CN101324054B - 桥梁节段梁临时墩的顶推就位施工方法 - Google Patents

桥梁节段梁临时墩的顶推就位施工方法 Download PDF

Info

Publication number
CN101324054B
CN101324054B CN2008100299249A CN200810029924A CN101324054B CN 101324054 B CN101324054 B CN 101324054B CN 2008100299249 A CN2008100299249 A CN 2008100299249A CN 200810029924 A CN200810029924 A CN 200810029924A CN 101324054 B CN101324054 B CN 101324054B
Authority
CN
China
Prior art keywords
pier
pushing tow
interim pier
interim
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008100299249A
Other languages
English (en)
Other versions
CN101324054A (zh
Inventor
杜官民
郭全心
尹本文
艾占祥
刘向阳
廖云沼
郑震
王杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
CRECGZ No 2 Engineering Co Ltd
China Railway Port and Channel Engineering Group Co Ltd
Original Assignee
3rd Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 3rd Engineering Co Ltd of MBEC filed Critical 3rd Engineering Co Ltd of MBEC
Priority to CN2008100299249A priority Critical patent/CN101324054B/zh
Publication of CN101324054A publication Critical patent/CN101324054A/zh
Application granted granted Critical
Publication of CN101324054B publication Critical patent/CN101324054B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种桥梁节段梁临时墩的顶推就位施工方法,通过临时墩异地拼装顶推到位的技术方案,解决了高、大型临时墩节段梁架设要求占用临时墩墩位,同时解决了根据工期要求临时墩顶的节段梁架设后应即时就位固结的技术难题。

