CN102359069A - 下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法 - Google Patents

下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法 Download PDF

Info

Publication number
CN102359069A
CN102359069A CN2011101861432A CN201110186143A CN102359069A CN 102359069 A CN102359069 A CN 102359069A CN 2011101861432 A CN2011101861432 A CN 2011101861432A CN 201110186143 A CN201110186143 A CN 201110186143A CN 102359069 A CN102359069 A CN 102359069A
Authority
CN
China
Prior art keywords
existing line
frame bridge
jacking
horizontal
line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101861432A
Other languages
English (en)
Inventor
杨基好
宋善岭
房瑞泉
陈广彩
武尊杨
何磊
康达观
李怀贺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 10 Engineering Group Co Ltd
Original Assignee
China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 10 Engineering Group Co Ltd filed Critical China Railway No 10 Engineering Group Co Ltd
Priority to CN2011101861432A priority Critical patent/CN102359069A/zh
Publication of CN102359069A publication Critical patent/CN102359069A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明公开了一种下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法,包括在既有线路的沿线路方向上进行吊轨(9)加固和在既有线路下面用多个有一定间距垂直于线路方向的横抬梁(5)进行支撑,沿线路两侧,在横抬梁(5)下面左右各通过人工挖孔桩(1)作为横抬梁的支撑点;在框架顶(8)和横抬梁(5)之间沿顶进方向铺设钢滑道(6);通过枕木(20)与横抬梁(5)之间的楔形木(12)来满足线路纵坡和横坡的要求;在破除挖孔桩前,桩顶的荷载必须先通过钢滑道(6)转移至框架顶(8)上,然后循环破桩、顶进。本发明增强了线路的竖向、横向刚度,保证了顶进时线路的稳定,减少了人工养护线路的工作量,从而保证了行车的安全。

