) | 2012-03-23 | 2012-03-23 | 围护板吊装平台 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100940592A CN102605941A (zh) | 2012-03-23 | 2012-03-23 | 围护板吊装平台 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102605941A true CN102605941A (zh) | 2012-07-25 |
Family
ID=46523670
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100940592A Pending CN102605941A (zh) | 2012-03-23 | 2012-03-23 | 围护板吊装平台 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102605941A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105442773A (zh) * | 2015-12-31 | 2016-03-30 | 沈阳三新实业有限公司 | 金属屋面内板安装施工工艺及其施工平台 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0117862B1 (fr) * | 1983-02-24 | 1988-12-28 | NOVITEC sc | Engin de levage en particulier nacelle |
CN2193401Y (zh) * | 1993-05-17 | 1995-03-29 | 周魁刚 | 轻便升降脚手装置 |
CN2384929Y (zh) * | 1999-08-16 | 2000-06-28 | 焦作矿务局建筑安装工程总公司 | 自升式门架提升机 |
CN201144515Y (zh) * | 2008-01-04 | 2008-11-05 | 中国建筑第八工程局广州分公司 | 钢结构高空施工平台 |
EP2014912A2 (de) * | 2007-06-06 | 2009-01-14 | ICEC Holding AG | Windkraftanlage mit Gondel und Verfahren zum Erstellen einer solchen Windkraftanlage |
CN201834511U (zh) * | 2010-08-31 | 2011-05-18 | 中建工业设备安装有限公司 | 高耸异形建筑卸料转运平台 |
-
2012
- 2012-03-23 CN CN2012100940592A patent/CN102605941A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0117862B1 (fr) * | 1983-02-24 | 1988-12-28 | NOVITEC sc | Engin de levage en particulier nacelle |
CN2193401Y (zh) * | 1993-05-17 | 1995-03-29 | 周魁刚 | 轻便升降脚手装置 |
CN2384929Y (zh) * | 1999-08-16 | 2000-06-28 | 焦作矿务局建筑安装工程总公司 | 自升式门架提升机 |
EP2014912A2 (de) * | 2007-06-06 | 2009-01-14 | ICEC Holding AG | Windkraftanlage mit Gondel und Verfahren zum Erstellen einer solchen Windkraftanlage |
CN201144515Y (zh) * | 2008-01-04 | 2008-11-05 | 中国建筑第八工程局广州分公司 | 钢结构高空施工平台 |
CN201834511U (zh) * | 2010-08-31 | 2011-05-18 | 中建工业设备安装有限公司 | 高耸异形建筑卸料转运平台 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105442773A (zh) * | 2015-12-31 | 2016-03-30 | 沈阳三新实业有限公司 | 金属屋面内板安装施工工艺及其施工平台 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202450774U (zh) | 小步距自爬升电梯井筒模板 | |
CN102337782B (zh) | 一种高大空间顶部施工桁架平台提升系统 | |
CN204804298U (zh) | 一种建筑材料吊装施工脚手架 | |
CN105692470A (zh) | 内爬式塔吊及其操作方法 | |
CN103485574B (zh) | 一种造粒塔塔顶钢筋混凝土结构施工方法 | |
CN203654702U (zh) | 一种钢筋混凝土烟囱施工操作平台 | |
CN102493666A (zh) | 一种超大超重构件高空平移安装施工方法 | |
CN102080451B (zh) | 工业厂房网架的施工方法 | |
CN108049666A (zh) | 一种超大平面多层钢桁架电子厂房钢结构的梯次安装方法 | |
CN105442773A (zh) | 金属屋面内板安装施工工艺及其施工平台 | |
CN204626930U (zh) | 一种集成式升降架操作平台 | |
JP2015055062A (ja) | タワークレーンの昇降式作業足場装置 | |
CN104404888A (zh) | 一种大型空中坡度调整吊装系统及应用 | |
CN102605941A (zh) | 围护板吊装平台 | |
CN216889833U (zh) | 一种爬升系统 | |
CN216549362U (zh) | 一种基坑上方构件的拼装吊装装置 | |
CN212832684U (zh) | 自行式组合升降多功能高空作业平台车 | |
CN101664963B (zh) | 大体积预应力砼箱梁张拉多功能操作平台 | |
CN204402001U (zh) | 用于钢结构屋面内板安装的可移动式操作平台系统 | |
CN206220460U (zh) | 用于塔筒的操作平台 | |
CN211472175U (zh) | 一种适用于钢桥施工的高空作业平台装置 | |
CN102733612B (zh) | 电动葫芦轨道安装方法 | |
CN114856922A (zh) | 一种安装风能发电风机及塔筒的装置及其施工方法 | |
CN210366717U (zh) | 一种应用于落地式和自爬式整体施工作业平台 | |
CN110424811B (zh) | 一种钢结构间冷塔展开平台的施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120725 |