Description

桥梁节段梁临时墩的顶推就位施工方法
技术领域
本发明涉及特大型桥梁节段梁拼装架设施工方法,特别是一种桥梁节段梁临时墩的施工方法。
背景技术
在建设大跨度的特大型桥梁及在台风多发地区建设大型桥梁时,常常需要设置临时墩来支撑拼装过程中的节段梁,以增加节段梁悬臂拼装过程中的抗风稳定性,抵消节段梁架设过程中的不平衡力。
施工过程中,墩顶节段梁架设后,临时墩应即时就位固结,但临时墩墩顶节段梁架设要求占用临时墩墩位,所以在现场拼装高、大临时墩将耽误工期,是不可取的。目前未见有高、大临时墩长距离整体顶推滑移就位这方面的有关报道。
发明内容
本发明要解决的技术问题是对大型桥梁临时墩实现异地拼装,顶推到位。
为达上述目的,本发明采用如下的桥梁节段梁临时墩的顶推就位施工方法:
A、以就近已竣工的永久墩作附墙拼装塔式吊机;
B、在临时墩设计位置打桩,浇注混凝土承台;对施工地基面进行处理以达到设计要求的承载力;
C、在永久墩与临时墩设计位置之间铺设临时墩走行轨道;
D、利用所述塔式吊机拼装临时墩,在临时墩的底部安装走行装置;
E、以千斤油顶顶推的方式,推动临时墩沿走行轨道走行到达混凝土承台桩位上,墩顶与已架设完成的节段梁连接,在混凝土承台上方浇注混凝土以把临时墩与地基相固定,临时墩就位完毕。
在工地场地有限的条件下,为了更有效地利有现场空间,作为一种优选方案,临时墩采用由左、右两个立柱和至少一个平联连接而成的门式框架结构,两立柱之间形成用于运送待架设节段梁的运输通道;任一立柱由多根主受力钢管和多个连接系连接而成,每根主受力钢管由多节钢管拼接而成;主受力钢管底部装有走行装置;立柱顺桥向两侧各设置有底部带有行走轮箱的支腿,支腿与立柱之间连接有抗风撑。
为了增强临时墩的抗弯稳定性,所述临时墩拼装过程中,在完成主受力钢管的第二节钢管拼装后,向钢管内灌注混凝土。
为了进一步提高临时墩的稳定性,所述支腿上安装有配重块。
优选地,所述走行装置为带轴承滚动装置的走行轮箱。所述临时墩底部的走行装置为多个走行轮箱,每个走行轮箱由一套千斤油顶顶推前行;多套千斤油顶同时进行顶推,顶推方法为多点连续顶推。
所述临时墩的顶推方案具体如下:各千斤油顶安装于各走行轮箱后侧,千斤油顶一端着顶于行走轮箱分配梁上,另一端着顶于顶推后座分配梁,顶推后座分配梁两端各用一根钢绞线拉住,其两端均采用夹片锚,一端锚于顶推后座分配梁上,一端锚于带挂钩的拉板之上,该挂钩勾在走行滑道的预埋凹槽内,形成反拉装置;顶推时,每顶一个行程,将顶推后座分配梁前移,打紧顶推后座分配梁上锚具夹片,继续顶推;当拉板锚固端与顶推后座分配梁之间不够千斤顶一个行程时,将拉板挂钩从走行滑道凹槽内拉出,前移一定位置,上紧两端夹片;重复以上操作直至顶推到位。
为了保证各千斤油顶顶推同步性,所述临时墩走行轨道为沿两立柱的走行路线铺设的两根钢轨,沿着钢轨每5cm做一个刻度标记,严格控制每个顶推行程,以防止临时墩受扭变形以及轮箱脱轨。
对于高、大型临时墩节段梁架设要求占用临时墩墩位,同时根据工期要求,临时墩顶节段梁架设后,临时墩应即时就位固结的技术难题,本发明通过临时墩异地拼装顶推到位的技术方案,得到了很好的解决。
本发明利用已经竣工的永久墩作塔吊的附墙拼装塔吊,并在永久墩处拼装临时墩,然后顶推就位,设计思路新颖,结构安全、经济适用。临时墩主要利用钢管进行拼装,结构形式采用门式结构,既经济又安全,施工工艺新颖可靠,值得在类似项目施工中推广。利用滚动式走行轮箱及多台千斤顶顶推临时墩,当临时墩拖拉就位后与墩顶梁段进行精确对位,施工工艺简单、快捷、准确,在类似工程中有重大的借鉴意义。不在原位提前拼装好临时墩,既不影响节段梁的吊装工期,又为高、大形结构物长距离顶推就位提供了工程实例。
附图说明
图1是本发明的临时墩顶推就位施工方案示意图。
图2是在顶推方向上观察到的临时墩的结构示意图。
图3是走行轮箱及千斤顶的工位结构示意图。
图4是图3的I-I剖视图。
具体实施方式
下面结合附图和实施例对本发明作进一步详细说明。