Description

下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法
技术领域
本发明涉及一种框架桥顶进施工线路加固方法,具体是一种防止线路发生横向位移、增强线路竖向刚度、确保下穿铁路框架桥顶进时不影响行车的既有线路加固方法。
背景技术
对于下穿铁路框架桥小夹角、大高度斜向顶进施工的既有线路加固方法,传统的做法是搭设便梁,对于长大框架桥,便梁不能满足跨度要求;传统的做法还有采用一般吊轨、横抬梁加固线路,由于横抬梁与框架顶进方向夹角较大,顶进时横抬梁一端受到摩擦会发生转动或翻转,导致线路几何尺寸发生变化而影响行车安全;采用一般吊轨、横抬梁加固线路的方法,横抬梁需满足框架前端开挖放坡跨度要求,普通型钢横抬梁不能满足受力跨度要求;一般吊轨、横抬梁加固线路在顶进时由于横抬梁高程的变化造成线路变化,容易形成三角坑,产生晃车,影响行车安全;为防止线路发生横移,传统方法采用钢丝绳+地锚的方法反向拉线路,由于钢丝绳具有弹性,在钢丝绳伸长受力时线路已经发生横向位移。很多施工单位在框架桥顶进时采取增多线路养护人员,加强线路观测和养护,发现线路发生变化立即停止施工进行线路维护,但仍存在一些问题,一是线路发生变化可能影响行车安全;二是增派大量线路养护人员,增加了施工成本;三是线路发生变化停止施工影响了施工效率及工期。
发明内容
本发明所要解决的问题是提供了一种利用各种型钢与桩基础加固线路的方法,有效地解决了框架桥轴线与既有线夹角小、框架较高、线路发生横向移动、线路形成三角坑、影响行车安全等问题。
为实现上述目的,本发明提供了一种下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法,包括在既有线路的沿线路方向上进行吊轨加固和在既有线路下面用多个有一定间距垂直于线路方向的横抬梁进行支撑,沿线路两侧,在横抬梁下面左右各通过人工挖孔桩作为横抬梁的支撑点;框架桥的上部即框架顶和横抬梁之间设置钢滑道,钢滑道沿框架桥顶进方向铺设;通过枕木与横抬梁之间的楔形木来满足线路纵坡和横坡的要求;顶进施工时,在框架桥前端挖掘,当到达挖孔桩时,破除第一根挖孔桩,在破除挖孔桩前,桩顶的荷载必须先通过钢滑道转移至框架顶板上,然后顶进至第二根挖孔桩,破除后再顶进,如此循环破桩、顶进。本方法利用吊轨、横抬梁结合人工挖孔桩,使线路加固有较稳定的基础,钢滑道的设置使得顶进更容易,既有线受扰动更少。钢滑道底标高一致,横抬梁标高均一致,由于线路存在横坡及纵坡,采用楔形木来填充枕木与横抬梁之间的空隙,楔形木的坡度与线路横坡坡度一致,楔形木高度根据实际测量枕木底与横抬梁高差确定,从而满足线路横坡与纵坡的要求。所述挖孔桩通过纵向连接系梁3、横向连接系梁4纵横连接在一起。工字钢系梁将挖孔桩纵横进行连接,挖孔桩形成一个网状整体,有效地防止顶进挖土时挖孔桩暴露出来后而倾倒,挖孔桩内均配置了适量钢筋,挖孔桩满足竖向承载力和横向弯矩的要求,挖孔桩基础使框架顶进时线路保持稳定。
在待顶进框架桥的既有线路的另一侧设置阻挡桩,用于阻挡横抬梁沿垂直于既有线路方向移动,也用于阻挡钢滑道沿框架桥沿顶进方向移动。实现了顶进时钢滑道及其上的既有线路保持静止,从而保证了线路几何尺寸不变。
在框架桥待前端挖掘深基坑为时,采取分台阶的方法开挖。
在枕木上方采用3扣+7扣+3扣吊轨加固既有线路,基本轨中间采用7扣轨,基本轨外侧采用3扣轨,扣轨紧固在枕木上。通过吊轨和横抬梁加固线路,增强了线路的竖向刚度。
将枕木、楔形木、横抬梁之间加固,横抬梁、钢滑道之间加固。这样使它们之间固定牢固。
钢滑道与框架顶之间有良好的润滑。这样减小了框架同滑道之间的摩擦,更容易使既有线路在顶进时保持稳定。
整个顶进作业必须在天窗点内完成,并派专职线路工养护线路,确保行车的绝对安全。
本发明具有如下优点:
1、该方法有效地控制了线路横移的发生,保证了线路的稳定,保证了行车的安全,解决了下穿铁路框架桥小夹角大高度斜向顶进时的既有线路的固定的难题。
2、该方法挖孔桩为线路提供了稳固的基础,从而减少了养护人员的工作量,提高了工作效率,保证了行车的安全。
3、该方法原理简单、取材方便、容易施工、安全系数高,具有较高的实用性。
附图说明
图1是本发明的俯视图;
图2是图1的A-A截面图;
图3是图1的B-B截面图;
图4是吊轨示意图;
