CN101967887A - Large-span light steel structure roof girder hoisting method - Google Patents
Large-span light steel structure roof girder hoisting method Download PDFInfo
- Publication number
- CN101967887A CN101967887A CN2009100554656A CN200910055465A CN101967887A CN 101967887 A CN101967887 A CN 101967887A CN 2009100554656 A CN2009100554656 A CN 2009100554656A CN 200910055465 A CN200910055465 A CN 200910055465A CN 101967887 A CN101967887 A CN 101967887A
- Authority
- CN
- China
- Prior art keywords
- roof girder
- lifting
- roof
- suspender
- girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention relates to a large-span light steel structure roof girder hoisting method which is characterized by comprising the following steps of: splicing and assembling to form an integral hoisting roof girder on ground in a hoisting site, selecting a hoisting steel wire rope, selecting a hoisting truck and a hoisting sling, executing initial hoisting and executing final hoisting. After the technical scheme is adopted, the invention has the advantage of high quality and is safe and quick to carry out hoisting construction.
Description
Technical field
The present invention relates to a kind of steel work roof girder hanging method, specifically, is a kind of large span light section steel structure roof girder hanging method.
Background technology
Large span light section steel structure factory building is the Production Regional that the large span large space can be provided that assembles with light high-efficiency steel and the heat insulation cladding of efficient and light weight, have in light weight, short construction period, easy for installation, anti-seismic performance is good, handsome in appearance, clean, lively rhythm, the inner space is big, than general characteristics such as the easier compartment of structure, therefore be widely used in general industrial or agricultural building, commercial, the service building, the standard office building, school, hospital architecture, villa, tourism building, all kinds of warehouses building, amusement, stadiums, the earthquake zone building, the building that the duration is tight, old housing reform is built, building field such as overhaul.
But the lifting quality of large span lightweight section structure factory building roof beam is difficult to control, and roof girder stands up the process easy deformation, hoisting process is difficult to control high-altitude stability, and very easily causes the human and material resources waste.
Therefore known large span light section steel structure roof girder hanging method exists above-mentioned all inconvenience and problem.
Summary of the invention
Purpose of the present invention is to propose a kind of large span light section steel structure roof girder hanging method that guarantees assembling quality.
Another object of the present invention is to propose a kind of roof girder that prevents and stands up the span light section steel structure roof girder hanging method that is out of shape in the process.
Another purpose of the present invention is to propose a kind of large span light section steel structure roof girder hanging method in hoisting process control high-altitude stability.
For achieving the above object, technical solution of the present invention is:
A kind of large span light section steel structure roof girder hanging method is characterized in that may further comprise the steps:
First step: carry out ground spliced a slice integral hoisting roof girder that is assembled in the lifting place, after being transported into the scene, to properly put on large span light section steel structure roof truss in order to avoid it deforms, level up the splicing place with sleeper, measure the sleeper relative elevation with level gauge, the discrepancy in elevation needs in the 5mm scope, so that described roof girder does not deform.
Second step: select the lifting wire rope for use.
Third step: select a crane and a suspender for use.
The 4th step: carry out initially lifting, before described roof girder lifting, determine the particular location of good described crane earlier, when described roof girder lifts, should slowly lift by crane, when treating described roof girder built on stilts 200mm, stop to hoist, described roof girder of scrutiny and suspender have or not distortion, determine errorless after, lifting is to the installation site, and behind described roof girder hoisted in position, two ends high-strength bolt node adopts interim bolt earlier, lifted first, second roof girder pulled on safety net immediately, prevents that the operating personnel high-altitude from falling, tie-rod and Eurya plant bar between the roof truss are installed then, are made two roof trusses form a stabilization element.
The 5th step: carry out finally lifting: the method by first, second sheet room frame of above lifting continues all the other roof trusses of lifting, behind every lifting 5 Pin room framves, after verticality, spacing, the quality of inspection roof truss meets standard, just can make the high-strength bolt that roof truss is connected with steel column.
Large span light section steel structure roof girder hanging method of the present invention can also be further achieved by the following technical measures.
Aforesaid hanging method wherein in described first step, also comprises with No. 10 channel-section steels stiffener as the roof girder web, to increase the rigidity of roof girder web, makes to stand up in the roof girder lifting and reduces distortion in the process.Roof girder installs dismountable this stiffener in back, also can not remove.