如图1所示,临时墩拼装前,首先在临时墩设计位置钻孔桩7,用混凝土建承台6。充分利用永久墩11墩身施工时预埋件,以使塔式吊机10牢固附着于永久墩11上。对地基面进行严格处理,底层填筑并压实0.8米厚砂砾垫层9,面层浇筑0.5米厚混凝土8,以达到设计要求承载力。然后,在永久墩11与临时墩设计位置之间铺设临时墩走行轨道14(位于混凝土8之上,见图3)。走行轨道用P43的两根钢轨制成,轨道铺设的质量直接影响到顶推施工成败,因此对轨道铺设应严格控制,轨道平面高差偏差控制在±2mm之内;钢轨线型尽量保持直线型,偏差控制在±5mm以内;两钢轨之间的接头必须平顺,不得有错台。
准备工作完成后,即进行拼装。如图2所示,临时墩由两个立柱4和至少一个平联18组成。临时墩立柱4的每根主受力钢管4a由五节钢管组成,每节长度约12m。首先在每根主受力钢管4a底部安装两个走行轮箱16,走行轮箱16摆放位置必须保证横桥向、顺桥向都平行,且在同一水平面。钢管节段用塔式吊机10逐节吊装,节与节之间接头连接除水平焊缝以外,竖向还需加焊加劲板,以加强接缝强度。上、下两节钢管对位时,用两台全站仪(经纬仪)对其进行两垂直方向的垂直度测量,接口处不得出现折线,单根钢管的垂直度偏差按其长度的千分之三控制,完工以后墩顶最大垂度偏差不超过30mm。在焊接时,为了减少焊接时的温度收缩变形,影响垂直度,必须对钢管进行对称焊接。在完成第二节钢管拼装后,为增强抗弯稳定性,按设计要求向钢管内灌注混凝土,增强墩身整体抗弯稳定性。
为了确保临时墩在顶推过程中顺桥向的稳定性,在临时墩顺桥向两侧各设置了万能杆件支腿3。万能杆件支腿3拼装在临时墩中间空地处完成,当第一节钢管全部安装到位并与平联18连接完成后,利用吊机吊装拼接。在支腿3处需安装走行轮箱16。完成后即时安装稳定作用的配重5,以保持墩身稳定。为了保证临时墩整体稳定性,并使临时墩形成整体框架结构,临时墩钢管立柱之间需增加各种连接系4b。
临时墩拼装完毕如图2所示,临时墩为由左、右两个立柱4至少一个平联18连接而成的门式框架结构,两立柱4之间形成用于运送待架设节段梁13的运输通道;任一立柱4由多根主受力钢管4a和多个连接系4b连接而成,每根主受力钢管4a由多节钢管拼接而成;主受力钢管4a底部装有带轴承滚动装置的走行轮箱16;立柱4顺桥向两侧(即顶推方向上)各设置有底部带有行走轮箱的支腿3,支腿3与立柱4之间还连接有抗风撑2,在支腿3上还安装有配重块5。
临时墩拼装完毕,进行顶推施工。由于临时墩自重及走行轮箱16的滑轮与钢轨之间的摩擦系数可计算出顶推力以及采用千斤油顶12的数量。顶推方法为多点连续顶推,油顶行程为50cm。考虑到千斤油顶顶推时方向的掌握以及减少前支腿对钢轨的下顶力,千斤油顶安装于各行走轮箱后侧,千斤油顶一端着顶于轮箱分配梁19上,另一端顶于顶推后座分配梁17,顶推后座分配梁17两端各用一根钢绞线拉住,其两端均采用夹片锚,一端锚于顶推后座分配梁17上,一端锚于拉板15(带挂钩,挂钩钩住滑道预埋凹槽内,形成反拉装置)之上。如图3、图4所示。顶推时,每顶一个行程,将顶推后座分配梁前移,打紧顶推后座分配梁上锚具夹片,继续顶推。当拉板锚固端与顶推后座分配梁之间不够千斤顶一个行程时,将拉板挂钩从滑道凹槽内拉出,前移一定位置,上紧两端夹片。重复操作直至顶推到位。如图1所示,A为临时墩拼装位置,B为临时墩就位位置,采用如上方法可把临时墩顶推就位。
在顶推过程中,必须保证每台千斤油顶12顶推同步性,具体控制方法为:沿着钢轨每5cm做好刻度标记,严格控制每顶行程,以防止临时墩受扭变形以及轮箱脱轨。同时,对万能杆件支腿3的变形进行不间断的检查,并通过油表读数的异常检查前进时遇到的阻碍。每顶推5m,用全站仪对钢管立柱垂直度进行测量。有专人检查滑道变形情况,以保证施工顺利。
上述具体实施方式为本发明的优选实施例,并不能对本发明的权利要求进行限定,其他的任何未背离本发明的技术方案而所做的改变或其它等效的置换方式,都包含在本发明的保护范围之内。