图中:1、挖孔桩,2、抗滑桩,3、纵向连接系梁,4、横向连接系梁,5、横抬梁,6、钢滑道,7、连接型钢,8、框架顶,9、吊轨,10、U型卡,11、U型钢板一,12、楔形木,13、挡块一,14、挡块二,15、顶杆,16、框架桥,17、钢筋砼冠梁,18、阻挡桩,19、基本轨,20枕木,21、带丝螺栓,22、U型钢板二。
具体实施方式
下面结合附图和实施例对本发明的技术方案进行描述:
本发明是针对下穿铁路框架桥小夹角、大高度斜向顶进施工的既有线路加固方法。例如两条铁路线相交,既有线为单线铁路,相交处前后位于右偏曲线上,曲线半径4500m,下穿框架桥与既有线交角为31°06′;框架桥为1-11m钢筋混凝土斜交正做框架桥,箱体总高12.80m,正截面宽13.60m,沿既有线方向斜宽26.33m,横长41.50m,框架桥内设计净高10.5m。
本发明采取吊轨+横抬梁+挖孔桩相结合的方式加固线路,如图所示,线路两侧的44棵挖孔桩1和框架桥16就位前端的9根抗滑桩2,线路两侧挖孔桩1通过I32a工字钢纵向连接系梁3、横向连接系梁4纵横连接在一起作为顶进时线路加固的基础,实现了线路支撑基础能满足竖向受力的要求,挖孔桩形成一个网状整体,有效地防止顶进挖土时挖孔桩暴露出来后而倾倒,挖孔桩内均配置了适量钢筋,挖孔桩满足竖向承载力和横向弯矩的要求,挖孔桩基础使框架顶进时线路保持稳定;抗滑桩2桩顶利用钢筋砼冠梁17将其连接成一个整体锚固于土中作为阻挡桩18用来阻挡钢滑道6纵向移动;在枕木20下方平行于枕木放置一组H型钢作为横抬梁5,横抬梁间距3米,在框架顶8和横抬梁5中间安装8根H型钢滑道6,线路两侧钢滑道6采用连接型钢7进行横向连接以增强钢滑道6整体稳定性,钢滑道6前端固定在抗滑桩2上端的冠梁内,顶进时在钢滑道6和框架顶8之间铺设钢板并涂抹黄油以减少摩擦力,钢滑道6的作用在于将其上部的横抬梁5等与框架顶8隔离开来,摩擦仅在钢滑道6和框架顶8之间,不影响滑道以上的部分,从而保证了线路不发生横移,实现了顶进时滑道及以上线路保持静止,从而保证了线路几何尺寸不变。所有钢滑道6均落在框架顶8,因此8根钢滑道6底标高一致,横抬梁5标高均一致。为增强线路竖向刚度采用吊轨9和横抬梁5相结合的方法,在枕木上方采用3扣+7扣+3扣吊轨加固线路,基本轨19中间采用7扣轨,基本轨外侧采用3扣轨,在下面没有横抬梁的部位,吊轨9与枕木20的连接采用U型卡10和U型钢板一11,吊轨加固后的线路可满足3米跨度要求,在枕木20下方平行于枕木放置一组H型钢作为横抬梁5,横抬梁间距3米,每组横抬梁5由两根H428×400型钢组成,横抬梁长12米,受力计算跨度9.5米,在下面有横抬梁的部位,吊轨9、枕木20和横抬梁5通过焊接在横抬梁上的带丝螺栓21和U型钢板二22连接在一起。调整线路横坡、纵坡的楔形木12长3米,宽0.8米,楔形木12的坡度与线路横坡坡度一致,楔形木12高度根据实际测量枕木底与横抬梁高差确定,从而满足线路横坡与纵坡的要求。为防止枕木在楔形木上滑动,在楔形木放入线路下后并塞紧,在其前后端将型钢焊在横抬梁上作为挡块一13,控制楔形木和线路滑动。为了确保基本轨19能与横抬梁5不发生相对移动,即枕木20与楔形木12不发生相对滑动,在横抬梁5上轨道的两侧固定安装挡块二14,在3扣轨和挡块二14之间安放顶杆15。通过以上方法的实施,无论是在顶进土方开挖时还是在破除挖孔桩时线路均能保持稳定状态,几乎没有发生变化。
本发明具体实施过程如下:在限速100Km/h的慢行条件下施工人工挖孔桩→基本轨应力放散→架设便梁加固线路→穿工字钢连接系梁、钢滑道→撤除便梁→更换木枕→吊轨、U型卡连接→穿横抬梁、放入楔形木→U型卡连接→框架顶进,在完成线路加固后进行框架的顶进作业,顶进时挖孔桩必须逐根破除,破除第一根挖孔桩,然后顶进至第二根挖孔桩,破除后再顶进,如此循环破桩、顶进,每破除一根挖孔桩后顶进一段距离,在破除每根挖孔桩前必须先把荷载转移至框架顶板上,保证了线路横抬梁支点的稳定;深基坑采取分台阶的方法开挖,由于营业线施工禁止爆破,采用挖掘机分台阶开挖,在顶进开挖的过程中设一个台阶,台阶下5米,台阶上8米,在挖土的过程中保持台阶5米宽度;顶进作业在天窗点内进行,同时派线路工加强监视和养护确保线路稳定和行车的绝对安全。
虽然本发明以较佳实施例揭露如上,然其并非用以限定本发明,在不背离本发明精神及其实质的情况下,熟悉本领域的技术人员当可根据本发明作出各种相应的改变和变形,但这些相应的改变和变形都应属于本发明所附的权利要求的保护范围。

