CN103276907B - Hoisting method for large-span hinged type herringbone steel arch - Google Patents

Hoisting method for large-span hinged type herringbone steel arch Download PDF

Info

Publication number
CN103276907B
CN103276907B CN201310188893.2A CN201310188893A CN103276907B CN 103276907 B CN103276907 B CN 103276907B CN 201310188893 A CN201310188893 A CN 201310188893A CN 103276907 B CN103276907 B CN 103276907B
Authority
CN
China
Prior art keywords
component
steel arch
hoisting
herringbone steel
herringbone
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310188893.2A
Other languages
Chinese (zh)
Other versions
CN103276907A (en
Inventor
王文凯
王富军
刘瑞峰
李玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
Original Assignee
China Huaye Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN201310188893.2A priority Critical patent/CN103276907B/en
Publication of CN103276907A publication Critical patent/CN103276907A/en
Application granted granted Critical
Publication of CN103276907B publication Critical patent/CN103276907B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a hoisting method for a large-span hinged type herringbone steel arch. The hoisting method comprises the steps of conducting hinge joint connection, setting hoisting points, installing hoisting rings, determining the lengths of hoisting steel wire ropes, hoisting and the like. According to the hoisting method for the large-span hinged type herringbone steel arch, due to integral and multipoint hoisting, the technical problems that hinge pin installation in high attitude is difficult, high in construction cost, low in working efficiency and the like are effectively solved. In addition, due to the facts that two hoists are used for hoisting, multipoint hoisting is adopted, and the hoisting points are set reasonably, the situation that the herringbone steel arch deforms due to lack of rigidity in the hoisting process is avoided. Due to the fact that the hoisting steel wire ropes with suitable lengths are selected, the installation angle of the herringbone steel arch is effectively controlled, and two column feet is made to be positioned on bases easily.