Aforesaid hanging method, selecting for use in the lifting wire rope of wherein said second step, the specification of selecting the described wire rope between a crane and a suspender for use is the wire rope of φ 21.5 for the 6*19 diameter, its rupture pull force is 245.5KN, and selecting the specification of the described wire rope between a suspender and a slice integral hoisting steel roof truss for use is the wire rope of φ 26 for the 6*19 diameter, and its rupture pull force is 362.0KN.
Aforesaid hanging method, wherein said crane are one 50 tons of mobile cranes, long 32.75 meters of bar, and 7 meters of operating radius can lift by crane 10 tons; Described suspender is a balance sling that is made into the triangle girder by seamless steel pipe and the L50 angle steel of φ 219*6, φ 76*3.5, long 18 meters of described suspender.
After adopting technique scheme, large span light section steel structure roof girder hanging method of the present invention has lifting construction safety, quick, high-quality advantage.
Description of drawings
Fig. 1 is 55 meters long-span roofing assembly unit schematic diagrames of the embodiment of the invention.
Fig. 2 is the suspender schematic diagram of the embodiment of the invention.
Fig. 3 is that the roof girder web of the embodiment of the invention is reinforced schematic diagram.
Fig. 4 is 55 meters large span light section steel structure roof girder lifting schematic diagrames.
A among the figure, B, C and D are respectively the position of reinforcement point.
The specific embodiment
Below in conjunction with embodiment and accompanying drawing thereof the present invention is illustrated further.
Embodiments of the invention: large span light section steel structure roof girder hanging method of the present invention is applied to the lifting of 55 meters large span light section steel structure roof girders, because the length overlength of the roof girder of 55 meters spans, can process in factory, but its transport difficulty is big, also uneconomical, therefore stride roof girder to 55 meters and carry out sectional making processing, be transported to splicing lifting behind the job site.After being transported into the scene, to properly put on large span light section steel structure roof truss in order to avoid it deforms, level up the splicing place with sleeper, measure the sleeper relative elevation with level gauge, the discrepancy in elevation needs in the 5mm scope, so that described roof girder does not deform, Fig. 1 is 55 meters long-span roofing assembly unit schematic diagrames of the embodiment of the invention.Also available No. 10 channel-section steels, make in the roof girder lifting and stand up minimizing distortion in the process to increase the rigidity of roof girder web as the stiffener of roof girder web.Roof girder installs dismountable this stiffener in back, also can not remove, and Fig. 3 is that the roof girder web of the embodiment of the invention is reinforced schematic diagram, A among the figure, and B, C and D are respectively the position of reinforcement point.It more than is described first step.
Second step: select the lifting wire rope for use, according to the colligation form of roof girder and suspender weight and lifting, selecting the single maximum weighted of wire rope between described crane and suspender for use is 3.0t.Selecting specification is the wire rope of φ 21.5 for the 6*19 diameter, and its rupture pull force is 245.5KN, then its:
Lifting safety factor f=245.5 * 0.85/ (9.8 * 3.0)=7.1.
Get lifting safety factor permissible value [f]=6, then f>[f];
Selecting the single maximum weighted of wire rope between described suspender and member for use is 5.0t.Selecting specification is the wire rope of φ 26 for the 6*19 diameter, and its rupture pull force is 362.0KN, then its:
Lifting safety factor f=362.0 * 0.85/ (9.8 * 5.0)=6.3
Get lifting safety factor permissible value [f]=6, then f>[f].
Third step: select a crane and a suspender for use, selecting crane for use is one 50 tons of mobile cranes, long 32.75 meters of bar, and 7 meters of operating radius can lift by crane 10 tons; Because the roof girder overlength steadily, adopts a balance sling to lift for guaranteeing lifting.Described suspender is that a seamless steel pipe and a L50 angle steel by φ 219*6, φ 76*3.5 is made into triangular truss formula balancing pole suspender, long 18 meters of described suspender, and Fig. 2 is described suspender schematic diagram.When lifting,, in the lifting process, adjust balance simultaneously, 9.2 tons of roof girder and suspender deadweights in the present embodiment with chain block with 6 some liftings of triangular truss formula balancing pole suspender binding.Fig. 4 is 55 meters large span light section steel structure roof girder lifting schematic diagrames, wherein colludes into an equilateral triangle by the suspension hook top with three points at suspender two ends, and in other words, the angle of the outside steel wire of suspension hook and triangular truss formula balancing pole suspender is 60 degree.