Claims (7)

1.一种下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法,包括在既有线路的沿既有线路方向上进行吊轨(9)加固和在既有线路下面用多个有一定间距垂直于既有线路方向的横抬梁(5)进行支撑,其特征在于:沿既有线路两侧,在横抬梁(5)下面左右各通过人工挖孔桩(1)作为横抬梁的支撑点;框架桥(16)的上部即框架顶(8)和横抬梁(5)之间设置钢滑道(6),钢滑道(6)沿框架桥(16)顶进方向铺设;通过枕木(20)与横抬梁(5)之间的楔形木(12)来满足既有线路纵坡和横坡的要求;顶进施工时,在框架桥(16)前端挖掘,当到达挖孔桩(1)时,破除第一根挖孔桩(1),在破除挖孔桩前,桩顶的荷载必须先通过钢滑道(6)转移至框架顶(8)上,然后顶进至第二根挖孔桩(1),破除后再顶进,如此循环破桩、顶进。
2.根据权利要求1所述的下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法,其特征在于:所述挖孔桩(1)通过纵向连接系梁(3)、横向连接系梁(4)纵横连接在一起。
3.根据权利要求1所述的下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法,其特征在于:在待顶进框架桥(16)的既有线路的另一侧设置阻挡桩(18),用于阻挡横抬梁(5)沿垂直于既有线路方向移动,也用于阻挡钢滑道(6)沿框架桥沿顶进方向移动。
4.根据权利要求1所述的下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法,其特征在于:在框架桥(16)待前端挖掘深基坑为时,采取分台阶的方法开挖。
5.根据权利要求1所述的下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法,其特征在于:在枕木(20)上方采用3扣+7扣+3扣吊轨(9)加固既有线路,基本轨(19)中间采用7扣轨,基本轨外侧采用3扣轨,扣轨紧固在枕木(20)上。
6.根据权利要求1所述的下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法,其特征在于:将枕木(20)、楔形木(12)、横抬梁(5)之间加固,横抬梁(5)、钢滑道(6)之间加固。
7.根据权利要求1所述的下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法,其特征在于:钢滑道(6)与框架顶(8)之间有良好的润滑。
CN2011101861432A 2011-07-05 2011-07-05 下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法 Pending CN102359069A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101861432A CN102359069A (zh) 2011-07-05 2011-07-05 下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101861432A CN102359069A (zh) 2011-07-05 2011-07-05 下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法

Publications (1)

Publication Number Publication Date
CN102359069A true CN102359069A (zh) 2012-02-22

Family

ID=45584444

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101861432A Pending CN102359069A (zh) 2011-07-05 2011-07-05 下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法

Country Status (1)

Country Link
CN (1) CN102359069A (zh)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102808381A (zh) * 2012-08-21 2012-12-05 中铁十局集团有限公司 高水位粉砂土地质下穿多股铁路框架桥顶进对接施工方法
CN102900027A (zh) * 2012-10-22 2013-01-30 中铁十局集团有限公司 一种上跨既有线下穿既有桥梁的贝雷梁的拆除方法
CN102926299A (zh) * 2012-11-19 2013-02-13 房士杰 一种铁路架空固定装置及采用此装置增建铁路桥涵的方法
CN102979041A (zh) * 2012-12-26 2013-03-20 中铁七局集团郑州工程有限公司 下穿铁路道岔群顶进卡跨度箱桥施工的软架空加固顶进法
CN103031803A (zh) * 2013-01-17 2013-04-10 铁道第三勘察设计院集团有限公司 小交角低高度钢筋混凝土跨线桥结构
CN103410096A (zh) * 2013-08-15 2013-11-27 中铁六局集团天津铁路建设有限公司 斜交顶进过程中在偏转端利用顶镐进行纠偏的箱体顶进法
CN103437254A (zh) * 2013-09-07 2013-12-11 中铁六局集团有限公司 框架桥顶进铁路岔区线路加固装置
CN103775093A (zh) * 2014-02-07 2014-05-07 中交一公局第一工程有限公司 斜交正做偏压浅埋隧道进洞套拱的施工方法
CN104099872A (zh) * 2014-06-30 2014-10-15 中铁四局集团第四工程有限公司 一种下穿铁路大跨度箱涵纵挑横抬顶进施工方法
CN104110001A (zh) * 2014-07-17 2014-10-22 中铁工程设计咨询集团有限公司 固定装置和轨道线路加固体系
CN104110000A (zh) * 2014-07-17 2014-10-22 中铁工程设计咨询集团有限公司 固定装置和轨道线路加固体系
CN104264591A (zh) * 2014-10-30 2015-01-07 中铁六局集团有限公司 在线路高差较大区域顶桥的施工方法
CN104746430A (zh) * 2013-12-25 2015-07-01 中铁六局集团有限公司 一种改进的顶进挖土施工方法
CN106245533A (zh) * 2016-08-30 2016-12-21 中铁第四勘察设计院集团有限公司 一种既有线顶进防护施工方法
CN107675628A (zh) * 2017-10-12 2018-02-09 中铁六局集团有限公司 城市道路框架桥上穿运营地铁下穿运营铁路顶进施工方法
CN110468729A (zh) * 2019-09-09 2019-11-19 中铁八局集团第六工程有限公司 一种框架桥施工方法
CN113186768A (zh) * 2021-04-21 2021-07-30 中铁六局集团太原铁路建设有限公司 提高既有线拆除框构后路基回填质量工法
CN114059455A (zh) * 2021-12-28 2022-02-18 中铁六局集团石家庄铁路建设有限公司 基于下穿重载铁路的立交桥施工方法
CN114182583A (zh) * 2021-11-30 2022-03-15 上海同济工程咨询有限公司 便梁的支撑结构