Description

The hanging method of large span radial type herringbone steel arch
Technical field
The present invention relates to a kind of hanging method, particularly a kind of hanging method of large span radial type herringbone steel arch.
Background technology
Herringbone steel arch form of structure is more common in the 60 to 70's of last century, and present this structure is domestic rarely found.Herringbone steel arch comprises component I and component II, and every part is welded H section steel, and the top of component I and component II is articulated and connected, and two suspension columns of bow member are articulated and connected with the base on embedded board, and many Pin bow member forms factory building main frame.Many large-sized workshop two suspension column spans are generally more than 50 meters, and top mark is high more than 30 meters.
At present, this large span radial type herringbone steel arch two kinds of modes are installed: one be bulk-breaking formula lifting, namely component I and component II are lifted respectively, and then connect.The lifting of this hanging method is convenient, fast, but when the component I of herringbone steel arch is connected with component II, top bearing pin is not easily installed.When installing top bearing pin, need to set up the scaffold of more than 30 meter high or special lifting machine, construction cost is high.And install in high-altitude that bearing pin not easily operates, operating efficiency is low.Another kind method adopts integral hoisting mode, and the method needs first the top group of component I and component II to be fitted together on ground, and in the process of integral hoisting, two components will with two suspension column lines for axis be Space Rotating 90 degree.When adopting this holistic approach to lift, because bow member side rigidity is inadequate, easily occur the problem that bow member is out of shape, can not meet the technical requirements of installation, installation difficulty is larger.
Summary of the invention
In order to solve in prior art, during large span radial type herringbone steel arch employing integral hoisting, bow member is yielding, can not meet installation specification, the technical problem that installation difficulty is large, the object of this invention is to provide a kind of hanging method of large span radial type herringbone steel arch, the method adopts monolithic, multipoint hoisting, solves the yielding technical problem of bow member, meet construction demand, and this hanging method is simple to operate, operating efficiency is high.
To achieve these goals, present invention employs following technical scheme: a kind of hanging method of large span radial type herringbone steel arch, comprises the following steps:
The component I of herringbone steel arch and the top of component II are articulated and connected by step 1. on the ground, are assembled into herringbone steel arch;
Step 2. selects two cranes, respectively in order to lifting components I and component II according to the weight of component I and component II and on-site hoisting condition;
Step 3., according to the shape of component I and component II, is determined the center of gravity of component I and component II respectively, with each center of gravity for symmetrical centre, is at least arranged 4 suspension centres respectively, and be fixedly installed hoisting ring on each component on each suspension centre;
Step 4. is by computer graphics software, draw the physical location after herringbone steel arch installation on computers, directly over the center of gravity gib head of two cranes being placed in respectively component I, component II, connect gib head and hoisting ring, measure each hoisting ring in component I and component II and, to the distance of gib head, accurately determine the length lifting wire rope;
Two hoisting rings that the every side of center of gravity of step 5. component I, component II is adjacent connect with a lifting wire rope;
The gib head of two cranes is placed in directly over the center of gravity of component I and component II by step 6. respectively, then the lifting wire rope be connected on hoisting ring is hung on the gib head of crane, check errorless after, two cranes lift by crane simultaneously, after top is liftoff, check that component is with or without distortion, if component has buckling phenomenon, should readjust the distance between suspension centre or increase suspension centre again; If component is not out of shape, continue lifting, herringbone steel arch with two suspension column lines for axis rotates, until herringbone steel arch top reaches installed height mark, herringbone steel arch erects completely, now, herringbone steel arch with two suspension column lines for axis at Space Rotating 90 degree.
After step 7. herringbone steel arch erects completely, adjusted by translation, herringbone steel arch is moved to installation site, with bearing pin, the base on two suspension columns and embedded board is fixed, and fastened lashing, herringbone steel arch is firm.
Preferably, in step 3, described suspension centre is set to 4 respectively on component I and component II.Multipoint hoisting, reasonable Arrangement lifting point, produces distortion because rigidity is inadequate when avoiding herringbone steel arch lifting.
Preferably, in step 3, on each component, be equidistant between adjacent two suspension centres.
Preferably, described hoisting ring is welded in component I and component II.Be connected firmly, difficult drop-off, construction cost is low.
Advantageous Effects of the present invention is:
1. lifted by two cranes, multipoint hoisting, reasonable Arrangement lifting point, solve herringbone steel arch in integral hoisting process and produce the technical problem of being out of shape not because of rigidity, meet construction requirement.
2., by selecting the lifting wire rope of appropriate length, effectively control the setting angle of herringbone bow member, make two suspension columns easily in place, easy for installation on base, operating efficiency is high.
3. adopt ground entirety group right, integral hoisting, after avoiding monolithic lifting, the technology brought by work high above the ground installation bearing pin and safety problem.
Accompanying drawing explanation
Fig. 1 behaves Zee bar steel Z arch frame structure schematic diagram;
Fig. 2 is the suspension centre arrangement diagram of herringbone steel arch;
Fig. 3 is the erection drawing of herringbone steel arch;
Fig. 4 is the top view before herringbone steel arch lifting;
Fig. 5 is the top view after herringbone steel arch lifting.
Reference numeral
Detailed description of the invention
Below in conjunction with accompanying drawing, the preferred embodiment of the present invention is described in further detail.
Fig. 1 behaves Zee bar steel Z arch frame structure schematic diagram, and as shown in Figure 1, described herringbone steel arch 1 comprises symmetrically arranged component I101 and component II 102, and component I101 and component II 102 are welded H section steel, also can be the material that other are applicable to.Described component I101 is connected by hinge with the top of component II 102, and the distance between component I101 and two suspension columns 2 of component II 102 is design width; After lifting, two suspension columns 2 are articulated and connected with the base 4 on embedded board 3.This herringbone steel arch 1 lifts as follows:
The component I101 of herringbone steel arch 1 as shown in Figure 4, is connected by hinge with the top of component II 102, is assembled into herringbone steel arch by step 1. on the ground;
Step 2. selects two suitable cranes 5, respectively in order to lifting components I and component II according to the weight of component I101 and component II 102 and on-site hoisting condition;
Step 3., according to the shape of component I101 and component II 102, determines the center of gravity 11 of component I101 and component II 102, respectively with each center of gravity 11 for symmetrical centre, 4 suspension centres are set on each component respectively, preferably, on each component, be equidistant between adjacent two suspension centres; Then on each suspension centre, be fixedly installed hoisting ring, in the present embodiment, preferably hoisting ring be fixedly connected in component I101 and component II 102 by the mode of welding;
Step 4. as shown in Figures 2 and 3, by computer graphics software, draw the physical location after herringbone steel arch 1 installation on computers, directly over the center of gravity 11 gib head 6 of two cranes being placed in respectively component I, component II, connect gib head 6 and each hoisting ring, measure each hoisting ring in component I and component II and, to the distance of gib head 6, accurately determine the length lifting wire rope; Obviously, because component I and component II are for being symmetrical arranged, two cranes are also symmetrical arranged, so, only need measure the distance on a component between each hoisting ring to corresponding crane hook.
As shown in Figures 2 and 3, two hoisting rings that the every side of center of gravity of component I, component II is adjacent connect with a lifting wire rope step 5., and the two ends namely lifting wire rope II8 connect hoisting ring III14 and hoisting ring IV15; The two ends of lifting wire rope I7 connect hoisting ring I12 and hoisting ring II13; Equally, four hoisting rings in component II are connected with lifting wire rope IV10 respectively by lifting wire rope III9;
The gib head 6 of two cranes is placed in directly over the center of gravity 11 of component I and component II by step 6. respectively, then the lifting wire rope be connected on hoisting ring is hung on the gib head of crane, check errorless after, two cranes 5 lift by crane simultaneously, after ground is left at the top of component I and component II, check that component I and component II are with or without distortion, if component I and component II have buckling phenomenon, should readjust the distance between suspension centre or increase suspension centre again; If component I and component II are not out of shape, then continue lifting, herringbone steel arch 1 with two suspension column 2 lines for axis is at Space Rotating, until the top of herringbone steel arch 1 reaches installed height mark, herringbone steel arch erects completely, as shown in Figure 5, now, herringbone steel arch with two suspension column 2 lines for axis at Space Rotating 90 degree.
Step 7. as shown in Figure 5, after herringbone steel arch 1 erects completely, is adjusted by translation, herringbone steel arch is moved to installation site, is fixed by two suspension columns 2, and fastened lashing with bearing pin with the base on embedded board, and herringbone steel arch is firm, completes lifting.
In sum, the hanging method of large span radial type herringbone steel arch of the present invention, by monolithic, multipoint hoisting, efficiently solves high-altitude and installs bearing pin difficulty greatly, the technical problems such as construction cost is high, and operating efficiency is low; , lifted by two cranes meanwhile, adopt multipoint hoisting, reasonable Arrangement lifting point, avoid herringbone steel arch in the process of lifting because rigidity produces distortion not.And by selecting the lifting wire rope of appropriate length, effectively controlling the setting angle of herringbone bow member, making two suspension columns easily in place on base.
What finally illustrate is, above embodiment is only in order to illustrate technical scheme of the present invention and unrestricted, although with reference to preferred embodiment to invention has been detailed description, those of ordinary skill in the art is to be understood that, can modify to technical scheme of the present invention or equivalent replacement, and not departing from aim and the scope of technical solution of the present invention, it all should be encompassed in the middle of right of the present invention.