Claims (4)

1.一种桥梁节段梁临时墩的顶推就位施工方法,其特征在于包括如下步骤:
A、以就近已竣工的永久墩作附墙拼装塔式吊机;
B、在临时墩设计位置打桩,浇注混凝土承台;对施工地基面进行处理以达到设计要求的承载力;
C、在永久墩与临时墩设计位置之间铺设临时墩走行轨道;
D、利用所述塔式吊机拼装临时墩,在临时墩的底部安装走行装置;
E、以千斤油顶顶推的方式,推动临时墩沿走行轨道走行到达混凝土承台桩位上,墩顶与已架设完成的节段梁连接,在混凝土承台上方浇注混凝土以把临时墩与地基相固定,临时墩就位完毕;
其中,所述临时墩为由左、右两个立柱和至少一个平联连接而成的门式框架结构,两立柱之间形成用于运送待架设节段梁的运输通道;任一立柱由多根主受力钢管和多个连接系连接而成,每根主受力钢管由多节钢管拼接而成;主受力钢管底部装有走行装置;立柱顺桥向两侧各设置有底部带有行走轮箱的支腿,支腿与立柱之间连接有抗风撑;
所述走行装置为带轴承滚动装置的走行轮箱;
所述每个走行轮箱由一套千斤油顶顶推前行;多套千斤油顶同时进行顶推,顶推方法为多点连续顶推;
所述多点连续顶推的方式如下:各千斤油顶安装于各行走轮箱后侧,千斤油顶一端着顶于行走轮箱分配梁上,另一端着顶于顶推后座分配梁,顶推后座分配梁两端各用一根钢绞线拉住,其两端均采用夹片锚,一端锚于顶推后座分配梁上,一端锚于带挂钩的拉板之上,该挂钩勾在走行滑道的预埋凹槽内,形成反拉装置;顶推时,每顶一个行程,将顶推后座分配梁前移,打紧顶推后座分配梁上锚具夹片,继续顶推;当拉板锚固端与顶推后座分配梁之间不够千斤顶一个行程时,将拉板挂钩从走行滑道凹槽内拉出,前移一定位置,上紧两端夹片;重复以上操作直至顶推到位。
2.根据权利要求1所述的施工方法,其特征在于:所述临时墩拼装过程中,在完成主受力钢管的第二节钢管拼装后,向各钢管内灌注混凝土。
3.根据权利要求1所述的施工方法,其特征在于:所述支腿上安装有具稳定作用的配重块。
4.根据权利要求1所述的施工方法,其特征在于:所述临时墩走行轨道为沿两立柱的走行路线铺设的两根钢轨,沿着钢轨每5cm做一个刻度标记。
CN2008100299249A 2008-08-01 2008-08-01 桥梁节段梁临时墩的顶推就位施工方法 Active CN101324054B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100299249A CN101324054B (zh) 2008-08-01 2008-08-01 桥梁节段梁临时墩的顶推就位施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100299249A CN101324054B (zh) 2008-08-01 2008-08-01 桥梁节段梁临时墩的顶推就位施工方法

Publications (2)

Publication Number Publication Date
CN101324054A CN101324054A (zh) 2008-12-17
CN101324054B true CN101324054B (zh) 2010-12-01

Family

ID=40187744

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100299249A Active CN101324054B (zh) 2008-08-01 2008-08-01 桥梁节段梁临时墩的顶推就位施工方法

Country Status (1)

Country Link
CN (1) CN101324054B (zh)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102199915B (zh) * 2010-03-23 2012-07-11 柳州欧维姆机械股份有限公司 步履式顶推装置及其用于桥梁顶推施工的方法
CN105568860B (zh) * 2015-12-31 2018-01-02 广西路桥工程集团有限公司 一种采用装配式重型钢管支撑装置的临时墩施工方法
CN107815975B (zh) * 2017-11-28 2023-06-09 江西乔田重工有限公司 多联多跨钢梁基于独立非刚性桥墩的多点同步顶推装置和施工方法
CN111663451B (zh) * 2020-06-18 2022-04-08 中铁四局集团有限公司 高山峡谷大跨度上承式连续钢桁梁桥的超高塔架施工方法
CN113957809A (zh) * 2021-09-03 2022-01-21 中交路桥建设有限公司 一种梁段滑移安装施工方法
CN114346599B (zh) * 2021-12-22 2022-12-16 江苏玖沐精工装备科技有限公司 一种挂篮主桁流水线同心加工工艺
CN115613477B (zh) * 2022-10-21 2023-10-24 四川公路桥梁建设集团有限公司 一种主梁悬臂无轨三角挂篮及施工方法