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008261137A (ja) * 2007-04-11 2008-10-30 Asahi Engineering Kk ラーメン橋構造
CN101838955A (zh) * 2010-05-31 2010-09-22 中铁二十一局集团有限公司 一种既有线路横抬加固方法及结构
CN101963061A (zh) * 2010-10-19 2011-02-02 浙江省建工集团有限责任公司 一种铁路既有线地下箱涵的施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008261137A (ja) * 2007-04-11 2008-10-30 Asahi Engineering Kk ラーメン橋構造
CN101838955A (zh) * 2010-05-31 2010-09-22 中铁二十一局集团有限公司 一种既有线路横抬加固方法及结构
CN101963061A (zh) * 2010-10-19 2011-02-02 浙江省建工集团有限责任公司 一种铁路既有线地下箱涵的施工方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张爱红: "经一路框架桥顶进施工", 《铁道勘察》, no. 3, 30 June 2005 (2005-06-30) *
李欣,刘忠华: "道岔下面斜交大跨度框架桥顶进施工", 《华东交通大学学报》, vol. 22, no. 2, 30 April 2005 (2005-04-30) *
杨福刚,李乔荣: "既有线框构桥顶进施工技术", 《铁道建筑》, no. 9, 30 September 2009 (2009-09-30) *

Cited By (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102808381A (zh) * 2012-08-21 2012-12-05 中铁十局集团有限公司 高水位粉砂土地质下穿多股铁路框架桥顶进对接施工方法
CN102808381B (zh) * 2012-08-21 2014-09-03 中铁十局集团有限公司 高水位粉砂土地质下穿多股铁路框架桥顶进对接施工方法
CN102900027A (zh) * 2012-10-22 2013-01-30 中铁十局集团有限公司 一种上跨既有线下穿既有桥梁的贝雷梁的拆除方法
CN102926299B (zh) * 2012-11-19 2014-07-16 房士杰 一种铁路架空固定装置及采用此装置增建铁路桥涵的方法
CN102926299A (zh) * 2012-11-19 2013-02-13 房士杰 一种铁路架空固定装置及采用此装置增建铁路桥涵的方法
CN102979041A (zh) * 2012-12-26 2013-03-20 中铁七局集团郑州工程有限公司 下穿铁路道岔群顶进卡跨度箱桥施工的软架空加固顶进法
CN102979041B (zh) * 2012-12-26 2015-01-21 中铁七局集团郑州工程有限公司 下穿铁路道岔群顶进大跨度箱桥施工的软架空加固顶进法
CN103031803A (zh) * 2013-01-17 2013-04-10 铁道第三勘察设计院集团有限公司 小交角低高度钢筋混凝土跨线桥结构
CN103031803B (zh) * 2013-01-17 2014-11-26 铁道第三勘察设计院集团有限公司 小交角低高度钢筋混凝土跨线桥结构
CN103410096A (zh) * 2013-08-15 2013-11-27 中铁六局集团天津铁路建设有限公司 斜交顶进过程中在偏转端利用顶镐进行纠偏的箱体顶进法
CN103410096B (zh) * 2013-08-15 2015-06-03 中铁六局集团天津铁路建设有限公司 斜交顶进过程中在偏转端利用顶镐进行纠偏的箱体顶进法
CN103437254A (zh) * 2013-09-07 2013-12-11 中铁六局集团有限公司 框架桥顶进铁路岔区线路加固装置
CN103437254B (zh) * 2013-09-07 2016-04-06 中铁六局集团有限公司 框架桥顶进铁路岔区线路加固装置
CN104746430B (zh) * 2013-12-25 2017-01-04 中铁六局集团有限公司 一种改进的顶进挖土施工方法
CN104746430A (zh) * 2013-12-25 2015-07-01 中铁六局集团有限公司 一种改进的顶进挖土施工方法
CN103775093A (zh) * 2014-02-07 2014-05-07 中交一公局第一工程有限公司 斜交正做偏压浅埋隧道进洞套拱的施工方法
CN104099872B (zh) * 2014-06-30 2016-08-17 中铁四局集团第四工程有限公司 一种下穿铁路大跨度箱涵纵挑横抬顶进施工方法
CN104099872A (zh) * 2014-06-30 2014-10-15 中铁四局集团第四工程有限公司 一种下穿铁路大跨度箱涵纵挑横抬顶进施工方法
CN104110000A (zh) * 2014-07-17 2014-10-22 中铁工程设计咨询集团有限公司 固定装置和轨道线路加固体系
CN104110000B (zh) * 2014-07-17 2015-12-30 中铁工程设计咨询集团有限公司 固定装置和轨道线路加固体系
CN104110001A (zh) * 2014-07-17 2014-10-22 中铁工程设计咨询集团有限公司 固定装置和轨道线路加固体系
CN104110001B (zh) * 2014-07-17 2015-12-30 中铁工程设计咨询集团有限公司 固定装置和轨道线路加固体系
CN104264591A (zh) * 2014-10-30 2015-01-07 中铁六局集团有限公司 在线路高差较大区域顶桥的施工方法
CN106245533A (zh) * 2016-08-30 2016-12-21 中铁第四勘察设计院集团有限公司 一种既有线顶进防护施工方法
CN106245533B (zh) * 2016-08-30 2018-03-13 中铁第四勘察设计院集团有限公司 一种既有线顶进防护施工方法
CN107675628A (zh) * 2017-10-12 2018-02-09 中铁六局集团有限公司 城市道路框架桥上穿运营地铁下穿运营铁路顶进施工方法
CN110468729A (zh) * 2019-09-09 2019-11-19 中铁八局集团第六工程有限公司 一种框架桥施工方法
CN110468729B (zh) * 2019-09-09 2021-08-17 中铁八局集团昆明铁路建设有限公司 一种框架桥施工方法
CN113186768A (zh) * 2021-04-21 2021-07-30 中铁六局集团太原铁路建设有限公司 提高既有线拆除框构后路基回填质量工法
CN114182583A (zh) * 2021-11-30 2022-03-15 上海同济工程咨询有限公司 便梁的支撑结构
CN114059455A (zh) * 2021-12-28 2022-02-18 中铁六局集团石家庄铁路建设有限公司 基于下穿重载铁路的立交桥施工方法