Claims (4)

1. a hanging method for large span radial type herringbone steel arch, is characterized in that comprising the following steps:
The component I of herringbone steel arch and the top of component II are articulated and connected by step 1. on the ground, are assembled into herringbone steel arch;
Step 2. selects two cranes, respectively in order to lifting components I and component II according to the weight of component I and component II and on-site hoisting condition;
Step 3., according to the shape of component I and component II, is determined the center of gravity of component I and component II respectively, with each center of gravity for symmetrical centre, is at least arranged 4 suspension centres respectively, and be fixedly installed hoisting ring on each component on each suspension centre;
Step 4. is by computer graphics software, draw the physical location after herringbone steel arch installation on computers, directly over the center of gravity gib head of two cranes being placed in respectively component I, component II, connect gib head and hoisting ring, measure each hoisting ring in component I and component II and, to the distance of gib head, accurately determine the length lifting wire rope;
Two hoisting rings that the every side of center of gravity of step 5. component I, component II is adjacent connect with a lifting wire rope;
The gib head of two cranes is placed in directly over the center of gravity of component I and component II by step 6. respectively, then the lifting wire rope be connected on hoisting ring is hung on the gib head of crane, check errorless after, two cranes lift by crane simultaneously, after top is liftoff, check that component is with or without distortion, if component has buckling phenomenon, should readjust the distance between suspension centre or increase suspension centre again; If component is not out of shape, then continue lifting, herringbone steel arch with two suspension column lines for axis rotates, until herringbone steel arch top reaches installed height mark, herringbone steel arch erects completely, now, herringbone steel arch with two suspension column lines for axis at Space Rotating 90 degree;
After step 7. herringbone steel arch erects completely, adjusted by translation, herringbone steel arch is moved to installation site, with bearing pin, the base on two suspension columns and embedded board is fixed, and fastened lashing, herringbone steel arch is firm.
2. the hanging method of large span radial type herringbone steel arch according to claim 1, it is characterized in that: in step 3, described suspension centre is set to 4 respectively on component I and component II.
3. the hanging method of large span radial type herringbone steel arch according to claim 1 and 2, is characterized in that: in step 3, on each component, is equidistant between adjacent two suspension centres.
4. the hanging method of large span radial type herringbone steel arch according to claim 1, is characterized in that: described hoisting ring is welded in component I and component II.
CN201310188893.2A 2013-05-21 2013-05-21 Hoisting method for large-span hinged type herringbone steel arch Active CN103276907B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310188893.2A CN103276907B (en) 2013-05-21 2013-05-21 Hoisting method for large-span hinged type herringbone steel arch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310188893.2A CN103276907B (en) 2013-05-21 2013-05-21 Hoisting method for large-span hinged type herringbone steel arch

Publications (2)

Publication Number Publication Date
CN103276907A CN103276907A (en) 2013-09-04
CN103276907B true CN103276907B (en) 2015-06-10