Also Published As

Publication number Publication date
CN101324054A (zh) 2008-12-17

Similar Documents

Publication Publication Date Title
CN103266573B (zh) 自锚式悬索桥钢箱梁单向单点三滑道同步顶推施工方法
CN101324054B (zh) 桥梁节段梁临时墩的顶推就位施工方法
CN101935987B (zh) 曲线桥大跨度钢管拱整体滑移施工方法
CN101781879B (zh) 独塔无背索斜拉桥施工方法
CN106012797A (zh) 一种全地锚式独塔双跨斜拉桥结构及其施工方法
CN104562936A (zh) 一种连续系杆钢管拱桥施工方法
CN104727227B (zh) 一种中承式钢箱系杆拱桥敞口格构式钢梁整节段架设方法
CN111794119B (zh) 一种提篮式钢箱系杆拱临时支撑系统及吊装方法
CN111676816B (zh) 一种钢桁梁及框架墩钢横梁搭建施工方法
CN110847062A (zh) 80米跨宽幅钢箱梁厂内整孔拼装双幅架设施工方法
CN102220741B (zh) 跨越现有线路且与既有线并行的钢混结合梁施工工艺
CN104018426A (zh) 一种钢桁梁安装方法
CN102797223B (zh) 海塘区客运专线膺架法现浇道岔连续梁施工方法
CN110093863A (zh) 一种不设置前支腿的双工作面一体化架桥机
CN113622316A (zh) 钢桁架梁多点牵引式顶推施工系统及其施工方法
CN110093862A (zh) 可实现纵横向拼装的三工作面架桥机及盖梁无便道节段拼装工法
CN110205948A (zh) 一种宽体架桥机及其架设方法
CN103806374B (zh) 装配式公路钢桥整体轨道架设推送系统及架设推送工艺
CN202989781U (zh) 宽幅变宽现浇箱梁移动支架
CN111188281A (zh) 一种预制梁架设施工机械横向移动支撑系统及施工方法
CN115961549A (zh) 一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法
CN210368664U (zh) 一种宽体架桥机
CN210315235U (zh) 可实现纵横向拼装的三工作面架桥机
CN113774813A (zh) 便于安装大节段钢桁架箱梁的牵引纠偏设备
CN102425109A (zh) 采用大跨度龙门吊机吊装系杆的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: CHINA RAILWAY PORT AND CHANNEL ENGINEERING GROUP Co.,Ltd.

Assignor: The 3th Engineering Co., Ltd. of China Zhongtie Major Bridge Engineering Group

Contract record no.: 2011440000233

Denomination of invention: Incremental launching positioning construction method of bridge subsection girder temporary pier

Granted publication date: 20101201

License type: Exclusive License

Open date: 20081217

Record date: 20110325

C56 Change in the name or address of the patentee

Owner name: THE SECOND CO., LTD. OF CHINA RAILWAY PORT CHANNEL

Free format text: FORMER NAME: THE 3TH ENGINEERING CO., LTD. OF CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING GROUP

CP01 Change in the name or title of a patent holder

Address after: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou

Patentee after: The Second Co., Ltd. of China Railway Port Channel Engineering Group

Address before: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou

Patentee before: The 3th Engineering Co., Ltd. of China Zhongtie Major Bridge Engineering Group

ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY PORT CHANNEL ENGINEERING CO., LTD.

Effective date: 20130402

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20130402

Address after: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou

Patentee after: THE SECOND CO., LTD. OF CHINA RAILWAY PORT CHANNEL ENGINEERING Group

Patentee after: CHINA RAILWAY PORT AND CHANNEL ENGINEERING GROUP Co.,Ltd.

Address before: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou

Patentee before: The Second Co., Ltd. of China Railway Port Channel Engineering Group

CP01 Change in the name or title of a patent holder

Address after: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou

Co-patentee after: CHINA RAILWAY PORT AND CHANNEL ENGINEERING GROUP Co.,Ltd.

Patentee after: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP SECOND ENGINEERING Co.,Ltd.

Address before: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou

Co-patentee before: CHINA RAILWAY PORT AND CHANNEL ENGINEERING GROUP Co.,Ltd.

Patentee before: The Second Co., Ltd. of China Railway Port Channel Engineering Group

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20191211

Address after: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou

Co-patentee after: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP Co.,Ltd.

Patentee after: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP SECOND ENGINEERING Co.,Ltd.

Address before: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou

Co-patentee before: CHINA RAILWAY PORT AND CHANNEL ENGINEERING GROUP Co.,Ltd.

Patentee before: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP SECOND ENGINEERING Co.,Ltd.

TR01 Transfer of patent right