Similar Documents

Publication Publication Date Title
CN102359069A (zh) 下穿铁路框架桥小夹角大高度斜顶进施工既有线加固方法
CN102926299B (zh) 一种铁路架空固定装置及采用此装置增建铁路桥涵的方法
CN102979041B (zh) 下穿铁路道岔群顶进大跨度箱桥施工的软架空加固顶进法
CN102182147B (zh) 一种钢箱梁架设方法
CN103485288B (zh) 一种穿越既有线的双层顶进涵施工工艺
CN106149576B (zh) 上跨既有线桥梁整组拆除与安装施工方法
CN203487475U (zh) 既有线顶进桥涵施工用线路架空加固结构
CN103437254B (zh) 框架桥顶进铁路岔区线路加固装置
CN202148493U (zh) 下穿铁路框架桥小夹角大高度斜顶进施工既有线加固装置
CN106522112B (zh) 斜拉桥边跨梁段架设系统及其方法
CN203855866U (zh) 工便梁大跨度框架桥架空顶
CN102943440A (zh) 一种桥梁的施工方法
CN105239510A (zh) 用于高墩小半径曲线现浇箱梁的拆装梁支架及其施工方法
CN101324054B (zh) 桥梁节段梁临时墩的顶推就位施工方法
CN102587284B (zh) 独立扒杆梁板安装施工工法
CN202369933U (zh) 栈桥悬臂提梁系统及桥面预制梁架设施工系统
CN110924436A (zh) 一种铁路框构桥顶进前导式钢箱棚刃角及其施工方法
CN204676374U (zh) 一种铁路线路的加固机构
CN112144401B (zh) 一种基于曲线轨迹和大纵坡环境下的架桥机过跨方法
CN103967052B (zh) 一种防护新旧框构桥基底高差土体的方法
CN101122115B (zh) 一种在高墩、大跨桥梁施工项目中的塔吊移位的施工方法
CN202989781U (zh) 宽幅变宽现浇箱梁移动支架
CN109440653B (zh) 适用于特殊空间下的架梁施工方法及辅助移梁设备
CN106758586B (zh) 小半径曲线及缓和曲线上加固铁路的方法
CN202865708U (zh) 一种铁路架空固定装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120222