The 4th step: carry out initially lifting, before described roof girder lifting, determine the particular location of good described crane earlier, when described roof girder lifts, should slowly lift by crane, when treating described roof girder built on stilts 200mm, stop to hoist, described roof girder of scrutiny and suspender have or not distortion, determine errorless after, lifting is to the installation site, and behind described roof girder hoisted in position, two ends high-strength bolt node adopts interim bolt earlier, lifted first, second roof girder pulled on safety net immediately, prevents that the operating personnel high-altitude from falling, tie-rod and Eurya plant bar between the roof truss are installed then, are made two roof trusses form a stabilization element.
The 5th step: carry out finally lifting: the method by first, second sheet room frame of above lifting continues all the other roof trusses of lifting, behind every lifting 5 Pin room framves, after verticality, spacing, the quality of inspection roof truss meets standard, just can make the high-strength bolt that roof truss is connected with steel column.
Large span light section steel structure roof girder hanging method of the present invention uses in the large span light section steel structure roof girder hoisting engineering of Shanghai Baosteel A Sailuo laser assembly solder engineering first phase, second phase and west, Hongqiao Airport, Shanghai freight terminal, effect is remarkable, has obtained exploiting entity, supervisor and owner's abundant affirmation.
Above embodiment is only for the usefulness that the present invention is described, but not limitation of the present invention, person skilled in the relevant technique under the situation that does not break away from the spirit and scope of the present invention, can also be made various conversion or variation.Therefore, all technical schemes that are equal to also should belong to category of the present invention, should be limited by each claim.
Claims (4)
1. large span light section steel structure roof girder hanging method is characterized in that may further comprise the steps:
First step: carry out ground spliced a slice integral hoisting roof girder that is assembled in the lifting place, level up the splicing place with sleeper, measure the sleeper relative elevation with level gauge, the discrepancy in elevation needs in the 5mm scope, so that described roof girder does not deform.
Second step: select the lifting wire rope for use.
Third step: select a crane and a suspender for use,
The 4th step: carry out initially lifting, before described roof girder lifting, determine the particular location of good described crane earlier, when described roof girder lifts, should slowly lift by crane, when treating described roof girder built on stilts 200mm, stop to hoist, described roof girder of scrutiny and suspender have or not distortion, determine errorless after, lifting is to the installation site, and behind described roof girder hoisted in position, two ends high-strength bolt node adopts interim bolt earlier, lifted first, second roof girder pulled on safety net immediately, prevents that the operating personnel high-altitude from falling, tie-rod and Eurya plant bar between the roof truss are installed then, are made two roof trusses form a stabilization element.
The 5th step: carry out finally lifting, method by first, second sheet roof girder of above lifting continues all the other roof girders of lifting, behind every lifting 5 Pin room framves, after verticality, spacing, the quality of inspection roof truss meets standard, just can make the high-strength bolt that roof truss is connected with steel column.
2. large span light section steel structure roof girder hanging method as claimed in claim 1, it is characterized in that, in described first step, also comprise with No. 10 channel-section steels stiffener as the roof girder web, to increase the rigidity of roof girder web, make in the roof girder lifting and stand up minimizing distortion in the process.
3. large span light section steel structure roof girder hanging method as claimed in claim 1, it is characterized in that, selecting for use in the lifting wire rope of described second step, the specification of selecting the wire rope between described crane and suspender for use is the wire rope of φ 21.5 for the 6*19 diameter, its rupture pull force is 245.5KN, and selecting the specification of the wire rope between described suspender and a slice integral hoisting roof girder for use is the wire rope of φ 26 for the 6*19 diameter, and its rupture pull force is 362.0KN.
4. large span light section steel structure roof girder hanging method as claimed in claim 1 is characterized in that, in described crane of selecting for use of described third step and suspender, selecting described crane for use is one 50 tons of mobile cranes, long 32.75 meters of bar, 7 meters of operating radius can lift by crane 10 tons; Described suspender is a balance sling that is made into the triangle girder by seamless steel pipe and the L50 angle steel of φ 219*6, φ 76*3.5, long 18 meters of described suspender.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100554656A CN101967887A (en) | 2009-07-28 | 2009-07-28 | Large-span light steel structure roof girder hoisting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100554656A CN101967887A (en) | 2009-07-28 | 2009-07-28 | Large-span light steel structure roof girder hoisting method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101967887A true CN101967887A (en) | 2011-02-09 |
Family
ID=43547102
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009100554656A Pending CN101967887A (en) | 2009-07-28 | 2009-07-28 | Large-span light steel structure roof girder hoisting method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101967887A (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102277966A (en) * | 2011-05-12 | 2011-12-14 | 驻马店市三超实业有限公司 | Girder assembling method for manufacturing of steel structure |
CN102287050A (en) * | 2011-07-13 | 2011-12-21 | 葛加君 | Construction method for long-span steel reinforced concrete roof truss |
CN102777037A (en) * | 2011-05-13 | 2012-11-14 | 中国建筑第八工程局有限公司 | Simple and practical hoisting construction method of long-span steel girder |
CN102864936A (en) * | 2012-10-10 | 2013-01-09 | 江苏南通六建建设集团有限公司 | Combination lifting construction method for large-scale high hollow building roof of steel structure |
CN103010954A (en) * | 2012-12-07 | 2013-04-03 | 中国建筑第八工程局有限公司 | Multi-point hoisting method for heterogeneous prefabricated part |
CN103276907A (en) * | 2013-05-21 | 2013-09-04 | 中国华冶科工集团有限公司 | Hoisting method for large-span hinged type herringbone steel arch |
CN103883129A (en) * | 2014-03-17 | 2014-06-25 | 中国华冶科工集团有限公司 | Method for installing steel structure roof beams |
CN104389432A (en) * | 2014-10-21 | 2015-03-04 | 北京建工土木工程有限公司 | Integral lifting equipment of steel truss-supported concrete house roof system and construction method |
CN106351454A (en) * | 2016-08-29 | 2017-01-25 | 中国十七冶集团有限公司 | Method for combined installation of steel structure roof with steel plant |
CN108252409A (en) * | 2016-12-29 | 2018-07-06 | 中冶宝钢技术服务有限公司 | A kind of method of steel construction full wafer lifting steel column |
CN110397287A (en) * | 2019-05-21 | 2019-11-01 | 安徽伟宏钢结构集团股份有限公司 | A kind of fast hoisting technique of module-type steel structure component |
CN110980500A (en) * | 2019-12-06 | 2020-04-10 | 中国三冶集团有限公司 | Balanced stress auxiliary hanging beam and roof structure integral hoisting method |
CN111749474A (en) * | 2020-07-02 | 2020-10-09 | 上海建工四建集团有限公司 | Construction method of clean workshop |
CN113323404A (en) * | 2021-05-25 | 2021-08-31 | 北京港源幕墙有限公司 | Installation method of integrated steel truss |
CN113931457A (en) * | 2021-09-30 | 2022-01-14 | 上海宝冶集团有限公司 | Hoisting method of large-span steel structure of limited working surface of heating furnace area |
CN116065818A (en) * | 2021-10-29 | 2023-05-05 | 山东省高速养护集团有限公司 | Steel structure warehouse construction technology |
-
2009
- 2009-07-28 CN CN2009100554656A patent/CN101967887A/en active Pending
Cited By (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102277966B (en) * | 2011-05-12 | 2013-01-23 | 驻马店市三超实业有限公司 | Girder assembling method for manufacturing of steel structure |
CN102277966A (en) * | 2011-05-12 | 2011-12-14 | 驻马店市三超实业有限公司 | Girder assembling method for manufacturing of steel structure |
CN102777037B (en) * | 2011-05-13 | 2014-11-26 | 中国建筑第八工程局有限公司 | Simple and practical hoisting construction method of long-span steel girder |
CN102777037A (en) * | 2011-05-13 | 2012-11-14 | 中国建筑第八工程局有限公司 | Simple and practical hoisting construction method of long-span steel girder |
CN102287050A (en) * | 2011-07-13 | 2011-12-21 | 葛加君 | Construction method for long-span steel reinforced concrete roof truss |
CN102864936A (en) * | 2012-10-10 | 2013-01-09 | 江苏南通六建建设集团有限公司 | Combination lifting construction method for large-scale high hollow building roof of steel structure |
CN102864936B (en) * | 2012-10-10 | 2014-08-13 | 南通大学 | Combination lifting construction method for large-scale high hollow building roof of steel structure |
CN103010954A (en) * | 2012-12-07 | 2013-04-03 | 中国建筑第八工程局有限公司 | Multi-point hoisting method for heterogeneous prefabricated part |
CN103010954B (en) * | 2012-12-07 | 2015-11-18 | 中国建筑第八工程局有限公司 | Special-shaped prefabricated components multipoint hoisting method |
CN103276907A (en) * | 2013-05-21 | 2013-09-04 | 中国华冶科工集团有限公司 | Hoisting method for large-span hinged type herringbone steel arch |
CN103276907B (en) * | 2013-05-21 | 2015-06-10 | 中国华冶科工集团有限公司 | Hoisting method for large-span hinged type herringbone steel arch |
CN103883129A (en) * | 2014-03-17 | 2014-06-25 | 中国华冶科工集团有限公司 | Method for installing steel structure roof beams |
CN103883129B (en) * | 2014-03-17 | 2016-06-22 | 中国华冶科工集团有限公司 | A kind of steel structural roof beam installation method |
CN104389432A (en) * | 2014-10-21 | 2015-03-04 | 北京建工土木工程有限公司 | Integral lifting equipment of steel truss-supported concrete house roof system and construction method |
CN106351454B (en) * | 2016-08-29 | 2019-10-18 | 中国十七冶集团有限公司 | A kind of steel-making workshop steel structural roof combined installation method |
CN106351454A (en) * | 2016-08-29 | 2017-01-25 | 中国十七冶集团有限公司 | Method for combined installation of steel structure roof with steel plant |
CN108252409A (en) * | 2016-12-29 | 2018-07-06 | 中冶宝钢技术服务有限公司 | A kind of method of steel construction full wafer lifting steel column |
CN110397287A (en) * | 2019-05-21 | 2019-11-01 | 安徽伟宏钢结构集团股份有限公司 | A kind of fast hoisting technique of module-type steel structure component |
CN110980500A (en) * | 2019-12-06 | 2020-04-10 | 中国三冶集团有限公司 | Balanced stress auxiliary hanging beam and roof structure integral hoisting method |
CN111749474A (en) * | 2020-07-02 | 2020-10-09 | 上海建工四建集团有限公司 | Construction method of clean workshop |
CN111749474B (en) * | 2020-07-02 | 2021-10-08 | 上海建工四建集团有限公司 | Construction method of clean workshop |
CN113323404A (en) * | 2021-05-25 | 2021-08-31 | 北京港源幕墙有限公司 | Installation method of integrated steel truss |
CN113931457A (en) * | 2021-09-30 | 2022-01-14 | 上海宝冶集团有限公司 | Hoisting method of large-span steel structure of limited working surface of heating furnace area |
CN116065818A (en) * | 2021-10-29 | 2023-05-05 | 山东省高速养护集团有限公司 | Steel structure warehouse construction technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101967887A (en) | Large-span light steel structure roof girder hoisting method | |
CN101892736B (en) | High altitude moving hanging basket construction method | |
CN101787732B (en) | Cable-stayed multi-layer framework structure and construction control method thereof | |
CN103669845A (en) | High-altitude long-span overhung cornice formwork supporting system and constructing method thereof | |
CN102535845A (en) | Construction method of bearing frame of corridor structure | |
CN203296361U (en) | Long-span steel structure cross assembling hoisting platform | |
CN208899886U (en) | Cantilever frame platform | |
CN106759909B (en) | Bearing structure system and its construction method are hung up under one kind | |
CN111779274A (en) | Construction method for integrally lifting temporary hoisting point of large-span unequal-height steel structure net rack | |
CN108842954A (en) | A kind of huge different section Honeycomb Beam structural system construction method of installation of aerofoil profile roofing | |
CN111218987A (en) | Bearing type net rack construction method | |
CN102003078A (en) | Assembling method of net rack | |
CN107938515B (en) | Erection method of large-span lightweight emergency bridge suitable for emergency rescue and disaster relief | |
CN204401995U (en) | Encorbelment support system in a kind of center of installing for dome structure | |
CN114837483B (en) | High-low span portal steel frame building structure and construction process thereof | |
CN105804401B (en) | A kind of construction steel moulding bed and the method using its lighting roof steel construction of constructing | |
CN205617805U (en) | Steel bed -jig is used in steel construction construction of daylighting top | |
CN205444935U (en) | Special -shaped steel space frame construction and installation structure of complicated large -span department | |
CN201411926Y (en) | Arc beam hoisting structure | |
CN110469126B (en) | Binding trolley for concrete reinforcing steel bars and binding construction method thereof | |
CN112575948A (en) | Truss string beam and cantilever truss combined roof truss and construction method | |
CN208294101U (en) | A kind of large-span steel girder mounting slip and promote coupling apparatus | |
CN220011942U (en) | Temporary lifting support device of high-altitude suspension steel structure | |
CN218114742U (en) | Carrying pole beam hoisting system and carrying pole beam hoisting system | |
CN105084229B (en) | Roof crane and application to roof-midspan longitudinal steel beam hoisting |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Open date: 20110209 |