Family

ID=49059513

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310188893.2A Active CN103276907B (en) 2013-05-21 2013-05-21 Hoisting method for large-span hinged type herringbone steel arch

Country Status (1)

Country Link
CN (1) CN103276907B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103835502A (en) * 2014-02-28 2014-06-04 中天建设集团有限公司 Distributor balance lifting method
CN104264781B (en) * 2014-10-31 2016-05-18 中国建筑第二工程局有限公司 Latticed cylindrical surface steel structure latticed shell and construction method thereof
CN105971291B (en) * 2016-05-12 2018-03-06 中国华冶科工集团有限公司 A kind of hanging method of L-shaped space truss
CN105883580B (en) * 2016-06-20 2019-05-10 南通振华重型装备制造有限公司 A kind of track crane girder web plate hoisting
CN106115459B (en) * 2016-07-15 2017-08-08 沈阳建筑大学 The method for preventing ashlar post from fractureing or breaking in transport and hoisting process
CN115613703A (en) * 2022-09-30 2023-01-17 上海游艺机工程有限公司 A super-large herringbone frame hoisting method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH074049A (en) * 1993-06-21 1995-01-10 Taisei Corp Building construction method
CN101255768A (en) * 2008-03-21 2008-09-03 宁波建工集团有限公司 Method for high altitude installation of large span steel truss
CN101839068A (en) * 2010-04-08 2010-09-22 宝厦建设(集团)股份有限公司 Prestressing method for installing large-span double-layer latticed shell structure
CN101967887A (en) * 2009-07-28 2011-02-09 中冶成工上海五冶建设有限公司 Large-span light steel structure roof girder hoisting method
CN102127972A (en) * 2010-12-31 2011-07-20 攀钢集团冶金工程技术有限公司 Hoisting method
CN102777043A (en) * 2012-08-03 2012-11-14 浙江精工钢结构有限公司 Construction method for lifting arch structure in zero-deformation state

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH074049A (en) * 1993-06-21 1995-01-10 Taisei Corp Building construction method
CN101255768A (en) * 2008-03-21 2008-09-03 宁波建工集团有限公司 Method for high altitude installation of large span steel truss
CN101967887A (en) * 2009-07-28 2011-02-09 中冶成工上海五冶建设有限公司 Large-span light steel structure roof girder hoisting method
CN101839068A (en) * 2010-04-08 2010-09-22 宝厦建设(集团)股份有限公司 Prestressing method for installing large-span double-layer latticed shell structure
CN102127972A (en) * 2010-12-31 2011-07-20 攀钢集团冶金工程技术有限公司 Hoisting method
CN102777043A (en) * 2012-08-03 2012-11-14 浙江精工钢结构有限公司 Construction method for lifting arch structure in zero-deformation state

Also Published As

Publication number Publication date
CN103276907A (en) 2013-09-04

Similar Documents

Publication Publication Date Title
CN206278848U (en) A kind of dynamic Ding many loop wheel machine pedestal operation platforms of Sheng rotation types of overall Zi
CN106939707A (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN105604334A (en) Rapid-construction method used for overall installation of large-span steel truss
CN103276907A (en) Hoisting method for large-span hinged type herringbone steel arch
CN104929364B (en) Auxiliary construction method for longspan cantilever entire laminated Vierendeel truss structure
CN109231023B (en) Method for installing jib system of portal crane
CN106760197A (en) A kind of method that allowable error is installed in steel column structure and its control
CN106081870A (en) A kind of nuclear power station steel dome balance hanging method
CN109081247A (en) A kind of hanging method of vestibule large-span steel girder
CN101503908B (en) Construction method for spacing suspension cable structural template support platform
CN104746883A (en) Construction method for three-crane lifting installation used for bow-shaped space truss
CN104803303B (en) A kind of single movable-arm floor mast with rock type counter-jib
CN101284628A (en) Hoisting method for framework of large tonnage pressing machine
CN102910532B (en) Method for butting and hoisting large box type derricks in air
CN211689943U (en) Assembled pier column formwork overturn buffer device
CN203845689U (en) Indoor assembleable large equipment lifting device
CN204802884U (en) Storage tank flip -chip balanced hoisting device
CN105040591A (en) Positioning device for waveform steel web and positioning method thereof
CN104989111A (en) Construction method for steel structure high-rise hoisting
CN203513127U (en) Tower crane and its hoisting pole
CN104234445A (en) Restoration-security multifunctional bracket of deformed wooden structure building
CN204057780U (en) Hoisting crane and jib, auxiliary bracing or strutting arrangement
CN204569237U (en) A kind of oscillating type pole equilibrium arm
CN202899734U (en) Rotary holding pole cap
CN102383613B (en) Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant